SlideShare a Scribd company logo
1 of 2
Download to read offline
The information available on this Safety Flash and our associated web site is provided in good faith and only for the purposes
of enhancing safety and best practice. For the avoidance of doubt no legal liability shall be attached to any guidance and/or
recommendation and/or statement herein contained.
- 1 -
Marine Safety Forum – Safety Flash 13-30
Issued: 1st
July 2013
Subject: Spill of Backloaded Slops
A recent incident has revealed that the vessels concerns were ignored and pressure was put on
the vessel Master to incorrectly load slops into a brine tank. The slops were successfully pumped
ashore and the tanks cleaned to Brine Standard by shore side tank cleaners. During the tank
cleaning operation, the vessel was informed by the cleaning company that there was insufficient
water pressure to flush the lines so as to ensure that the same were suitably cleaned. A 2.5 inch
diameter fire hose was used to flush the vessels 4 inch cargo lines.
The vessel was aware that while the tank had been successfully cleaned there was the possibility
that cargo lines were still contaminated with slops due to the inadequate water pressure. With this
in mind, it was decided to ensure that the cargo lines were cleaned prior to loading any further
product so as to avoid contamination.
In order to check the lines, FW was filled into the brine tanks. It was planned to pump this FW from
the Brine tank into the vessels slop tank via the cargo manifold by way of a fire hose connected by
a reducer. Whilst one end of the fire hose was connected to the reducer, the other was incorrectly
secured using rope.
The pump speed was set to 15% and as expected, slop contaminated product was observed
coming out. Approximately a minute after the transfer commenced, the pressure increased and the
end of the hose secured with rope came loose and sprayed the deck and cargo rail walkway with
product from the brine line. Some of this product went over the side, of which 5 litres was
estimated as oil.
The pump was stopped immediately and the product cleaned off the vessels deck and cargo rail
walkway. The relevant authorities were notified and an investigation into the incident conducted.
It must be stressed that the action taken by the vessel to confirm the cleanliness of the brine line
was a positive step which unfortunately, was inadequately planned. It is clear that had better
communication and planning taken place by all parties involved, this incident could have been
avoided.
The information available on this Safety Flash and our associated web site is provided in good faith and only for the purposes
of enhancing safety and best practice. For the avoidance of doubt no legal liability shall be attached to any guidance and/or
recommendation and/or statement herein contained.
- 2 -
Immediate Cause
Inadequate Task Planning by the vessel
 Incorrect Securing of Hose end which should have been suitably Risk Assessed.
 Use of a 2.5 inch hose connected to a 4 inch line and build-up of pressure from such a
configuration not considered.
 Poor seamanship.
Root Cause
 Inadequate Planning by offshore facility and logistics provider to not clean the empty Mud
tanks during the vessels 30 hour stay in port prior to going on location.
 Vessels concerns were not taken into account, the Vessel Master should have refused
to backload slops into the Brine tanks.
 Poor Communication on part of all parties concerned including the vessel.
 Breach of Rule/Standard/Procedure by all parties concerned.
Actions taken and/or planned
 A Time Out for Safety was conducted with all parties involved where it was stressed that if
any job is considered unsafe, it must be stopped.
 The Vessel was instructed that slops must not be loaded into brine tanks as per the
requirements of the Certificate of Fitness.
 The Charterer confirmed that they will be increasing positive reinforcement for Time Out
For Safety/Stop the Job.
 The Vessel was instructed to communicate directly with the Contract Holder, Vessel
Manager and DPA if it was felt that undue pressure was being applied to perform an
operation that was considered incorrect or unsafe.
Under no circumstances is any wet bulk product other than brine permitted to be
loaded/backloaded into brine tanks. Brine tanks and their associated pumps are for the carriage of
brine only and not for slops or mud.
If a vessel does not have any clean mud tanks available into which slops can be backloaded, then
the vessel must refuse to accept the slops.
It is then the responsibility of the offshore facility/asset to make arrangements for the slops to be
backloaded onto another vessel.
This also applies to backflushing of wet bulk filling/discharge lines after tank cleaning. Lines are not
to be backflushed into brine tanks or any other tanks which are not designed for this purpose to
make life easier for the tank cleaning company.
If you are unsure or uncomfortable, regarding any instructions which you receive, from offshore
facilities or shore side logistics, then you are to contact your company immediately for clarification.

More Related Content

What's hot (9)

CaptainsMast
CaptainsMastCaptainsMast
CaptainsMast
 
Vessel General Permit
Vessel General PermitVessel General Permit
Vessel General Permit
 
Mgn 71 muster and drills
Mgn 71 muster and drillsMgn 71 muster and drills
Mgn 71 muster and drills
 
Psc checklist
Psc checklistPsc checklist
Psc checklist
 
Job Description
Job DescriptionJob Description
Job Description
 
Schedule 5
Schedule 5Schedule 5
Schedule 5
 
Psc pocket checklist
Psc pocket checklistPsc pocket checklist
Psc pocket checklist
 
Isps (1)
Isps (1)Isps (1)
Isps (1)
 
Safe Manning JCowan pg38 MP March15
Safe Manning JCowan pg38 MP March15Safe Manning JCowan pg38 MP March15
Safe Manning JCowan pg38 MP March15
 

Similar to Msf safety-flash-13.30

Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5Paulo P
 
Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5Paulo P
 
Msf safety-flash-13.24
Msf safety-flash-13.24Msf safety-flash-13.24
Msf safety-flash-13.24OCIMF OVID
 
Esp booklet for oil tankers tcm155-206361
Esp booklet for oil tankers tcm155-206361Esp booklet for oil tankers tcm155-206361
Esp booklet for oil tankers tcm155-206361KristijanJakimovski1
 
Example bunker checklist
Example bunker checklistExample bunker checklist
Example bunker checklistNor Masyiah
 
Ju t lifting bulletin
Ju t lifting bulletinJu t lifting bulletin
Ju t lifting bulletinAlan Bassett
 
Insight into Ship Operations - Rahul Bhargav Academic Conference 2018
Insight into Ship Operations - Rahul Bhargav Academic Conference 2018Insight into Ship Operations - Rahul Bhargav Academic Conference 2018
Insight into Ship Operations - Rahul Bhargav Academic Conference 2018Marexmedia
 
Joel B NMIF Operations Team Lead
Joel B NMIF Operations Team LeadJoel B NMIF Operations Team Lead
Joel B NMIF Operations Team LeadJoel Balahadia
 
Seaworthynes
SeaworthynesSeaworthynes
SeaworthynesJay Singh
 
IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004Abdulla Wanis
 
205073848 transpo-11-20
205073848 transpo-11-20205073848 transpo-11-20
205073848 transpo-11-20homeworkping7
 
126623979 maritime-ipr-cases
126623979 maritime-ipr-cases126623979 maritime-ipr-cases
126623979 maritime-ipr-caseshomeworkping8
 
A case study relating to Ballast Water Treatment System (BWTS)
A case study relating to Ballast Water Treatment System (BWTS)  A case study relating to Ballast Water Treatment System (BWTS)
A case study relating to Ballast Water Treatment System (BWTS) Nilendra Kumar
 
Preparation of the Cargo Plan
Preparation of the Cargo PlanPreparation of the Cargo Plan
Preparation of the Cargo PlanDivine Greatman
 

Similar to Msf safety-flash-13.30 (20)

Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5
 
Presentation chapter 5
Presentation chapter 5Presentation chapter 5
Presentation chapter 5
 
Imsbc
ImsbcImsbc
Imsbc
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 
Msf safety-flash-13.24
Msf safety-flash-13.24Msf safety-flash-13.24
Msf safety-flash-13.24
 
Dry docking operations
Dry docking operationsDry docking operations
Dry docking operations
 
Esp booklet for oil tankers tcm155-206361
Esp booklet for oil tankers tcm155-206361Esp booklet for oil tankers tcm155-206361
Esp booklet for oil tankers tcm155-206361
 
Draft survey
Draft surveyDraft survey
Draft survey
 
Example bunker checklist
Example bunker checklistExample bunker checklist
Example bunker checklist
 
Ju t lifting bulletin
Ju t lifting bulletinJu t lifting bulletin
Ju t lifting bulletin
 
Masters Guide to Container Securing
 Masters Guide to Container Securing Masters Guide to Container Securing
Masters Guide to Container Securing
 
Insight into Ship Operations - Rahul Bhargav Academic Conference 2018
Insight into Ship Operations - Rahul Bhargav Academic Conference 2018Insight into Ship Operations - Rahul Bhargav Academic Conference 2018
Insight into Ship Operations - Rahul Bhargav Academic Conference 2018
 
Joel B NMIF Operations Team Lead
Joel B NMIF Operations Team LeadJoel B NMIF Operations Team Lead
Joel B NMIF Operations Team Lead
 
Seaworthynes
SeaworthynesSeaworthynes
Seaworthynes
 
IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004
 
205073848 transpo-11-20
205073848 transpo-11-20205073848 transpo-11-20
205073848 transpo-11-20
 
126623979 maritime-ipr-cases
126623979 maritime-ipr-cases126623979 maritime-ipr-cases
126623979 maritime-ipr-cases
 
A case study relating to Ballast Water Treatment System (BWTS)
A case study relating to Ballast Water Treatment System (BWTS)  A case study relating to Ballast Water Treatment System (BWTS)
A case study relating to Ballast Water Treatment System (BWTS)
 
Hanks 2015 CV-3 updated
Hanks 2015 CV-3 updatedHanks 2015 CV-3 updated
Hanks 2015 CV-3 updated
 
Preparation of the Cargo Plan
Preparation of the Cargo PlanPreparation of the Cargo Plan
Preparation of the Cargo Plan
 

More from OCIMF OVID

Ovid newsletter may 2014
Ovid newsletter  may 2014Ovid newsletter  may 2014
Ovid newsletter may 2014OCIMF OVID
 
Http _www.maib.gov.uk_cms_resources.cfm_file=_sbs_typhoon_report
Http  _www.maib.gov.uk_cms_resources.cfm_file=_sbs_typhoon_reportHttp  _www.maib.gov.uk_cms_resources.cfm_file=_sbs_typhoon_report
Http _www.maib.gov.uk_cms_resources.cfm_file=_sbs_typhoon_reportOCIMF OVID
 
Msf safety-flash-13.34
Msf safety-flash-13.34Msf safety-flash-13.34
Msf safety-flash-13.34OCIMF OVID
 
Ovid newsletter august 2013
Ovid newsletter  august 2013Ovid newsletter  august 2013
Ovid newsletter august 2013OCIMF OVID
 
Msf safety-flash-13.32
Msf safety-flash-13.32Msf safety-flash-13.32
Msf safety-flash-13.32OCIMF OVID
 
Msf safety-flash-13.31
Msf safety-flash-13.31Msf safety-flash-13.31
Msf safety-flash-13.31OCIMF OVID
 
Msf safety-flash-13.30
Msf safety-flash-13.30Msf safety-flash-13.30
Msf safety-flash-13.30OCIMF OVID
 
Msf safety-flash-13.29
Msf safety-flash-13.29Msf safety-flash-13.29
Msf safety-flash-13.29OCIMF OVID
 
Msf safety-flash-13.29
Msf safety-flash-13.29Msf safety-flash-13.29
Msf safety-flash-13.29OCIMF OVID
 
Ocimf annual report_2013
Ocimf annual report_2013Ocimf annual report_2013
Ocimf annual report_2013OCIMF OVID
 
Msf safety-flash-13.28
Msf safety-flash-13.28Msf safety-flash-13.28
Msf safety-flash-13.28OCIMF OVID
 
Msf safety-flash-13.25
Msf safety-flash-13.25Msf safety-flash-13.25
Msf safety-flash-13.25OCIMF OVID
 
OVIQ Sample Master
OVIQ Sample Master OVIQ Sample Master
OVIQ Sample Master OCIMF OVID
 

More from OCIMF OVID (14)

Ovid newsletter may 2014
Ovid newsletter  may 2014Ovid newsletter  may 2014
Ovid newsletter may 2014
 
Http _www.maib.gov.uk_cms_resources.cfm_file=_sbs_typhoon_report
Http  _www.maib.gov.uk_cms_resources.cfm_file=_sbs_typhoon_reportHttp  _www.maib.gov.uk_cms_resources.cfm_file=_sbs_typhoon_report
Http _www.maib.gov.uk_cms_resources.cfm_file=_sbs_typhoon_report
 
Msf safety-flash-13.34
Msf safety-flash-13.34Msf safety-flash-13.34
Msf safety-flash-13.34
 
Ovid newsletter august 2013
Ovid newsletter  august 2013Ovid newsletter  august 2013
Ovid newsletter august 2013
 
Tn.jsp
Tn.jspTn.jsp
Tn.jsp
 
Msf safety-flash-13.32
Msf safety-flash-13.32Msf safety-flash-13.32
Msf safety-flash-13.32
 
Msf safety-flash-13.31
Msf safety-flash-13.31Msf safety-flash-13.31
Msf safety-flash-13.31
 
Msf safety-flash-13.30
Msf safety-flash-13.30Msf safety-flash-13.30
Msf safety-flash-13.30
 
Msf safety-flash-13.29
Msf safety-flash-13.29Msf safety-flash-13.29
Msf safety-flash-13.29
 
Msf safety-flash-13.29
Msf safety-flash-13.29Msf safety-flash-13.29
Msf safety-flash-13.29
 
Ocimf annual report_2013
Ocimf annual report_2013Ocimf annual report_2013
Ocimf annual report_2013
 
Msf safety-flash-13.28
Msf safety-flash-13.28Msf safety-flash-13.28
Msf safety-flash-13.28
 
Msf safety-flash-13.25
Msf safety-flash-13.25Msf safety-flash-13.25
Msf safety-flash-13.25
 
OVIQ Sample Master
OVIQ Sample Master OVIQ Sample Master
OVIQ Sample Master
 

Msf safety-flash-13.30

  • 1. The information available on this Safety Flash and our associated web site is provided in good faith and only for the purposes of enhancing safety and best practice. For the avoidance of doubt no legal liability shall be attached to any guidance and/or recommendation and/or statement herein contained. - 1 - Marine Safety Forum – Safety Flash 13-30 Issued: 1st July 2013 Subject: Spill of Backloaded Slops A recent incident has revealed that the vessels concerns were ignored and pressure was put on the vessel Master to incorrectly load slops into a brine tank. The slops were successfully pumped ashore and the tanks cleaned to Brine Standard by shore side tank cleaners. During the tank cleaning operation, the vessel was informed by the cleaning company that there was insufficient water pressure to flush the lines so as to ensure that the same were suitably cleaned. A 2.5 inch diameter fire hose was used to flush the vessels 4 inch cargo lines. The vessel was aware that while the tank had been successfully cleaned there was the possibility that cargo lines were still contaminated with slops due to the inadequate water pressure. With this in mind, it was decided to ensure that the cargo lines were cleaned prior to loading any further product so as to avoid contamination. In order to check the lines, FW was filled into the brine tanks. It was planned to pump this FW from the Brine tank into the vessels slop tank via the cargo manifold by way of a fire hose connected by a reducer. Whilst one end of the fire hose was connected to the reducer, the other was incorrectly secured using rope. The pump speed was set to 15% and as expected, slop contaminated product was observed coming out. Approximately a minute after the transfer commenced, the pressure increased and the end of the hose secured with rope came loose and sprayed the deck and cargo rail walkway with product from the brine line. Some of this product went over the side, of which 5 litres was estimated as oil. The pump was stopped immediately and the product cleaned off the vessels deck and cargo rail walkway. The relevant authorities were notified and an investigation into the incident conducted. It must be stressed that the action taken by the vessel to confirm the cleanliness of the brine line was a positive step which unfortunately, was inadequately planned. It is clear that had better communication and planning taken place by all parties involved, this incident could have been avoided.
  • 2. The information available on this Safety Flash and our associated web site is provided in good faith and only for the purposes of enhancing safety and best practice. For the avoidance of doubt no legal liability shall be attached to any guidance and/or recommendation and/or statement herein contained. - 2 - Immediate Cause Inadequate Task Planning by the vessel  Incorrect Securing of Hose end which should have been suitably Risk Assessed.  Use of a 2.5 inch hose connected to a 4 inch line and build-up of pressure from such a configuration not considered.  Poor seamanship. Root Cause  Inadequate Planning by offshore facility and logistics provider to not clean the empty Mud tanks during the vessels 30 hour stay in port prior to going on location.  Vessels concerns were not taken into account, the Vessel Master should have refused to backload slops into the Brine tanks.  Poor Communication on part of all parties concerned including the vessel.  Breach of Rule/Standard/Procedure by all parties concerned. Actions taken and/or planned  A Time Out for Safety was conducted with all parties involved where it was stressed that if any job is considered unsafe, it must be stopped.  The Vessel was instructed that slops must not be loaded into brine tanks as per the requirements of the Certificate of Fitness.  The Charterer confirmed that they will be increasing positive reinforcement for Time Out For Safety/Stop the Job.  The Vessel was instructed to communicate directly with the Contract Holder, Vessel Manager and DPA if it was felt that undue pressure was being applied to perform an operation that was considered incorrect or unsafe. Under no circumstances is any wet bulk product other than brine permitted to be loaded/backloaded into brine tanks. Brine tanks and their associated pumps are for the carriage of brine only and not for slops or mud. If a vessel does not have any clean mud tanks available into which slops can be backloaded, then the vessel must refuse to accept the slops. It is then the responsibility of the offshore facility/asset to make arrangements for the slops to be backloaded onto another vessel. This also applies to backflushing of wet bulk filling/discharge lines after tank cleaning. Lines are not to be backflushed into brine tanks or any other tanks which are not designed for this purpose to make life easier for the tank cleaning company. If you are unsure or uncomfortable, regarding any instructions which you receive, from offshore facilities or shore side logistics, then you are to contact your company immediately for clarification.