SlideShare a Scribd company logo
SRI DAMODARAM SANJEEVIAH POWER STATION (APGENCO)
Contents
Introduction
Literature Survey
Methodology
Layout of thermal plant
Study of Turbine
Introduction
REGION COAL GAS/Liquid Fuel Renewable TOTAL
Northern 9,015 2,344 35 11,394
Western 12,000 1,313 50 13,313
Southern 4,600 360 260 5,220
Eastern 9,470 - 10 9,480
Islands - - 5 5
Hydro - - - 800
JVs 4,999 1,967 - 6,966
Total 40,084(MW) 5,984(MW) 360(MW) 47,228(MW)
About APGENCO
 APGENCO (NELLORE) is normally
called as Sri Damodaram Sanjeeviah
thermal power plant
 APGENCO was setup in 2008 with
100% ownership by Government of
AP. In the last 8 years, APGENCO has
grown into the largest power utility in
AP.
 To meet the increasing power
demand in state planned this mega
power project in fast track basis.
 The total installed capacity of super
critical power plant is 2*800MW
 APGENCO has plans to become
8,000MW company by 2032.
 First Super Critical plant in AP is
APGENCO (NELLORE)
BAY OF BENGAL
MADHYA PRADESH
KARNATAKA
TAMILNADU
MAHARASHTRA
CHITOOR
CUDDAPAH
ANANTHAPUR
NELLORE
KARNOOL
PRAKASHAM
MAHBOOBNAGAR
GUNTUR
KRISHNA
NULGUNDA
RANGAREDDY
WARANGAL
KHAMMAM
KARIMNAGARNIZAMABAD
MEDAK
ADILABAD
WEST
EAST
VIZAG
GODAVARI
GODAVARI
VIJANAGARAM
SRIKAKULAM
Kothagudem
TPSs
700 MW + 500
MW
Vijayawada TPS
1760 MW
Rayalaseema TPS
1050 MW
Ramagundam TPS 62.5
MW
Nellore TPS
1600 MW
Total:
5670 MW
PRINCIPLE OF
THERMAL POWER
PLANT
 The Rankine cycle is an idealized
thermodynamic cycle of a heat
engine that converts heat into
mechanical work.
 This gives a theoretical
maximum Carnot efficiency for the
steam turbine alone of about 63%
compared with an actual overall
thermal efficiency of up to 42% for a
modern coal-fired power station.
 In an ideal Rankine cycle the pump and
turbine would be isentropic, i.e., the
pump and turbine would generate no
entropy and hence maximize the net
work output.
1. Cooling tower 10. Steam Control valve 19. Superheater
2. Cooling water pump
11. High pressure steam
turbine
20. Forced draught (draft) fan
3. transmission line (3-phase) 12. Deaerator 21. Reheater
4. Step-up transformer (3-
phase)
13. Feedwater heater 22. Combustion air intake
5. Electrical generator (3-phase) 14. Coal conveyor 23. Economiser
6. Low pressure steam turbine 15. Coal hopper 24. Air preheater
7. Condensate pump 16. Coal pulverizer 25. Precipitator
8. Surface condenser 17. Boiler steam drum 26. Induced draught (draft) fan
9. Intermediate pressure steam
turbine
18. Bottom ash hopper 27. Flue gas stack
Typical Diagram of a Coal-fired Thermal Power Station
Problem Identification:
Great difficulty in transportation of coal.
Unavailability of good quality of coal.
Problems of ash removal.
Factors include
Rake arrival schedules.
Changes in production scheduling.
Deviation from delivery rates etc.
These can be reduced by
Simultaneous arrival of rake.
Modeling approach.
queing approach.
STEAM
TURBINE
Why Multi Stage turbines are used?
Multistage turbines are back pressure turbines that can be made available in form of single
stage or multi-stage options.
These turbines find application for drive application/power generation applications and are of
straight-back pressure type.
Finding application in areas where back pressure steam is fully utilized, the power generation is
incidental to process steam demands.
Components of Steam Turbine Cycle
1. High Pressure Turbine
(HP Turbine)
2. Intermediate Pressure
Turbine
(IP Turbine)
3. Low Pressure Turbine
(LP Turbine)
4. Condenser
5. Cooling Tower 6. Low Pressure Heater
(LP Heater)
7. Deaerator 8. High Pressure Heater
(HP Heater)
9. Motor Driven Boiler
Feed Pump (MDBFP)
10. Turbine Driven Boiler
Feed Pump (TDBFP)
165 ksc, 540°C
40 ksc, 350°C
45 ksc, 565°C 7-8 ksc, 350°C
6 ksc, 160°C
0.1 ksc, 45°C
0.1 ksc, 45°C
ΔT=10°C
5 3 2
2*121*17 2*6
(BFP)
High Pressure
Turbine (HP Turbine)
 High pressure and temperature fluid
at the inlet of the turbine exit as
lower pressure and temperature
fluid. The difference is energy
converted by the turbine to
mechanical rotational energy, less
any aerodynamic and mechanical in
efficiencies incurred in the process.
 The high pressure casing is made of
creep resisting Chromium-
molybdenum-vanadium(Cr-Mo-V)
steel casting.
 The turbine is equipped with
emergency stop valves to cut of
steam supply and with control
valves to regulate supply.
 It has 17 rotor blades with first
impulse stage and others are
reaction.
Intermediate
Pressure Turbine
(IP Turbine)
 Intermediate pressure turbine
having more pressure then L.P
turbine and less than the high
pressure turbine(H.P) . Its blade is
larger than high pressure turbine.
 The size of blades of I.P steam
turbine is larger than H.P steam
turbine , but smaller than L.P
steam turbine.
 It has inlet of the main steam line
after the reheat process and in
outlet main steam line straight
goes to lp turbine.
 It has 2*12 stage of blades and 7th
stage steam line goes to TDBFP.
Low Pressure
Turbine (LP Turbine)
 LP turbine is designed to be a dual
flow turbine. Steam enters the
centre of the turbine from the
crossover pipe and flows across the
reaction blading in two opposite
directions.
 This configuration reduces axial
thrust on the turbine and allows for
a smaller turbine installation.
 Titanium alloys offer high strength
to intermediate temperatures at a
density almost half that of steel and
nickel-based super alloys.
 LP blade is larger than HP & IP.
Steps involved in design of Steam Turbine
1. Perform thermodynamic and axial thrust calculations to decide diameters and axial length of blading.
2. Perform rotor dynamic calculation and suggest any change of lengths and diameters to repeat step one.
3. Select suitable turbine extensions and diameters to meet above blading geometry.
4. Select suitable materials to meet steam parameters.
5. Select suitable governing system and protection system.
6. Prepare ordering / manufacturing documents incorporating above selections.
Mini project presentation

More Related Content

What's hot

OBRA THERMAL POWER PLANT
OBRA THERMAL POWER PLANTOBRA THERMAL POWER PLANT
OBRA THERMAL POWER PLANT
Faraz Khan
 
Inplant training report
Inplant training reportInplant training report
Inplant training reportapplesam8
 
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
haxxo24
 
training reportON Thermal power plantt (nashik tps)pdf
 training reportON Thermal power plantt (nashik tps)pdf training reportON Thermal power plantt (nashik tps)pdf
training reportON Thermal power plantt (nashik tps)pdf
Sagar Mehta
 
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESHppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESHAKHILESH KUMAR
 
Summer Training Report on thermal power plant
Summer Training Report on thermal power plantSummer Training Report on thermal power plant
Summer Training Report on thermal power plant
MohdAreebQureshi
 
Parichha thermal power point PPT
Parichha thermal power point PPTParichha thermal power point PPT
Parichha thermal power point PPT
ankit shrivastava
 
Basic mechanical engineeering- Power plants
Basic mechanical engineeering- Power plantsBasic mechanical engineeering- Power plants
Basic mechanical engineeering- Power plantsSteve M S
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
haxxo24
 
Bathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportBathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportLovesh Singla
 
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
PALANIVEL SUBBIAH
 
INTRODUCTION TO THERMAL POWER PLANTS
INTRODUCTION TO THERMAL POWER PLANTSINTRODUCTION TO THERMAL POWER PLANTS
INTRODUCTION TO THERMAL POWER PLANTSVanita Thakkar
 
Power from renewable energy
Power from renewable energyPower from renewable energy
Power from renewable energy
Balamurugan Subburaj
 
Chhattisgarh State Power Generation Company Limited
Chhattisgarh State Power Generation Company LimitedChhattisgarh State Power Generation Company Limited
Chhattisgarh State Power Generation Company Limited
Deepak Kurrey
 
Thermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit HingeThermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit Hinge
amit307
 
Ntpc training ppt
Ntpc training pptNtpc training ppt
Ntpc training ppt
ANKESH KUMAR
 
Combined operation of power plants
Combined operation of power plantsCombined operation of power plants
Combined operation of power plants
Nishkam Dhiman
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
abdul mohammad
 
Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants
Arnab Nandi
 

What's hot (20)

OBRA THERMAL POWER PLANT
OBRA THERMAL POWER PLANTOBRA THERMAL POWER PLANT
OBRA THERMAL POWER PLANT
 
Inplant training report
Inplant training reportInplant training report
Inplant training report
 
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
 
training reportON Thermal power plantt (nashik tps)pdf
 training reportON Thermal power plantt (nashik tps)pdf training reportON Thermal power plantt (nashik tps)pdf
training reportON Thermal power plantt (nashik tps)pdf
 
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESHppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
ppt on NTPC kahalgaon ,bhagalpur ( bihar) BY AKHILESH & PRIYESH
 
Summer Training Report on thermal power plant
Summer Training Report on thermal power plantSummer Training Report on thermal power plant
Summer Training Report on thermal power plant
 
Parichha thermal power point PPT
Parichha thermal power point PPTParichha thermal power point PPT
Parichha thermal power point PPT
 
Basic mechanical engineeering- Power plants
Basic mechanical engineeering- Power plantsBasic mechanical engineeering- Power plants
Basic mechanical engineeering- Power plants
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Bathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester reportBathinda thermal power plant mid semester report
Bathinda thermal power plant mid semester report
 
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
Unit 1 Coal based Power plants of Power Plant Engg (ME6701)
 
INTRODUCTION TO THERMAL POWER PLANTS
INTRODUCTION TO THERMAL POWER PLANTSINTRODUCTION TO THERMAL POWER PLANTS
INTRODUCTION TO THERMAL POWER PLANTS
 
Power from renewable energy
Power from renewable energyPower from renewable energy
Power from renewable energy
 
Chhattisgarh State Power Generation Company Limited
Chhattisgarh State Power Generation Company LimitedChhattisgarh State Power Generation Company Limited
Chhattisgarh State Power Generation Company Limited
 
Thermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit HingeThermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit Hinge
 
Ntpc training ppt
Ntpc training pptNtpc training ppt
Ntpc training ppt
 
Combined operation of power plants
Combined operation of power plantsCombined operation of power plants
Combined operation of power plants
 
report on VTPS
report on VTPSreport on VTPS
report on VTPS
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
 
Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants
 

Similar to Mini project presentation

Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
Amit Kumar
 
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESSTUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
Mohammed Sameer
 
Thermal Power Plant PPT
Thermal Power Plant PPTThermal Power Plant PPT
Thermal Power Plant PPT
parmod saharan
 
ppt on kstps 2016
ppt on kstps 2016ppt on kstps 2016
ppt on kstps 2016
Apoorva Sharma
 
Steam turbines
Steam turbinesSteam turbines
Steam turbines
Anil Redemption
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
Utkarsh Chaubey
 
Durgapur Projects Limited
Durgapur Projects LimitedDurgapur Projects Limited
Durgapur Projects Limited
Supriya Gorai
 
fluied power engineering
fluied power engineeringfluied power engineering
fluied power engineering
Mechanical Design Engineering
 
Themal power plant NTPC
Themal power plant NTPCThemal power plant NTPC
Themal power plant NTPC
Rahul Kurapati
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
Tarun Kumar
 
Boiler and cogeneration
Boiler and cogenerationBoiler and cogeneration
Boiler and cogeneration
Anshika Srivastava
 
Pm ppt
Pm pptPm ppt
Installation & Working of Coal Fired Thermal Power Plant
Installation & Working of Coal Fired Thermal Power PlantInstallation & Working of Coal Fired Thermal Power Plant
Installation & Working of Coal Fired Thermal Power Plant
Muhammad Awais
 
Dev
DevDev
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training Report
Shani Kumar Singh
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
Ranjan kumar
 
NTPC _Traning report_dhiraj
NTPC _Traning report_dhirajNTPC _Traning report_dhiraj
NTPC _Traning report_dhirajDhiraj Kumar
 
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
guru nanak institute of technology
 

Similar to Mini project presentation (20)

Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
 
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESSTUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
 
Thermal Power Plant PPT
Thermal Power Plant PPTThermal Power Plant PPT
Thermal Power Plant PPT
 
ppt on kstps 2016
ppt on kstps 2016ppt on kstps 2016
ppt on kstps 2016
 
Steam turbines
Steam turbinesSteam turbines
Steam turbines
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
 
Durgapur Projects Limited
Durgapur Projects LimitedDurgapur Projects Limited
Durgapur Projects Limited
 
fluied power engineering
fluied power engineeringfluied power engineering
fluied power engineering
 
Themal power plant NTPC
Themal power plant NTPCThemal power plant NTPC
Themal power plant NTPC
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
Boiler and cogeneration
Boiler and cogenerationBoiler and cogeneration
Boiler and cogeneration
 
Pm ppt
Pm pptPm ppt
Pm ppt
 
Installation & Working of Coal Fired Thermal Power Plant
Installation & Working of Coal Fired Thermal Power PlantInstallation & Working of Coal Fired Thermal Power Plant
Installation & Working of Coal Fired Thermal Power Plant
 
V.T ppt
V.T pptV.T ppt
V.T ppt
 
Dev
DevDev
Dev
 
CESC PROJECT
CESC PROJECTCESC PROJECT
CESC PROJECT
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training Report
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
 
NTPC _Traning report_dhiraj
NTPC _Traning report_dhirajNTPC _Traning report_dhiraj
NTPC _Traning report_dhiraj
 
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
 

Recently uploaded

ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 

Recently uploaded (20)

ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 

Mini project presentation

  • 1. SRI DAMODARAM SANJEEVIAH POWER STATION (APGENCO)
  • 3. Introduction REGION COAL GAS/Liquid Fuel Renewable TOTAL Northern 9,015 2,344 35 11,394 Western 12,000 1,313 50 13,313 Southern 4,600 360 260 5,220 Eastern 9,470 - 10 9,480 Islands - - 5 5 Hydro - - - 800 JVs 4,999 1,967 - 6,966 Total 40,084(MW) 5,984(MW) 360(MW) 47,228(MW)
  • 4. About APGENCO  APGENCO (NELLORE) is normally called as Sri Damodaram Sanjeeviah thermal power plant  APGENCO was setup in 2008 with 100% ownership by Government of AP. In the last 8 years, APGENCO has grown into the largest power utility in AP.  To meet the increasing power demand in state planned this mega power project in fast track basis.  The total installed capacity of super critical power plant is 2*800MW  APGENCO has plans to become 8,000MW company by 2032.  First Super Critical plant in AP is APGENCO (NELLORE) BAY OF BENGAL MADHYA PRADESH KARNATAKA TAMILNADU MAHARASHTRA CHITOOR CUDDAPAH ANANTHAPUR NELLORE KARNOOL PRAKASHAM MAHBOOBNAGAR GUNTUR KRISHNA NULGUNDA RANGAREDDY WARANGAL KHAMMAM KARIMNAGARNIZAMABAD MEDAK ADILABAD WEST EAST VIZAG GODAVARI GODAVARI VIJANAGARAM SRIKAKULAM Kothagudem TPSs 700 MW + 500 MW Vijayawada TPS 1760 MW Rayalaseema TPS 1050 MW Ramagundam TPS 62.5 MW Nellore TPS 1600 MW Total: 5670 MW
  • 5. PRINCIPLE OF THERMAL POWER PLANT  The Rankine cycle is an idealized thermodynamic cycle of a heat engine that converts heat into mechanical work.  This gives a theoretical maximum Carnot efficiency for the steam turbine alone of about 63% compared with an actual overall thermal efficiency of up to 42% for a modern coal-fired power station.  In an ideal Rankine cycle the pump and turbine would be isentropic, i.e., the pump and turbine would generate no entropy and hence maximize the net work output.
  • 6. 1. Cooling tower 10. Steam Control valve 19. Superheater 2. Cooling water pump 11. High pressure steam turbine 20. Forced draught (draft) fan 3. transmission line (3-phase) 12. Deaerator 21. Reheater 4. Step-up transformer (3- phase) 13. Feedwater heater 22. Combustion air intake 5. Electrical generator (3-phase) 14. Coal conveyor 23. Economiser 6. Low pressure steam turbine 15. Coal hopper 24. Air preheater 7. Condensate pump 16. Coal pulverizer 25. Precipitator 8. Surface condenser 17. Boiler steam drum 26. Induced draught (draft) fan 9. Intermediate pressure steam turbine 18. Bottom ash hopper 27. Flue gas stack Typical Diagram of a Coal-fired Thermal Power Station
  • 7. Problem Identification: Great difficulty in transportation of coal. Unavailability of good quality of coal. Problems of ash removal.
  • 8. Factors include Rake arrival schedules. Changes in production scheduling. Deviation from delivery rates etc. These can be reduced by Simultaneous arrival of rake. Modeling approach. queing approach.
  • 9.
  • 11. Why Multi Stage turbines are used? Multistage turbines are back pressure turbines that can be made available in form of single stage or multi-stage options. These turbines find application for drive application/power generation applications and are of straight-back pressure type. Finding application in areas where back pressure steam is fully utilized, the power generation is incidental to process steam demands.
  • 12. Components of Steam Turbine Cycle 1. High Pressure Turbine (HP Turbine) 2. Intermediate Pressure Turbine (IP Turbine) 3. Low Pressure Turbine (LP Turbine) 4. Condenser 5. Cooling Tower 6. Low Pressure Heater (LP Heater) 7. Deaerator 8. High Pressure Heater (HP Heater) 9. Motor Driven Boiler Feed Pump (MDBFP) 10. Turbine Driven Boiler Feed Pump (TDBFP)
  • 13. 165 ksc, 540°C 40 ksc, 350°C 45 ksc, 565°C 7-8 ksc, 350°C 6 ksc, 160°C 0.1 ksc, 45°C 0.1 ksc, 45°C ΔT=10°C 5 3 2 2*121*17 2*6 (BFP)
  • 14. High Pressure Turbine (HP Turbine)  High pressure and temperature fluid at the inlet of the turbine exit as lower pressure and temperature fluid. The difference is energy converted by the turbine to mechanical rotational energy, less any aerodynamic and mechanical in efficiencies incurred in the process.  The high pressure casing is made of creep resisting Chromium- molybdenum-vanadium(Cr-Mo-V) steel casting.  The turbine is equipped with emergency stop valves to cut of steam supply and with control valves to regulate supply.  It has 17 rotor blades with first impulse stage and others are reaction.
  • 15. Intermediate Pressure Turbine (IP Turbine)  Intermediate pressure turbine having more pressure then L.P turbine and less than the high pressure turbine(H.P) . Its blade is larger than high pressure turbine.  The size of blades of I.P steam turbine is larger than H.P steam turbine , but smaller than L.P steam turbine.  It has inlet of the main steam line after the reheat process and in outlet main steam line straight goes to lp turbine.  It has 2*12 stage of blades and 7th stage steam line goes to TDBFP.
  • 16. Low Pressure Turbine (LP Turbine)  LP turbine is designed to be a dual flow turbine. Steam enters the centre of the turbine from the crossover pipe and flows across the reaction blading in two opposite directions.  This configuration reduces axial thrust on the turbine and allows for a smaller turbine installation.  Titanium alloys offer high strength to intermediate temperatures at a density almost half that of steel and nickel-based super alloys.  LP blade is larger than HP & IP.
  • 17.
  • 18. Steps involved in design of Steam Turbine 1. Perform thermodynamic and axial thrust calculations to decide diameters and axial length of blading. 2. Perform rotor dynamic calculation and suggest any change of lengths and diameters to repeat step one. 3. Select suitable turbine extensions and diameters to meet above blading geometry. 4. Select suitable materials to meet steam parameters. 5. Select suitable governing system and protection system. 6. Prepare ordering / manufacturing documents incorporating above selections.