SlideShare a Scribd company logo
1 of 11
MINI CASE
Project Management at MM2
“We’ve got a real ‘warm puppy’ here,” Brian Smith told Werner
McCann. “Make sure
you make the most of it. We could use a winner.”
Smith was MM’s CIO, and McCann was his top project
manager. The puppy in
question was MM’s new venture into direct-to-customer
marketing of its green meters, a
product designed to help better manage electrical consumption,
and the term referred
to the project’s wide appeal. The strategy had been a hit with
analysts ever since it had
been revealed to the financial community, and the company’s
stock was doing extremely
well as a result. “At last,” one had written in his popular
newsletter, “we have a com-
pany that is willing to put power literally and figuratively in
consumers’ hands. If MM
can deliver on its promises, we fully expect this company to
reap the rewards.”
Needless to say, the Green project was popular internally, too.
“I’m giving it to you
because you have the most project-management experience
we’ve got,” Smith had said.
“There’s a lot riding on this one.” As he walked away from
Smith’s office, McCann wasn’t
sure whether to feel complimented or terrified. He had certainly
managed some success-
ful projects for the company (previously known as ModMeters)
over the past five years
but never anything like this one. That’s the problem with
project management, he thought. In
IT almost every project is completely different. Experience only
takes you part of the way.
And Green was different. It was the first truly enterprisewide
project the com-
pany had ever done, and McCann was having conniptions as he
thought about telling
Fred Tompkins, the powerful head of manufacturing, that he
might not be able to have
everything his own way. McCann knew that, to be successful,
this project had to take an
outside-in approach—that is, to take the end customers’ point of
view on the company.
That meant integrating marketing, ordering, manufacturing,
shipping, and service
into one seamless process that wouldn’t bounce the customer
from one department to
another in the company. MM had always had separate systems
for each of its “silos,”
and this project would work against the company’s traditional
culture and processes.
The Green project was also going to have to integrate with IT’s
information manage-
ment renewal (IMR) project. Separate silos had always meant
separate databases, and
the IMR project was supposed to resolve inconsistencies among
them and provide
accurate and integrated information to different parts of the
company. This was a huge
political challenge, but, unless it worked, McCann couldn’t
deliver on his mandate.
Then there was the issue of resources. McCann groaned at the
thought. MM had
some good people but not enough to get through all of the
projects in the IT plan within
the promised timelines. Because of the importance of the Green
project, he knew he’d
get good cooperation on staffing, but the fact remained that he
would have to go out-
side for some of the technical skills he needed to get the job
done. Finally, there was the
schedule that had to be met. Somehow, during the preliminary
assessment phase, it
2 Smith, H. A., and J. D. McKeen. “Project Management at
MM.” #1-L05-1-009, Queen’s School of Business,
November 2005. Reproduced by permission of Queen’s
University, School of Business, Kingston, Ontario.
324
Project Management at MM 325
had become clear that September 5 was to be the “hard launch”
date. There were good
reasons for this—the fall was when consumers usually became
concerned with their
energy consumption—but McCann worried that a date barely
twelve months from now
would put too much pressure on his team. “We’ve got to get in
there first, before the
competition,” Smith had said to him. “The board expects us to
deliver. You’ve got my
backing and the support of the full executive team, but you have
to deliver this one.”
SIX WEEKS LATER
It was full steam ahead on the Green project. It’s amazing what
a board mandate and
executive sponsorship can do for a project, thought McCann,
who knew how hard it usu-
ally was to get business attention to IT initiatives. He now had a
full-time business coun-
terpart, Raj Sambamurthy. Samba, as he was known to his
colleagues, had come out of
Tompkins’s division and was doing a fantastic job of getting the
right people in the room
to make the decisions they needed to move ahead. The Green
steering committee was no
Mickey Mouse group either. Smith, Tompkins, and every VP
affected by the project were
meeting biweekly with him and Samba to review every aspect of
the project’s progress.
McCann had pulled no punches when communicating with the
committee.
“You’ve given me the mandate and the budget to get this project
off the ground,” he had
told them. “But we have to be clear about what we’re trying to
accomplish.” Together,
they had hammered out a value proposition that emphasized the
strategic value of the
project and some of the measures they would use to monitor its
ultimate success. The
requirements and design phase had also gone smoothly because
everyone was so moti-
vated to ensure the project’s success. “Linking success to all
our annual bonuses sure
helped that!” McCann had remarked wryly to Samba.
Now McCann was beginning to pull together his dream team of
implementers.
The team had chosen a package known as Web-4-U as the front
end of the project, but it
would take a lot of work to customize it to suit their unique
product and, even more, to
integrate it with MM’s outmoded back-end systems. The Web-4-
U company was based
in Ireland but had promised to provide 24/7 consultation on an
as-needed basis. In
addition, Samba had now assembled a small team of business
analysts to work on the
business processes they would need. They were working out of
the firm’s Cloverdale
office, a thirty-minute drive from IT’s downtown location. (It
was a shame they couldn’t
all be together, but space was at a premium at headquarters.
McCann made a mental
note to look into some new collaboration software he’d heard
about.) Now that these
two pieces were in place, McCann felt free to focus on the
technical “guts” of the sys-
tem. “Maybe this will work out after all,” he said.
THREE MONTHS TO LAUNCH DATE
By June, however, McCann was tearing out what little hair was
left on his head. He
was seriously considering moving to a remote Peruvian hamlet
and breeding llamas.
“Anything would be better than this mess,” he told Yung Lee,
the senior IT architect,
over coffee. They were poring over the project’s critical path.
“The way I see it,” Lee
stated matter-of-factly, “we have two choices: We can continue
with this inferior tech-
nology and meet our deadline but not deliver on our
functionality, or we can redo the
plan and go back to the steering committee with a revised
delivery date and budget.”
326� 4FDUJPO�*7� r�
*5�1PSUGPMJP�%FWFMPQNFOU�BOE�.BOBHFNFOU
McCann sighed. Techies always saw things in black and white,
but his world
contained much more gray. And so much was riding on this—
credibility (his, IT’s, the
company’s), competitiveness, and stock price. He dreaded being
the bearer of this bad
news, so he said, “Let’s go over this one more time.”
“It’s not going to get any better, but here goes.” Lee took a deep
breath. “Web-4-U
is based on outmoded technology. It was the best available last
year, but this year the
industry has agreed on a new standard, and if we persist in
using Web-4-U, we are
going to be out of date before Green even hits the street. We
need to go back and com-
pletely rethink our technical approach based on the new
standard and then redesign
our Web interface. I know it’s a setback and expensive, but it
has to be done.”
“How come we didn’t know about this earlier?” McCann
demanded.
Lee replied, “When the standard was announced, we didn’t
realize what the
implications were at first. It was only in our quarterly
architecture meeting that the
subject came up. That’s why I’m here now.” The architects were
a breed apart, thought
McCann. All tech and no business sense. They’d lost almost
three months because of
this. “By the way,” Lee concluded, “Web-4-U knew about this,
too. They’re scrambling
to rewrite their code. I guess they figured if you didn’t know
right away, there would be
more chance of you sticking with them.”
The chances of that are slim to none, thought McCann. His next
software provider,
whoever that was, was going to be sitting right here under his
steely gaze. Seeing an
agitated Wendy Chan at his door, he brought the meeting to a
hasty close. “I’m going
to have to discuss this with Brian,” he told Lee. “We can’t
surprise him with this at the
steering committee meeting. Hang tight for a couple of days,
and I’ll get back to you.”
“OK,” said Lee, “but remember that we’re wasting time.”
Easy for you to say, thought McCann as he gestured Chan into
his office. She was
his counterpart at the IMR project, and they had always had a
good working relationship.
“I just wanted to give you a heads-up that we’ve got a serious
problem at IMR that will
affect you,” she began. Llamas began prancing into his mind’s
eye. “Tompkins is refus-
ing to switch to our new data dictionary. We’ve spent months
hammering this out with
the team, but he says he wasn’t kept informed about the
implications of the changes, and
now he’s refusing to play ball. I don’t know how he could say
that. He’s had a rep on the
team from the beginning, and we’ve been sending him regular
progress reports.”
McCann was copied on those reports. Their pages of techno-
jargon would put
anyone to sleep! He was sure that Tompkins had never got past
the first page of any of
those reports. His rep was a dweeb, too, someone Tompkins
thought he could live with-
out in his daily operations.
“Damn! This is something I don’t need.” Like all IT guys,
McCann hated corpo-
rate politics with a passion. He didn’t understand them and
wasn’t good at them. Why
hadn’t Samba and his team picked up on this? They were
plugged into the business.
Now he was going to have to deal with Chan’s problem as well
as his own if he wanted
to get the Green project going. Their back-end processes
wouldn’t work at all unless
everyone was using the same information in the same format.
Why couldn’t Tompkins
see that? Did he want the Green project to fail?
“The best way to deal with this one,” advised Chan, “is to force
him to accept
these changes. Go to John Johnson and tell him that you need
Tompkins to change his
business processes to fit our data dictionary. It’s for the good of
the company, after all.”
Chan’s strong suit wasn’t her political savvy.
Project Management at MM 327
“You’re right that we need Tompkins on our side,” said
McCann, “but there may
be a better way. Let me talk to Samba. He’s got his ear to the
ground in the business.
I’ll speak with him and get back to you.”
After a bit of chitchat, Wendy Chan left McCann to his PERT
chart, trying again
to determine the extra cost in time if they went with the new
technology. Just then
the phone rang. It was Linda Perkins, McCann’s newly hired
work-at-home usability
designer. She was one of the best in the business, and he was
lucky to have snagged her
just coming off maternity leave. His promise of flexible
working hours and full benefits
had lured her back to work two months before her year-long
leave ended. “You’ve got
to do something about your HR department!” Perkins
announced. “They’ve just told
me that I’m not eligible for health and dental benefits because I
don’t work on the prem-
ises! Furthermore, they want to classify me as contingent staff,
not managerial, because
I don’t fit in one of their petty little categories for employees.
You promised me that you
had covered all this before I took the job! I gave up a good job
at LifeCo so I could work
from home.”
McCann had indeed covered this issue in principle with Rick
Morrow, IT’s HR
representative, but that had been almost eight months ago.
Morrow had since left the
firm. McCann wondered if he had left any paperwork on this
matter. The HR IT spot
had not yet been filled, and all of the IT managers were upset
about HR’s unreceptive
attitude when it came to adapting its policies to the realities of
today’s IT world. “OK,
Linda, just hang in there for a day or two and I’ll get this all
sorted out,” he promised.
“How’s the usability testing coming along?”
“That’s another thing I wanted to talk with you about. The
team’s making changes
to the look and feel of the product without consulting me,” she
fumed. “I can’t do my
job without being in the loop. You have to make them tell me
when they’re doing things
like this.”
McCann sighed. Getting Perkins on the project had been such a
coup that he
hadn’t given much thought to how the lines of communication
would work within
such a large team. “I hear you, Linda, and we’ll work this out.
Can you just give me a
few days to figure out how we can improve things?”
Hanging up, he grabbed his jacket and slunk out of the office as
quickly as he
could before any other problems could present themselves. If he
just kept walking
south, he’d make it to the Andes in three, maybe four, months.
He could teach him-
self Spanish along the way. At least the llamas would appreciate
his efforts! MM could
take its project and give it to some other poor schmuck. No way
was he going back! He
walked furiously down the street, mentally ticking off the
reasons he had been a fool to
fall for Smith’s sweet talk. Then, unbidden, a plan of attack
formed in his head. Walking
always did the trick. Getting out of the office cleared his head
and focused his priorities.
He turned back the way he had come, now eager to get back in
the fray. He had some
things to do right away, and others he had to put in place ASAP.
Discussion Questions
1. Some organizational factors increase a project’s likelihood
of success. Identify these
“facilitators” for the Green project.
2. Other organizational factors decrease a project’s likelihood
of success. Identify these
“barriers” for the Green project.
3. Outline the things that McCann needs to do right away.

More Related Content

Similar to Mini CaseProject Management at MM2We’ve got a real ‘war.docx

Mini CaseIT Planning at ModMeters4Brian Smith, CIO of Mo.docx
Mini CaseIT Planning at ModMeters4Brian Smith, CIO of Mo.docxMini CaseIT Planning at ModMeters4Brian Smith, CIO of Mo.docx
Mini CaseIT Planning at ModMeters4Brian Smith, CIO of Mo.docx
audeleypearl
 
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docxNeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
gertrudebellgrove
 
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docxNeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
poulterbarbara
 
Designing digital transformation v.2.7
Designing digital transformation v.2.7Designing digital transformation v.2.7
Designing digital transformation v.2.7
Nigel Green
 
Submit a report that discusses the techniques used by malware deve.docx
Submit a report that discusses the techniques used by malware deve.docxSubmit a report that discusses the techniques used by malware deve.docx
Submit a report that discusses the techniques used by malware deve.docx
david4611
 
Teem Fivve ver 4.0
Teem Fivve ver 4.0Teem Fivve ver 4.0
Teem Fivve ver 4.0
Codie Leigh
 
New foldercssstyles.css The navbar container .topnav .docx
New foldercssstyles.css The navbar container .topnav .docxNew foldercssstyles.css The navbar container .topnav .docx
New foldercssstyles.css The navbar container .topnav .docx
vannagoforth
 
Death by Google Alerts: 461 Pages of Social Media Competitive Analysis in 3 W...
Death by Google Alerts: 461 Pages of Social Media Competitive Analysis in 3 W...Death by Google Alerts: 461 Pages of Social Media Competitive Analysis in 3 W...
Death by Google Alerts: 461 Pages of Social Media Competitive Analysis in 3 W...
Jamison K. Bell | OvenPOP 360
 

Similar to Mini CaseProject Management at MM2We’ve got a real ‘war.docx (20)

Mini CaseIT Planning at ModMeters4Brian Smith, CIO of Mo.docx
Mini CaseIT Planning at ModMeters4Brian Smith, CIO of Mo.docxMini CaseIT Planning at ModMeters4Brian Smith, CIO of Mo.docx
Mini CaseIT Planning at ModMeters4Brian Smith, CIO of Mo.docx
 
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docxNeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
 
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docxNeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
NeuroscienceResourcesStahl, S. M. (2013). Stahl’s ess.docx
 
The Amazing Ways Artificial Intelligence (AI) Can Now Detect Dangers At Work
The Amazing Ways Artificial Intelligence (AI) Can Now Detect Dangers At WorkThe Amazing Ways Artificial Intelligence (AI) Can Now Detect Dangers At Work
The Amazing Ways Artificial Intelligence (AI) Can Now Detect Dangers At Work
 
Marketing Portfolio
Marketing PortfolioMarketing Portfolio
Marketing Portfolio
 
Connected planning for construction
Connected planning for constructionConnected planning for construction
Connected planning for construction
 
Designing digital transformation v.2.7
Designing digital transformation v.2.7Designing digital transformation v.2.7
Designing digital transformation v.2.7
 
Turnround at the Preston Plant
Turnround at the Preston PlantTurnround at the Preston Plant
Turnround at the Preston Plant
 
Submit a report that discusses the techniques used by malware deve.docx
Submit a report that discusses the techniques used by malware deve.docxSubmit a report that discusses the techniques used by malware deve.docx
Submit a report that discusses the techniques used by malware deve.docx
 
Teem Fivve ver 4.0
Teem Fivve ver 4.0Teem Fivve ver 4.0
Teem Fivve ver 4.0
 
New foldercssstyles.css The navbar container .topnav .docx
New foldercssstyles.css The navbar container .topnav .docxNew foldercssstyles.css The navbar container .topnav .docx
New foldercssstyles.css The navbar container .topnav .docx
 
Binder1
Binder1Binder1
Binder1
 
Ad Week Europe, B2B Forum- The Future of B2B: The Rise of the Data-Driven, Cu...
Ad Week Europe, B2B Forum- The Future of B2B: The Rise of the Data-Driven, Cu...Ad Week Europe, B2B Forum- The Future of B2B: The Rise of the Data-Driven, Cu...
Ad Week Europe, B2B Forum- The Future of B2B: The Rise of the Data-Driven, Cu...
 
Northwestern University Building Tech Symposium Summary
Northwestern University Building Tech Symposium  SummaryNorthwestern University Building Tech Symposium  Summary
Northwestern University Building Tech Symposium Summary
 
Gene and Mik Summarize Their Favorite Talks from DOES 2017
Gene and Mik Summarize Their Favorite Talks from DOES 2017Gene and Mik Summarize Their Favorite Talks from DOES 2017
Gene and Mik Summarize Their Favorite Talks from DOES 2017
 
M2M and Venture Capital
M2M and Venture CapitalM2M and Venture Capital
M2M and Venture Capital
 
Wk9
Wk9 Wk9
Wk9
 
Digital disruption and the uncertain times we live in
Digital disruption and the uncertain times we live inDigital disruption and the uncertain times we live in
Digital disruption and the uncertain times we live in
 
Death by Google Alerts: 461 Pages of Social Media Competitive Analysis in 3 W...
Death by Google Alerts: 461 Pages of Social Media Competitive Analysis in 3 W...Death by Google Alerts: 461 Pages of Social Media Competitive Analysis in 3 W...
Death by Google Alerts: 461 Pages of Social Media Competitive Analysis in 3 W...
 
Scan2us
Scan2usScan2us
Scan2us
 

More from altheaboyer

InstructionsUsing theWeek 5 research template identify.docx
InstructionsUsing theWeek 5 research template identify.docxInstructionsUsing theWeek 5 research template identify.docx
InstructionsUsing theWeek 5 research template identify.docx
altheaboyer
 
InstructionsWritten Assignment 1The purpose of this assignment i.docx
InstructionsWritten Assignment 1The purpose of this assignment i.docxInstructionsWritten Assignment 1The purpose of this assignment i.docx
InstructionsWritten Assignment 1The purpose of this assignment i.docx
altheaboyer
 
InstructionsPlease complete the required federal corporation .docx
InstructionsPlease complete the required federal corporation .docxInstructionsPlease complete the required federal corporation .docx
InstructionsPlease complete the required federal corporation .docx
altheaboyer
 
InstructionsHW Assignments will be uploaded to Kean Blackboard a.docx
InstructionsHW Assignments will be uploaded to Kean Blackboard a.docxInstructionsHW Assignments will be uploaded to Kean Blackboard a.docx
InstructionsHW Assignments will be uploaded to Kean Blackboard a.docx
altheaboyer
 
instructions1.   Create an APA-style Title Page for this assignm.docx
instructions1.   Create an APA-style Title Page for this assignm.docxinstructions1.   Create an APA-style Title Page for this assignm.docx
instructions1.   Create an APA-style Title Page for this assignm.docx
altheaboyer
 
Instructions1. Create an APA-style Title Page for this a.docx
Instructions1. Create an APA-style Title Page for this a.docxInstructions1. Create an APA-style Title Page for this a.docx
Instructions1. Create an APA-style Title Page for this a.docx
altheaboyer
 
InstructionsDirections Be sure to make an electronic copy of your.docx
InstructionsDirections Be sure to make an electronic copy of your.docxInstructionsDirections Be sure to make an electronic copy of your.docx
InstructionsDirections Be sure to make an electronic copy of your.docx
altheaboyer
 
InstructionsDisciplinary Assignment Part 1 Instructions.docx
InstructionsDisciplinary Assignment Part 1 Instructions.docxInstructionsDisciplinary Assignment Part 1 Instructions.docx
InstructionsDisciplinary Assignment Part 1 Instructions.docx
altheaboyer
 
InstructionsFor this assignment propose a scenario where you.docx
InstructionsFor this assignment propose a scenario where you.docxInstructionsFor this assignment propose a scenario where you.docx
InstructionsFor this assignment propose a scenario where you.docx
altheaboyer
 
instructions1.   Create an APA-style Title Page for this assig.docx
instructions1.   Create an APA-style Title Page for this assig.docxinstructions1.   Create an APA-style Title Page for this assig.docx
instructions1.   Create an APA-style Title Page for this assig.docx
altheaboyer
 

More from altheaboyer (20)

InstructionsUNIXLinux Versus Mac Versus WindowsWrite a 4.docx
InstructionsUNIXLinux Versus Mac Versus WindowsWrite a 4.docxInstructionsUNIXLinux Versus Mac Versus WindowsWrite a 4.docx
InstructionsUNIXLinux Versus Mac Versus WindowsWrite a 4.docx
 
InstructionsUsing theWeek 5 research template identify.docx
InstructionsUsing theWeek 5 research template identify.docxInstructionsUsing theWeek 5 research template identify.docx
InstructionsUsing theWeek 5 research template identify.docx
 
InstructionsWritten Assignment 1The purpose of this assignment i.docx
InstructionsWritten Assignment 1The purpose of this assignment i.docxInstructionsWritten Assignment 1The purpose of this assignment i.docx
InstructionsWritten Assignment 1The purpose of this assignment i.docx
 
InstructionsRead the assigned article by Linstrom (2004), an.docx
InstructionsRead the assigned article by Linstrom (2004), an.docxInstructionsRead the assigned article by Linstrom (2004), an.docx
InstructionsRead the assigned article by Linstrom (2004), an.docx
 
InstructionsPlease complete the required federal corporation .docx
InstructionsPlease complete the required federal corporation .docxInstructionsPlease complete the required federal corporation .docx
InstructionsPlease complete the required federal corporation .docx
 
InstructionsHW Assignments will be uploaded to Kean Blackboard a.docx
InstructionsHW Assignments will be uploaded to Kean Blackboard a.docxInstructionsHW Assignments will be uploaded to Kean Blackboard a.docx
InstructionsHW Assignments will be uploaded to Kean Blackboard a.docx
 
InstructionsDue within 6-7 hoursSelect a past act of terrorism.docx
InstructionsDue within 6-7 hoursSelect a past act of terrorism.docxInstructionsDue within 6-7 hoursSelect a past act of terrorism.docx
InstructionsDue within 6-7 hoursSelect a past act of terrorism.docx
 
INSTRUCTIONSA detailed and thoughtful response Minimum of 500 wor.docx
INSTRUCTIONSA detailed and thoughtful response Minimum of 500 wor.docxINSTRUCTIONSA detailed and thoughtful response Minimum of 500 wor.docx
INSTRUCTIONSA detailed and thoughtful response Minimum of 500 wor.docx
 
InstructionsDevelop a six-to-eight-page document in Word format d.docx
InstructionsDevelop a six-to-eight-page document in Word format d.docxInstructionsDevelop a six-to-eight-page document in Word format d.docx
InstructionsDevelop a six-to-eight-page document in Word format d.docx
 
InstructionsCheck with TURN IT IN Create a portable forensi.docx
InstructionsCheck with TURN IT IN Create a portable forensi.docxInstructionsCheck with TURN IT IN Create a portable forensi.docx
InstructionsCheck with TURN IT IN Create a portable forensi.docx
 
InstructionsContent ReviewDirectionsRespond to each item. Eac.docx
InstructionsContent ReviewDirectionsRespond to each item. Eac.docxInstructionsContent ReviewDirectionsRespond to each item. Eac.docx
InstructionsContent ReviewDirectionsRespond to each item. Eac.docx
 
instructions1.   Create an APA-style Title Page for this assignm.docx
instructions1.   Create an APA-style Title Page for this assignm.docxinstructions1.   Create an APA-style Title Page for this assignm.docx
instructions1.   Create an APA-style Title Page for this assignm.docx
 
Instructions1. Prepare a bank reconciliation.2. Journalize the n.docx
Instructions1. Prepare a bank reconciliation.2. Journalize the n.docxInstructions1. Prepare a bank reconciliation.2. Journalize the n.docx
Instructions1. Prepare a bank reconciliation.2. Journalize the n.docx
 
Instructions1. Create an APA-style Title Page for this a.docx
Instructions1. Create an APA-style Title Page for this a.docxInstructions1. Create an APA-style Title Page for this a.docx
Instructions1. Create an APA-style Title Page for this a.docx
 
Instructions You are responsible for creating a healthcare system .docx
Instructions You are responsible for creating a healthcare system .docxInstructions You are responsible for creating a healthcare system .docx
Instructions You are responsible for creating a healthcare system .docx
 
Instructions  Create a 1-2 page questionnaire for your patients .docx
Instructions  Create a 1-2 page questionnaire for your patients .docxInstructions  Create a 1-2 page questionnaire for your patients .docx
Instructions  Create a 1-2 page questionnaire for your patients .docx
 
InstructionsDirections Be sure to make an electronic copy of your.docx
InstructionsDirections Be sure to make an electronic copy of your.docxInstructionsDirections Be sure to make an electronic copy of your.docx
InstructionsDirections Be sure to make an electronic copy of your.docx
 
InstructionsDisciplinary Assignment Part 1 Instructions.docx
InstructionsDisciplinary Assignment Part 1 Instructions.docxInstructionsDisciplinary Assignment Part 1 Instructions.docx
InstructionsDisciplinary Assignment Part 1 Instructions.docx
 
InstructionsFor this assignment propose a scenario where you.docx
InstructionsFor this assignment propose a scenario where you.docxInstructionsFor this assignment propose a scenario where you.docx
InstructionsFor this assignment propose a scenario where you.docx
 
instructions1.   Create an APA-style Title Page for this assig.docx
instructions1.   Create an APA-style Title Page for this assig.docxinstructions1.   Create an APA-style Title Page for this assig.docx
instructions1.   Create an APA-style Title Page for this assig.docx
 

Recently uploaded

Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 

Recently uploaded (20)

2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 

Mini CaseProject Management at MM2We’ve got a real ‘war.docx

  • 1. MINI CASE Project Management at MM2 “We’ve got a real ‘warm puppy’ here,” Brian Smith told Werner McCann. “Make sure you make the most of it. We could use a winner.” Smith was MM’s CIO, and McCann was his top project manager. The puppy in question was MM’s new venture into direct-to-customer marketing of its green meters, a product designed to help better manage electrical consumption, and the term referred to the project’s wide appeal. The strategy had been a hit with analysts ever since it had been revealed to the financial community, and the company’s stock was doing extremely well as a result. “At last,” one had written in his popular newsletter, “we have a com- pany that is willing to put power literally and figuratively in consumers’ hands. If MM can deliver on its promises, we fully expect this company to reap the rewards.” Needless to say, the Green project was popular internally, too. “I’m giving it to you because you have the most project-management experience we’ve got,” Smith had said. “There’s a lot riding on this one.” As he walked away from Smith’s office, McCann wasn’t sure whether to feel complimented or terrified. He had certainly managed some success-
  • 2. ful projects for the company (previously known as ModMeters) over the past five years but never anything like this one. That’s the problem with project management, he thought. In IT almost every project is completely different. Experience only takes you part of the way. And Green was different. It was the first truly enterprisewide project the com- pany had ever done, and McCann was having conniptions as he thought about telling Fred Tompkins, the powerful head of manufacturing, that he might not be able to have everything his own way. McCann knew that, to be successful, this project had to take an outside-in approach—that is, to take the end customers’ point of view on the company. That meant integrating marketing, ordering, manufacturing, shipping, and service into one seamless process that wouldn’t bounce the customer from one department to another in the company. MM had always had separate systems for each of its “silos,” and this project would work against the company’s traditional culture and processes. The Green project was also going to have to integrate with IT’s information manage- ment renewal (IMR) project. Separate silos had always meant separate databases, and the IMR project was supposed to resolve inconsistencies among them and provide accurate and integrated information to different parts of the company. This was a huge political challenge, but, unless it worked, McCann couldn’t deliver on his mandate.
  • 3. Then there was the issue of resources. McCann groaned at the thought. MM had some good people but not enough to get through all of the projects in the IT plan within the promised timelines. Because of the importance of the Green project, he knew he’d get good cooperation on staffing, but the fact remained that he would have to go out- side for some of the technical skills he needed to get the job done. Finally, there was the schedule that had to be met. Somehow, during the preliminary assessment phase, it 2 Smith, H. A., and J. D. McKeen. “Project Management at MM.” #1-L05-1-009, Queen’s School of Business, November 2005. Reproduced by permission of Queen’s University, School of Business, Kingston, Ontario. 324 Project Management at MM 325 had become clear that September 5 was to be the “hard launch” date. There were good reasons for this—the fall was when consumers usually became concerned with their energy consumption—but McCann worried that a date barely twelve months from now would put too much pressure on his team. “We’ve got to get in there first, before the competition,” Smith had said to him. “The board expects us to deliver. You’ve got my backing and the support of the full executive team, but you have to deliver this one.”
  • 4. SIX WEEKS LATER It was full steam ahead on the Green project. It’s amazing what a board mandate and executive sponsorship can do for a project, thought McCann, who knew how hard it usu- ally was to get business attention to IT initiatives. He now had a full-time business coun- terpart, Raj Sambamurthy. Samba, as he was known to his colleagues, had come out of Tompkins’s division and was doing a fantastic job of getting the right people in the room to make the decisions they needed to move ahead. The Green steering committee was no Mickey Mouse group either. Smith, Tompkins, and every VP affected by the project were meeting biweekly with him and Samba to review every aspect of the project’s progress. McCann had pulled no punches when communicating with the committee. “You’ve given me the mandate and the budget to get this project off the ground,” he had told them. “But we have to be clear about what we’re trying to accomplish.” Together, they had hammered out a value proposition that emphasized the strategic value of the project and some of the measures they would use to monitor its ultimate success. The requirements and design phase had also gone smoothly because everyone was so moti- vated to ensure the project’s success. “Linking success to all our annual bonuses sure helped that!” McCann had remarked wryly to Samba.
  • 5. Now McCann was beginning to pull together his dream team of implementers. The team had chosen a package known as Web-4-U as the front end of the project, but it would take a lot of work to customize it to suit their unique product and, even more, to integrate it with MM’s outmoded back-end systems. The Web-4- U company was based in Ireland but had promised to provide 24/7 consultation on an as-needed basis. In addition, Samba had now assembled a small team of business analysts to work on the business processes they would need. They were working out of the firm’s Cloverdale office, a thirty-minute drive from IT’s downtown location. (It was a shame they couldn’t all be together, but space was at a premium at headquarters. McCann made a mental note to look into some new collaboration software he’d heard about.) Now that these two pieces were in place, McCann felt free to focus on the technical “guts” of the sys- tem. “Maybe this will work out after all,” he said. THREE MONTHS TO LAUNCH DATE By June, however, McCann was tearing out what little hair was left on his head. He was seriously considering moving to a remote Peruvian hamlet and breeding llamas. “Anything would be better than this mess,” he told Yung Lee, the senior IT architect, over coffee. They were poring over the project’s critical path. “The way I see it,” Lee stated matter-of-factly, “we have two choices: We can continue with this inferior tech-
  • 6. nology and meet our deadline but not deliver on our functionality, or we can redo the plan and go back to the steering committee with a revised delivery date and budget.” 326� 4FDUJPO�*7� r� *5�1PSUGPMJP�%FWFMPQNFOU�BOE�.BOBHFNFOU McCann sighed. Techies always saw things in black and white, but his world contained much more gray. And so much was riding on this— credibility (his, IT’s, the company’s), competitiveness, and stock price. He dreaded being the bearer of this bad news, so he said, “Let’s go over this one more time.” “It’s not going to get any better, but here goes.” Lee took a deep breath. “Web-4-U is based on outmoded technology. It was the best available last year, but this year the industry has agreed on a new standard, and if we persist in using Web-4-U, we are going to be out of date before Green even hits the street. We need to go back and com- pletely rethink our technical approach based on the new standard and then redesign our Web interface. I know it’s a setback and expensive, but it has to be done.” “How come we didn’t know about this earlier?” McCann demanded. Lee replied, “When the standard was announced, we didn’t realize what the
  • 7. implications were at first. It was only in our quarterly architecture meeting that the subject came up. That’s why I’m here now.” The architects were a breed apart, thought McCann. All tech and no business sense. They’d lost almost three months because of this. “By the way,” Lee concluded, “Web-4-U knew about this, too. They’re scrambling to rewrite their code. I guess they figured if you didn’t know right away, there would be more chance of you sticking with them.” The chances of that are slim to none, thought McCann. His next software provider, whoever that was, was going to be sitting right here under his steely gaze. Seeing an agitated Wendy Chan at his door, he brought the meeting to a hasty close. “I’m going to have to discuss this with Brian,” he told Lee. “We can’t surprise him with this at the steering committee meeting. Hang tight for a couple of days, and I’ll get back to you.” “OK,” said Lee, “but remember that we’re wasting time.” Easy for you to say, thought McCann as he gestured Chan into his office. She was his counterpart at the IMR project, and they had always had a good working relationship. “I just wanted to give you a heads-up that we’ve got a serious problem at IMR that will affect you,” she began. Llamas began prancing into his mind’s eye. “Tompkins is refus- ing to switch to our new data dictionary. We’ve spent months hammering this out with the team, but he says he wasn’t kept informed about the
  • 8. implications of the changes, and now he’s refusing to play ball. I don’t know how he could say that. He’s had a rep on the team from the beginning, and we’ve been sending him regular progress reports.” McCann was copied on those reports. Their pages of techno- jargon would put anyone to sleep! He was sure that Tompkins had never got past the first page of any of those reports. His rep was a dweeb, too, someone Tompkins thought he could live with- out in his daily operations. “Damn! This is something I don’t need.” Like all IT guys, McCann hated corpo- rate politics with a passion. He didn’t understand them and wasn’t good at them. Why hadn’t Samba and his team picked up on this? They were plugged into the business. Now he was going to have to deal with Chan’s problem as well as his own if he wanted to get the Green project going. Their back-end processes wouldn’t work at all unless everyone was using the same information in the same format. Why couldn’t Tompkins see that? Did he want the Green project to fail? “The best way to deal with this one,” advised Chan, “is to force him to accept these changes. Go to John Johnson and tell him that you need Tompkins to change his business processes to fit our data dictionary. It’s for the good of the company, after all.” Chan’s strong suit wasn’t her political savvy.
  • 9. Project Management at MM 327 “You’re right that we need Tompkins on our side,” said McCann, “but there may be a better way. Let me talk to Samba. He’s got his ear to the ground in the business. I’ll speak with him and get back to you.” After a bit of chitchat, Wendy Chan left McCann to his PERT chart, trying again to determine the extra cost in time if they went with the new technology. Just then the phone rang. It was Linda Perkins, McCann’s newly hired work-at-home usability designer. She was one of the best in the business, and he was lucky to have snagged her just coming off maternity leave. His promise of flexible working hours and full benefits had lured her back to work two months before her year-long leave ended. “You’ve got to do something about your HR department!” Perkins announced. “They’ve just told me that I’m not eligible for health and dental benefits because I don’t work on the prem- ises! Furthermore, they want to classify me as contingent staff, not managerial, because I don’t fit in one of their petty little categories for employees. You promised me that you had covered all this before I took the job! I gave up a good job at LifeCo so I could work from home.” McCann had indeed covered this issue in principle with Rick Morrow, IT’s HR
  • 10. representative, but that had been almost eight months ago. Morrow had since left the firm. McCann wondered if he had left any paperwork on this matter. The HR IT spot had not yet been filled, and all of the IT managers were upset about HR’s unreceptive attitude when it came to adapting its policies to the realities of today’s IT world. “OK, Linda, just hang in there for a day or two and I’ll get this all sorted out,” he promised. “How’s the usability testing coming along?” “That’s another thing I wanted to talk with you about. The team’s making changes to the look and feel of the product without consulting me,” she fumed. “I can’t do my job without being in the loop. You have to make them tell me when they’re doing things like this.” McCann sighed. Getting Perkins on the project had been such a coup that he hadn’t given much thought to how the lines of communication would work within such a large team. “I hear you, Linda, and we’ll work this out. Can you just give me a few days to figure out how we can improve things?” Hanging up, he grabbed his jacket and slunk out of the office as quickly as he could before any other problems could present themselves. If he just kept walking south, he’d make it to the Andes in three, maybe four, months. He could teach him- self Spanish along the way. At least the llamas would appreciate his efforts! MM could
  • 11. take its project and give it to some other poor schmuck. No way was he going back! He walked furiously down the street, mentally ticking off the reasons he had been a fool to fall for Smith’s sweet talk. Then, unbidden, a plan of attack formed in his head. Walking always did the trick. Getting out of the office cleared his head and focused his priorities. He turned back the way he had come, now eager to get back in the fray. He had some things to do right away, and others he had to put in place ASAP. Discussion Questions 1. Some organizational factors increase a project’s likelihood of success. Identify these “facilitators” for the Green project. 2. Other organizational factors decrease a project’s likelihood of success. Identify these “barriers” for the Green project. 3. Outline the things that McCann needs to do right away.