SlideShare a Scribd company logo
1 of 39
Design of an Improved
Bayonet Ultra Heat Exchanger
Team 11
5/1/12
Team Members
• Harshith D'mello
• Dylan Herman
• James Hum
• Kent Yee Lui
• James Sowin
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 2
Acknowledgements
• Prof. Chia-Fon Lee
• Prof. Stephen Platt
• Prof. Emad Jassim
• Lance Hibbeler
• Seid Koric and Ahmed Taha
• Jay Menacher
• Ralf Möller, Keith Parrish and their dedicated
team of machinists
• Eclipse Inc, specifically Val Smirnov, Rick
Wenger, Jason Smith and Andrew Fortener
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 3
Overview
• Introduction
• Proposed Solution
• Computational Fluid Dynamics Analysis
• Experimental Testing
• Energy Savings Estimate
• Cost Analysis
• Budget
• Conclusions and Recommendations
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 4
Introduction
Original BU
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 5
Background
• Bayonet Ultra (BU) heat exchanger
o Used in industrial burners
o Typical operating temperature between
1500 - 2200 °F
o Implemented in furnaces, used to heat
ambient air
o Saves fuel in burner by recuperating heat
from exhaust gases
o Typically single tube, but BU series is
predominantly multitube
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 6
Project Goals
• Increase the effectiveness of the original BU
o Robust
o Maintain pressure drops
o Easily manufacturable
o Maintain current exterior dimensions
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 7
• Concentric tube
arrangement
• CFD on original design
showed lack of heat
transfer through inner
tube
• Complicated design and high number of parts
• Decided to abandon concentric tube design in all potential ideas
• Inlet-outlet pairs with connected ends to be underlying concept
hereafter
Original Design
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 8
Proposed Solution
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 9
Explanation of Decision Matrix
• Decision matrix created to rank design concepts
• 5 categories (weight)
o No. of parts (10)
o No. of welds (10)
o Machinability (10)
o Scalability (5)
o Pressure Drop (15)
• Ranking from 1 to 5
• Maximum score of 250
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 10
First Concept
• Circular bends
• 12 tubes, 6 inlet-outlet pairs
• Min. bend radius for safe tube
bending is 1.5 times tube
diameter
• Decision matrix result
• Score: 130
• Rank: 4
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 11
Second Concept
• Compartments of four tubes
(two inlets and two outlets)
• Welding torch of 12 mm
diameter has to weld on inside
• Impossible to weld airtight
• Decision matrix result
• Score: 140
• Rank: 3
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 12
Third Concept
• 90° bends forming
rectangular loops
• Similar issues with
welding torch clearance
• Decision matrix result
• Score: 90
• Rank: 6 (worst)
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 13
Fourth Concept
• Inner & Outer manifold
• Outer manifold:
• 9 pipes - 4 inlet, 5 outlet
• Inner manifold:
• 3 pipes - 1 inlet, 2 outlet
• Decision matrix result
• Score: 145
• Rank: 2
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 14
Final Prototype Concept
• Adapted to 8 circular tubes
• Larger bend radii leads to
increased amount of space
• High manufacturability due
to single bend radius and
pipe symmetry
• Decision matrix result
• Score: 240
• Rank: 1 (best)
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 15
Final Design Concept Flow Path
Compartment at hot air outlet quickens exit
of preheated air, preventing loss of heat to
cold air inlet section
Speaker: H. D’Mello
5/1/2012 Team 11 – Heat Exchanger 16
Exhaust Out
Exhaust In
Cold Air Inlet
Hot Air Outlet
Computational Fluid
Dynamics (CFD)
Analysis
Speaker: J. Hum
5/1/2012 Team 11 – Heat Exchanger 17
Design Models
• Include exchanger tubes and
exhaust gas only
• Design 3 - 45° Welded Bends
• Design 4 – Ring Manifolds
Speaker: J. Hum
5/1/2012 Team 11 – Heat Exchanger 18
Design Models
Speaker: J. Hum
5/1/2012 Team 11 – Heat Exchanger 19
Computational Comparison
Speaker: J. Hum
5/1/2012 Team 11 – Heat Exchanger 20
Original BU – Symmetry
Prototype BU
Flow Profiles
• Previous designs had tubes
behind other bends
• Potential for baffles
• High pressure drop in outlet
chamber and fitting
Tube inlet: 2.2 “W.C.
Tube outlet: 1.2 “W.C.
• Similar drop at exhaust outlet
Pressure (inches-water)
1.2 “W.C.
2.2 “W.C.
Speaker: J. Hum
5/1/2012 Team 11 – Heat Exchanger 21
Velocity (ft/s)
Exhaust
Exhaust
Prototype Experimental Comparison
Speaker: J. Hum
5/1/2012 Team 11 – Heat Exchanger 22
Experimental
Testing
Speaker: J. Sowin
5/1/2012 Team 11 – Heat Exchanger 23
Test Procedure
•Exhaust air simulating 200-350 kBtu/hr with 12% excess air
•Three flow rates varying the exhaust temperatures from 700-1100°F
•Temperatures measured at all inlets, outlets and on tubes with thermocouples
•Flow rates measured for exhaust and pre-heat air by an orifice plate pressure drop
•Pressure drops measured for exhaust and pre-heat air with manometers
Electric
Heaters
Pre-Heat Air
Blower
Insulated BU
Recuperator
Orifice Flowmeter
K-type
Thermocouple
Wires
Speaker: J. Sowin
5/1/2012 Team 11 – Heat Exchanger 24
•9 K-type thermocouples: spaced throughout the BU
•Temperature read out from electric heater
•2 Orifices : placed 4 feet from blowers, pressure drop measured by
manometer
•2 Static pressure manometers: placed at exhaust inlet and pre-heated air inlet
Thermocouple Placements
Speaker: J. Sowin
5/1/2012 Team 11 – Heat Exchanger 25
Experimental Results
Average Effectiveness Overall = 22% for original BU
Average Effectiveness Overall = 26% for redesigned BU
Effectiveness
Speaker: J. Sowin
5/1/2012 Team 11 – Heat Exchanger 26
Experimental Results
Air Pressure Drop
Speaker: J. Sowin
5/1/2012 Team 11 – Heat Exchanger 27
Energy Savings
Estimate
Speaker: K. Lui
5/1/2012 Team 11 – Heat Exchanger 28
Assumptions
• BU heat exchanger run time
o Eight hours per day
o 365 days per year
• Propane is used as the fuel gas
o Energy content = 91,690 Btu/gal [1]
o Cost = $2.05/gal (Feb 2011) [2]
• Comparing old and new designs in terms of
o Energy saved
o Cost saved
[1] Energy Density of Propane
http://hypertextbook.com/facts/2002/EricLeung.shtml
[2] Propane Prices by Sales Type, U.S. Energy Information Administration
http://www.eia.gov/dnav/pet/pet_pri_prop_dcu_nus_m.htm
Speaker: K. Lui
5/1/2012 Team 11 – Heat Exchanger 29
Average Increase = 4.25%
Speaker: K. Lui
5/1/2012 Team 11 – Heat Exchanger 30
14
24
34
44
54
64
74
84
94
104
600 800 1000 1200 1400 1600 1800 2000 2200
EnergySaved(MMBtu/year)
Exhaust Inlet Temperature (°F)
Energy Saved per Year
Q_a (old) = 2000 scfh
Q_a (old) = 2830 scfh
Q_a (old) = 3500 scfh
Q_a (new) = 2000 scfh
Q_a (new) = 2830 scfh
Q_a (new) = 3500 scfh
Average Increase = 4.25%
Speaker: K. Lui
5/1/2012 Team 11 – Heat Exchanger 31
300
500
700
900
1100
1300
1500
1700
1900
2100
2300
600 800 1000 1200 1400 1600 1800 2000 2200
CostSaved($/year)
Exhaust Inlet Temperature (°F)
Cost Saved per Year (Propane as the fuel)
Q_a (old) = 2000 scfh
Q_a (old) = 2830 scfh
Q_a (old) = 3500 scfh
Q_a (new) = 2000 scfh
Q_a (new) = 2830 scfh
Q_a (new) = 3500 scfh
Cost Analysis
Speaker: D. Herman
5/1/2012 Team 11 – Heat Exchanger 32
Original BU
• 36 total parts
• 4 subassemblies
• 46 individual welds
Overall cost estimate:
$411.22
Speaker: D. Herman
5/1/2012 Team 11 – Heat Exchanger 33
Redesigned BU
• 13 total parts (63% reduction)
• 2 subassemblies
• 23 individual welds (50% reduction)
Overall cost estimate:
47% reduction
Speaker: D. Herman
5/1/2012 Team 11 – Heat Exchanger 34
$215.29
Budget
Speaker: D. Herman
5/1/2012 Team 11 – Heat Exchanger 35
Cost Breakdown
Speaker: D. Herman
5/1/2012 Team 11 – Heat Exchanger 36
$1,153.53
$493.12
$566.10
$1,002.49
$2,252.67Final Project Costs
Total Experimental Testing Costs
Total Cost of Final Build
Total Travel Costs
Estimated Project Costs
Machining Time 3 18 $50.00 $900
Pipes 1 3 $35.78 $107.34
FedEx Shipping 2 2 $60.00 $120.00
Sheet Metal 12" X 24 " 12" X 24 " $26.19 $26.19
Machining Time 3 7 $50.00 $350.00
Pipes 4 4 $35.78 $143.12
Travel Plant visits 2 3 $188.70 $566.10
Cost
Experimental Testing
Final Design Build
Quantity $/UnitType Original Quanity
Conclusions and
Recommendations
Speaker: D. Herman
5/1/2012 Team 11 – Heat Exchanger 37
• Average effectiveness increased from 22%
to 26%
• Cost of manufacturing decreased by 47%
o 1/3 of the original number of parts
o 50% fewer individual welds
• Air pressure drop reduction of 27%
• Future recommendations
o Determine the optimum tube diameter and number
of tube pairings
o Redesign exhaust and air outlets
o Further test the implementation of external fins
Speaker: D. Herman
5/1/2012 Team 11 – Heat Exchanger 38
Summary
Thank You
Questions?
Comments?

More Related Content

Similar to ME470FinalPresentation

Microsoft PowerPoint - Ch120884.PDF
Microsoft PowerPoint - Ch120884.PDFMicrosoft PowerPoint - Ch120884.PDF
Microsoft PowerPoint - Ch120884.PDFhesam ahmadian
 
March5 2009-workshop-slides
March5 2009-workshop-slidesMarch5 2009-workshop-slides
March5 2009-workshop-slidesSWITCHOntario
 
Methane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesMethane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesGerard B. Hawkins
 
Senior Project Presentation
Senior Project PresentationSenior Project Presentation
Senior Project PresentationGeoffrey McMahon
 
Gi energy renewable energy opportunities with infrastructure projects june ...
Gi energy   renewable energy opportunities with infrastructure projects june ...Gi energy   renewable energy opportunities with infrastructure projects june ...
Gi energy renewable energy opportunities with infrastructure projects june ...GI Energy
 
Internally heat integrated distillation column for close boiling mixure
Internally heat integrated distillation column for close boiling mixure Internally heat integrated distillation column for close boiling mixure
Internally heat integrated distillation column for close boiling mixure Shahbaz khan
 
Waste Heat Recovery Boilers - Trust Well Engineers (India) Pvt. Ltd.
Waste Heat Recovery Boilers - Trust Well Engineers (India) Pvt. Ltd.Waste Heat Recovery Boilers - Trust Well Engineers (India) Pvt. Ltd.
Waste Heat Recovery Boilers - Trust Well Engineers (India) Pvt. Ltd.bharati372416
 
Introduction to heat_exchangers
Introduction to heat_exchangersIntroduction to heat_exchangers
Introduction to heat_exchangersnabyl2008
 
Introduction to heat exchangers
Introduction to heat exchangersIntroduction to heat exchangers
Introduction to heat exchangersAhmed Alamin
 
Toruble shooting of HPH to attend poor performance
Toruble shooting of HPH to attend poor performanceToruble shooting of HPH to attend poor performance
Toruble shooting of HPH to attend poor performanceitismail4dinesh
 
K10870 AAFTAB ALAM RAC ME 6TH SEM
K10870 AAFTAB ALAM RAC ME 6TH SEMK10870 AAFTAB ALAM RAC ME 6TH SEM
K10870 AAFTAB ALAM RAC ME 6TH SEMGuddu Ali
 
K10870 AAFTAB ALAM RAC ME 6TH SEM
K10870 AAFTAB ALAM RAC ME 6TH SEMK10870 AAFTAB ALAM RAC ME 6TH SEM
K10870 AAFTAB ALAM RAC ME 6TH SEMGuddu Ali
 
FEEMSSD presentation on shell and tube heat exchanger75 .pptx
FEEMSSD presentation on shell and tube heat exchanger75 .pptxFEEMSSD presentation on shell and tube heat exchanger75 .pptx
FEEMSSD presentation on shell and tube heat exchanger75 .pptxAdarshPandey510683
 
DCP & Oil immersion cooling
DCP & Oil immersion coolingDCP & Oil immersion cooling
DCP & Oil immersion coolingParth Soni
 

Similar to ME470FinalPresentation (20)

Microsoft PowerPoint - Ch120884.PDF
Microsoft PowerPoint - Ch120884.PDFMicrosoft PowerPoint - Ch120884.PDF
Microsoft PowerPoint - Ch120884.PDF
 
CDR_Pres
CDR_PresCDR_Pres
CDR_Pres
 
March5 2009-workshop-slides
March5 2009-workshop-slidesMarch5 2009-workshop-slides
March5 2009-workshop-slides
 
Methane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube StudiesMethane Steam Reformer Re-tube Studies
Methane Steam Reformer Re-tube Studies
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
rac k10998 ppt
rac k10998 pptrac k10998 ppt
rac k10998 ppt
 
Senior Project Presentation
Senior Project PresentationSenior Project Presentation
Senior Project Presentation
 
Gi energy renewable energy opportunities with infrastructure projects june ...
Gi energy   renewable energy opportunities with infrastructure projects june ...Gi energy   renewable energy opportunities with infrastructure projects june ...
Gi energy renewable energy opportunities with infrastructure projects june ...
 
Internally heat integrated distillation column for close boiling mixure
Internally heat integrated distillation column for close boiling mixure Internally heat integrated distillation column for close boiling mixure
Internally heat integrated distillation column for close boiling mixure
 
Waste Heat Recovery Boilers - Trust Well Engineers (India) Pvt. Ltd.
Waste Heat Recovery Boilers - Trust Well Engineers (India) Pvt. Ltd.Waste Heat Recovery Boilers - Trust Well Engineers (India) Pvt. Ltd.
Waste Heat Recovery Boilers - Trust Well Engineers (India) Pvt. Ltd.
 
Introduction to heat_exchangers
Introduction to heat_exchangersIntroduction to heat_exchangers
Introduction to heat_exchangers
 
Introduction to heat exchangers
Introduction to heat exchangersIntroduction to heat exchangers
Introduction to heat exchangers
 
Toruble shooting of HPH to attend poor performance
Toruble shooting of HPH to attend poor performanceToruble shooting of HPH to attend poor performance
Toruble shooting of HPH to attend poor performance
 
Condensing Boilers
Condensing BoilersCondensing Boilers
Condensing Boilers
 
FYP_ Presentation.pdf
FYP_ Presentation.pdfFYP_ Presentation.pdf
FYP_ Presentation.pdf
 
K10870 AAFTAB ALAM RAC ME 6TH SEM
K10870 AAFTAB ALAM RAC ME 6TH SEMK10870 AAFTAB ALAM RAC ME 6TH SEM
K10870 AAFTAB ALAM RAC ME 6TH SEM
 
K10870 AAFTAB ALAM RAC ME 6TH SEM
K10870 AAFTAB ALAM RAC ME 6TH SEMK10870 AAFTAB ALAM RAC ME 6TH SEM
K10870 AAFTAB ALAM RAC ME 6TH SEM
 
FEEMSSD presentation on shell and tube heat exchanger75 .pptx
FEEMSSD presentation on shell and tube heat exchanger75 .pptxFEEMSSD presentation on shell and tube heat exchanger75 .pptx
FEEMSSD presentation on shell and tube heat exchanger75 .pptx
 
DCP & Oil immersion cooling
DCP & Oil immersion coolingDCP & Oil immersion cooling
DCP & Oil immersion cooling
 
Note 3.pdf
Note 3.pdfNote 3.pdf
Note 3.pdf
 

ME470FinalPresentation

  • 1. Design of an Improved Bayonet Ultra Heat Exchanger Team 11 5/1/12
  • 2. Team Members • Harshith D'mello • Dylan Herman • James Hum • Kent Yee Lui • James Sowin Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 2
  • 3. Acknowledgements • Prof. Chia-Fon Lee • Prof. Stephen Platt • Prof. Emad Jassim • Lance Hibbeler • Seid Koric and Ahmed Taha • Jay Menacher • Ralf Möller, Keith Parrish and their dedicated team of machinists • Eclipse Inc, specifically Val Smirnov, Rick Wenger, Jason Smith and Andrew Fortener Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 3
  • 4. Overview • Introduction • Proposed Solution • Computational Fluid Dynamics Analysis • Experimental Testing • Energy Savings Estimate • Cost Analysis • Budget • Conclusions and Recommendations Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 4
  • 5. Introduction Original BU Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 5
  • 6. Background • Bayonet Ultra (BU) heat exchanger o Used in industrial burners o Typical operating temperature between 1500 - 2200 °F o Implemented in furnaces, used to heat ambient air o Saves fuel in burner by recuperating heat from exhaust gases o Typically single tube, but BU series is predominantly multitube Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 6
  • 7. Project Goals • Increase the effectiveness of the original BU o Robust o Maintain pressure drops o Easily manufacturable o Maintain current exterior dimensions Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 7
  • 8. • Concentric tube arrangement • CFD on original design showed lack of heat transfer through inner tube • Complicated design and high number of parts • Decided to abandon concentric tube design in all potential ideas • Inlet-outlet pairs with connected ends to be underlying concept hereafter Original Design Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 8
  • 9. Proposed Solution Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 9
  • 10. Explanation of Decision Matrix • Decision matrix created to rank design concepts • 5 categories (weight) o No. of parts (10) o No. of welds (10) o Machinability (10) o Scalability (5) o Pressure Drop (15) • Ranking from 1 to 5 • Maximum score of 250 Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 10
  • 11. First Concept • Circular bends • 12 tubes, 6 inlet-outlet pairs • Min. bend radius for safe tube bending is 1.5 times tube diameter • Decision matrix result • Score: 130 • Rank: 4 Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 11
  • 12. Second Concept • Compartments of four tubes (two inlets and two outlets) • Welding torch of 12 mm diameter has to weld on inside • Impossible to weld airtight • Decision matrix result • Score: 140 • Rank: 3 Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 12
  • 13. Third Concept • 90° bends forming rectangular loops • Similar issues with welding torch clearance • Decision matrix result • Score: 90 • Rank: 6 (worst) Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 13
  • 14. Fourth Concept • Inner & Outer manifold • Outer manifold: • 9 pipes - 4 inlet, 5 outlet • Inner manifold: • 3 pipes - 1 inlet, 2 outlet • Decision matrix result • Score: 145 • Rank: 2 Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 14
  • 15. Final Prototype Concept • Adapted to 8 circular tubes • Larger bend radii leads to increased amount of space • High manufacturability due to single bend radius and pipe symmetry • Decision matrix result • Score: 240 • Rank: 1 (best) Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 15
  • 16. Final Design Concept Flow Path Compartment at hot air outlet quickens exit of preheated air, preventing loss of heat to cold air inlet section Speaker: H. D’Mello 5/1/2012 Team 11 – Heat Exchanger 16 Exhaust Out Exhaust In Cold Air Inlet Hot Air Outlet
  • 17. Computational Fluid Dynamics (CFD) Analysis Speaker: J. Hum 5/1/2012 Team 11 – Heat Exchanger 17
  • 18. Design Models • Include exchanger tubes and exhaust gas only • Design 3 - 45° Welded Bends • Design 4 – Ring Manifolds Speaker: J. Hum 5/1/2012 Team 11 – Heat Exchanger 18
  • 19. Design Models Speaker: J. Hum 5/1/2012 Team 11 – Heat Exchanger 19
  • 20. Computational Comparison Speaker: J. Hum 5/1/2012 Team 11 – Heat Exchanger 20 Original BU – Symmetry Prototype BU
  • 21. Flow Profiles • Previous designs had tubes behind other bends • Potential for baffles • High pressure drop in outlet chamber and fitting Tube inlet: 2.2 “W.C. Tube outlet: 1.2 “W.C. • Similar drop at exhaust outlet Pressure (inches-water) 1.2 “W.C. 2.2 “W.C. Speaker: J. Hum 5/1/2012 Team 11 – Heat Exchanger 21 Velocity (ft/s) Exhaust Exhaust
  • 22. Prototype Experimental Comparison Speaker: J. Hum 5/1/2012 Team 11 – Heat Exchanger 22
  • 23. Experimental Testing Speaker: J. Sowin 5/1/2012 Team 11 – Heat Exchanger 23
  • 24. Test Procedure •Exhaust air simulating 200-350 kBtu/hr with 12% excess air •Three flow rates varying the exhaust temperatures from 700-1100°F •Temperatures measured at all inlets, outlets and on tubes with thermocouples •Flow rates measured for exhaust and pre-heat air by an orifice plate pressure drop •Pressure drops measured for exhaust and pre-heat air with manometers Electric Heaters Pre-Heat Air Blower Insulated BU Recuperator Orifice Flowmeter K-type Thermocouple Wires Speaker: J. Sowin 5/1/2012 Team 11 – Heat Exchanger 24
  • 25. •9 K-type thermocouples: spaced throughout the BU •Temperature read out from electric heater •2 Orifices : placed 4 feet from blowers, pressure drop measured by manometer •2 Static pressure manometers: placed at exhaust inlet and pre-heated air inlet Thermocouple Placements Speaker: J. Sowin 5/1/2012 Team 11 – Heat Exchanger 25
  • 26. Experimental Results Average Effectiveness Overall = 22% for original BU Average Effectiveness Overall = 26% for redesigned BU Effectiveness Speaker: J. Sowin 5/1/2012 Team 11 – Heat Exchanger 26
  • 27. Experimental Results Air Pressure Drop Speaker: J. Sowin 5/1/2012 Team 11 – Heat Exchanger 27
  • 28. Energy Savings Estimate Speaker: K. Lui 5/1/2012 Team 11 – Heat Exchanger 28
  • 29. Assumptions • BU heat exchanger run time o Eight hours per day o 365 days per year • Propane is used as the fuel gas o Energy content = 91,690 Btu/gal [1] o Cost = $2.05/gal (Feb 2011) [2] • Comparing old and new designs in terms of o Energy saved o Cost saved [1] Energy Density of Propane http://hypertextbook.com/facts/2002/EricLeung.shtml [2] Propane Prices by Sales Type, U.S. Energy Information Administration http://www.eia.gov/dnav/pet/pet_pri_prop_dcu_nus_m.htm Speaker: K. Lui 5/1/2012 Team 11 – Heat Exchanger 29
  • 30. Average Increase = 4.25% Speaker: K. Lui 5/1/2012 Team 11 – Heat Exchanger 30 14 24 34 44 54 64 74 84 94 104 600 800 1000 1200 1400 1600 1800 2000 2200 EnergySaved(MMBtu/year) Exhaust Inlet Temperature (°F) Energy Saved per Year Q_a (old) = 2000 scfh Q_a (old) = 2830 scfh Q_a (old) = 3500 scfh Q_a (new) = 2000 scfh Q_a (new) = 2830 scfh Q_a (new) = 3500 scfh
  • 31. Average Increase = 4.25% Speaker: K. Lui 5/1/2012 Team 11 – Heat Exchanger 31 300 500 700 900 1100 1300 1500 1700 1900 2100 2300 600 800 1000 1200 1400 1600 1800 2000 2200 CostSaved($/year) Exhaust Inlet Temperature (°F) Cost Saved per Year (Propane as the fuel) Q_a (old) = 2000 scfh Q_a (old) = 2830 scfh Q_a (old) = 3500 scfh Q_a (new) = 2000 scfh Q_a (new) = 2830 scfh Q_a (new) = 3500 scfh
  • 32. Cost Analysis Speaker: D. Herman 5/1/2012 Team 11 – Heat Exchanger 32
  • 33. Original BU • 36 total parts • 4 subassemblies • 46 individual welds Overall cost estimate: $411.22 Speaker: D. Herman 5/1/2012 Team 11 – Heat Exchanger 33
  • 34. Redesigned BU • 13 total parts (63% reduction) • 2 subassemblies • 23 individual welds (50% reduction) Overall cost estimate: 47% reduction Speaker: D. Herman 5/1/2012 Team 11 – Heat Exchanger 34 $215.29
  • 35. Budget Speaker: D. Herman 5/1/2012 Team 11 – Heat Exchanger 35
  • 36. Cost Breakdown Speaker: D. Herman 5/1/2012 Team 11 – Heat Exchanger 36 $1,153.53 $493.12 $566.10 $1,002.49 $2,252.67Final Project Costs Total Experimental Testing Costs Total Cost of Final Build Total Travel Costs Estimated Project Costs Machining Time 3 18 $50.00 $900 Pipes 1 3 $35.78 $107.34 FedEx Shipping 2 2 $60.00 $120.00 Sheet Metal 12" X 24 " 12" X 24 " $26.19 $26.19 Machining Time 3 7 $50.00 $350.00 Pipes 4 4 $35.78 $143.12 Travel Plant visits 2 3 $188.70 $566.10 Cost Experimental Testing Final Design Build Quantity $/UnitType Original Quanity
  • 37. Conclusions and Recommendations Speaker: D. Herman 5/1/2012 Team 11 – Heat Exchanger 37
  • 38. • Average effectiveness increased from 22% to 26% • Cost of manufacturing decreased by 47% o 1/3 of the original number of parts o 50% fewer individual welds • Air pressure drop reduction of 27% • Future recommendations o Determine the optimum tube diameter and number of tube pairings o Redesign exhaust and air outlets o Further test the implementation of external fins Speaker: D. Herman 5/1/2012 Team 11 – Heat Exchanger 38 Summary

Editor's Notes

  1. We used CFD analysis, specifically FLUENT in Ansys Workbench, to analyze our tube designs and predict the changes in flow and key variables, namely preheat temperature and pressure drop.
  2. We created design models to directly compare impact of new tube arrays. As you can see we ignored the housing and inlet/outlet fittings, focusing only on the exchanger tubes and exhaust domain. Here we have the performance for the original BU, design 3 which is the 45deg welded bends and Design 4 which had inner and outer manifolds. Preheat air temperature, which is the most important number, what we send to the burner, is on the left axis, burner input on the lower axis. The typical range of 200 to 400 thousand btu/hr is directly related to the flow rates on both exhaust and air sides. We see a 5 to 8% increase in preheat air temperatures, with decreasing gains at high flow rates for the manifold design.
  3. These are the pressure drops associated with those two designs. You’ll note that the square bend design has significantly increased air pressure drop and much lower exhaust drop. This is because this design required smaller diameter tubes, shifting the greater pressure drop towards the air side. The manifold design had higher pressure drop on both sides. So these charts are why we didn’t like the designs from a pressure drop aspect. One thing to note is that looking at the original design, the pressure drops in air and exhaust are very close, where as the actual numbers youd find on the datasheet show the air drop higher by 2 to 5 times. This is because these models only contain the tubes, and I’ll explain this further in a few slides.
  4. So now we have the full models of the original BU and the prototype. You can see that the original design had a symmetry plane that we took advantage of. So here’s the combined performance chart, preheat temperature on the left axis corresponding to the red curves, pressure drop on the right. We vary over the operating range of 100 to 400 KBTU/hr. Again solid lines are the original, dashed are the prototype. We have a 4 to 12% increase in preheat temperature, 20% decrease in air pressure drop, and up to 10% increase in exhaust pressure drop, although as I stated before, the exhaust numbers are much lower than the air numbers, and because this is a closed loop system we can say that these offset to an overall reduction in pressure drop.
  5. Here we see the flow profiles in the exhaust section and pressure drop in one of the exchanger tubes. The flow here is colored by velocity. We see two zones with low flow velocity. The one behind the tube bends here does not affect our design since we have removed the central set of 3 tubes. This zone here is due to positioning of the exhaust outlet, and existed in the original design as well. This creates a potential for adding a baffle before the exhaust outlet to eliminate this zone. We also note that for the majority of the interaction region there is high velocity flow at the edges of the radiant tube where our exchanger tubes are located, always a good sign. Here we see the pressure contour in one of the exchanger tubes. As I alluded to earlier, the pressure drop in the tubes themselves is not a clear majority of the overall pressure drop. We see a pressure drop here of 1 “WC. This means the remaining 1.2 “WC drop is due to the rapid expansion and compression as the heated gasses enter the chamber and are forced through the outlet. A similar pressure drop occurs in the exhaust region heading into the 90deg exhaust outlet. While we had to keep the exterior dimensions and fittings the same, we believe this is a key area to look at redesigning the outlets and chambers to further reduce the pressure drop.
  6. For tests, exhaust inlet increases with increasing flow rate (approaches set point)
  7. 22 individual parts costed as well as 4 sub assemblies which served as a baseline comparison for the new design. A painting finishing process was then added. the same methodology was used for both analyses
  8. Costing the original BU with aPriori serves as a baseline comparison for the new design
  9. Talk about cost over run