The London 2012 Games – on time,
on budget
Hugh Robertson, MP – Minister for Sport and the Olympics
David Goldstone – Finance Director, Government Olympic Executive




Wednesday 18 July 2012
JULY 2012
               9 days to Olympic Games Opening Ceremony




  Olympic Park delivered on time and within budget
  £476 million of uncommitted contingency remaining
  Successful test events, Diamond Jubilee and Olympic
   Torch Relay
  We are in a strong position but not complacent;
UNCLASSIFIED
   challenges remain
THE CHALLENGE – 2005




  Transform one of the most deprived areas of the UK
  Create an extraordinary legacy for the UK and the world
  Deliver the Olympic Park – largest construction project in
   Europe
  Equivalent to building Heathrow Terminal 5 twice over in
UNCLASSIFIED
   half the time
UNCLASSIFIED
    The contaminated site was filled with disused tyres and industrial waste
UNCLASSIFIED
       The site was limited by old infrastructure and poor transport links
UNCLASSIFIED
 The site was criss-crossed by electricity pylons that had to be dismantled
UNCLASSIFIED
               The UK’s largest and greenest clean-up operation
OLYMPIC PARK




  2.5 sq km site – bigger than Hyde Park
  A whole new quarter of East London
  A place to work, live and play
UNCLASSIFIED
  Designed not just for Games but for long-term legacy
NEW WORLD-CLASS SPORTS VENUES
A NEW COMMUNITY – FOR GAMES & LEGACY




  Olympic & Paralympic Village
 – Home to 23,000 athletes and officials during Games
 – Converted into more than 2,800 homes in legacy
  A new school (Chobham Academy) and new health centre
UNCLASSIFIED
NEW INFRASTRUCTURE AND TRANSPORT
                 FOR EAST LONDON




  New power, water and sanitation
  30 bridges and connections
  East London one of the most connected parts of the capital
  £6.5bn investment into transport system
UNCLASSIFIED
  Stratford station capacity trebled to over 200 trains per hour
The London 2012 Games – on
time, on budget
Hugh Robertson, MP – Minister for Sport and the Olympics
David Goldstone – Finance Director, Government Olympic Executive




Wednesday 18 July 2012
Public Sector Funding Package: Funders
  2007 Baseline Budget           31 May 2012
           £9.325bn                   £9.298bn



                 Lottery
                                            Lottery
                  2.175
                                             2.175
      Central                    Central
    Government        London                     London
                               Government         0.875
       5.975           1.175
                                  6.248
Public Sector Funding Package: Programmes
               Programme                          2007 Baseline Budget (£m)   31 May 2012 (£m)
 ODA and Park Transformation                                     8,099 A          7,057 B
 Elite and community sports                                       290               290
 Paralympic Games                                                 66                95
 Look                                                             32                33
 Security                                                         838              1,028
 LOCOG                                                             0                183
 Operational programmes                                            0                220
 Tourism campaign                                                  0                 4
                                                                       C
 PSFP contingency remaining                                        0                388
 Total                                                           9,325             9,298


  LOCOG c.£2.1bn budget privately funded

 Notes
 A
   ODA baseline budget contained £350m for Park transformation
 B
   ODA forecast of £6,761m, plus £296m for Park transformation
 C
   Contingency was held against ODA programme
Contingency Remaining

    Contingency    November 2007    31 May 2012 (£m)
     Available      Baseline (£m)

ODA Programme           968               88
contingency

“Funders” / PSFP       1,004              388
contingency

Total                  1,972              476
ODA Expenditure: 75p in every £1
    leaves a lasting legacy


      Works specific
      to the Games
           25%

                        Long term
                       regeneration
                           75%
Meeting the Challenges
Credit crunch
• Village and Broadcast/Media
  Centre were to be privately
  funded
• Decision to bring into public
  ownership was made in
  2009, due to credit crunch
• Village was sold to private
  developers in 2011 for approx.
  £550m (in addition to approx.
  £270m earlier receipts)
• Competition for legacy tenant for the
  Broadcast/Media Centre is near completion
Meeting the Challenges

          From construction to operations
          Savings from the construction
          phase have been utilised to
          support operational requirements:
          • Park operations
          • Crowd management
          • Increased security
          • Ceremonies
Meeting the Challenges




Managing to time and within budget
• “Big Build” complete at one year to go
• £1bn total ODA savings reinvested to meet pressures
• Nearly £500m of uncommitted contingency remains

The London 2012 Games - on time, on budget

  • 1.
    The London 2012Games – on time, on budget Hugh Robertson, MP – Minister for Sport and the Olympics David Goldstone – Finance Director, Government Olympic Executive Wednesday 18 July 2012
  • 2.
    JULY 2012 9 days to Olympic Games Opening Ceremony  Olympic Park delivered on time and within budget  £476 million of uncommitted contingency remaining  Successful test events, Diamond Jubilee and Olympic Torch Relay  We are in a strong position but not complacent; UNCLASSIFIED challenges remain
  • 3.
    THE CHALLENGE –2005  Transform one of the most deprived areas of the UK  Create an extraordinary legacy for the UK and the world  Deliver the Olympic Park – largest construction project in Europe  Equivalent to building Heathrow Terminal 5 twice over in UNCLASSIFIED half the time
  • 4.
    UNCLASSIFIED The contaminated site was filled with disused tyres and industrial waste
  • 5.
    UNCLASSIFIED The site was limited by old infrastructure and poor transport links
  • 6.
    UNCLASSIFIED The sitewas criss-crossed by electricity pylons that had to be dismantled
  • 7.
    UNCLASSIFIED The UK’s largest and greenest clean-up operation
  • 8.
    OLYMPIC PARK 2.5 sq km site – bigger than Hyde Park  A whole new quarter of East London  A place to work, live and play UNCLASSIFIED  Designed not just for Games but for long-term legacy
  • 9.
  • 10.
    A NEW COMMUNITY– FOR GAMES & LEGACY  Olympic & Paralympic Village – Home to 23,000 athletes and officials during Games – Converted into more than 2,800 homes in legacy  A new school (Chobham Academy) and new health centre UNCLASSIFIED
  • 11.
    NEW INFRASTRUCTURE ANDTRANSPORT FOR EAST LONDON  New power, water and sanitation  30 bridges and connections  East London one of the most connected parts of the capital  £6.5bn investment into transport system UNCLASSIFIED  Stratford station capacity trebled to over 200 trains per hour
  • 12.
    The London 2012Games – on time, on budget Hugh Robertson, MP – Minister for Sport and the Olympics David Goldstone – Finance Director, Government Olympic Executive Wednesday 18 July 2012
  • 13.
    Public Sector FundingPackage: Funders 2007 Baseline Budget 31 May 2012 £9.325bn £9.298bn Lottery Lottery 2.175 2.175 Central Central Government London London Government 0.875 5.975 1.175 6.248
  • 14.
    Public Sector FundingPackage: Programmes Programme 2007 Baseline Budget (£m) 31 May 2012 (£m) ODA and Park Transformation 8,099 A 7,057 B Elite and community sports 290 290 Paralympic Games 66 95 Look 32 33 Security 838 1,028 LOCOG 0 183 Operational programmes 0 220 Tourism campaign 0 4 C PSFP contingency remaining 0 388 Total 9,325 9,298 LOCOG c.£2.1bn budget privately funded Notes A ODA baseline budget contained £350m for Park transformation B ODA forecast of £6,761m, plus £296m for Park transformation C Contingency was held against ODA programme
  • 15.
    Contingency Remaining Contingency November 2007 31 May 2012 (£m) Available Baseline (£m) ODA Programme 968 88 contingency “Funders” / PSFP 1,004 388 contingency Total 1,972 476
  • 16.
    ODA Expenditure: 75pin every £1 leaves a lasting legacy Works specific to the Games 25% Long term regeneration 75%
  • 17.
    Meeting the Challenges Creditcrunch • Village and Broadcast/Media Centre were to be privately funded • Decision to bring into public ownership was made in 2009, due to credit crunch • Village was sold to private developers in 2011 for approx. £550m (in addition to approx. £270m earlier receipts) • Competition for legacy tenant for the Broadcast/Media Centre is near completion
  • 18.
    Meeting the Challenges From construction to operations Savings from the construction phase have been utilised to support operational requirements: • Park operations • Crowd management • Increased security • Ceremonies
  • 19.
    Meeting the Challenges Managingto time and within budget • “Big Build” complete at one year to go • £1bn total ODA savings reinvested to meet pressures • Nearly £500m of uncommitted contingency remains