ICLEI’s Sustainability
   Planning Toolkit




  MAPD Annual Conference – June 4, 2010
Angela Vincent – Northeast/Mid-Atlantic Regional Director
ICLEI – A Worldwide Movement


           ICLEI Local Government Members:
           1100 globally
           600+ U.S.A.
           38 in Massachusetts
             • Representing 30% of the population
ICLEI’s Mission

 Our mission is to build, serve, and drive a
 movement of local governments to advance
 deep reductions in greenhouse gas emissions
 and achieve tangible improvements in local
 sustainability.
Benefits of Local Climate Action

Save money
Improve air quality
Create local jobs
Protect public health
Improve the quality of life
Create legacy of leadership
Empowering Massachusetts’ Local
           Governments
Framework for approaching climate protection
Emissions Analysis Software and Decision Support Tool
Standard Methodology and Technical Assistance
Implementation Tools and Resources (publications)
ICLEI Trainings and Events
Technical, policy, and communications assistance
Regional, national and international network of peers
Five Milestones for Climate Mitigation
ICLEI Tools & Resources

GHG Accounting Software & Tools
Climate & Air Pollution Planning Assistant (CAPPA)
Implementation Guidebooks & Case Studies
Member Networking
Local Government Success Stories
Implementation Guidebooks & Toolkits

 Revolving Energy Fund Guide
 Outreach & Communications
 Recycling & Solid Waste
 Environmentally Preferable Purchasing
 Transportation & Land Use
 Small Communities
 Green Jobs
 Sustainability Planning Toolkit
Sustainability Planning Toolkit


                 Comprehensive guide on the
                 basics to creating a sustainability
                 plan

                 For local governments of all sizes
                 Includes guidance on approach to
                 the planning process

                 Includes templates for creating a
                 sustainability team, typical plan
                 outline, measurement of strategies,
                 and engaging the public
Background on Sustainability
              Planning Toolkit
Goal:
  – Create a replicable planning process
    and model based on PlaNYC
Tasks:
  – Develop PlaNYC case study and
    Sustainability Planning Toolkit
  – Pilot guidelines and templates in toolkit
    with
        – New Rochelle, NY
        – Newark, NJ
        – Miami-Dade County, FL
Why Develop a Sustainability Plan?

• Tie together all sustainability initiatives and programs
  under an overarching plan
• Develop metrics and indicators for measuring progress
• Raise community awareness
• Develop common goals
• Encourage interdepartmental cooperation
How does ICLEI and the STAR
              Program define sustainability?
                                               •    Affordability & Social Equity (affordable and workforce
                                                    housing, poverty, human services and race and social
                                                    equity)

                                               •    Children, Health & Safety (community health and
                                                    wellness, access to health care, and public safety)

                                               •    Education, Arts & Community (education excellence,
                                                    arts and culture, and civic engagement and vitality)



                                                    Social

•   Natural Systems (ecosystems
    and habitat, water and                        Sustainable                 •    Economic Development (clean
    stormwater, air quality, waste,    Environmental        Economic               technologies and green jobs,
    and resource conservation)                                                     local commerce, tourism, and
                                                                                   local food system)
•   Planning & Design (land use,
    transportation and mobility, and                                          •    Employment & Workforce
    parks, open space and                                                          Training (green job training,
    recreation)                                                                    employment and workforce
                                                                                   wages, and youth skills)
•   Energy & Climate (energy,
    greenhouse gas emissions and
    other air pollutants, renewable
    energy, and green building)
√ Part of plan
        Example Policy Areas to Include                                       ♦Existing policy



     Policy Areas        New York City   Santa Monica   Denver   Sacramento    Westchester County

                              √               √           √          √                   √
Energy/ Buildings

Transportation
                              √               √           √          √                   √
Air Quality
                              √               √                      √
                              √               √           √          √                   √
Water Resources

Climate
                              √               √           √          √                   √
Land Use / Brownfields
                              √               √           √          √                   √
Waste
                              ♦               √           √          √                   √
Open Space and Habitat
Conservation
                              √               √           √          √                   √
Affordable Housing
                              √               √           ♦          ♦                   ♦
Public Education
                              √               √           √          √                   √
Civic Engagement
                                              √           √          √
Green Economic
Development                   ♦               √           √
Green procurement
                              ♦               √           √          √                   √
Public Health and
Nutrition                                     √           ?          √
ICLEI’s Five Milestones for Sustainability

                            Integration with STAR
                              Community Index


                                       STAR Provisional
                                            Goals
                                         (June 2010)
STAR Performance
Management Tool
     (2011)




                                 STAR Measures
                                    (2011)
Stakeholders Involved in Developing
a Sustainability Plan
                                             Sustainability Coordinator            Sustainability
                                         •
                                         •
                                                Coordinate planning process
                                                Manage writing of the
                                                                                      Team
                                                Sustainability Plan
     Sustainability                      •      Coordinate implementation of
                                                                                       Interdepartmental
    Advisory Board                              the Sustainability Plan                      Team

•       Participate in topic
        specific working groups                                                    •      Analyze Issues
•       Brainstorm high priority                                                   •      Research Best
                                                                                          Practices
        issues                                     Sustainability                  •      Develop goals
•       Develop goals
•       Input on strategies and                        Plan                        •      Develop strategies
        initiatives                                                                       and initiatives
•       Advice on planning
        process


            External                                                           Community
            Experts                                                            Stakeholder
                                                General Public
         (Universities,                                                          Groups
        Consultants etc)
                                                                               •        Brainstorm high priority
    •      Define high priority issues         •      Participate in public             issues
    •      Analyze issues and                         meetings                 •        Brainstorm strategies
           strategies as requested             •      Submit ideas online               via public outreach
    •      Provide supporting data                                                      process
Getting Started: Make a
   Commitment and Organize Team
Designate a Sustainability Coordinator       ICLEI Tools and Templates
Define the vision and purpose for the plan
Make a commitment: obtain chief elected      • Sample timeline
     official buy-in for the plan            • Outreach and Public
                                               Communication
Develop a workplan for the planning
     process and for public outreach           Template
                                             • Sustainability Team
Organize an interdepartmental team of
                                               Formation Checklist
     local government staff to develop the
     plan
Gather ideas for the scope of the plan
Form a Sustainability Advisory Board
Kick-Off Sustainability Advisory Board
     meetings
Launch and publicly announce the
     planning process
Milestone 1: Conduct Sustainability
 Assessment
                                        ICLEI Tools and Templates
Begin to define the scope of the plan
Inventory existing sustainability       • Sustainability
    initiatives                           Assessment Checklist
Develop a greenhouse gas emissions      • Clean Air Climate
    inventory for government
    operations and the community          Protection (CACP)
                                          Software
Gather and analyze data for the
    Sustainability Assessment           • Forecasting Guide
                                          (coming soon)
Gather ideas from key stakeholder
    groups
Create a sustainability assessment
    report
Sustainability Assessment Checklist

Existing Sustainability Initiatives
Sources of greenhouse gas emissions
Major sources of pollution
State of major infrastructure systems
Health of natural resources
Open spaces
Sustainability of land use and development patterns
Major public health issues
How affordable is it to live
Opportunities to engage in civic affairs?
Demographics
Transportation systems
Miami-Dade County’s Sustainability
             Assessment
                     Milestone 1
           Conduct Sustainability Assessment



Demographics                        Housing & Buildings
Climate Change                      Land Use
Economy                             Local Industry & Business
Energy                              Schools
Environment                         Solid Waste & Recycling
Government Operations               Transportation
Health                              Water




                                                                19
CACP 2009 Inventory Software
Milestone 2: Set Sustainability Goals

                                          ICLEI Tools and Templates
Define clear, relevant, and measurable     • Matrix of Sustainability
     goals that address the key issues       Strategies
     identified in the Sustainability      • Sustainability and
     Assessment                              Climate Action Plan
Brainstorm and analyze strategies for        examples
     achieving goals                       • ICLEI’s Climate and Air
Set an emissions reductions target that      Pollution Planning
     is aggressive but achievable            Assistant (CAPPA)
                                             decision support tool
Solicit ideas from the public for
                                           • Target Setting Guide
     sustainability goals
                                             (coming soon)
Announce the goals to the public
STAR Environment Goals
STAR Economy Goals
STAR Society Goals
GREENR CONTENT – BIG GOALS
Milestone 3: Develop Sustainability
   Plan
                                                ICLEI Tools and Templates
Prepare for public outreach process              • Measures Analysis
Perform outreach                                   Template
Develop and prioritize measures                  • ICLEI’s Climate and Air
Develop implementation plans for each measure      Pollution Planning
Create outline for the plan                        Assistant (CAPPA)
Write the plan                                     decision support tool
Release a draft plan for public comment (if      • Matrix of Sustainability
      appropriate)                                 Strategies
Finalize and release the plan                    • Sustainability Plan
                                                   Template
                                                 • ICLEI’s Outreach and
                                                   Communications Guide
CAPPA – Climate Action Planning
Milestone 3: Develop Sustainability
Plan
GREENR CONTENT – BASIC STRUCTURE
Milestone 4: Implement the
Sustainability Plan
Implement the measures in the        ICLEI Tools and Templates
     plan and track implementation   •   ICLEI’s Action Center and
                                         Member Center on the
     status
                                         ICLEI website for a variety
Formalize the planning process           of guidebooks, best
Coordinate with a coalition of           practices, and
     advocacy groups                     implementation tools.
                                     •   Revolving Energy Fund
                                         Guide
                                     •   Solid Waste and Recycling
                                         Guide
                                     •   Green Playbook +
                                         Neighborhoods website
                                     •   Environmentally
                                         Preferrable Purchasing
                                         Guide
PlaNYC: Achievements in Action

Over 2/3 of initiatives are on-time or ahead of
  schedule
Achievements in Land, Water, Transportation, Energy,
  Air and Climate Change goals, including:
   –   21 transit-oriented rezonings with inclusionary zoning
   –   20 stormwater retention pilot projects launched
   –   200 miles of bike lanes and 2,000 biked racks installed
   –   76,751 City parking placards reduced
   –   260 energy efficiency projects completed in City govt.
   –   22% of taxi fleet converted to hybrids
Milestone 5: Monitor/Evaluate
Implementation Progress
                               ICLEI Tools and Templates
Develop an Annual Progress      • Sustainability
    Report                        Assessment Checklist
                                • STAR Community Index
Develop and report on a set       performance
    of sustainability             management system
    indicators
Update the Greenhouse Gas      What to Include in Annual
    Inventory                      Progress Report
Highlight successes on           Responsible Parties
                                 Status of Measures
    sustainability plan
                                 Quantified Progress
    website                      Achievements and
Keep the sustainability team      challenges
    updated                      Next steps
What to Include in a Sustainability Plan

Facts, charts, and figures
Goals
    • Emissions reductions target (short-term
       and long-term)
    • Transportation, air, water, buildings, open
       space, etc.
Short & Long-term Measures with implementation
   plans
    • Timing, funding, and responsibilities
Matrix of measures and goals
Implementation & Monitoring Framework and
   Timeline
Relationship to other plans
Planning process
Download the Sustainability
    Planning Toolkit
http://www.icleiusa.org/sustainabilitytoolkit
Action Center – One Stop Shop
Upcoming ICLEI Events


2010 Local Action Summit
  September 24 – 26, 2010
          Hyatt Regency
       Washington, D.C.
  http://www.icleiusa.org/main-page/news-
    events/iclei-local-action-summit-2010
Questions/Discussion


Contact Us:
Angela Vincent
(617) 960-3420 x202
angela.vincent@iclei.org


Allison Webster – New England Liaison
(617) 960-3420 x207
allison.webster@iclei.org
www.icleiusa.org/northeast

MAPD 2010 - ICLEI sustainability toolkit

  • 1.
    ICLEI’s Sustainability Planning Toolkit MAPD Annual Conference – June 4, 2010 Angela Vincent – Northeast/Mid-Atlantic Regional Director
  • 2.
    ICLEI – AWorldwide Movement ICLEI Local Government Members: 1100 globally 600+ U.S.A. 38 in Massachusetts • Representing 30% of the population
  • 3.
    ICLEI’s Mission Ourmission is to build, serve, and drive a movement of local governments to advance deep reductions in greenhouse gas emissions and achieve tangible improvements in local sustainability.
  • 4.
    Benefits of LocalClimate Action Save money Improve air quality Create local jobs Protect public health Improve the quality of life Create legacy of leadership
  • 5.
    Empowering Massachusetts’ Local Governments Framework for approaching climate protection Emissions Analysis Software and Decision Support Tool Standard Methodology and Technical Assistance Implementation Tools and Resources (publications) ICLEI Trainings and Events Technical, policy, and communications assistance Regional, national and international network of peers
  • 6.
    Five Milestones forClimate Mitigation
  • 7.
    ICLEI Tools &Resources GHG Accounting Software & Tools Climate & Air Pollution Planning Assistant (CAPPA) Implementation Guidebooks & Case Studies Member Networking Local Government Success Stories
  • 8.
    Implementation Guidebooks &Toolkits Revolving Energy Fund Guide Outreach & Communications Recycling & Solid Waste Environmentally Preferable Purchasing Transportation & Land Use Small Communities Green Jobs Sustainability Planning Toolkit
  • 9.
    Sustainability Planning Toolkit Comprehensive guide on the basics to creating a sustainability plan For local governments of all sizes Includes guidance on approach to the planning process Includes templates for creating a sustainability team, typical plan outline, measurement of strategies, and engaging the public
  • 10.
    Background on Sustainability Planning Toolkit Goal: – Create a replicable planning process and model based on PlaNYC Tasks: – Develop PlaNYC case study and Sustainability Planning Toolkit – Pilot guidelines and templates in toolkit with – New Rochelle, NY – Newark, NJ – Miami-Dade County, FL
  • 11.
    Why Develop aSustainability Plan? • Tie together all sustainability initiatives and programs under an overarching plan • Develop metrics and indicators for measuring progress • Raise community awareness • Develop common goals • Encourage interdepartmental cooperation
  • 12.
    How does ICLEIand the STAR Program define sustainability? • Affordability & Social Equity (affordable and workforce housing, poverty, human services and race and social equity) • Children, Health & Safety (community health and wellness, access to health care, and public safety) • Education, Arts & Community (education excellence, arts and culture, and civic engagement and vitality) Social • Natural Systems (ecosystems and habitat, water and Sustainable • Economic Development (clean stormwater, air quality, waste, Environmental Economic technologies and green jobs, and resource conservation) local commerce, tourism, and local food system) • Planning & Design (land use, transportation and mobility, and • Employment & Workforce parks, open space and Training (green job training, recreation) employment and workforce wages, and youth skills) • Energy & Climate (energy, greenhouse gas emissions and other air pollutants, renewable energy, and green building)
  • 13.
    √ Part ofplan Example Policy Areas to Include ♦Existing policy Policy Areas New York City Santa Monica Denver Sacramento Westchester County √ √ √ √ √ Energy/ Buildings Transportation √ √ √ √ √ Air Quality √ √ √ √ √ √ √ √ Water Resources Climate √ √ √ √ √ Land Use / Brownfields √ √ √ √ √ Waste ♦ √ √ √ √ Open Space and Habitat Conservation √ √ √ √ √ Affordable Housing √ √ ♦ ♦ ♦ Public Education √ √ √ √ √ Civic Engagement √ √ √ Green Economic Development ♦ √ √ Green procurement ♦ √ √ √ √ Public Health and Nutrition √ ? √
  • 14.
    ICLEI’s Five Milestonesfor Sustainability Integration with STAR Community Index STAR Provisional Goals (June 2010) STAR Performance Management Tool (2011) STAR Measures (2011)
  • 15.
    Stakeholders Involved inDeveloping a Sustainability Plan Sustainability Coordinator Sustainability • • Coordinate planning process Manage writing of the Team Sustainability Plan Sustainability • Coordinate implementation of Interdepartmental Advisory Board the Sustainability Plan Team • Participate in topic specific working groups • Analyze Issues • Brainstorm high priority • Research Best Practices issues Sustainability • Develop goals • Develop goals • Input on strategies and Plan • Develop strategies initiatives and initiatives • Advice on planning process External Community Experts Stakeholder General Public (Universities, Groups Consultants etc) • Brainstorm high priority • Define high priority issues • Participate in public issues • Analyze issues and meetings • Brainstorm strategies strategies as requested • Submit ideas online via public outreach • Provide supporting data process
  • 16.
    Getting Started: Makea Commitment and Organize Team Designate a Sustainability Coordinator ICLEI Tools and Templates Define the vision and purpose for the plan Make a commitment: obtain chief elected • Sample timeline official buy-in for the plan • Outreach and Public Communication Develop a workplan for the planning process and for public outreach Template • Sustainability Team Organize an interdepartmental team of Formation Checklist local government staff to develop the plan Gather ideas for the scope of the plan Form a Sustainability Advisory Board Kick-Off Sustainability Advisory Board meetings Launch and publicly announce the planning process
  • 17.
    Milestone 1: ConductSustainability Assessment ICLEI Tools and Templates Begin to define the scope of the plan Inventory existing sustainability • Sustainability initiatives Assessment Checklist Develop a greenhouse gas emissions • Clean Air Climate inventory for government operations and the community Protection (CACP) Software Gather and analyze data for the Sustainability Assessment • Forecasting Guide (coming soon) Gather ideas from key stakeholder groups Create a sustainability assessment report
  • 18.
    Sustainability Assessment Checklist ExistingSustainability Initiatives Sources of greenhouse gas emissions Major sources of pollution State of major infrastructure systems Health of natural resources Open spaces Sustainability of land use and development patterns Major public health issues How affordable is it to live Opportunities to engage in civic affairs? Demographics Transportation systems
  • 19.
    Miami-Dade County’s Sustainability Assessment Milestone 1 Conduct Sustainability Assessment Demographics Housing & Buildings Climate Change Land Use Economy Local Industry & Business Energy Schools Environment Solid Waste & Recycling Government Operations Transportation Health Water 19
  • 20.
  • 21.
    Milestone 2: SetSustainability Goals ICLEI Tools and Templates Define clear, relevant, and measurable • Matrix of Sustainability goals that address the key issues Strategies identified in the Sustainability • Sustainability and Assessment Climate Action Plan Brainstorm and analyze strategies for examples achieving goals • ICLEI’s Climate and Air Set an emissions reductions target that Pollution Planning is aggressive but achievable Assistant (CAPPA) decision support tool Solicit ideas from the public for • Target Setting Guide sustainability goals (coming soon) Announce the goals to the public
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
    Milestone 3: DevelopSustainability Plan ICLEI Tools and Templates Prepare for public outreach process • Measures Analysis Perform outreach Template Develop and prioritize measures • ICLEI’s Climate and Air Develop implementation plans for each measure Pollution Planning Create outline for the plan Assistant (CAPPA) Write the plan decision support tool Release a draft plan for public comment (if • Matrix of Sustainability appropriate) Strategies Finalize and release the plan • Sustainability Plan Template • ICLEI’s Outreach and Communications Guide
  • 27.
    CAPPA – ClimateAction Planning
  • 28.
    Milestone 3: DevelopSustainability Plan
  • 29.
    GREENR CONTENT –BASIC STRUCTURE
  • 30.
    Milestone 4: Implementthe Sustainability Plan Implement the measures in the ICLEI Tools and Templates plan and track implementation • ICLEI’s Action Center and Member Center on the status ICLEI website for a variety Formalize the planning process of guidebooks, best Coordinate with a coalition of practices, and advocacy groups implementation tools. • Revolving Energy Fund Guide • Solid Waste and Recycling Guide • Green Playbook + Neighborhoods website • Environmentally Preferrable Purchasing Guide
  • 31.
    PlaNYC: Achievements inAction Over 2/3 of initiatives are on-time or ahead of schedule Achievements in Land, Water, Transportation, Energy, Air and Climate Change goals, including: – 21 transit-oriented rezonings with inclusionary zoning – 20 stormwater retention pilot projects launched – 200 miles of bike lanes and 2,000 biked racks installed – 76,751 City parking placards reduced – 260 energy efficiency projects completed in City govt. – 22% of taxi fleet converted to hybrids
  • 32.
    Milestone 5: Monitor/Evaluate ImplementationProgress ICLEI Tools and Templates Develop an Annual Progress • Sustainability Report Assessment Checklist • STAR Community Index Develop and report on a set performance of sustainability management system indicators Update the Greenhouse Gas What to Include in Annual Inventory Progress Report Highlight successes on  Responsible Parties  Status of Measures sustainability plan  Quantified Progress website  Achievements and Keep the sustainability team challenges updated  Next steps
  • 33.
    What to Includein a Sustainability Plan Facts, charts, and figures Goals • Emissions reductions target (short-term and long-term) • Transportation, air, water, buildings, open space, etc. Short & Long-term Measures with implementation plans • Timing, funding, and responsibilities Matrix of measures and goals Implementation & Monitoring Framework and Timeline Relationship to other plans Planning process
  • 34.
    Download the Sustainability Planning Toolkit http://www.icleiusa.org/sustainabilitytoolkit
  • 35.
    Action Center –One Stop Shop
  • 36.
    Upcoming ICLEI Events 2010Local Action Summit September 24 – 26, 2010 Hyatt Regency Washington, D.C. http://www.icleiusa.org/main-page/news- events/iclei-local-action-summit-2010
  • 37.
    Questions/Discussion Contact Us: Angela Vincent (617)960-3420 x202 angela.vincent@iclei.org Allison Webster – New England Liaison (617) 960-3420 x207 allison.webster@iclei.org www.icleiusa.org/northeast