SlideShare a Scribd company logo
1 of 41
Download to read offline
Mobile Equipment Power
Requirements
L0
CCE 4204
Mobile Equipment Power
Requirements
 The constructor must select the proper equipment to
relocate and/or process materials economically.
 The analysis procedure for matching the best possible
machine to the project task requires inquiry into amachine to the project task requires inquiry into a
machine’s mechanical capability.
 The engineer must first calculate the power required to
propel the machine and its load.
 This power requirement is established by two factors:
1. Rolling Resistance
2. Grade Resistance
Mobile Equipment Power
Requirements
 Equipment manufacturers publish performance charts
for individual machine models.
 These charts enable the equipment planner to analyze
a machine’s ability to perform under a given set of joba machine’s ability to perform under a given set of job
and load conditions.
Payload
 The payload capacity of construction excavation and
hauling equipment can be expressed either
volumetrically or gravimetrically.
 Volumetric capacity can be stated as struck or heaped Volumetric capacity can be stated as struck or heaped
volume and either volume can be expressed in terms of
loose cubic yard, bank cubic yard, or compacted cubic
yard.
 The payload capacity of excavation buckets and
hauling units is often stated by the manufacturer in
terms of the volume of loose material, assuming that
the material is heaped at a specified angle of repose
Machine Performance
Cycle time and payload determine a machine’s
production rate, and machine travel speed directly
affects cycle time.
The three power questions:
1. Required Power
2. Available Power
3. Usable Power
Required Power
 Power required is the power needed to overcome
resisting forces and cause machine motion.
 The forces resisting the movement of mobile The forces resisting the movement of mobile
equipment are:
1. Rolling Resistance
2. Grade Resistance
Rolling Resistance
The resistance of a level surface to constant-velocity
motion across it.
Grade Resistance
The force-opposing movement of a machine up a
frictionless slope.
Total Resistance
Therefore, power required is the power necessary to
overcome the total resistance to machine movement,
which is the sum of rolling and grade resistance.
Total Resistance(TR) = Rolling Resistance(RR)+Grade
Resistance(GR)
Mechanisms of Rolling
Resistance
Rolling Resistance Varies with
the Condition of the Surface
Rolling Resistance Varies with
the Condition of the Surface
Rolling Resistance
The maintenance of low-rolling resistance haul roads is
one of the best financial investments an earthmoving
contractor can make. The cost of having a grader to
maintain the haul road is repaid in increasedmaintain the haul road is repaid in increased
production.
Rolling Resistance
 The rolling resistance in pounds per gross ton is . . .
R = P (lbs.)
W (tons)W (tons)
Where:
R = Rolling resistance in pounds per ton
P = Total tension in tow cable in pounds
W = Gross weight of mobile vehicle in tons
Rolling Resistance
When tire penetration is known, an approximate
rolling resistance value for a wheeled vehicle can be
calculated . . .
RR = [40 + (30 * TP)] * GVW
Where:
RR = Rolling resistance in pounds
TP = Tire penetration in inches
GVW = Gross vehicle weight in tons
Grade Assistance
The effect of gravitational force in aiding movement of
a vehicle down a slope.
Grade Resistance/Assistance
 The force-opposing movement of a machine up a
frictionless slope is known as grade resistance.
 It acts against the total weight of the machine, whether
track type or wheel type.track type or wheel type.
 When a machine moves up an adverse slope, the power
required to keep it moving increases approximately in
proportion to the slope of the road.
 If a machine moves down a sloping road, the power
required to keep it moving is reduced in proportion to
the slope of the road. This is known as grade
assistance.
Grade Resistance
 The most common method of expressing a slope is by
gradient in percent.
 A 1% slope is one where the surface rises or drops 1 ft.
vertically in a horizontal distance of 100 ft.vertically in a horizontal distance of 100 ft.
 If the slope is 5%, the surface rises or drops 5 ft. per 100
ft. of horizontal distance.
 If the surface rises, the slope is defined as plus,
whereas if it drops, the slope is defined as minus.
Frictionless Slope-Force
Relationships
Frictionless Slope-Force
Relationships
 F = W sin α
 N = W cos α
For angles less than 10°, sin α ≈ tan α (the small –angleFor angles less than 10°, sin α ≈ tan α (the small –angle
assumption); with that substitution:
 F = W tan α
 tan α = V = G%
H 100
Frictionless Slope-Force
Relationships
 F = W * G%
100
If we substitute W = 2,000 lb/ton, the formula reducesIf we substitute W = 2,000 lb/ton, the formula reduces
to:
 F = 20 lb/ton * G%
This formula is valid for a G up to about 10%, that is,
the small angle assumption (sin α ≈ tan α).
Total Resistance
 Total resistance equals rolling resistance plus grade
resistance or rolling resistance minus grade assistance.
 It can also be expressed as an effective grade.
Rolling resistance expressed in lb/ton = G%
20 lb/ton
Haul Routes
Hauling efficiency is achieved by careful planning of
haul routes.
Available Power
 Internal combustion engines power most construction
equipment.
 Because diesel engines perform better under heavy-
duty applications than gasoline engines, dieselduty applications than gasoline engines, diesel
powered machines are the workhorses of the
construction industry.
 Diesel engines have longer service lives and lower fuel
consumption.
 Diesel fuel presents less of a fire hazard.
Work and Power
 Work is defined as force through distance.
Work = Force * Distance
Torque
 An internal combustion engine by the combustion of
fuel in a piston develops a mechanical force that acts
on a crankshaft having a radius r.
 The crankshaft in turn drives the flywheel and gears The crankshaft in turn drives the flywheel and gears
that power the other components of the machine.
 The force from a rotating object, such as crankshafts (a
“twisting” force), is termed torque.
The Relationship Between
Horsepower and Torque
Horsepower (hp) = 6.2832 * rpm * Torque = rpm *Torque
33,000 5,25233,000 5,252
 Conversely, to calculate torque . . .
Torque = 5,252 * hp
rpm
Horsepower Rating
 Manufacturers rate machine horsepower as either
gross or flywheel (sometimes listed as net horsepower)
 Gross horsepower is the actual power generated by the
engine prior to load losses for auxiliary systems, suchengine prior to load losses for auxiliary systems, such
as the alternator, air conditioner compressors, and
water pump.
 Flywheel horsepower (fwhp) can be considered as
usable horsepower.
 It is the power available to operate a machine-power
the driveline-after deducting for power losses in the
engine.
Rim pull
 Rim pull is a term that is used to designate the tractive
force between the tires of machine’s driving wheels
and the surface on which they travel.
 If the coefficient of traction is sufficiently high there If the coefficient of traction is sufficiently high there
will be no tire slippage, in which case maximum rim
pull is a function of the power of the engine and the
gear ratios between the engine and the driving wheels.
 If the driving wheels slip on the supporting surface,
the maximum effective rim pull will be equal to the
total pressure the tires exert on the surface multiplied
by the coefficient of traction.
Coefficient of Traction
The factor that determines the maximum possible
tractive force between the powered running gear of a
machine and the surface on which it travels.
Rim Pull Equation
Rim Pull = 375 * hp * efficiency (lb)
speed (mph)
The efficiency of most tractors and trucks will range
from 0.80 to 0.85 (use 0.85 if efficiency is not known).
Drawbar Pull
 The towing force a crawler tractor can exert on a load is
referred to as drawbar pull.
 Drawbar pull is typically expressed in pounds.
 To determine the drawbar pull available for towing a To determine the drawbar pull available for towing a
load it is necessary to subtract from the total pulling
force available at the engine the force required to
overcome the total resistance imposed by the haul
conditions.
 If a crawler tractor tows a load up a slope, its drawbar
pull will be reduced by 20 lb for each ton of weight of
the tractor for each 1% slope.
Usable Power
 Usable power depends on project conditions:
primarily, haul-road surface condition, altitude, and
temperature.
Usable force = Coefficient of traction * Weight on
powered running gear
Performance Charts
 Equipment manufacturers publish performance
charts for individual machine models.
 These charts enable the equipment estimator/planner
to analyze a machine’s ability to perform under a givento analyze a machine’s ability to perform under a given
set of project-imposed load conditions.
 The performance chart is a graphical representation of
the power and corresponding speed the engine and
transmission can deliver.
 The load condition is stated as either rim pull or
drawbar pull.
Rim Pull Performance Charts
 Required Power  Total Resistance
1. Estimate the rim pull (power) required – total
resistance (rolling resistance plus grade resistance) –
based on the probable job conditions.based on the probable job conditions.
2. Locate the power requirement value on the left
vertical scale and project a line horizontally to the
right intersecting a gear curve.
3. From the point at which the horizontal line
intersects the gear curve, project a line vertically to
the bottom x axes, which indicates the speed in mph.
Rim Pull Performance Charts
 Effective Grade  Total Resistance
1. Determine the machine weight both when the
machine is empty and loaded. These two weights,
empty and loaded, are often referred to as the netempty and loaded, are often referred to as the net
vehicle weight and gross vehicle weight.
2. Calculate a total resistance (the sum of rolling plus
grade resistance both expressed as percent grade).
3. Project a line horizontally from the intersection
point of the vertical vehicle-weight projection and
the appropriate total-resistance diagonal.
Rim Pull Performance Charts
 From the point at which the horizontal line
intersects the gear range curve, project a line
vertically to the bottom x axes, which indicates the
machine speed in mph.machine speed in mph.
Retarder Chart
A graphical presentation that identifies the controlled
speed of a machine descending a slope when the
magnitude of the grade assistance is greater than the
rolling resistance.rolling resistance.
L0 Mobile Equipment Power Requirements

More Related Content

What's hot

Basics of crane
Basics of craneBasics of crane
Basics of cranePrem kumar
 
Structurala Analysis Report
Structurala Analysis ReportStructurala Analysis Report
Structurala Analysis Reportsurendra1985
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)ahsanrabbani
 
Design of RCC Column footing
Design of RCC Column footingDesign of RCC Column footing
Design of RCC Column footingArun Kurali
 
BAJA 2013 final year project report
BAJA 2013 final year project reportBAJA 2013 final year project report
BAJA 2013 final year project reportKalyan Potukuchi
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity SSudhaVelan
 
Strength of materials_I
Strength of materials_IStrength of materials_I
Strength of materials_IPralhad Kore
 
RDSO- GE G-1
 RDSO-   GE  G-1 RDSO-   GE  G-1
RDSO- GE G-1selva65
 
Types of cranes
Types of cranesTypes of cranes
Types of cranesZiad Salem
 
Engineering science N4 (FET College)
Engineering science N4 (FET College)Engineering science N4 (FET College)
Engineering science N4 (FET College)Jude Jay
 
Rigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh RajputRigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh RajputGaurav Singh Rajput
 

What's hot (20)

Basics of crane
Basics of craneBasics of crane
Basics of crane
 
Structural engineering i
Structural engineering iStructural engineering i
Structural engineering i
 
Structurala Analysis Report
Structurala Analysis ReportStructurala Analysis Report
Structurala Analysis Report
 
Ch 7 design of rcc footing
Ch 7 design of rcc footingCh 7 design of rcc footing
Ch 7 design of rcc footing
 
Bituminous mix design
Bituminous mix designBituminous mix design
Bituminous mix design
 
Roads & bridges
Roads & bridgesRoads & bridges
Roads & bridges
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailing
 
Design of RCC Column footing
Design of RCC Column footingDesign of RCC Column footing
Design of RCC Column footing
 
Torsion force
Torsion forceTorsion force
Torsion force
 
BAJA 2013 final year project report
BAJA 2013 final year project reportBAJA 2013 final year project report
BAJA 2013 final year project report
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
 
Architectural structures
Architectural structuresArchitectural structures
Architectural structures
 
Strength of materials_I
Strength of materials_IStrength of materials_I
Strength of materials_I
 
RDSO- GE G-1
 RDSO-   GE  G-1 RDSO-   GE  G-1
RDSO- GE G-1
 
gantry crane report
gantry crane reportgantry crane report
gantry crane report
 
Types of cranes
Types of cranesTypes of cranes
Types of cranes
 
Steel structures
Steel structuresSteel structures
Steel structures
 
Engineering science N4 (FET College)
Engineering science N4 (FET College)Engineering science N4 (FET College)
Engineering science N4 (FET College)
 
Rigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh RajputRigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh Rajput
 

Viewers also liked (14)

Four Wheel Steering System
Four  Wheel  Steering  SystemFour  Wheel  Steering  System
Four Wheel Steering System
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
CCIM Institute Cert
CCIM Institute CertCCIM Institute Cert
CCIM Institute Cert
 
Yura ohanyan
Yura ohanyanYura ohanyan
Yura ohanyan
 
RAZIK CV - updated
RAZIK CV - updated RAZIK CV - updated
RAZIK CV - updated
 
Taylor lautner
Taylor lautnerTaylor lautner
Taylor lautner
 
աշխարհի ամենամեծ...
աշխարհի ամենամեծ...աշխարհի ամենամեծ...
աշխարհի ամենամեծ...
 
Research, Design and Manufacturing of Formula Student Racecar.
Research, Design and Manufacturing of Formula Student Racecar.Research, Design and Manufacturing of Formula Student Racecar.
Research, Design and Manufacturing of Formula Student Racecar.
 
MohdHattaSafruddin - CV - 06.03.15
MohdHattaSafruddin - CV - 06.03.15MohdHattaSafruddin - CV - 06.03.15
MohdHattaSafruddin - CV - 06.03.15
 
Introduction to gps
Introduction to gpsIntroduction to gps
Introduction to gps
 
Land polluction for ES
Land polluction for ESLand polluction for ES
Land polluction for ES
 
Software Engineering concept
Software Engineering concept Software Engineering concept
Software Engineering concept
 
Buggy text features
Buggy text featuresBuggy text features
Buggy text features
 
Hydraulic jump
Hydraulic jumpHydraulic jump
Hydraulic jump
 

Similar to L0 Mobile Equipment Power Requirements

Design parameters of electric vehicles ksr
Design parameters of electric vehicles  ksrDesign parameters of electric vehicles  ksr
Design parameters of electric vehicles ksrPresidencyUniversity
 
Introduction to automobile engg.pptx
Introduction to automobile engg.pptxIntroduction to automobile engg.pptx
Introduction to automobile engg.pptxSangram Petkar
 
Vehicle dynamics ppt shiva
Vehicle dynamics ppt shivaVehicle dynamics ppt shiva
Vehicle dynamics ppt shivaShiva Nand
 
CV-2-Power Plant.pptx
CV-2-Power Plant.pptxCV-2-Power Plant.pptx
CV-2-Power Plant.pptxbvmohan1
 
عرض تقديمي لتصميم طريق وكيفية ابعاد الطريق
عرض تقديمي لتصميم طريق وكيفية ابعاد الطريقعرض تقديمي لتصميم طريق وكيفية ابعاد الطريق
عرض تقديمي لتصميم طريق وكيفية ابعاد الطريقssuser09e10f
 
SELECTION OF POWERTRAIN TO ACHIEVE PERFORMANCE OF VEHICLE
SELECTION OF POWERTRAIN TO ACHIEVE PERFORMANCE OF VEHICLESELECTION OF POWERTRAIN TO ACHIEVE PERFORMANCE OF VEHICLE
SELECTION OF POWERTRAIN TO ACHIEVE PERFORMANCE OF VEHICLEJournal For Research
 
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...Hossam Shafiq I
 
6 ijaems jul-2015-11-design of a drivetrain for sae baja racing off-road vehicle
6 ijaems jul-2015-11-design of a drivetrain for sae baja racing off-road vehicle6 ijaems jul-2015-11-design of a drivetrain for sae baja racing off-road vehicle
6 ijaems jul-2015-11-design of a drivetrain for sae baja racing off-road vehicleINFOGAIN PUBLICATION
 
Traction and related terms.pptx
Traction and related terms.pptxTraction and related terms.pptx
Traction and related terms.pptxKishanpatel239870
 
Q921 de1 lec 3 v1
Q921 de1 lec 3 v1Q921 de1 lec 3 v1
Q921 de1 lec 3 v1AFATous
 
Traction and Tractive Effort.pptx
Traction and Tractive Effort.pptxTraction and Tractive Effort.pptx
Traction and Tractive Effort.pptxchaitrali5
 
6 diseno optimo camino minero 2014 douglas canada
6 diseno optimo camino minero 2014 douglas canada6 diseno optimo camino minero 2014 douglas canada
6 diseno optimo camino minero 2014 douglas canadaSierra Francisco Justo
 
E&HV DIGITAL NOTES.pdf
E&HV DIGITAL NOTES.pdfE&HV DIGITAL NOTES.pdf
E&HV DIGITAL NOTES.pdfKalyan Anugu
 
Drive wheel motor torque calculations
Drive wheel motor torque calculationsDrive wheel motor torque calculations
Drive wheel motor torque calculationsAkshay Mistri
 
TRACTION AND ITS PREDICTION
TRACTION AND ITS PREDICTIONTRACTION AND ITS PREDICTION
TRACTION AND ITS PREDICTIONRanit Sarkar
 

Similar to L0 Mobile Equipment Power Requirements (20)

Design parameters of electric vehicles ksr
Design parameters of electric vehicles  ksrDesign parameters of electric vehicles  ksr
Design parameters of electric vehicles ksr
 
Che 10 engineering fundamental
Che  10 engineering fundamentalChe  10 engineering fundamental
Che 10 engineering fundamental
 
DOC-20220923-WA0025..pptx
DOC-20220923-WA0025..pptxDOC-20220923-WA0025..pptx
DOC-20220923-WA0025..pptx
 
Introduction to automobile engg.pptx
Introduction to automobile engg.pptxIntroduction to automobile engg.pptx
Introduction to automobile engg.pptx
 
Vehicle dynamics ppt shiva
Vehicle dynamics ppt shivaVehicle dynamics ppt shiva
Vehicle dynamics ppt shiva
 
CV-2-Power Plant.pptx
CV-2-Power Plant.pptxCV-2-Power Plant.pptx
CV-2-Power Plant.pptx
 
عرض تقديمي لتصميم طريق وكيفية ابعاد الطريق
عرض تقديمي لتصميم طريق وكيفية ابعاد الطريقعرض تقديمي لتصميم طريق وكيفية ابعاد الطريق
عرض تقديمي لتصميم طريق وكيفية ابعاد الطريق
 
SELECTION OF POWERTRAIN TO ACHIEVE PERFORMANCE OF VEHICLE
SELECTION OF POWERTRAIN TO ACHIEVE PERFORMANCE OF VEHICLESELECTION OF POWERTRAIN TO ACHIEVE PERFORMANCE OF VEHICLE
SELECTION OF POWERTRAIN TO ACHIEVE PERFORMANCE OF VEHICLE
 
UNIT-I-EV.pptx
UNIT-I-EV.pptxUNIT-I-EV.pptx
UNIT-I-EV.pptx
 
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
03 Train Resistance and Tractive Power (Railway Engineering Lectures هندسة ال...
 
6 ijaems jul-2015-11-design of a drivetrain for sae baja racing off-road vehicle
6 ijaems jul-2015-11-design of a drivetrain for sae baja racing off-road vehicle6 ijaems jul-2015-11-design of a drivetrain for sae baja racing off-road vehicle
6 ijaems jul-2015-11-design of a drivetrain for sae baja racing off-road vehicle
 
Traction and related terms.pptx
Traction and related terms.pptxTraction and related terms.pptx
Traction and related terms.pptx
 
Q921 de1 lec 3 v1
Q921 de1 lec 3 v1Q921 de1 lec 3 v1
Q921 de1 lec 3 v1
 
Traction and Tractive Effort.pptx
Traction and Tractive Effort.pptxTraction and Tractive Effort.pptx
Traction and Tractive Effort.pptx
 
6 diseno optimo camino minero 2014 douglas canada
6 diseno optimo camino minero 2014 douglas canada6 diseno optimo camino minero 2014 douglas canada
6 diseno optimo camino minero 2014 douglas canada
 
E&HV DIGITAL NOTES.pdf
E&HV DIGITAL NOTES.pdfE&HV DIGITAL NOTES.pdf
E&HV DIGITAL NOTES.pdf
 
Drive wheel motor torque calculations
Drive wheel motor torque calculationsDrive wheel motor torque calculations
Drive wheel motor torque calculations
 
Hybrid vehicles PPT
Hybrid vehicles PPTHybrid vehicles PPT
Hybrid vehicles PPT
 
1.2 bearing life
1.2 bearing life1.2 bearing life
1.2 bearing life
 
TRACTION AND ITS PREDICTION
TRACTION AND ITS PREDICTIONTRACTION AND ITS PREDICTION
TRACTION AND ITS PREDICTION
 

More from Don W. Lewis

L1 Planning for Earthwork Construction
L1 Planning for Earthwork ConstructionL1 Planning for Earthwork Construction
L1 Planning for Earthwork ConstructionDon W. Lewis
 
Contract_Plans_Reading.Plan_Book
Contract_Plans_Reading.Plan_BookContract_Plans_Reading.Plan_Book
Contract_Plans_Reading.Plan_BookDon W. Lewis
 
Contract_Plans_Reading.Textbook
Contract_Plans_Reading.TextbookContract_Plans_Reading.Textbook
Contract_Plans_Reading.TextbookDon W. Lewis
 
Kansas City Collapse
Kansas City CollapseKansas City Collapse
Kansas City CollapseDon W. Lewis
 
The TV Antenna Tower
The TV Antenna TowerThe TV Antenna Tower
The TV Antenna TowerDon W. Lewis
 
Testing Water and Ethics
Testing Water and EthicsTesting Water and Ethics
Testing Water and EthicsDon W. Lewis
 
The Space Shuttle Disasters
The Space Shuttle DisastersThe Space Shuttle Disasters
The Space Shuttle DisastersDon W. Lewis
 
Engineers in Organizations
Engineers in OrganizationsEngineers in Organizations
Engineers in OrganizationsDon W. Lewis
 
Masters Report.PDF
Masters Report.PDFMasters Report.PDF
Masters Report.PDFDon W. Lewis
 
Engineering Ethics
Engineering EthicsEngineering Ethics
Engineering EthicsDon W. Lewis
 
Analyzing Risk-Based corrective action plans
Analyzing Risk-Based corrective action plansAnalyzing Risk-Based corrective action plans
Analyzing Risk-Based corrective action plansDon W. Lewis
 

More from Don W. Lewis (18)

L1 Planning for Earthwork Construction
L1 Planning for Earthwork ConstructionL1 Planning for Earthwork Construction
L1 Planning for Earthwork Construction
 
Contract_Plans_Reading.Plan_Book
Contract_Plans_Reading.Plan_BookContract_Plans_Reading.Plan_Book
Contract_Plans_Reading.Plan_Book
 
Contract_Plans_Reading.Textbook
Contract_Plans_Reading.TextbookContract_Plans_Reading.Textbook
Contract_Plans_Reading.Textbook
 
Lewis_D
Lewis_DLewis_D
Lewis_D
 
Kansas City Collapse
Kansas City CollapseKansas City Collapse
Kansas City Collapse
 
The TV Antenna Tower
The TV Antenna TowerThe TV Antenna Tower
The TV Antenna Tower
 
Testing Water and Ethics
Testing Water and EthicsTesting Water and Ethics
Testing Water and Ethics
 
The Space Shuttle Disasters
The Space Shuttle DisastersThe Space Shuttle Disasters
The Space Shuttle Disasters
 
The Bruening Case
The Bruening CaseThe Bruening Case
The Bruening Case
 
Business Ethics
Business EthicsBusiness Ethics
Business Ethics
 
Anger Management
Anger ManagementAnger Management
Anger Management
 
Legal Ethics
Legal EthicsLegal Ethics
Legal Ethics
 
Medical Ethics
Medical EthicsMedical Ethics
Medical Ethics
 
Leading Teams
Leading TeamsLeading Teams
Leading Teams
 
Engineers in Organizations
Engineers in OrganizationsEngineers in Organizations
Engineers in Organizations
 
Masters Report.PDF
Masters Report.PDFMasters Report.PDF
Masters Report.PDF
 
Engineering Ethics
Engineering EthicsEngineering Ethics
Engineering Ethics
 
Analyzing Risk-Based corrective action plans
Analyzing Risk-Based corrective action plansAnalyzing Risk-Based corrective action plans
Analyzing Risk-Based corrective action plans
 

L0 Mobile Equipment Power Requirements

  • 2. Mobile Equipment Power Requirements  The constructor must select the proper equipment to relocate and/or process materials economically.  The analysis procedure for matching the best possible machine to the project task requires inquiry into amachine to the project task requires inquiry into a machine’s mechanical capability.  The engineer must first calculate the power required to propel the machine and its load.  This power requirement is established by two factors: 1. Rolling Resistance 2. Grade Resistance
  • 3. Mobile Equipment Power Requirements  Equipment manufacturers publish performance charts for individual machine models.  These charts enable the equipment planner to analyze a machine’s ability to perform under a given set of joba machine’s ability to perform under a given set of job and load conditions.
  • 4. Payload  The payload capacity of construction excavation and hauling equipment can be expressed either volumetrically or gravimetrically.  Volumetric capacity can be stated as struck or heaped Volumetric capacity can be stated as struck or heaped volume and either volume can be expressed in terms of loose cubic yard, bank cubic yard, or compacted cubic yard.  The payload capacity of excavation buckets and hauling units is often stated by the manufacturer in terms of the volume of loose material, assuming that the material is heaped at a specified angle of repose
  • 5. Machine Performance Cycle time and payload determine a machine’s production rate, and machine travel speed directly affects cycle time. The three power questions: 1. Required Power 2. Available Power 3. Usable Power
  • 6. Required Power  Power required is the power needed to overcome resisting forces and cause machine motion.  The forces resisting the movement of mobile The forces resisting the movement of mobile equipment are: 1. Rolling Resistance 2. Grade Resistance
  • 7. Rolling Resistance The resistance of a level surface to constant-velocity motion across it.
  • 8. Grade Resistance The force-opposing movement of a machine up a frictionless slope.
  • 9. Total Resistance Therefore, power required is the power necessary to overcome the total resistance to machine movement, which is the sum of rolling and grade resistance. Total Resistance(TR) = Rolling Resistance(RR)+Grade Resistance(GR)
  • 11. Rolling Resistance Varies with the Condition of the Surface
  • 12. Rolling Resistance Varies with the Condition of the Surface
  • 13. Rolling Resistance The maintenance of low-rolling resistance haul roads is one of the best financial investments an earthmoving contractor can make. The cost of having a grader to maintain the haul road is repaid in increasedmaintain the haul road is repaid in increased production.
  • 14. Rolling Resistance  The rolling resistance in pounds per gross ton is . . . R = P (lbs.) W (tons)W (tons) Where: R = Rolling resistance in pounds per ton P = Total tension in tow cable in pounds W = Gross weight of mobile vehicle in tons
  • 15. Rolling Resistance When tire penetration is known, an approximate rolling resistance value for a wheeled vehicle can be calculated . . . RR = [40 + (30 * TP)] * GVW Where: RR = Rolling resistance in pounds TP = Tire penetration in inches GVW = Gross vehicle weight in tons
  • 16. Grade Assistance The effect of gravitational force in aiding movement of a vehicle down a slope.
  • 17. Grade Resistance/Assistance  The force-opposing movement of a machine up a frictionless slope is known as grade resistance.  It acts against the total weight of the machine, whether track type or wheel type.track type or wheel type.  When a machine moves up an adverse slope, the power required to keep it moving increases approximately in proportion to the slope of the road.  If a machine moves down a sloping road, the power required to keep it moving is reduced in proportion to the slope of the road. This is known as grade assistance.
  • 18. Grade Resistance  The most common method of expressing a slope is by gradient in percent.  A 1% slope is one where the surface rises or drops 1 ft. vertically in a horizontal distance of 100 ft.vertically in a horizontal distance of 100 ft.  If the slope is 5%, the surface rises or drops 5 ft. per 100 ft. of horizontal distance.  If the surface rises, the slope is defined as plus, whereas if it drops, the slope is defined as minus.
  • 20. Frictionless Slope-Force Relationships  F = W sin α  N = W cos α For angles less than 10°, sin α ≈ tan α (the small –angleFor angles less than 10°, sin α ≈ tan α (the small –angle assumption); with that substitution:  F = W tan α  tan α = V = G% H 100
  • 21. Frictionless Slope-Force Relationships  F = W * G% 100 If we substitute W = 2,000 lb/ton, the formula reducesIf we substitute W = 2,000 lb/ton, the formula reduces to:  F = 20 lb/ton * G% This formula is valid for a G up to about 10%, that is, the small angle assumption (sin α ≈ tan α).
  • 22. Total Resistance  Total resistance equals rolling resistance plus grade resistance or rolling resistance minus grade assistance.  It can also be expressed as an effective grade. Rolling resistance expressed in lb/ton = G% 20 lb/ton
  • 23. Haul Routes Hauling efficiency is achieved by careful planning of haul routes.
  • 24. Available Power  Internal combustion engines power most construction equipment.  Because diesel engines perform better under heavy- duty applications than gasoline engines, dieselduty applications than gasoline engines, diesel powered machines are the workhorses of the construction industry.  Diesel engines have longer service lives and lower fuel consumption.  Diesel fuel presents less of a fire hazard.
  • 25. Work and Power  Work is defined as force through distance. Work = Force * Distance
  • 26. Torque  An internal combustion engine by the combustion of fuel in a piston develops a mechanical force that acts on a crankshaft having a radius r.  The crankshaft in turn drives the flywheel and gears The crankshaft in turn drives the flywheel and gears that power the other components of the machine.  The force from a rotating object, such as crankshafts (a “twisting” force), is termed torque.
  • 27. The Relationship Between Horsepower and Torque Horsepower (hp) = 6.2832 * rpm * Torque = rpm *Torque 33,000 5,25233,000 5,252  Conversely, to calculate torque . . . Torque = 5,252 * hp rpm
  • 28. Horsepower Rating  Manufacturers rate machine horsepower as either gross or flywheel (sometimes listed as net horsepower)  Gross horsepower is the actual power generated by the engine prior to load losses for auxiliary systems, suchengine prior to load losses for auxiliary systems, such as the alternator, air conditioner compressors, and water pump.  Flywheel horsepower (fwhp) can be considered as usable horsepower.  It is the power available to operate a machine-power the driveline-after deducting for power losses in the engine.
  • 29. Rim pull  Rim pull is a term that is used to designate the tractive force between the tires of machine’s driving wheels and the surface on which they travel.  If the coefficient of traction is sufficiently high there If the coefficient of traction is sufficiently high there will be no tire slippage, in which case maximum rim pull is a function of the power of the engine and the gear ratios between the engine and the driving wheels.  If the driving wheels slip on the supporting surface, the maximum effective rim pull will be equal to the total pressure the tires exert on the surface multiplied by the coefficient of traction.
  • 30. Coefficient of Traction The factor that determines the maximum possible tractive force between the powered running gear of a machine and the surface on which it travels.
  • 31. Rim Pull Equation Rim Pull = 375 * hp * efficiency (lb) speed (mph) The efficiency of most tractors and trucks will range from 0.80 to 0.85 (use 0.85 if efficiency is not known).
  • 32. Drawbar Pull  The towing force a crawler tractor can exert on a load is referred to as drawbar pull.  Drawbar pull is typically expressed in pounds.  To determine the drawbar pull available for towing a To determine the drawbar pull available for towing a load it is necessary to subtract from the total pulling force available at the engine the force required to overcome the total resistance imposed by the haul conditions.  If a crawler tractor tows a load up a slope, its drawbar pull will be reduced by 20 lb for each ton of weight of the tractor for each 1% slope.
  • 33. Usable Power  Usable power depends on project conditions: primarily, haul-road surface condition, altitude, and temperature. Usable force = Coefficient of traction * Weight on powered running gear
  • 34. Performance Charts  Equipment manufacturers publish performance charts for individual machine models.  These charts enable the equipment estimator/planner to analyze a machine’s ability to perform under a givento analyze a machine’s ability to perform under a given set of project-imposed load conditions.  The performance chart is a graphical representation of the power and corresponding speed the engine and transmission can deliver.  The load condition is stated as either rim pull or drawbar pull.
  • 35.
  • 36. Rim Pull Performance Charts  Required Power  Total Resistance 1. Estimate the rim pull (power) required – total resistance (rolling resistance plus grade resistance) – based on the probable job conditions.based on the probable job conditions. 2. Locate the power requirement value on the left vertical scale and project a line horizontally to the right intersecting a gear curve. 3. From the point at which the horizontal line intersects the gear curve, project a line vertically to the bottom x axes, which indicates the speed in mph.
  • 37.
  • 38. Rim Pull Performance Charts  Effective Grade  Total Resistance 1. Determine the machine weight both when the machine is empty and loaded. These two weights, empty and loaded, are often referred to as the netempty and loaded, are often referred to as the net vehicle weight and gross vehicle weight. 2. Calculate a total resistance (the sum of rolling plus grade resistance both expressed as percent grade). 3. Project a line horizontally from the intersection point of the vertical vehicle-weight projection and the appropriate total-resistance diagonal.
  • 39. Rim Pull Performance Charts  From the point at which the horizontal line intersects the gear range curve, project a line vertically to the bottom x axes, which indicates the machine speed in mph.machine speed in mph.
  • 40. Retarder Chart A graphical presentation that identifies the controlled speed of a machine descending a slope when the magnitude of the grade assistance is greater than the rolling resistance.rolling resistance.