SlideShare a Scribd company logo
1 of 21
Zone 2 Level 4 Roof Framing
Indooroopilly Shopping Centre
Zone 2 Level 4 Roof Framing
Erection Sequence Grid S25-S24 / D-A1
Step 1
1. Install RA1 Raking angles as per lift sequence
2. Install SC1 columns
3. Install TR11 then TR12
4. Install purlins & bridging
LIFT 1
LIFT 2
LIFT 4
LIFT 3
Erection Sequence Grid S25-S24 / D-A1
Step 2
1. Assemble walkway frames on the ground
2. Cladding to be complete once frames or installed
Erection Sequence Grid S25-S24 / D-A1
Step 3
1. Install B13 to U/S Slab on Grid S24
2. Install B16’s with mini crane as per lift sequence
3. Install SC1 column and B13 on Grid B as per lift sequence
LIFT 1
LIFT 2
LIFT 3
LIFT 4
LIFT 5
LIFT 7
LIFT 6
Erection Sequence Grid S25-S24 / D-A1
Step 4
1. Install SC1 columns supported by B16’s & B13
2. Install 2/TR9’s as per lift sequence
LIFT 1
LIFT 2
LIFT 3
LIFT 4
Erection Sequence Grid S25-S24 / D-A1
FRAME STEEL WEIGHT
(kg)
CLADDING WEIGHT
(kg) (Approx.)
TOTAL WEIGHT
(Approx.)
LENGTH WIDTH HEIGHT
Frame 5 1721 700 2421 10700 1850 2570
Frame 6 656 400 1056 3650 1850 2570
Frame 7 1260 600 1860 9170 1600 3070
Step 5
1. Install walkway frames as per lift sequence
2. Temporary propping as required
3. Install R3 & HC1’s Between Grids C-B
4. B9’s & Joists
5. Install Walkway Trusses
LIFT 4 & 5
LIFT 6 & 7
Erection Sequence Grid S25-S24 / D-A1
Step 5
1. Install R1 rafter on Grid B / R1 rafter on Between Grids B-A as per
lift sequence
2. Install SC1 & 2/TR9’s as per lift sequence
3. Install struts, bracing, purlins, bridging & fly bracing as required
LIFT 1 LIFT 3
LIFT 2
LIFT 4
LIFT 5
Erection Sequence Lower Roof Grid A-D
Step 1
1. Install SC1 as per lift sequence
2. Install B12 transfer beams
3. Install rafters to tie back to structure
Erection Sequence Lower Roof Grid A-D
Step 2
1. Install SC1’s as per lift sequence
2. Install Rafter to tie back to B12 with 4 tonne mini crane
3. Install WH1(u) and S1 as per lift sequence
4. Install Bracings, Raking angles, Fly bracings and
Purlins as required
Erection Sequence Lower Roof Grid A-D
Step 3
1. Install Trusses as per lift sequence
Erection Sequence Lower Roof Grid D-F
Step 1
1. Install SC1 & SC3 as per lift sequence
2. Install B1 on grid S26
3. Install rafters to tie back to B1 with 4 tonne mini crane
4. Install S1, and WH1 (u) as per Lift sequence
5. Install Bracings, Fly bracings and Purlins as required
Erection Sequence Lower Roof Grid D-F
Step 2
1. Install trusses as per lift sequence
Erection Sequence Lower Roof Grid F-H
Step 1
1. Install SC1, SC3 & SC4 as per lift sequence
2. Install B1 on grid 26
3. Install rafters to tie structure back to B1 with 4 tonne mini crane
4. Install S1 & WH1 (u) as per lift sequence
5. Install bracings, fly bracing, Raking angles and purlins as required
Erection Sequence Lower Roof Grid F-H
Step 2
1. Lift and secure trusses as per lift sequence
Erection Sequence Grid S24-S21
Step 1
1. Assemble walkway frames at HSS yard
2. Allow Wadsworth Contractors to Clad at HSS yard
Erection Sequence Grid S24-S21
Step 2
1. Install walkway framing North of grid 2A
2. Assemble columns, rafters & beams as per assembly detail
3. Lift assembled frames into position as per lift sequence
4. Install S2 struts to tie columns & rafters back to exist. Structure as per lift sequence
5. Install temporary bracing as required
FRAME STEEL WEIGHT (kg) TOTAL WEIGHT WIDTH HEIGHT
Frame 1 1240 1240 3260 13350
Frame 2 1220 1220 3260 13350
Frame 3 1130 1130 3260 13350
Frame 4 1090 1090 2760 13350
Erection Sequence Grid S24-S21
Step 3
1. Lift walkway frames into position and secure as per lift sequence
2. Install SC4 Column as per lift sequence
3. Install TR5 trusses as per lift sequence
4. Install rafter to tie back to existing structure
5. Lift walkway 4 and secure as per lift sequence
6. Install Purlins and bracings as required
FRAME STEEL WEIGHT
(kg)
CLADDING WEIGHT
(kg) (Approx.)
TOTAL WEIGHT
(Approx.)
LENGTH WIDTH HEIGHT
Frame 1 1222 600 1822 5270 1750 4260
Frame 2 1064 500 1564 6200 1750 2900
Frame 3 1043 500 1543 6040 1750 2900
Frame 4 700 400 1100 3840 1750 2900
Erection Sequence Grid S24-S21
Step 4
1. Lift TR5 trusses into position and secure as per lift sequence
2. Remove temporary bracing
LIFT 7
LIFT 8
LIFT 9
Erection Sequence Upper Roof Framing
FRAME STEEL WEIGHT
(kg)
TOTAL
WEIGHT
LENGTH WIDTH HEIGHT
Frame 1 5210 5210 11240 11200 250
Frame 2 5210 5210 11240 11200 250
Step 1
1. Install SC2 on Grid C-D/S26
2. Assemble Upper roof frame grids C-E/S26-S28 on the ground
3. Install assembled roof frame
4. Repeat process for roof frame on grids F-H/S26-S28
LIFT 1
LIFT 2
Erection Sequence Awning Roof Grid A-H
Step 1
1. Install SC2 as per lift sequence
2. Install B2 Rafter as per lift sequence
3. Install P2 to be bolted to B3 on ground and lifted into place
4. Repeat Process from Grids A-H
ASSEMBLY STEEL WEIGHT
(kg)
LENGTH WIDTH HEIGHT
Assembly 1 1600 6000 5060 460
Erection Grid A1-D1
Step 1
1. Lift Trusses and hangers assembly into position and secure
2. Install R8 to hangers
3. Install B14 between grids 2A - 3A as per lift sequence
4. Install purlins between grids 2A - 3A

More Related Content

What's hot

multistorey building design by sap and autocad
multistorey building design by sap and autocadmultistorey building design by sap and autocad
multistorey building design by sap and autocadRazes Dhakal
 
ANALYSIS & DESIGN OF G+3 STORIED REINFORCED CONCRETE BUILDING
ANALYSIS & DESIGN OF G+3 STORIED REINFORCED CONCRETE BUILDING ANALYSIS & DESIGN OF G+3 STORIED REINFORCED CONCRETE BUILDING
ANALYSIS & DESIGN OF G+3 STORIED REINFORCED CONCRETE BUILDING Abhilash Chandra Dey
 
Structural analysis and design of multi storey ppt
Structural analysis and design of multi storey pptStructural analysis and design of multi storey ppt
Structural analysis and design of multi storey pptSHIVUNAIKA B
 
Design of multistorey building
Design of multistorey buildingDesign of multistorey building
Design of multistorey buildingSivaji Djpk
 
Computer aided analysis and design of multi story building
Computer aided analysis and design of multi story buildingComputer aided analysis and design of multi story building
Computer aided analysis and design of multi story buildingparas6904
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGAnjneya Srivastava
 
Setting out of Tunnel
Setting out of TunnelSetting out of Tunnel
Setting out of TunnelSachinGunjal7
 
Analysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexAnalysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexDhananjay Singh
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadgopichand's
 

What's hot (11)

multistorey building design by sap and autocad
multistorey building design by sap and autocadmultistorey building design by sap and autocad
multistorey building design by sap and autocad
 
ANALYSIS & DESIGN OF G+3 STORIED REINFORCED CONCRETE BUILDING
ANALYSIS & DESIGN OF G+3 STORIED REINFORCED CONCRETE BUILDING ANALYSIS & DESIGN OF G+3 STORIED REINFORCED CONCRETE BUILDING
ANALYSIS & DESIGN OF G+3 STORIED REINFORCED CONCRETE BUILDING
 
Structural analysis and design of multi storey ppt
Structural analysis and design of multi storey pptStructural analysis and design of multi storey ppt
Structural analysis and design of multi storey ppt
 
Villa
VillaVilla
Villa
 
Ip83 6
Ip83 6Ip83 6
Ip83 6
 
Design of multistorey building
Design of multistorey buildingDesign of multistorey building
Design of multistorey building
 
Computer aided analysis and design of multi story building
Computer aided analysis and design of multi story buildingComputer aided analysis and design of multi story building
Computer aided analysis and design of multi story building
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
 
Setting out of Tunnel
Setting out of TunnelSetting out of Tunnel
Setting out of Tunnel
 
Analysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexAnalysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complex
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
 

Similar to Kumar sample erection sequence

Metro ppt-180628112005
Metro ppt-180628112005Metro ppt-180628112005
Metro ppt-180628112005PRATAP MISHRA
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
 
PDR Presentation
PDR PresentationPDR Presentation
PDR PresentationNate Pham
 
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALC
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALCRail Alliance Event on 25/02/15: Lighting Column Specification - ALC
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALCInstitution of Lighting Professionals
 
Understanding-api-4f-structures.pdf
Understanding-api-4f-structures.pdfUnderstanding-api-4f-structures.pdf
Understanding-api-4f-structures.pdfGordanKaniaj1
 
Design of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel BlockDesign of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel Blockjeyanthi4
 
BSCI 1173
BSCI 1173BSCI 1173
BSCI 1173Caulk
 
BoSS Mobile Access Product Guide
BoSS Mobile Access Product GuideBoSS Mobile Access Product Guide
BoSS Mobile Access Product GuideStuart Harling
 
SW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptxSW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptxLeDuc49898
 
Suspension Bridge
Suspension BridgeSuspension Bridge
Suspension BridgeAayushi5
 
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)Franco Bontempi Org Didattica
 
CIVIL AIR PATROL CDR
CIVIL AIR PATROL CDRCIVIL AIR PATROL CDR
CIVIL AIR PATROL CDRJason Labonte
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline PlanningVR M
 
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CREITH
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CREITHSAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CREITH
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CREITHSunit Dhingra
 
Benjamin colbrandt | C-Power offshore windmolenpark
Benjamin colbrandt  | C-Power offshore windmolenparkBenjamin colbrandt  | C-Power offshore windmolenpark
Benjamin colbrandt | C-Power offshore windmolenparkGreenbridge nv
 
Hitachi ex600 lch 5 excavator service repair manual
Hitachi ex600 lch 5 excavator service repair manualHitachi ex600 lch 5 excavator service repair manual
Hitachi ex600 lch 5 excavator service repair manualudfjjdjkskkem
 
Hitachi ex550 lc 5 excavator service repair manual
Hitachi ex550 lc 5 excavator service repair manualHitachi ex550 lc 5 excavator service repair manual
Hitachi ex550 lc 5 excavator service repair manualudfjjdjkskkem
 
Hitachi ex600 h 5 excavator service repair manual
Hitachi ex600 h 5 excavator service repair manualHitachi ex600 h 5 excavator service repair manual
Hitachi ex600 h 5 excavator service repair manualudfjjdjkskkem
 
Hitachi ex550 5 excavator service repair manual
Hitachi ex550 5 excavator service repair manualHitachi ex550 5 excavator service repair manual
Hitachi ex550 5 excavator service repair manualudfjjdjkskkem
 
Design of Elevated Viaduct.pptx
Design of Elevated Viaduct.pptxDesign of Elevated Viaduct.pptx
Design of Elevated Viaduct.pptxAman Khandelwal
 

Similar to Kumar sample erection sequence (20)

Metro ppt-180628112005
Metro ppt-180628112005Metro ppt-180628112005
Metro ppt-180628112005
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
 
PDR Presentation
PDR PresentationPDR Presentation
PDR Presentation
 
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALC
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALCRail Alliance Event on 25/02/15: Lighting Column Specification - ALC
Rail Alliance Event on 25/02/15: Lighting Column Specification - ALC
 
Understanding-api-4f-structures.pdf
Understanding-api-4f-structures.pdfUnderstanding-api-4f-structures.pdf
Understanding-api-4f-structures.pdf
 
Design of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel BlockDesign of G+8 RCC Training Institute & Hostel Block
Design of G+8 RCC Training Institute & Hostel Block
 
BSCI 1173
BSCI 1173BSCI 1173
BSCI 1173
 
BoSS Mobile Access Product Guide
BoSS Mobile Access Product GuideBoSS Mobile Access Product Guide
BoSS Mobile Access Product Guide
 
SW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptxSW Presentation-SC (05.09.2021).pptx
SW Presentation-SC (05.09.2021).pptx
 
Suspension Bridge
Suspension BridgeSuspension Bridge
Suspension Bridge
 
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)
CM - Jauregui - Sapienza University of Rome (60 min, part i, members modified)
 
CIVIL AIR PATROL CDR
CIVIL AIR PATROL CDRCIVIL AIR PATROL CDR
CIVIL AIR PATROL CDR
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
 
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CREITH
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CREITHSAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CREITH
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CREITH
 
Benjamin colbrandt | C-Power offshore windmolenpark
Benjamin colbrandt  | C-Power offshore windmolenparkBenjamin colbrandt  | C-Power offshore windmolenpark
Benjamin colbrandt | C-Power offshore windmolenpark
 
Hitachi ex600 lch 5 excavator service repair manual
Hitachi ex600 lch 5 excavator service repair manualHitachi ex600 lch 5 excavator service repair manual
Hitachi ex600 lch 5 excavator service repair manual
 
Hitachi ex550 lc 5 excavator service repair manual
Hitachi ex550 lc 5 excavator service repair manualHitachi ex550 lc 5 excavator service repair manual
Hitachi ex550 lc 5 excavator service repair manual
 
Hitachi ex600 h 5 excavator service repair manual
Hitachi ex600 h 5 excavator service repair manualHitachi ex600 h 5 excavator service repair manual
Hitachi ex600 h 5 excavator service repair manual
 
Hitachi ex550 5 excavator service repair manual
Hitachi ex550 5 excavator service repair manualHitachi ex550 5 excavator service repair manual
Hitachi ex550 5 excavator service repair manual
 
Design of Elevated Viaduct.pptx
Design of Elevated Viaduct.pptxDesign of Elevated Viaduct.pptx
Design of Elevated Viaduct.pptx
 

Recently uploaded

Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfrs7054576148
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 

Recently uploaded (20)

FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 

Kumar sample erection sequence

  • 1. Zone 2 Level 4 Roof Framing Indooroopilly Shopping Centre Zone 2 Level 4 Roof Framing
  • 2. Erection Sequence Grid S25-S24 / D-A1 Step 1 1. Install RA1 Raking angles as per lift sequence 2. Install SC1 columns 3. Install TR11 then TR12 4. Install purlins & bridging LIFT 1 LIFT 2 LIFT 4 LIFT 3
  • 3. Erection Sequence Grid S25-S24 / D-A1 Step 2 1. Assemble walkway frames on the ground 2. Cladding to be complete once frames or installed
  • 4. Erection Sequence Grid S25-S24 / D-A1 Step 3 1. Install B13 to U/S Slab on Grid S24 2. Install B16’s with mini crane as per lift sequence 3. Install SC1 column and B13 on Grid B as per lift sequence LIFT 1 LIFT 2 LIFT 3 LIFT 4 LIFT 5 LIFT 7 LIFT 6
  • 5. Erection Sequence Grid S25-S24 / D-A1 Step 4 1. Install SC1 columns supported by B16’s & B13 2. Install 2/TR9’s as per lift sequence LIFT 1 LIFT 2 LIFT 3 LIFT 4
  • 6. Erection Sequence Grid S25-S24 / D-A1 FRAME STEEL WEIGHT (kg) CLADDING WEIGHT (kg) (Approx.) TOTAL WEIGHT (Approx.) LENGTH WIDTH HEIGHT Frame 5 1721 700 2421 10700 1850 2570 Frame 6 656 400 1056 3650 1850 2570 Frame 7 1260 600 1860 9170 1600 3070 Step 5 1. Install walkway frames as per lift sequence 2. Temporary propping as required 3. Install R3 & HC1’s Between Grids C-B 4. B9’s & Joists 5. Install Walkway Trusses LIFT 4 & 5 LIFT 6 & 7
  • 7. Erection Sequence Grid S25-S24 / D-A1 Step 5 1. Install R1 rafter on Grid B / R1 rafter on Between Grids B-A as per lift sequence 2. Install SC1 & 2/TR9’s as per lift sequence 3. Install struts, bracing, purlins, bridging & fly bracing as required LIFT 1 LIFT 3 LIFT 2 LIFT 4 LIFT 5
  • 8. Erection Sequence Lower Roof Grid A-D Step 1 1. Install SC1 as per lift sequence 2. Install B12 transfer beams 3. Install rafters to tie back to structure
  • 9. Erection Sequence Lower Roof Grid A-D Step 2 1. Install SC1’s as per lift sequence 2. Install Rafter to tie back to B12 with 4 tonne mini crane 3. Install WH1(u) and S1 as per lift sequence 4. Install Bracings, Raking angles, Fly bracings and Purlins as required
  • 10. Erection Sequence Lower Roof Grid A-D Step 3 1. Install Trusses as per lift sequence
  • 11. Erection Sequence Lower Roof Grid D-F Step 1 1. Install SC1 & SC3 as per lift sequence 2. Install B1 on grid S26 3. Install rafters to tie back to B1 with 4 tonne mini crane 4. Install S1, and WH1 (u) as per Lift sequence 5. Install Bracings, Fly bracings and Purlins as required
  • 12. Erection Sequence Lower Roof Grid D-F Step 2 1. Install trusses as per lift sequence
  • 13. Erection Sequence Lower Roof Grid F-H Step 1 1. Install SC1, SC3 & SC4 as per lift sequence 2. Install B1 on grid 26 3. Install rafters to tie structure back to B1 with 4 tonne mini crane 4. Install S1 & WH1 (u) as per lift sequence 5. Install bracings, fly bracing, Raking angles and purlins as required
  • 14. Erection Sequence Lower Roof Grid F-H Step 2 1. Lift and secure trusses as per lift sequence
  • 15. Erection Sequence Grid S24-S21 Step 1 1. Assemble walkway frames at HSS yard 2. Allow Wadsworth Contractors to Clad at HSS yard
  • 16. Erection Sequence Grid S24-S21 Step 2 1. Install walkway framing North of grid 2A 2. Assemble columns, rafters & beams as per assembly detail 3. Lift assembled frames into position as per lift sequence 4. Install S2 struts to tie columns & rafters back to exist. Structure as per lift sequence 5. Install temporary bracing as required FRAME STEEL WEIGHT (kg) TOTAL WEIGHT WIDTH HEIGHT Frame 1 1240 1240 3260 13350 Frame 2 1220 1220 3260 13350 Frame 3 1130 1130 3260 13350 Frame 4 1090 1090 2760 13350
  • 17. Erection Sequence Grid S24-S21 Step 3 1. Lift walkway frames into position and secure as per lift sequence 2. Install SC4 Column as per lift sequence 3. Install TR5 trusses as per lift sequence 4. Install rafter to tie back to existing structure 5. Lift walkway 4 and secure as per lift sequence 6. Install Purlins and bracings as required FRAME STEEL WEIGHT (kg) CLADDING WEIGHT (kg) (Approx.) TOTAL WEIGHT (Approx.) LENGTH WIDTH HEIGHT Frame 1 1222 600 1822 5270 1750 4260 Frame 2 1064 500 1564 6200 1750 2900 Frame 3 1043 500 1543 6040 1750 2900 Frame 4 700 400 1100 3840 1750 2900
  • 18. Erection Sequence Grid S24-S21 Step 4 1. Lift TR5 trusses into position and secure as per lift sequence 2. Remove temporary bracing LIFT 7 LIFT 8 LIFT 9
  • 19. Erection Sequence Upper Roof Framing FRAME STEEL WEIGHT (kg) TOTAL WEIGHT LENGTH WIDTH HEIGHT Frame 1 5210 5210 11240 11200 250 Frame 2 5210 5210 11240 11200 250 Step 1 1. Install SC2 on Grid C-D/S26 2. Assemble Upper roof frame grids C-E/S26-S28 on the ground 3. Install assembled roof frame 4. Repeat process for roof frame on grids F-H/S26-S28 LIFT 1 LIFT 2
  • 20. Erection Sequence Awning Roof Grid A-H Step 1 1. Install SC2 as per lift sequence 2. Install B2 Rafter as per lift sequence 3. Install P2 to be bolted to B3 on ground and lifted into place 4. Repeat Process from Grids A-H ASSEMBLY STEEL WEIGHT (kg) LENGTH WIDTH HEIGHT Assembly 1 1600 6000 5060 460
  • 21. Erection Grid A1-D1 Step 1 1. Lift Trusses and hangers assembly into position and secure 2. Install R8 to hangers 3. Install B14 between grids 2A - 3A as per lift sequence 4. Install purlins between grids 2A - 3A