SlideShare a Scribd company logo
1 of 7
Download to read offline
KENGEN
INITIATION OF COVERAGE AND VALUATION REPORT
I initiate coverage of Kengen midway in its ambitious plan dubbed “Good to great” to generate
3,000MW of power by 2018 which falls in Horizon II. Horizon I was during the period 2008-2013,Horizon
II between 2013-2018 and Horizon III from 2018-2030.The specific achievements are;
Horizon I- To increase installed capacity by 500MW between July 2008 and June 2012.
Horizon II-To increase installed capacity by an additional 1500MW (To 3000MW) between July 2013
and june 2008.
Horizon III-To focus on expansion of opportunities beyond the country. Beyond 2018, KenGen with other power
generators will have achieved power stability and sustainability and therefore the company will trade
power with other Eastern Africa companies.
Their ambitious plan is in tandem with the National LCPDP (Least Cost Power Development Plan) that
seeks to increase and redistribute the energy mix to cheaper energy. During Horizon I they envisaged to
have an installed capacity of 1,500MW .They managed an installed capacity of by 1238.4MW falling
short by 261.4MW thereby managing an additional 292MW (installed Capacity in 2007 was 946MW).The
effective capacity was 1133MW caused by short falls from Hydro plants. Geothermal plants were
stable.The national LCPDP has identified geothermal generation has the main driver to meet this target;
The main risk to meeting this target is that geothermal power plants are very expensive to build.
Installed and Effective installed power by KENGEN stands as follows:
2010 2011 2012 2013 2014 2015
Installed 1,053.8 1,177.1 1,209.6 1,238.4 1,339.4 1,537.4
Effective 1,030.5 1,064.5 1,162.9 1,133.3 1,268.2
(Source Data:Kenya Power Financial statements)
In the Horizon II period meant to achieve 3,000MW, as of August 2015 installed capacity stood at
1,537MW with 200MW injected into the grid during the year. It is highly unlikely that they will meet
Horizon II targets.
Disclaimer: Information in the public domain claims an additional 280MW was injected in
December. This is erroneous as this refers to installed capacity of both olkaria I and IV. By financial end
year 2014 Olkaria I stood at 45MW and Olkaria IV at 70MW.Today it stands at 140MW each thus an
additional 165MW.Olkaria well head 43 struck an additional 33MW that will be added to the proposed
Olkaria V.Well head Power generation units are power production units that utilize the available steam
awaiting construction of conventional geothermal plants.
The following are the power projects meant to inject achieve the Horizon II targets.
Geothermal Olkaria I 140 Complete
Olkaria IV 140 Complete
Olkaria I unit 6 70 Financing
Olkaria V 140 Drilling & Financing
Olkaria VI 140 Drilling & Financing
Olkaria VII 140 Drilling & Financing
Well head Generation 350 Drilling & Financing
Wind Ngong wind Phase II 6.8 Implementation
Ngong wind II 13.6 Implementation
Meru Wind 100 Financing
Thermal
Kilifi Coal
Plant 600 Intial Stages
LNG plant 700 Initial Stages
Total 2540
Additional power as from August
2015 2227 (Subtracting complete and
obtained power)
From the above, growth in installed capacity (as from August 2015) is likely to come from wellhead
generation (350MW), wind(120MW) and Olkaria 1 unit 6 expected to inject in 540MW by 2018.Expected
installed capacity will be 1974MW, about 1000MW shortfall from horizon II targets.
Capital restructuring endeavour: Kengen seeks to recapitalize to meet its capital expenditures by
boosting its equity base. Currently it has 2,215,927,528 authorised shares at Ksh2.5 par with
2,198,361,456 shares issued and fully paid for. They intend to increase authorized shares to
10,000,000,000 shares at 2.5 par value by creating 7,784,072,472 shares. Kengen will seek to raise about
28.8 billion shillings from rights issue slated for Q1 2016.The government is not in a position to defend
its rights thus the debt guaranteed by the government to the company totaling 20.151Bn is slated for
conversion to equity, thereby raising 8.6 Bn in cash from the public. As such it is highly likely that the
Kengen will issue 2 shares from every 1 held at about Ksh 6.5 per share. This will reduce the interest
burden of the company, boost its equity capital thereby giving them more headroom to borrow to fund
capital expenditures.
The Financials.
Below is a snapshot of the financials.
2010 2011 2012 2013 2014 2015
FIVE YEAR
CAGR
Revenue (Bn) 11.5 15.2 17.4 17.7 18.5 26.6
EBITDA (bn) 7.1 10.2 11.9 11.6 11.5 17.8
Operating Profit (bn) 3.2 5.6 7.0 7.0 6.7 11.7
Pre-Tax Profit (bn) 2.5 3.7 4.0 4.0 4.2 8.7
EPS (Ksh) 1.49 0.95 1.28 2.38 1.29 5.24
DPS (Ksh) 0.50 0.50 0.60 0.60 0.40 0.65
Revenue Growth % -13% 32% 15% 2% 4% 44% 18.2%
EBITDA Growth % -23% 45% 16% -2% -1% 55% 20.3%
Earnings Growth % 59%
-
37% 36% 85% -46% 73% 28.5%
Operating Margin % 28% 37% 40% 40% 36% 44% 29.4%
Net profit margin 29% 14% 16% 29% 15% 43% 28.5%
Dividend Payout % 33% 53% 47% 25% 31% 12%
Return on Equity % 5% 3% 4% 7% 4% 8%
Return on Assets % 2% 1% 2% 3% 1% 3%
Growth of Total
borrowings 126% 12% 1% 17% 68% 8%
Gearing Ratio % 36% 49% 49% 51% 62% 50%
Capex Coverage 16% 24% 34% 60% 20% 45%
EBIT Coverage 1.1 1.3 1.6 1.7 1.6 3.9
P/CFO 17.7 6.6 6.2 1.5 2.0 1.6
Price/Sales 3.3 2.0 1.1 1.9 1.3 0.8
EV/ EBITDA 10.8 8.9 6.7 8.9 11.9 9.0
The five year CAGR has been boosted by the higher performance for the year 2015.
A significant factor in determining the fair value of Kengen (and by extension utility companies) is the
expected Capital expenditure.
2014 2015 2016 2017 2018 2019
Actual Capex (Ksh
Bn) 61.08 27.23 - - - -
Expected Capex (Ksh
Bn). 44.00 57.94 60.46 52.84 38.18 18.71
The expected capex is USD 3.16Bn to meet the horizon II target of 3000MW.However due to capital
raising challenges and delays and the time consuming nature of building power plants it is highly likely
they will achieve about 2000MW by end of 2018 at a capex of USD 1.17Bn and having laid down growth
for post 2018.
Per Share Data.
Investors seem to currently price utility companies very close to the cash flow generated per share.
(30.00)
(20.00)
(10.00)
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
2001 2003 2005 2007 2009 2011 2013 2015
Book value per share
Free cash flow per share
Year End Price
Cash flow generated from
operations per share
2015 2016E 2017E 2018E 2019E
CFO (Mn) 12,526 14,260 15,510 17,625 18,541
FC Inv (Mn) 27,232 41,596 36,355 26,271 12,870
Int payable (Mn) 2,186 2,749 3,157 3,564 4,380
FCFF (Mn) (13,176) (25,412) (18,636) (6,151) 8,737
Terminal Value 0 210,933
Discount factor 0.956 0.900 0.847 0.797
Discounted Cashflows 0 (24,287) (16,767) (5,210) 6,967
Discounted Terminal
value 0 168,188
FCFF VALUE (Mn) 128,892
COST OF EQUITY NSE 20 Market Return WACC 6.22%
Equity Level 30.00%
30TH APRIL
2002 1,124.82
Risk free rate
(FXD1/2012/20YR) 12.92%
30TH APRIL
2015 4,173.52
Historical equity risk premium 0.70% Annual Return 10.20%
Beta 1.18 Bond YTM 2004 9.50%
CAPM E(R) 13.74%
0.00% CURRENT CAPITAL MIX
cost of equity 4.12% EQUITY 141,594,091 55%
COST OF DEBT DEBT 117,039,768 45%
Debt level 70.00%
Cost of Debt 4.29% TOTAL 258,633,859
After tax cost of Debt 2.10%
FCFF Value 128,891,783
Less Debt 117,039,768
Equity Value 11,852,015
Equity Value per share 5.39
Current Price 8.35
Upside -35.43%
ASSUMPTIONS
1.Kengen will not achieve the desired 3000MW by 2018 but rather will have about 2000MW by 2018.
2.They will require about USD 1.17bn to fund installed capacity to 2000MW during Horizon II.
3. Target debt equity mix will be 70:30 inclusive of partnerships under the PPP model.
4.2% longterm growth rate.
5.Ksh 20.151Bn of government guaranteed debt will be converted to equity.
Though Kengen is a company of great national importance whose activities touch every person and
entity in the East African region, it is a poor growth stock. Power pricing structures have evolved to take
into considerations unrealized foreign exchange losses, capacity charging meant to accelerate return on
investments and energy charges to compensate for electricity produced and sold. Such safe guards have
kept Kengen afloat.Further its ambitious expansion plan will have disastrous effects on cash flow.
A further concern investors need to note are accounting policies the Kengen board applies;
a) They capitalize interest during the construction of power plants funded by debt. Power plants
take very long to come to fruition thus though acceptable it’s a concern to investors such that
were they to expense that portion of interest, profitability levels would be significantly affected.
b) They also capitalize a portion of depreciation related to the rigs used in well drilling to the wells
as part of the cost to the well.
It is very evident that they have supported the share price with a high dividend payout ratio. (It
has paid more than 50% of net profits as dividends in two of the last six years yet the share price
as fallen by more than 36% during the June 2009-June 2015 period.
ROE is below most investor expectation, debt is expected to grow considerably to fund plant
development and their market share is expected to reduce with entrants of new power producers.
RECOMMENDATION: SELL
It is highly unlikely for this stock to deliver long term value to its shareholders. Though revenue is
certainly guaranteed, it’s capital requirements make it a poor growth stock.
PAUL MAINA: HEAD OF RESEARCH, RELIC CAPITAL
KENGEN_VALUATION_REPORT

More Related Content

What's hot

CESC Q4FY15: Net sales up 13.64% y/y to INR14,160m, Firstcall recommend 'Buy'
CESC Q4FY15: Net sales up 13.64% y/y to INR14,160m, Firstcall recommend 'Buy'CESC Q4FY15: Net sales up 13.64% y/y to INR14,160m, Firstcall recommend 'Buy'
CESC Q4FY15: Net sales up 13.64% y/y to INR14,160m, Firstcall recommend 'Buy'IndiaNotes.com
 
NewBase 629 special 18 June 2015
NewBase 629 special 18 June 2015NewBase 629 special 18 June 2015
NewBase 629 special 18 June 2015Khaled Al Awadi
 
Capital Power April Investor Presentation
Capital Power April Investor PresentationCapital Power April Investor Presentation
Capital Power April Investor PresentationCapital Power
 
BWEN Q3 Slides
BWEN Q3 SlidesBWEN Q3 Slides
BWEN Q3 Slidesbroadwind
 
JLL Detroit Industrial Insight & Statistics - Q4 2019
JLL Detroit Industrial Insight & Statistics - Q4 2019JLL Detroit Industrial Insight & Statistics - Q4 2019
JLL Detroit Industrial Insight & Statistics - Q4 2019Harrison West
 
Electrical and Lightning Company Buyout
Electrical and Lightning Company Buyout Electrical and Lightning Company Buyout
Electrical and Lightning Company Buyout Venture Advisors
 
Madras cements 2 qfy2011 251010
Madras cements 2 qfy2011   251010Madras cements 2 qfy2011   251010
Madras cements 2 qfy2011 251010Angel Broking
 
New base 623 special 10 june 2015
New base 623 special 10 june 2015New base 623 special 10 june 2015
New base 623 special 10 june 2015Khaled Al Awadi
 
AIP Chicago Bridge & Iron Research Report (1)
AIP Chicago Bridge & Iron Research Report (1)AIP Chicago Bridge & Iron Research Report (1)
AIP Chicago Bridge & Iron Research Report (1)Ryan Sopinski
 
Wind turbine market in india 2014 - Sample
Wind turbine market in india 2014 - SampleWind turbine market in india 2014 - Sample
Wind turbine market in india 2014 - SampleNetscribes, Inc.
 
Suzlon - Q4 FY16 Earnings Presentation
Suzlon - Q4 FY16 Earnings Presentation Suzlon - Q4 FY16 Earnings Presentation
Suzlon - Q4 FY16 Earnings Presentation Suzlon Group
 
VII Meeting with Investors - CPFL Energia
VII Meeting with Investors - CPFL EnergiaVII Meeting with Investors - CPFL Energia
VII Meeting with Investors - CPFL EnergiaCPFL RI
 
I-Bytes Energy Industry
I-Bytes Energy IndustryI-Bytes Energy Industry
I-Bytes Energy IndustryEGBG Services
 
Ambuja ru3 qcy2010-221010
Ambuja ru3 qcy2010-221010Ambuja ru3 qcy2010-221010
Ambuja ru3 qcy2010-221010Angel Broking
 
energy future holindings txu_110906slides
energy future holindings txu_110906slidesenergy future holindings txu_110906slides
energy future holindings txu_110906slidesfinance29
 
Aumento Tarifa di Coriente - Facts & Figures
Aumento Tarifa di Coriente - Facts & FiguresAumento Tarifa di Coriente - Facts & Figures
Aumento Tarifa di Coriente - Facts & FiguresAissette Rivera
 

What's hot (19)

CESC Q4FY15: Net sales up 13.64% y/y to INR14,160m, Firstcall recommend 'Buy'
CESC Q4FY15: Net sales up 13.64% y/y to INR14,160m, Firstcall recommend 'Buy'CESC Q4FY15: Net sales up 13.64% y/y to INR14,160m, Firstcall recommend 'Buy'
CESC Q4FY15: Net sales up 13.64% y/y to INR14,160m, Firstcall recommend 'Buy'
 
NewBase 629 special 18 June 2015
NewBase 629 special 18 June 2015NewBase 629 special 18 June 2015
NewBase 629 special 18 June 2015
 
Australian Engineering & Mining Services M & A Activity
Australian Engineering & Mining Services M & A ActivityAustralian Engineering & Mining Services M & A Activity
Australian Engineering & Mining Services M & A Activity
 
Capital Power April Investor Presentation
Capital Power April Investor PresentationCapital Power April Investor Presentation
Capital Power April Investor Presentation
 
BWEN Q3 Slides
BWEN Q3 SlidesBWEN Q3 Slides
BWEN Q3 Slides
 
JLL Detroit Industrial Insight & Statistics - Q4 2019
JLL Detroit Industrial Insight & Statistics - Q4 2019JLL Detroit Industrial Insight & Statistics - Q4 2019
JLL Detroit Industrial Insight & Statistics - Q4 2019
 
Electrical and Lightning Company Buyout
Electrical and Lightning Company Buyout Electrical and Lightning Company Buyout
Electrical and Lightning Company Buyout
 
Madras cements 2 qfy2011 251010
Madras cements 2 qfy2011   251010Madras cements 2 qfy2011   251010
Madras cements 2 qfy2011 251010
 
New base 623 special 10 june 2015
New base 623 special 10 june 2015New base 623 special 10 june 2015
New base 623 special 10 june 2015
 
1 20 and 25-31
1 20 and 25-311 20 and 25-31
1 20 and 25-31
 
AIP Chicago Bridge & Iron Research Report (1)
AIP Chicago Bridge & Iron Research Report (1)AIP Chicago Bridge & Iron Research Report (1)
AIP Chicago Bridge & Iron Research Report (1)
 
Tariff Cloud Over Solar Projects
Tariff Cloud Over Solar ProjectsTariff Cloud Over Solar Projects
Tariff Cloud Over Solar Projects
 
Wind turbine market in india 2014 - Sample
Wind turbine market in india 2014 - SampleWind turbine market in india 2014 - Sample
Wind turbine market in india 2014 - Sample
 
Suzlon - Q4 FY16 Earnings Presentation
Suzlon - Q4 FY16 Earnings Presentation Suzlon - Q4 FY16 Earnings Presentation
Suzlon - Q4 FY16 Earnings Presentation
 
VII Meeting with Investors - CPFL Energia
VII Meeting with Investors - CPFL EnergiaVII Meeting with Investors - CPFL Energia
VII Meeting with Investors - CPFL Energia
 
I-Bytes Energy Industry
I-Bytes Energy IndustryI-Bytes Energy Industry
I-Bytes Energy Industry
 
Ambuja ru3 qcy2010-221010
Ambuja ru3 qcy2010-221010Ambuja ru3 qcy2010-221010
Ambuja ru3 qcy2010-221010
 
energy future holindings txu_110906slides
energy future holindings txu_110906slidesenergy future holindings txu_110906slides
energy future holindings txu_110906slides
 
Aumento Tarifa di Coriente - Facts & Figures
Aumento Tarifa di Coriente - Facts & FiguresAumento Tarifa di Coriente - Facts & Figures
Aumento Tarifa di Coriente - Facts & Figures
 

Similar to KENGEN_VALUATION_REPORT

Ntpc 2 qfy11 result update - 271010
Ntpc   2 qfy11 result update - 271010Ntpc   2 qfy11 result update - 271010
Ntpc 2 qfy11 result update - 271010Angel Broking
 
May 2015 investor deck ld micro final
May 2015 investor deck ld micro finalMay 2015 investor deck ld micro final
May 2015 investor deck ld micro finalbroadwind
 
May 2015 investor deck ld micro final
May 2015 investor deck ld micro finalMay 2015 investor deck ld micro final
May 2015 investor deck ld micro finalbroadwind
 
May 2015 investor deck b riley final
May 2015 investor deck b  riley finalMay 2015 investor deck b  riley final
May 2015 investor deck b riley finalbroadwind
 
Keppel Corporation UK Non-deal Roadshow 2019
Keppel Corporation UK Non-deal Roadshow 2019Keppel Corporation UK Non-deal Roadshow 2019
Keppel Corporation UK Non-deal Roadshow 2019KeppelCorporation
 
KENYA_POWER_VALUATION_REPORT_REVISED
KENYA_POWER_VALUATION_REPORT_REVISEDKENYA_POWER_VALUATION_REPORT_REVISED
KENYA_POWER_VALUATION_REPORT_REVISEDPaul Maina
 
14th Annual Report GTL Infrastructure Limited 2016-17
14th Annual Report GTL Infrastructure Limited 2016-1714th Annual Report GTL Infrastructure Limited 2016-17
14th Annual Report GTL Infrastructure Limited 2016-17GTL Infrastructure Ltd
 
QNBFS Weekly Market Report February 18, 2021
QNBFS Weekly Market Report February 18, 2021QNBFS Weekly Market Report February 18, 2021
QNBFS Weekly Market Report February 18, 2021QNB Group
 
May Investor Presentation
May Investor PresentationMay Investor Presentation
May Investor PresentationAES_BigSky
 
Market outlook 26 10 10
Market outlook 26 10 10Market outlook 26 10 10
Market outlook 26 10 10Angel Broking
 
Keppel Corporation Kuala Lumpur Non-Deal Roadshow Presentation Slides
Keppel Corporation Kuala Lumpur Non-Deal Roadshow Presentation SlidesKeppel Corporation Kuala Lumpur Non-Deal Roadshow Presentation Slides
Keppel Corporation Kuala Lumpur Non-Deal Roadshow Presentation SlidesKeppelCorporation
 
Financial Analysis HCC
Financial Analysis HCCFinancial Analysis HCC
Financial Analysis HCCJaspal Bhatia
 
Buy Rural Electrification, MoU signed with TSGENCO for funding for proposed p...
Buy Rural Electrification, MoU signed with TSGENCO for funding for proposed p...Buy Rural Electrification, MoU signed with TSGENCO for funding for proposed p...
Buy Rural Electrification, MoU signed with TSGENCO for funding for proposed p...IndiaNotes.com
 
QNBFS Weekly Market Report April 21, 2022
QNBFS Weekly Market Report April 21, 2022QNBFS Weekly Market Report April 21, 2022
QNBFS Weekly Market Report April 21, 2022QNB Group
 
Equity Research on SEAMEC Ltd
Equity Research on SEAMEC Ltd Equity Research on SEAMEC Ltd
Equity Research on SEAMEC Ltd Guruvindersingh4
 
Mytilineos (OW, TP_ €46.0_sh)_ Strong organic progress 14-03-2024.pdf
Mytilineos (OW, TP_ €46.0_sh)_ Strong organic progress 14-03-2024.pdfMytilineos (OW, TP_ €46.0_sh)_ Strong organic progress 14-03-2024.pdf
Mytilineos (OW, TP_ €46.0_sh)_ Strong organic progress 14-03-2024.pdfNewsroom8
 
Earnings release 3 q14_final
Earnings release 3 q14_finalEarnings release 3 q14_final
Earnings release 3 q14_finalCPFL RI
 
Keppel Corporation 2Q & 1H 2020 Results Presentation Slides
Keppel Corporation 2Q & 1H 2020 Results Presentation SlidesKeppel Corporation 2Q & 1H 2020 Results Presentation Slides
Keppel Corporation 2Q & 1H 2020 Results Presentation SlidesKeppelCorporation
 
EPC Oil and Gas Investment Opportunity
EPC Oil and Gas Investment OpportunityEPC Oil and Gas Investment Opportunity
EPC Oil and Gas Investment OpportunityVenture Advisors
 

Similar to KENGEN_VALUATION_REPORT (20)

Ntpc 2 qfy11 result update - 271010
Ntpc   2 qfy11 result update - 271010Ntpc   2 qfy11 result update - 271010
Ntpc 2 qfy11 result update - 271010
 
May 2015 investor deck ld micro final
May 2015 investor deck ld micro finalMay 2015 investor deck ld micro final
May 2015 investor deck ld micro final
 
May 2015 investor deck ld micro final
May 2015 investor deck ld micro finalMay 2015 investor deck ld micro final
May 2015 investor deck ld micro final
 
May 2015 investor deck b riley final
May 2015 investor deck b  riley finalMay 2015 investor deck b  riley final
May 2015 investor deck b riley final
 
Keppel Corporation UK Non-deal Roadshow 2019
Keppel Corporation UK Non-deal Roadshow 2019Keppel Corporation UK Non-deal Roadshow 2019
Keppel Corporation UK Non-deal Roadshow 2019
 
KENYA_POWER_VALUATION_REPORT_REVISED
KENYA_POWER_VALUATION_REPORT_REVISEDKENYA_POWER_VALUATION_REPORT_REVISED
KENYA_POWER_VALUATION_REPORT_REVISED
 
14th Annual Report GTL Infrastructure Limited 2016-17
14th Annual Report GTL Infrastructure Limited 2016-1714th Annual Report GTL Infrastructure Limited 2016-17
14th Annual Report GTL Infrastructure Limited 2016-17
 
QNBFS Weekly Market Report February 18, 2021
QNBFS Weekly Market Report February 18, 2021QNBFS Weekly Market Report February 18, 2021
QNBFS Weekly Market Report February 18, 2021
 
May Investor Presentation
May Investor PresentationMay Investor Presentation
May Investor Presentation
 
Market outlook 26 10 10
Market outlook 26 10 10Market outlook 26 10 10
Market outlook 26 10 10
 
Keppel Corporation Kuala Lumpur Non-Deal Roadshow Presentation Slides
Keppel Corporation Kuala Lumpur Non-Deal Roadshow Presentation SlidesKeppel Corporation Kuala Lumpur Non-Deal Roadshow Presentation Slides
Keppel Corporation Kuala Lumpur Non-Deal Roadshow Presentation Slides
 
Financial Analysis HCC
Financial Analysis HCCFinancial Analysis HCC
Financial Analysis HCC
 
Buy Rural Electrification, MoU signed with TSGENCO for funding for proposed p...
Buy Rural Electrification, MoU signed with TSGENCO for funding for proposed p...Buy Rural Electrification, MoU signed with TSGENCO for funding for proposed p...
Buy Rural Electrification, MoU signed with TSGENCO for funding for proposed p...
 
QNBFS Weekly Market Report April 21, 2022
QNBFS Weekly Market Report April 21, 2022QNBFS Weekly Market Report April 21, 2022
QNBFS Weekly Market Report April 21, 2022
 
Equity Research on SEAMEC Ltd
Equity Research on SEAMEC Ltd Equity Research on SEAMEC Ltd
Equity Research on SEAMEC Ltd
 
Suzlon
SuzlonSuzlon
Suzlon
 
Mytilineos (OW, TP_ €46.0_sh)_ Strong organic progress 14-03-2024.pdf
Mytilineos (OW, TP_ €46.0_sh)_ Strong organic progress 14-03-2024.pdfMytilineos (OW, TP_ €46.0_sh)_ Strong organic progress 14-03-2024.pdf
Mytilineos (OW, TP_ €46.0_sh)_ Strong organic progress 14-03-2024.pdf
 
Earnings release 3 q14_final
Earnings release 3 q14_finalEarnings release 3 q14_final
Earnings release 3 q14_final
 
Keppel Corporation 2Q & 1H 2020 Results Presentation Slides
Keppel Corporation 2Q & 1H 2020 Results Presentation SlidesKeppel Corporation 2Q & 1H 2020 Results Presentation Slides
Keppel Corporation 2Q & 1H 2020 Results Presentation Slides
 
EPC Oil and Gas Investment Opportunity
EPC Oil and Gas Investment OpportunityEPC Oil and Gas Investment Opportunity
EPC Oil and Gas Investment Opportunity
 

KENGEN_VALUATION_REPORT

  • 1. KENGEN INITIATION OF COVERAGE AND VALUATION REPORT I initiate coverage of Kengen midway in its ambitious plan dubbed “Good to great” to generate 3,000MW of power by 2018 which falls in Horizon II. Horizon I was during the period 2008-2013,Horizon II between 2013-2018 and Horizon III from 2018-2030.The specific achievements are; Horizon I- To increase installed capacity by 500MW between July 2008 and June 2012. Horizon II-To increase installed capacity by an additional 1500MW (To 3000MW) between July 2013 and june 2008. Horizon III-To focus on expansion of opportunities beyond the country. Beyond 2018, KenGen with other power generators will have achieved power stability and sustainability and therefore the company will trade power with other Eastern Africa companies. Their ambitious plan is in tandem with the National LCPDP (Least Cost Power Development Plan) that seeks to increase and redistribute the energy mix to cheaper energy. During Horizon I they envisaged to have an installed capacity of 1,500MW .They managed an installed capacity of by 1238.4MW falling short by 261.4MW thereby managing an additional 292MW (installed Capacity in 2007 was 946MW).The effective capacity was 1133MW caused by short falls from Hydro plants. Geothermal plants were stable.The national LCPDP has identified geothermal generation has the main driver to meet this target; The main risk to meeting this target is that geothermal power plants are very expensive to build. Installed and Effective installed power by KENGEN stands as follows: 2010 2011 2012 2013 2014 2015 Installed 1,053.8 1,177.1 1,209.6 1,238.4 1,339.4 1,537.4 Effective 1,030.5 1,064.5 1,162.9 1,133.3 1,268.2 (Source Data:Kenya Power Financial statements) In the Horizon II period meant to achieve 3,000MW, as of August 2015 installed capacity stood at 1,537MW with 200MW injected into the grid during the year. It is highly unlikely that they will meet Horizon II targets. Disclaimer: Information in the public domain claims an additional 280MW was injected in December. This is erroneous as this refers to installed capacity of both olkaria I and IV. By financial end year 2014 Olkaria I stood at 45MW and Olkaria IV at 70MW.Today it stands at 140MW each thus an additional 165MW.Olkaria well head 43 struck an additional 33MW that will be added to the proposed
  • 2. Olkaria V.Well head Power generation units are power production units that utilize the available steam awaiting construction of conventional geothermal plants. The following are the power projects meant to inject achieve the Horizon II targets. Geothermal Olkaria I 140 Complete Olkaria IV 140 Complete Olkaria I unit 6 70 Financing Olkaria V 140 Drilling & Financing Olkaria VI 140 Drilling & Financing Olkaria VII 140 Drilling & Financing Well head Generation 350 Drilling & Financing Wind Ngong wind Phase II 6.8 Implementation Ngong wind II 13.6 Implementation Meru Wind 100 Financing Thermal Kilifi Coal Plant 600 Intial Stages LNG plant 700 Initial Stages Total 2540 Additional power as from August 2015 2227 (Subtracting complete and obtained power) From the above, growth in installed capacity (as from August 2015) is likely to come from wellhead generation (350MW), wind(120MW) and Olkaria 1 unit 6 expected to inject in 540MW by 2018.Expected installed capacity will be 1974MW, about 1000MW shortfall from horizon II targets. Capital restructuring endeavour: Kengen seeks to recapitalize to meet its capital expenditures by boosting its equity base. Currently it has 2,215,927,528 authorised shares at Ksh2.5 par with 2,198,361,456 shares issued and fully paid for. They intend to increase authorized shares to 10,000,000,000 shares at 2.5 par value by creating 7,784,072,472 shares. Kengen will seek to raise about 28.8 billion shillings from rights issue slated for Q1 2016.The government is not in a position to defend its rights thus the debt guaranteed by the government to the company totaling 20.151Bn is slated for conversion to equity, thereby raising 8.6 Bn in cash from the public. As such it is highly likely that the Kengen will issue 2 shares from every 1 held at about Ksh 6.5 per share. This will reduce the interest burden of the company, boost its equity capital thereby giving them more headroom to borrow to fund capital expenditures.
  • 3. The Financials. Below is a snapshot of the financials. 2010 2011 2012 2013 2014 2015 FIVE YEAR CAGR Revenue (Bn) 11.5 15.2 17.4 17.7 18.5 26.6 EBITDA (bn) 7.1 10.2 11.9 11.6 11.5 17.8 Operating Profit (bn) 3.2 5.6 7.0 7.0 6.7 11.7 Pre-Tax Profit (bn) 2.5 3.7 4.0 4.0 4.2 8.7 EPS (Ksh) 1.49 0.95 1.28 2.38 1.29 5.24 DPS (Ksh) 0.50 0.50 0.60 0.60 0.40 0.65 Revenue Growth % -13% 32% 15% 2% 4% 44% 18.2% EBITDA Growth % -23% 45% 16% -2% -1% 55% 20.3% Earnings Growth % 59% - 37% 36% 85% -46% 73% 28.5% Operating Margin % 28% 37% 40% 40% 36% 44% 29.4% Net profit margin 29% 14% 16% 29% 15% 43% 28.5% Dividend Payout % 33% 53% 47% 25% 31% 12% Return on Equity % 5% 3% 4% 7% 4% 8% Return on Assets % 2% 1% 2% 3% 1% 3% Growth of Total borrowings 126% 12% 1% 17% 68% 8% Gearing Ratio % 36% 49% 49% 51% 62% 50% Capex Coverage 16% 24% 34% 60% 20% 45% EBIT Coverage 1.1 1.3 1.6 1.7 1.6 3.9 P/CFO 17.7 6.6 6.2 1.5 2.0 1.6 Price/Sales 3.3 2.0 1.1 1.9 1.3 0.8 EV/ EBITDA 10.8 8.9 6.7 8.9 11.9 9.0 The five year CAGR has been boosted by the higher performance for the year 2015. A significant factor in determining the fair value of Kengen (and by extension utility companies) is the expected Capital expenditure. 2014 2015 2016 2017 2018 2019 Actual Capex (Ksh Bn) 61.08 27.23 - - - - Expected Capex (Ksh Bn). 44.00 57.94 60.46 52.84 38.18 18.71
  • 4. The expected capex is USD 3.16Bn to meet the horizon II target of 3000MW.However due to capital raising challenges and delays and the time consuming nature of building power plants it is highly likely they will achieve about 2000MW by end of 2018 at a capex of USD 1.17Bn and having laid down growth for post 2018. Per Share Data. Investors seem to currently price utility companies very close to the cash flow generated per share. (30.00) (20.00) (10.00) 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 2001 2003 2005 2007 2009 2011 2013 2015 Book value per share Free cash flow per share Year End Price Cash flow generated from operations per share
  • 5. 2015 2016E 2017E 2018E 2019E CFO (Mn) 12,526 14,260 15,510 17,625 18,541 FC Inv (Mn) 27,232 41,596 36,355 26,271 12,870 Int payable (Mn) 2,186 2,749 3,157 3,564 4,380 FCFF (Mn) (13,176) (25,412) (18,636) (6,151) 8,737 Terminal Value 0 210,933 Discount factor 0.956 0.900 0.847 0.797 Discounted Cashflows 0 (24,287) (16,767) (5,210) 6,967 Discounted Terminal value 0 168,188 FCFF VALUE (Mn) 128,892 COST OF EQUITY NSE 20 Market Return WACC 6.22% Equity Level 30.00% 30TH APRIL 2002 1,124.82 Risk free rate (FXD1/2012/20YR) 12.92% 30TH APRIL 2015 4,173.52 Historical equity risk premium 0.70% Annual Return 10.20% Beta 1.18 Bond YTM 2004 9.50% CAPM E(R) 13.74% 0.00% CURRENT CAPITAL MIX cost of equity 4.12% EQUITY 141,594,091 55% COST OF DEBT DEBT 117,039,768 45% Debt level 70.00% Cost of Debt 4.29% TOTAL 258,633,859 After tax cost of Debt 2.10% FCFF Value 128,891,783 Less Debt 117,039,768 Equity Value 11,852,015 Equity Value per share 5.39 Current Price 8.35 Upside -35.43%
  • 6. ASSUMPTIONS 1.Kengen will not achieve the desired 3000MW by 2018 but rather will have about 2000MW by 2018. 2.They will require about USD 1.17bn to fund installed capacity to 2000MW during Horizon II. 3. Target debt equity mix will be 70:30 inclusive of partnerships under the PPP model. 4.2% longterm growth rate. 5.Ksh 20.151Bn of government guaranteed debt will be converted to equity. Though Kengen is a company of great national importance whose activities touch every person and entity in the East African region, it is a poor growth stock. Power pricing structures have evolved to take into considerations unrealized foreign exchange losses, capacity charging meant to accelerate return on investments and energy charges to compensate for electricity produced and sold. Such safe guards have kept Kengen afloat.Further its ambitious expansion plan will have disastrous effects on cash flow. A further concern investors need to note are accounting policies the Kengen board applies; a) They capitalize interest during the construction of power plants funded by debt. Power plants take very long to come to fruition thus though acceptable it’s a concern to investors such that were they to expense that portion of interest, profitability levels would be significantly affected. b) They also capitalize a portion of depreciation related to the rigs used in well drilling to the wells as part of the cost to the well. It is very evident that they have supported the share price with a high dividend payout ratio. (It has paid more than 50% of net profits as dividends in two of the last six years yet the share price as fallen by more than 36% during the June 2009-June 2015 period. ROE is below most investor expectation, debt is expected to grow considerably to fund plant development and their market share is expected to reduce with entrants of new power producers. RECOMMENDATION: SELL It is highly unlikely for this stock to deliver long term value to its shareholders. Though revenue is certainly guaranteed, it’s capital requirements make it a poor growth stock. PAUL MAINA: HEAD OF RESEARCH, RELIC CAPITAL