SlideShare a Scribd company logo
CHRISTOPHER P. WILLIAMS, ARCHITECTS
PO BOX 703  MEREDITH, NH 03253  603-279-6513
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
Hebron Town Hall Expansion
February 17, 2015
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
APPROACH TO THE CHALLENGE
 Historic Building Analysis – Fall 2010
 Christopher P. Williams Architects – Norman E. Larson, AIA
 H.E.Bergeron Engineers – Jason Ross, P.E. and Salvatore Disanza
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
HISTORIC BUILDING ANALYSIS
 Front Gabled Greek Revival Building
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
HISTORIC BUILDING ANALYSIS
 Typical Greek Revival Detailing
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
HISTORIC BUILDING ANALYSIS
 Gothic Revival Tower Elements
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
HISTORIC BUILDING ANALYSIS
 Stone Entry Steps – (not acceptable under ADA)
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
HISTORIC BUILDING ANALYSIS
 Stone foundation on east side and front
 Concrete foundation on west side and rear
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
HISTORIC BUILDING ANALYSIS
 Vinyl Replacement Windows
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
HISTORIC BUILDING ANALYSIS
 Poor Egress from Meeting Room (and over a generator too)
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
HISTORIC BUILDING ANALYSIS
 New windows and finishes on Main Level
 1974
 2010
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
HISTORIC BUILDING ANALYSIS
 New windows and finishes on Upper Level
 1974 (Librarian Isabel Blodgett)
 2010
 2010
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
HISTORIC BUILDING ANALYSIS
 Building Structure needs a little help
 Crawl Space
 Beam supporting 2nd
Floor
 2nd
Floor Frame
 Attic
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
APPROACH TO THE CHALLENGE
 Historic Building Analysis – Fall 2010
 Plan New Hampshire Design Charrette – September 23 and 24, 2011
 Robin LeBlanc – Plan NH Executive Director
 Brian Murphy, AIA – (Team Leader) ManyPenny Murphy Architecture
 Scott Collard – (Plan NH Charrette Committee Chair and Facilitator)
 Gordon Cormack – Cormack Construction Management
 Maggie Stier – New Hampshire Preservation Alliance
 Norman Larson – CPW Architects
 Jeffrey Taylor – Jeffrey Taylor Planning
 A very long list of Hebron Citizens and Elected Officials
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
PLAN NEW HAMPSHIRE DESIGN CHARRETTE
Listening Sessions – Friday Afternoon and Evening
Team Presentation – Saturday Afternoon (Brian Murphy)
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
PLAN NEW HAMPSHIRE DESIGN CHARRETTE
The iconic nature of the Town Common
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
APPROACH TO THE CHALLENGE
 Historic Building Analysis – Fall 2010
 Plan New Hampshire Design Charrette – September 23 and 24, 2011
 Town Offices Expansion and Refurbishment Committee Formed - 2014
 Roger Larochelle
 Paul Hazelton
 Mark Coulson
Trip Swartz
Patrick Moriarty
 Ellie Lonske
 Ivan Quinchia
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
APPROACH TO THE CHALLENGE
 Historic Building Analysis – Fall 2010
 Plan New Hampshire Design Charrette – September 23 and 24, 2011
 Town Offices Expansion and Refurbishment Committee Formed - 2014
 Program for Town Offices – July 2014
 Norman E. Larson, AIA
 Town Offices Committee
 Town Staff
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
BUILDING PROGRAM (SPACE NEEDS ANALYSIS)
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
BUILDING PROGRAM (SPACE NEEDS ANALYSIS)
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
APPROACH TO THE CHALLENGE
 Historic Building Analysis – Fall 2010
 Plan New Hampshire Design Charrette – September 23 and 24, 2011
 Town Offices Expansion and Refurbishment Committee Formed – 2014
 Program for Town Offices – July 2014
 Three Preliminary Schemes to solve the same problem – Presented August 2014
Scheme A – Addition to Rear– Administration on second floor (too small)
Scheme B – Two Story – Tax Collector and Town Clerk upstairs
Scheme C – One Story – All services on main floor
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
THREE PRELIMINARY SCHEMES
Scheme A – Addition to Rear– Administration on second floor (too small)
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
THREE PRELIMINARY SCHEMES
Scheme B – Two Story – Tax Collector and Town Clerk upstairs
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
THREE PRELIMINARY SCHEMES
Scheme C – One Story – All services on main floor
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
APPROACH TO THE CHALLENGE
 Historic Building Analysis – Fall 2010
 Plan New Hampshire Design Charrette – September 23 and 24, 2011
 Town Offices Expansion and Refurbishment Committee Formed - 2014
Program for Town Offices – July 2014
 Three Preliminary Schemes to solve the same problem – August 2014
 Collection of Community Input – September 2014
 Schemes B and C displayed in Town Hall and online
 Clear consensus to keeping all Town Offices on main level
 Several comments in favor of western facing gable
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
APPROACH TO THE CHALLENGE
 Historic Building Analysis – Fall 2010
 Plan New Hampshire Design Charrette – September 23 and 24, 2011
 Town Offices Expansion and Refurbishment Committee Formed - 2014
Program for Town Offices – July 2014
 Three Preliminary Schemes to solve the same problem – August 2014
 Collection of Community Input – September 2014
 Revised Schematic Design of two Schemes – October 2014
 Scheme D – North South Gable – all services on main floor - selected
 Scheme E – East West Gable – all services on main floor - rejected
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
REVISED SCHEMATIC DESIGN
 Scheme D – North South Gable – all services on main floor - selected
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
REVISED SCHEMATIC DESIGN
 Scheme E – East West Gable – all services on main floor - rejected
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
APPROACH TO THE CHALLENGE
 Historic Building Analysis – Fall 2010
 Plan New Hampshire Design Charrette – September 23 and 24, 2011
 Town Offices Expansion and Refurbishment Committee Formed - 2014
Program for Town Offices – July 2014
 Three Preliminary Schemes to solve the same problem – August 2014
 Collection of Community Input – September 2014
 Revised Schematic Design of two Schemes – October 2014
 Collection of Community Input – November 2014
 Drawings posted at the polling place
 Drawings and video made available online
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
APPROACH TO THE CHALLENGE
 Historic Building Analysis – Fall 2010
 Plan New Hampshire Design Charrette – September 23 and 24, 2011
 Town Offices Expansion and Refurbishment Committee Formed - 2014
Program for Town Offices – July 2014
 Three Preliminary Schemes to solve the same problem – August 2014
 Collection of Community Input – September 2014
 Revised Schematic Design of two Schemes – October 2014
 Collection of Community Input – November 2014
 Initiation of Design Development
 Revisions made to reflect Committee Input
 Development of Energy Performance and Construction Criteria
 Systems comparative cost analysis
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
Proposed Main Level Plan
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
Proposed Upper Level Plan
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
Proposed Basement Plan
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
Proposed Site Plan
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
Proposed Roof Plan
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
Proposed Building Elevations
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
Proposed Building Elevations
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
Proposed View from Northeast
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
 View of Proposed Entry
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
 View of Proposed Addition
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
DESIGN DEVELOPMENT
 View of Proposed Addition from West Shore Road (without woods)
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
APPROACH TO THE CHALLENGE
 Historic Building Analysis – Fall 2010
 Plan New Hampshire Design Charrette – September 23 and 24, 2011
 Town Offices Expansion and Refurbishment Committee Formed - 2014
Program for Town Offices – July 2014
 Three Preliminary Schemes to solve the same problem – August 2014
 Collection of Community Input – September 2014
 Revised Schematic Design of two Schemes – October 2014
 Collection of Community Input – November 2014
 Initiation of Design Development
What’s Next
 Confirm direction of the project with the voters
 Long and short term cost analysis of building systems and construction process
 Construction Documents including engineering
CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC
Thank you for your time and we welcome any questions you may have.
QUESTIONS

More Related Content

Viewers also liked

Production diary 15
Production diary 15Production diary 15
Production diary 15
Laila Jaleel
 
C++ Базовый. Занятие 05.
C++ Базовый. Занятие 05.C++ Базовый. Занятие 05.
C++ Базовый. Занятие 05.
Igor Shkulipa
 
Production diary 8
Production diary 8Production diary 8
Production diary 8
Laila Jaleel
 
Vijay Bhosekar_ Research Article_ Frontiers in Plant Science
Vijay Bhosekar_ Research Article_ Frontiers in Plant ScienceVijay Bhosekar_ Research Article_ Frontiers in Plant Science
Vijay Bhosekar_ Research Article_ Frontiers in Plant Sciencevijay bhosekar
 
C++ Базовый. Занятие 15.
C++ Базовый. Занятие 15.C++ Базовый. Занятие 15.
C++ Базовый. Занятие 15.
Igor Shkulipa
 
Capitulo IV análisis de resultados
Capitulo IV análisis de resultados Capitulo IV análisis de resultados
Capitulo IV análisis de resultados
Ida Morán
 
Fotos de la tesis
Fotos de la tesisFotos de la tesis
Fotos de la tesis
Ida Morán
 
Production diary 3
Production diary 3Production diary 3
Production diary 3
Laila Jaleel
 
JavaScript Базовый. Занятие 05.
JavaScript Базовый. Занятие 05.JavaScript Базовый. Занятие 05.
JavaScript Базовый. Занятие 05.
Igor Shkulipa
 
Production diary 17
Production diary 17Production diary 17
Production diary 17
Laila Jaleel
 
Κάτω στο γιαλό...
Κάτω στο γιαλό...Κάτω στο γιαλό...
Κάτω στο γιαλό...syllogos15sch
 
C# Web. Занятие 16.
C# Web. Занятие 16.C# Web. Занятие 16.
C# Web. Занятие 16.
Igor Shkulipa
 
Production diary 10
Production diary 10Production diary 10
Production diary 10
Laila Jaleel
 
Общие темы. Тема 02.
Общие темы. Тема 02.Общие темы. Тема 02.
Общие темы. Тема 02.
Igor Shkulipa
 
C++ Базовый. Занятие 02.
C++ Базовый. Занятие 02.C++ Базовый. Занятие 02.
C++ Базовый. Занятие 02.
Igor Shkulipa
 

Viewers also liked (17)

Production diary 15
Production diary 15Production diary 15
Production diary 15
 
C++ Базовый. Занятие 05.
C++ Базовый. Занятие 05.C++ Базовый. Занятие 05.
C++ Базовый. Занятие 05.
 
Production diary 8
Production diary 8Production diary 8
Production diary 8
 
Vijay Bhosekar_ Research Article_ Frontiers in Plant Science
Vijay Bhosekar_ Research Article_ Frontiers in Plant ScienceVijay Bhosekar_ Research Article_ Frontiers in Plant Science
Vijay Bhosekar_ Research Article_ Frontiers in Plant Science
 
C++ Базовый. Занятие 15.
C++ Базовый. Занятие 15.C++ Базовый. Занятие 15.
C++ Базовый. Занятие 15.
 
Capitulo IV análisis de resultados
Capitulo IV análisis de resultados Capitulo IV análisis de resultados
Capitulo IV análisis de resultados
 
psychiatry
psychiatrypsychiatry
psychiatry
 
Fotos de la tesis
Fotos de la tesisFotos de la tesis
Fotos de la tesis
 
Production diary 3
Production diary 3Production diary 3
Production diary 3
 
Print Brochure 3NM v6
Print Brochure 3NM v6Print Brochure 3NM v6
Print Brochure 3NM v6
 
JavaScript Базовый. Занятие 05.
JavaScript Базовый. Занятие 05.JavaScript Базовый. Занятие 05.
JavaScript Базовый. Занятие 05.
 
Production diary 17
Production diary 17Production diary 17
Production diary 17
 
Κάτω στο γιαλό...
Κάτω στο γιαλό...Κάτω στο γιαλό...
Κάτω στο γιαλό...
 
C# Web. Занятие 16.
C# Web. Занятие 16.C# Web. Занятие 16.
C# Web. Занятие 16.
 
Production diary 10
Production diary 10Production diary 10
Production diary 10
 
Общие темы. Тема 02.
Общие темы. Тема 02.Общие темы. Тема 02.
Общие темы. Тема 02.
 
C++ Базовый. Занятие 02.
C++ Базовый. Занятие 02.C++ Базовый. Занятие 02.
C++ Базовый. Занятие 02.
 

Similar to Hebron NH Academy Building Presentation 02-17-15

Brian Rich's Resume & Portfolio
Brian Rich's Resume & PortfolioBrian Rich's Resume & Portfolio
Brian Rich's Resume & Portfolio
Brian Rich
 
PCH-Aviation Conceptual Plan
PCH-Aviation Conceptual PlanPCH-Aviation Conceptual Plan
PCH-Aviation Conceptual Plan
justinforhb
 
Substantial Completion - North West Street Sidewalk Improvements
Substantial Completion - North West Street Sidewalk ImprovementsSubstantial Completion - North West Street Sidewalk Improvements
Substantial Completion - North West Street Sidewalk Improvements
Fairfax County
 
Pedestrian Improvements at Highland Street, Backlick Road, Amherst Ave. Inter...
Pedestrian Improvements at Highland Street, Backlick Road, Amherst Ave. Inter...Pedestrian Improvements at Highland Street, Backlick Road, Amherst Ave. Inter...
Pedestrian Improvements at Highland Street, Backlick Road, Amherst Ave. Inter...
Fairfax County
 
Bath, Maine Design And Resiliency Team (DART) Project
Bath, Maine Design And Resiliency Team (DART) ProjectBath, Maine Design And Resiliency Team (DART) Project
Bath, Maine Design And Resiliency Team (DART) Project
American Institute of Architects
 
Field Of Dreams - Copy
Field Of Dreams - CopyField Of Dreams - Copy
Field Of Dreams - CopyBrian Hauff
 
Sasaki associates
Sasaki associatesSasaki associates
Sasaki associates
Akhil Akash vadlamudi
 
April 12 Planning Public Forum
April 12 Planning Public ForumApril 12 Planning Public Forum
April 12 Planning Public Forumpublicinvolvement
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
Fairfax County
 
Taming Tyson's Corner - Transforming the Edge City Transit Oriented Developme...
Taming Tyson's Corner - Transforming the Edge City Transit Oriented Developme...Taming Tyson's Corner - Transforming the Edge City Transit Oriented Developme...
Taming Tyson's Corner - Transforming the Edge City Transit Oriented Developme...
Peter Bass, LEED AP, PMP
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
Fairfax County
 
Oak Harbor Design Open House
Oak Harbor Design Open HouseOak Harbor Design Open House
Oak Harbor Design Open House
publicinvolvement
 
Buildings that use Thermal breaks to solve thermal bridging issues.
Buildings that use Thermal breaks to solve thermal bridging issues.Buildings that use Thermal breaks to solve thermal bridging issues.
Buildings that use Thermal breaks to solve thermal bridging issues.atennyson
 
CHC Policy Series Economic Development Briefing
CHC Policy Series Economic Development BriefingCHC Policy Series Economic Development Briefing
CHC Policy Series Economic Development Briefing
The Chamber For a Greater Chapel Hill-Carrboro
 
Final slide presentation 2 10-17
Final slide presentation 2 10-17Final slide presentation 2 10-17
Final slide presentation 2 10-17
DCPublicLibrary
 
Portfolio of work - James Sia Architect
Portfolio of work - James Sia ArchitectPortfolio of work - James Sia Architect
Portfolio of work - James Sia ArchitectJames Sia
 
Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017
melissanatech
 

Similar to Hebron NH Academy Building Presentation 02-17-15 (20)

Brian Rich's Resume & Portfolio
Brian Rich's Resume & PortfolioBrian Rich's Resume & Portfolio
Brian Rich's Resume & Portfolio
 
PCH-Aviation Conceptual Plan
PCH-Aviation Conceptual PlanPCH-Aviation Conceptual Plan
PCH-Aviation Conceptual Plan
 
Substantial Completion - North West Street Sidewalk Improvements
Substantial Completion - North West Street Sidewalk ImprovementsSubstantial Completion - North West Street Sidewalk Improvements
Substantial Completion - North West Street Sidewalk Improvements
 
Pedestrian Improvements at Highland Street, Backlick Road, Amherst Ave. Inter...
Pedestrian Improvements at Highland Street, Backlick Road, Amherst Ave. Inter...Pedestrian Improvements at Highland Street, Backlick Road, Amherst Ave. Inter...
Pedestrian Improvements at Highland Street, Backlick Road, Amherst Ave. Inter...
 
Recent projects
Recent projectsRecent projects
Recent projects
 
Bath, Maine Design And Resiliency Team (DART) Project
Bath, Maine Design And Resiliency Team (DART) ProjectBath, Maine Design And Resiliency Team (DART) Project
Bath, Maine Design And Resiliency Team (DART) Project
 
New recent projects
New recent projectsNew recent projects
New recent projects
 
Field Of Dreams - Copy
Field Of Dreams - CopyField Of Dreams - Copy
Field Of Dreams - Copy
 
Sasaki associates
Sasaki associatesSasaki associates
Sasaki associates
 
April 12 Planning Public Forum
April 12 Planning Public ForumApril 12 Planning Public Forum
April 12 Planning Public Forum
 
Miller J Portfolio
Miller J PortfolioMiller J Portfolio
Miller J Portfolio
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
 
Taming Tyson's Corner - Transforming the Edge City Transit Oriented Developme...
Taming Tyson's Corner - Transforming the Edge City Transit Oriented Developme...Taming Tyson's Corner - Transforming the Edge City Transit Oriented Developme...
Taming Tyson's Corner - Transforming the Edge City Transit Oriented Developme...
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
 
Oak Harbor Design Open House
Oak Harbor Design Open HouseOak Harbor Design Open House
Oak Harbor Design Open House
 
Buildings that use Thermal breaks to solve thermal bridging issues.
Buildings that use Thermal breaks to solve thermal bridging issues.Buildings that use Thermal breaks to solve thermal bridging issues.
Buildings that use Thermal breaks to solve thermal bridging issues.
 
CHC Policy Series Economic Development Briefing
CHC Policy Series Economic Development BriefingCHC Policy Series Economic Development Briefing
CHC Policy Series Economic Development Briefing
 
Final slide presentation 2 10-17
Final slide presentation 2 10-17Final slide presentation 2 10-17
Final slide presentation 2 10-17
 
Portfolio of work - James Sia Architect
Portfolio of work - James Sia ArchitectPortfolio of work - James Sia Architect
Portfolio of work - James Sia Architect
 
Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017
 

Hebron NH Academy Building Presentation 02-17-15

  • 1. CHRISTOPHER P. WILLIAMS, ARCHITECTS PO BOX 703  MEREDITH, NH 03253  603-279-6513 CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC Hebron Town Hall Expansion February 17, 2015
  • 2. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC APPROACH TO THE CHALLENGE  Historic Building Analysis – Fall 2010  Christopher P. Williams Architects – Norman E. Larson, AIA  H.E.Bergeron Engineers – Jason Ross, P.E. and Salvatore Disanza
  • 3. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC HISTORIC BUILDING ANALYSIS  Front Gabled Greek Revival Building
  • 4. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC HISTORIC BUILDING ANALYSIS  Typical Greek Revival Detailing
  • 5. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC HISTORIC BUILDING ANALYSIS  Gothic Revival Tower Elements
  • 6. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC HISTORIC BUILDING ANALYSIS  Stone Entry Steps – (not acceptable under ADA)
  • 7. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC HISTORIC BUILDING ANALYSIS  Stone foundation on east side and front  Concrete foundation on west side and rear
  • 8. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC HISTORIC BUILDING ANALYSIS  Vinyl Replacement Windows
  • 9. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC HISTORIC BUILDING ANALYSIS  Poor Egress from Meeting Room (and over a generator too)
  • 10. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC HISTORIC BUILDING ANALYSIS  New windows and finishes on Main Level  1974  2010
  • 11. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC HISTORIC BUILDING ANALYSIS  New windows and finishes on Upper Level  1974 (Librarian Isabel Blodgett)  2010  2010
  • 12. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC HISTORIC BUILDING ANALYSIS  Building Structure needs a little help  Crawl Space  Beam supporting 2nd Floor  2nd Floor Frame  Attic
  • 13. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC APPROACH TO THE CHALLENGE  Historic Building Analysis – Fall 2010  Plan New Hampshire Design Charrette – September 23 and 24, 2011  Robin LeBlanc – Plan NH Executive Director  Brian Murphy, AIA – (Team Leader) ManyPenny Murphy Architecture  Scott Collard – (Plan NH Charrette Committee Chair and Facilitator)  Gordon Cormack – Cormack Construction Management  Maggie Stier – New Hampshire Preservation Alliance  Norman Larson – CPW Architects  Jeffrey Taylor – Jeffrey Taylor Planning  A very long list of Hebron Citizens and Elected Officials
  • 14. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC PLAN NEW HAMPSHIRE DESIGN CHARRETTE Listening Sessions – Friday Afternoon and Evening Team Presentation – Saturday Afternoon (Brian Murphy)
  • 15. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC PLAN NEW HAMPSHIRE DESIGN CHARRETTE The iconic nature of the Town Common
  • 16. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC APPROACH TO THE CHALLENGE  Historic Building Analysis – Fall 2010  Plan New Hampshire Design Charrette – September 23 and 24, 2011  Town Offices Expansion and Refurbishment Committee Formed - 2014  Roger Larochelle  Paul Hazelton  Mark Coulson Trip Swartz Patrick Moriarty  Ellie Lonske  Ivan Quinchia
  • 17. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC APPROACH TO THE CHALLENGE  Historic Building Analysis – Fall 2010  Plan New Hampshire Design Charrette – September 23 and 24, 2011  Town Offices Expansion and Refurbishment Committee Formed - 2014  Program for Town Offices – July 2014  Norman E. Larson, AIA  Town Offices Committee  Town Staff
  • 18. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC BUILDING PROGRAM (SPACE NEEDS ANALYSIS)
  • 19. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC BUILDING PROGRAM (SPACE NEEDS ANALYSIS)
  • 20. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC APPROACH TO THE CHALLENGE  Historic Building Analysis – Fall 2010  Plan New Hampshire Design Charrette – September 23 and 24, 2011  Town Offices Expansion and Refurbishment Committee Formed – 2014  Program for Town Offices – July 2014  Three Preliminary Schemes to solve the same problem – Presented August 2014 Scheme A – Addition to Rear– Administration on second floor (too small) Scheme B – Two Story – Tax Collector and Town Clerk upstairs Scheme C – One Story – All services on main floor
  • 21. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC THREE PRELIMINARY SCHEMES Scheme A – Addition to Rear– Administration on second floor (too small)
  • 22. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC THREE PRELIMINARY SCHEMES Scheme B – Two Story – Tax Collector and Town Clerk upstairs
  • 23. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC THREE PRELIMINARY SCHEMES Scheme C – One Story – All services on main floor
  • 24. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC APPROACH TO THE CHALLENGE  Historic Building Analysis – Fall 2010  Plan New Hampshire Design Charrette – September 23 and 24, 2011  Town Offices Expansion and Refurbishment Committee Formed - 2014 Program for Town Offices – July 2014  Three Preliminary Schemes to solve the same problem – August 2014  Collection of Community Input – September 2014  Schemes B and C displayed in Town Hall and online  Clear consensus to keeping all Town Offices on main level  Several comments in favor of western facing gable
  • 25. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC APPROACH TO THE CHALLENGE  Historic Building Analysis – Fall 2010  Plan New Hampshire Design Charrette – September 23 and 24, 2011  Town Offices Expansion and Refurbishment Committee Formed - 2014 Program for Town Offices – July 2014  Three Preliminary Schemes to solve the same problem – August 2014  Collection of Community Input – September 2014  Revised Schematic Design of two Schemes – October 2014  Scheme D – North South Gable – all services on main floor - selected  Scheme E – East West Gable – all services on main floor - rejected
  • 26. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC REVISED SCHEMATIC DESIGN  Scheme D – North South Gable – all services on main floor - selected
  • 27. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC REVISED SCHEMATIC DESIGN  Scheme E – East West Gable – all services on main floor - rejected
  • 28. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC APPROACH TO THE CHALLENGE  Historic Building Analysis – Fall 2010  Plan New Hampshire Design Charrette – September 23 and 24, 2011  Town Offices Expansion and Refurbishment Committee Formed - 2014 Program for Town Offices – July 2014  Three Preliminary Schemes to solve the same problem – August 2014  Collection of Community Input – September 2014  Revised Schematic Design of two Schemes – October 2014  Collection of Community Input – November 2014  Drawings posted at the polling place  Drawings and video made available online
  • 29. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC APPROACH TO THE CHALLENGE  Historic Building Analysis – Fall 2010  Plan New Hampshire Design Charrette – September 23 and 24, 2011  Town Offices Expansion and Refurbishment Committee Formed - 2014 Program for Town Offices – July 2014  Three Preliminary Schemes to solve the same problem – August 2014  Collection of Community Input – September 2014  Revised Schematic Design of two Schemes – October 2014  Collection of Community Input – November 2014  Initiation of Design Development  Revisions made to reflect Committee Input  Development of Energy Performance and Construction Criteria  Systems comparative cost analysis
  • 30. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT Proposed Main Level Plan
  • 31. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT Proposed Upper Level Plan
  • 32. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT Proposed Basement Plan
  • 33. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT Proposed Site Plan
  • 34. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT Proposed Roof Plan
  • 35. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT Proposed Building Elevations
  • 36. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT Proposed Building Elevations
  • 37. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT Proposed View from Northeast
  • 38. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT  View of Proposed Entry
  • 39. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT  View of Proposed Addition
  • 40. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC DESIGN DEVELOPMENT  View of Proposed Addition from West Shore Road (without woods)
  • 41. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC APPROACH TO THE CHALLENGE  Historic Building Analysis – Fall 2010  Plan New Hampshire Design Charrette – September 23 and 24, 2011  Town Offices Expansion and Refurbishment Committee Formed - 2014 Program for Town Offices – July 2014  Three Preliminary Schemes to solve the same problem – August 2014  Collection of Community Input – September 2014  Revised Schematic Design of two Schemes – October 2014  Collection of Community Input – November 2014  Initiation of Design Development What’s Next  Confirm direction of the project with the voters  Long and short term cost analysis of building systems and construction process  Construction Documents including engineering
  • 42. CHRISTOPHER P. WILLIAMS ARCHITECTS, PLLC Thank you for your time and we welcome any questions you may have. QUESTIONS

Editor's Notes

  1. This is a collection of photos
  2. This is a collection of photos
  3. This is a collection of photos
  4. This is a collection of photos
  5. This is a collection of photos
  6. This is a collection of photos
  7. This is a collection of photos
  8. This is a collection of photos
  9. This is a collection of photos
  10. This is a collection of photos
  11. This is a collection of photos
  12. This is a collection of photos
  13. This is a collection of photos
  14. This is a collection of photos
  15. This is a collection of photos
  16. This is a collection of photos
  17. This is a collection of photos
  18. This is a collection of photos
  19. This is a collection of photos
  20. This is a collection of photos
  21. This is a collection of photos
  22. This is a collection of photos
  23. This is a collection of photos
  24. This is a collection of photos
  25. This is a collection of photos
  26. This is a collection of photos
  27. This is a collection of photos
  28. This is a collection of photos
  29. This is a collection of photos
  30. This is a collection of photos
  31. This is a collection of photos
  32. This is a collection of photos
  33. This is a collection of photos
  34. This is a collection of photos
  35. This is a collection of photos
  36. This is a collection of photos
  37. This is a collection of photos
  38. This is a collection of photos
  39. This is a collection of photos
  40. This is a collection of photos
  41. This is a collection of photos
  42. This is a collection of photos