GS EP SAF 226 rev. 04 – main modifications
General
This document highlights the main modifications brought to GS EP SAF 226.
It is not intended to be exhaustive.
What is the purpose of the revision?
Update following EP branch re-organisation (March 2011)
Update of reference document list
Wording changes for a clearer distinction between Company’s requirements and
recommendations
Revision of the section related to SIMOPS
Addition of a new section specific to subsea well safety systems
EP/DEV/ED/ECP – October 2011
3. 3
GS EP SAF 226 rev. 04 – main modifications
Summary of modifications
Section 1: scope modification to include subsea systems
Section 3: change of terminology for annulus (first annulus = annulus A; first
surrounding casing = annulus B etc)
Section 9: simplification of this section related to Simultaneous Operations – the
safety requirements remain the same as before
Section 10: new section dedicated to subsea systems
Appendix 1: modified to cover subsea wells / for all completed wells, the annulus
DSHV is not considered as part of the internal barrier envelope anymore
Appendix 7: new appendix regarding typical subsea wellhead safety logic diagram
Appendixes 8 to 10: new appendixes regarding typical production / gas injection /
water injection wellhead arrangements