SlideShare a Scribd company logo
GRP PROGRAM CONSTRUCTION
PROGRESS
SJRA Board of
Directors
Meeting
April 25, 2013
GRP Review
Committee
Meeting
April 22, 2013
ACCESS ROAD ASPHALT PROJECT
CONSTRUCTION ADMINISTRATION
Project Data Thru 03/31/2013 - Project Complete
Project Budget: $ 481,791.00
Contracted Amount: $ 413,829.00
Change Orders: $ [1,544.41]
Estimate to Complete: $ 412,284.59
Amount Invoiced: $ 412,284.59
Budget Remaining: $ 69,506.41
Percent In-Place Work: 100%
Completion Date: March 28, 2013
Project Data Thru 03/31/2013 - Early Work Package 4
Project Budget: $191,000,000.00
Contracted Amount: $190,704,740.00
Change Orders: $ 0.00
Estimate to Complete: $191,000,000.00
Amount Invoiced: $ 20,440,274.58
Budget Remaining: $170,559,725.42
Percent In-Place Work: 23.40%
Completion Date: June 1, 2015
SURFACE WATER FACILITY
CONSTRUCTION ADMINISTRATION
Raw Water Intake foundation forming system
RAW WATER INTAKE AND PUMP STATION
April 02, 2013
Raw Water Intake foundation forming system
RAW WATER INTAKE AND PUMP STATION
April 09, 2013
Concrete placement at Raw Water Intake bridge
RAW WATER INTAKE AND PUMP STATION
April 05, 2013
HIGH SERVICE PUMP STATION
March progress photograph of the Pump Room
March 04, 2013
Underground plumbing and electric installation
HIGH SERVICE PUMP STATION
April 04, 2013
Stabilized soil backfill at the Discharge Bay
HIGH SERVICE PUMP STATION
April 04, 2013
GROUND STORAGE TANKS
March progress photograph at GST2
March 06, 2013
Installation of interior concrete baffle walls at GST2
GROUND STORAGE TANKS
March 28, 2013
March progress photograph at Granulated Activated Carbon
Building
WATER TREATMENT PLANT
March 15, 2013
Concrete encasement of piping at Granulated Activated Carbon
Building
WATER TREATMENT PLANT
April 01, 2013
March progress photograph at Membrane Building
WATER TREATMENT PLANT
March11, 2013
Southeast pipe gallery at the Membrane Building
WATER TREATMENT PLANT
April 02, 2013
42” Membrane feed piping from Pretreatment Facility
WATER TREATMENT PLANT
April 02, 2013
March progress photograph at Pretreatment Facility
WATER TREATMENT PLANT
March 15, 2013
Underground utility installation at Pretreatment Facility
WATER TREATMENT PLANT
April 01, 2013

More Related Content

Viewers also liked

GRP Program Water Line Construction Progress
GRP Program Water Line Construction ProgressGRP Program Water Line Construction Progress
GRP Program Water Line Construction Progress
San Jacinto River Authority
 
Creating a Water Conservation Plan
Creating a Water Conservation PlanCreating a Water Conservation Plan
Creating a Water Conservation Plan
The Texas Network, LLC
 
San Jacinto River Authority Water Quality 2011
San Jacinto River Authority Water Quality 2011San Jacinto River Authority Water Quality 2011
San Jacinto River Authority Water Quality 2011
The Texas Network, LLC
 
Lake Conroe Surface Water Pilot Plant PowerPoint
Lake Conroe Surface Water Pilot Plant PowerPointLake Conroe Surface Water Pilot Plant PowerPoint
Lake Conroe Surface Water Pilot Plant PowerPoint
San Jacinto River Authority
 
Water conservation
Water conservationWater conservation
Water conservation
Nidhi Vispute
 
Surface Water Facilities construction progress 11-2012
Surface Water Facilities construction progress  11-2012Surface Water Facilities construction progress  11-2012
Surface Water Facilities construction progress 11-2012
San Jacinto River Authority
 
OrthoGo Презентация нового логотипа вариант 1
OrthoGo Презентация нового логотипа вариант 1OrthoGo Презентация нового логотипа вариант 1
OrthoGo Презентация нового логотипа вариант 1
brandaid
 

Viewers also liked (7)

GRP Program Water Line Construction Progress
GRP Program Water Line Construction ProgressGRP Program Water Line Construction Progress
GRP Program Water Line Construction Progress
 
Creating a Water Conservation Plan
Creating a Water Conservation PlanCreating a Water Conservation Plan
Creating a Water Conservation Plan
 
San Jacinto River Authority Water Quality 2011
San Jacinto River Authority Water Quality 2011San Jacinto River Authority Water Quality 2011
San Jacinto River Authority Water Quality 2011
 
Lake Conroe Surface Water Pilot Plant PowerPoint
Lake Conroe Surface Water Pilot Plant PowerPointLake Conroe Surface Water Pilot Plant PowerPoint
Lake Conroe Surface Water Pilot Plant PowerPoint
 
Water conservation
Water conservationWater conservation
Water conservation
 
Surface Water Facilities construction progress 11-2012
Surface Water Facilities construction progress  11-2012Surface Water Facilities construction progress  11-2012
Surface Water Facilities construction progress 11-2012
 
OrthoGo Презентация нового логотипа вариант 1
OrthoGo Презентация нового логотипа вариант 1OrthoGo Презентация нового логотипа вариант 1
OrthoGo Презентация нового логотипа вариант 1
 

Similar to GRP Program Construction Progress April 2013

Road Safety Project Challenge
Road Safety Project ChallengeRoad Safety Project Challenge
Road Safety Project Challenge
Caribbean Development Bank
 
Sdlc project planning phase
Sdlc project planning phaseSdlc project planning phase
Sdlc project planning phase
Sejal Gandhi
 
June2013en
June2013enJune2013en
Mp surface water
Mp surface waterMp surface water
Mp surface water
hydrologywebsite1
 
Website project summary pages 131107
Website project summary pages 131107Website project summary pages 131107
Website project summary pages 131107
Houston Community College
 
Final Review
Final ReviewFinal Review
Final Review
Amit Binglesh
 
April2013en
April2013enApril2013en
May2013en
May2013enMay2013en
2015 04-07 city-council_workshop_presentation
2015 04-07 city-council_workshop_presentation2015 04-07 city-council_workshop_presentation
2015 04-07 city-council_workshop_presentation
publicinvolvement
 
Олекса Стельмах «Де мій проект? Типові помилки управління вотерфолним проектом»
Олекса Стельмах «Де мій проект? Типові помилки управління вотерфолним проектом»Олекса Стельмах «Де мій проект? Типові помилки управління вотерфолним проектом»
Олекса Стельмах «Де мій проект? Типові помилки управління вотерфолним проектом»
Lviv Startup Club
 
Building Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - PresentationBuilding Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - Presentation
Yee Len Wan
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
PRIYANSHU KUMAR
 
Norhtern Power Distribution Project
Norhtern Power Distribution ProjectNorhtern Power Distribution Project
Norhtern Power Distribution Project
Damrong Charles Phomdouangsy(Laos)
 
Chhattisgarh
ChhattisgarhChhattisgarh
Chhattisgarh
hydrologywebsite1
 
2013 CIP executive summary 131204
2013 CIP executive summary 1312042013 CIP executive summary 131204
2013 CIP executive summary 131204
Houston Community College
 
Detailed Project Status Report Template
Detailed Project Status Report TemplateDetailed Project Status Report Template
Detailed Project Status Report Template
Techno-PM PTY LTD
 
RadGridExport
RadGridExportRadGridExport
RadGridExport
Laureana E. Cortez
 
Project HSE Progress .pptx
Project HSE  Progress  .pptxProject HSE  Progress  .pptx
Project HSE Progress .pptx
DILIP KUMAR M.Tech (ACT)
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docx
ericbrooks84875
 

Similar to GRP Program Construction Progress April 2013 (19)

Road Safety Project Challenge
Road Safety Project ChallengeRoad Safety Project Challenge
Road Safety Project Challenge
 
Sdlc project planning phase
Sdlc project planning phaseSdlc project planning phase
Sdlc project planning phase
 
June2013en
June2013enJune2013en
June2013en
 
Mp surface water
Mp surface waterMp surface water
Mp surface water
 
Website project summary pages 131107
Website project summary pages 131107Website project summary pages 131107
Website project summary pages 131107
 
Final Review
Final ReviewFinal Review
Final Review
 
April2013en
April2013enApril2013en
April2013en
 
May2013en
May2013enMay2013en
May2013en
 
2015 04-07 city-council_workshop_presentation
2015 04-07 city-council_workshop_presentation2015 04-07 city-council_workshop_presentation
2015 04-07 city-council_workshop_presentation
 
Олекса Стельмах «Де мій проект? Типові помилки управління вотерфолним проектом»
Олекса Стельмах «Де мій проект? Типові помилки управління вотерфолним проектом»Олекса Стельмах «Де мій проект? Типові помилки управління вотерфолним проектом»
Олекса Стельмах «Де мій проект? Типові помилки управління вотерфолним проектом»
 
Building Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - PresentationBuilding Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - Presentation
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Norhtern Power Distribution Project
Norhtern Power Distribution ProjectNorhtern Power Distribution Project
Norhtern Power Distribution Project
 
Chhattisgarh
ChhattisgarhChhattisgarh
Chhattisgarh
 
2013 CIP executive summary 131204
2013 CIP executive summary 1312042013 CIP executive summary 131204
2013 CIP executive summary 131204
 
Detailed Project Status Report Template
Detailed Project Status Report TemplateDetailed Project Status Report Template
Detailed Project Status Report Template
 
RadGridExport
RadGridExportRadGridExport
RadGridExport
 
Project HSE Progress .pptx
Project HSE  Progress  .pptxProject HSE  Progress  .pptx
Project HSE Progress .pptx
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docx
 

More from San Jacinto River Authority

Zebra Mussels in Texas
Zebra Mussels in TexasZebra Mussels in Texas
Zebra Mussels in Texas
San Jacinto River Authority
 
Lake conroe zebra mussels action plan
Lake conroe zebra mussels action planLake conroe zebra mussels action plan
Lake conroe zebra mussels action plan
San Jacinto River Authority
 
The Lake Report 03/05/13
The Lake Report 03/05/13The Lake Report 03/05/13
The Lake Report 03/05/13
San Jacinto River Authority
 
The Lake Report 12/06/2012
The Lake Report 12/06/2012The Lake Report 12/06/2012
The Lake Report 12/06/2012
San Jacinto River Authority
 
The Lake Report 11/07/2012
The Lake Report 11/07/2012The Lake Report 11/07/2012
The Lake Report 11/07/2012
San Jacinto River Authority
 
The Lake Report 08-01-12
The Lake Report 08-01-12The Lake Report 08-01-12
The Lake Report 08-01-12
San Jacinto River Authority
 
SJRA Highlands Division
SJRA Highlands DivisionSJRA Highlands Division
SJRA Highlands Division
San Jacinto River Authority
 
U.S. Drought monitor Texas presentation 2010 to 2012
U.S. Drought monitor Texas presentation 2010 to 2012U.S. Drought monitor Texas presentation 2010 to 2012
U.S. Drought monitor Texas presentation 2010 to 2012
San Jacinto River Authority
 
SJRA and the Catahoula
SJRA and the CatahoulaSJRA and the Catahoula
SJRA and the Catahoula
San Jacinto River Authority
 
GRP Monthly Report February 2012
GRP Monthly Report February 2012GRP Monthly Report February 2012
GRP Monthly Report February 2012
San Jacinto River Authority
 
The lake report 2-13-12
The lake report 2-13-12The lake report 2-13-12
The lake report 2-13-12
San Jacinto River Authority
 
Lake Conroe Clean-Up
Lake Conroe Clean-UpLake Conroe Clean-Up
Lake Conroe Clean-Up
San Jacinto River Authority
 
The Lake Report 01-24-12
The Lake Report 01-24-12The Lake Report 01-24-12
The Lake Report 01-24-12
San Jacinto River Authority
 

More from San Jacinto River Authority (13)

Zebra Mussels in Texas
Zebra Mussels in TexasZebra Mussels in Texas
Zebra Mussels in Texas
 
Lake conroe zebra mussels action plan
Lake conroe zebra mussels action planLake conroe zebra mussels action plan
Lake conroe zebra mussels action plan
 
The Lake Report 03/05/13
The Lake Report 03/05/13The Lake Report 03/05/13
The Lake Report 03/05/13
 
The Lake Report 12/06/2012
The Lake Report 12/06/2012The Lake Report 12/06/2012
The Lake Report 12/06/2012
 
The Lake Report 11/07/2012
The Lake Report 11/07/2012The Lake Report 11/07/2012
The Lake Report 11/07/2012
 
The Lake Report 08-01-12
The Lake Report 08-01-12The Lake Report 08-01-12
The Lake Report 08-01-12
 
SJRA Highlands Division
SJRA Highlands DivisionSJRA Highlands Division
SJRA Highlands Division
 
U.S. Drought monitor Texas presentation 2010 to 2012
U.S. Drought monitor Texas presentation 2010 to 2012U.S. Drought monitor Texas presentation 2010 to 2012
U.S. Drought monitor Texas presentation 2010 to 2012
 
SJRA and the Catahoula
SJRA and the CatahoulaSJRA and the Catahoula
SJRA and the Catahoula
 
GRP Monthly Report February 2012
GRP Monthly Report February 2012GRP Monthly Report February 2012
GRP Monthly Report February 2012
 
The lake report 2-13-12
The lake report 2-13-12The lake report 2-13-12
The lake report 2-13-12
 
Lake Conroe Clean-Up
Lake Conroe Clean-UpLake Conroe Clean-Up
Lake Conroe Clean-Up
 
The Lake Report 01-24-12
The Lake Report 01-24-12The Lake Report 01-24-12
The Lake Report 01-24-12
 

Recently uploaded

Essential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptxEssential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptx
Pragencyuk
 
What Ukraine Has Lost During Russia’s Invasion
What Ukraine Has Lost During Russia’s InvasionWhat Ukraine Has Lost During Russia’s Invasion
What Ukraine Has Lost During Russia’s Invasion
LUMINATIVE MEDIA/PROJECT COUNSEL MEDIA GROUP
 
Acolyte Episodes review (TV series)..pdf
Acolyte Episodes review (TV series)..pdfAcolyte Episodes review (TV series)..pdf
Acolyte Episodes review (TV series)..pdf
46adnanshahzad
 
MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)
Filippo64
 
Letter-from-ECI-to-MeiTY-21st-march-2024.pdf
Letter-from-ECI-to-MeiTY-21st-march-2024.pdfLetter-from-ECI-to-MeiTY-21st-march-2024.pdf
Letter-from-ECI-to-MeiTY-21st-march-2024.pdf
bhavenpr
 
Gabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary JudgmentGabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary Judgment
Abdul-Hakim Shabazz
 
EED - The Container Port PERFORMANCE INDEX 2023
EED - The Container Port PERFORMANCE INDEX 2023EED - The Container Port PERFORMANCE INDEX 2023
EED - The Container Port PERFORMANCE INDEX 2023
El Estrecho Digital
 
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
CIkumparan
 
Hindustan Insider 2nd edition release now
Hindustan Insider 2nd edition release nowHindustan Insider 2nd edition release now
Hindustan Insider 2nd edition release now
hindustaninsider22
 

Recently uploaded (9)

Essential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptxEssential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptx
 
What Ukraine Has Lost During Russia’s Invasion
What Ukraine Has Lost During Russia’s InvasionWhat Ukraine Has Lost During Russia’s Invasion
What Ukraine Has Lost During Russia’s Invasion
 
Acolyte Episodes review (TV series)..pdf
Acolyte Episodes review (TV series)..pdfAcolyte Episodes review (TV series)..pdf
Acolyte Episodes review (TV series)..pdf
 
MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)
 
Letter-from-ECI-to-MeiTY-21st-march-2024.pdf
Letter-from-ECI-to-MeiTY-21st-march-2024.pdfLetter-from-ECI-to-MeiTY-21st-march-2024.pdf
Letter-from-ECI-to-MeiTY-21st-march-2024.pdf
 
Gabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary JudgmentGabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary Judgment
 
EED - The Container Port PERFORMANCE INDEX 2023
EED - The Container Port PERFORMANCE INDEX 2023EED - The Container Port PERFORMANCE INDEX 2023
EED - The Container Port PERFORMANCE INDEX 2023
 
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
 
Hindustan Insider 2nd edition release now
Hindustan Insider 2nd edition release nowHindustan Insider 2nd edition release now
Hindustan Insider 2nd edition release now
 

GRP Program Construction Progress April 2013

  • 1. GRP PROGRAM CONSTRUCTION PROGRESS SJRA Board of Directors Meeting April 25, 2013 GRP Review Committee Meeting April 22, 2013
  • 2. ACCESS ROAD ASPHALT PROJECT CONSTRUCTION ADMINISTRATION Project Data Thru 03/31/2013 - Project Complete Project Budget: $ 481,791.00 Contracted Amount: $ 413,829.00 Change Orders: $ [1,544.41] Estimate to Complete: $ 412,284.59 Amount Invoiced: $ 412,284.59 Budget Remaining: $ 69,506.41 Percent In-Place Work: 100% Completion Date: March 28, 2013
  • 3. Project Data Thru 03/31/2013 - Early Work Package 4 Project Budget: $191,000,000.00 Contracted Amount: $190,704,740.00 Change Orders: $ 0.00 Estimate to Complete: $191,000,000.00 Amount Invoiced: $ 20,440,274.58 Budget Remaining: $170,559,725.42 Percent In-Place Work: 23.40% Completion Date: June 1, 2015 SURFACE WATER FACILITY CONSTRUCTION ADMINISTRATION
  • 4. Raw Water Intake foundation forming system RAW WATER INTAKE AND PUMP STATION April 02, 2013
  • 5. Raw Water Intake foundation forming system RAW WATER INTAKE AND PUMP STATION April 09, 2013
  • 6. Concrete placement at Raw Water Intake bridge RAW WATER INTAKE AND PUMP STATION April 05, 2013
  • 7. HIGH SERVICE PUMP STATION March progress photograph of the Pump Room March 04, 2013
  • 8. Underground plumbing and electric installation HIGH SERVICE PUMP STATION April 04, 2013
  • 9. Stabilized soil backfill at the Discharge Bay HIGH SERVICE PUMP STATION April 04, 2013
  • 10. GROUND STORAGE TANKS March progress photograph at GST2 March 06, 2013
  • 11. Installation of interior concrete baffle walls at GST2 GROUND STORAGE TANKS March 28, 2013
  • 12. March progress photograph at Granulated Activated Carbon Building WATER TREATMENT PLANT March 15, 2013
  • 13. Concrete encasement of piping at Granulated Activated Carbon Building WATER TREATMENT PLANT April 01, 2013
  • 14. March progress photograph at Membrane Building WATER TREATMENT PLANT March11, 2013
  • 15. Southeast pipe gallery at the Membrane Building WATER TREATMENT PLANT April 02, 2013
  • 16. 42” Membrane feed piping from Pretreatment Facility WATER TREATMENT PLANT April 02, 2013
  • 17. March progress photograph at Pretreatment Facility WATER TREATMENT PLANT March 15, 2013
  • 18. Underground utility installation at Pretreatment Facility WATER TREATMENT PLANT April 01, 2013