SlideShare a Scribd company logo
STREAMLINING
PROCESSES ON
THE WORLD’S
LARGEST
PROJECT.
BARROW ISLAND
WESTERN AUSTRALIA
JAN
2014
JUNE
2013
INSTALLATION OF
AMINE ABSORBER
LOAD-OUT OF REACTORS
Discover more on www.mammoet.com
FROM SHIP TO SITE: CARE AND COMPLEXITY ON A MASSIVE SCALE.
JAN
2014
SPHERE MODULE ON SITEDEC
2013
REFRIGERATION COURTYARD
MODULE ON ITS WAY
A Z
Gorgon is the single biggest LNG
investment in history. When
completed, it will be one of the
world’s largest liquefied natural
gas plants, providing 15 million
tons of LNG per year from Barrow
Island, a Class A Nature Reserve
in Australia. This environmentally
sensitive project requires a
heavy lifting and transport partner
with the engineering capacity,
expertise and fleet of equipment
to safely manage the offloading
and installation of the many
modules that arrive - and without
any compromise to the stringent
Quarantine Management System.
Chevron has approved Mammoet
as their Gorgon partner for the
engineered heavy lifting and transport
activities. Among other qualifications,
deep experience with Australian
quarantine practices made Mammoet
the right choice for the Gorgon team.
Mammoet is responsible for lifting,
transportation and installation of
all modules, the biggest of which
weigh as much as 6,200 tons. All
tasks must be completed with no
compromise to the complex Gorgon
Quarantine Management System
(QMS) – with some 300 procedures,
checklists, and guidelines. The
philosophy is simple: zero tolerance
for the introduction of non-indigenous
species. All Gorgon modules must
undergo the QMS process.
In addition, every single piece of
Mammoet equipment – large and
small, new and used – has to go
through the same inspection.
For this job, Mammoet is planning
and executing hundreds of sub-
projects: load-outs, load-ins,
transport and installation activities.
The challenge is to complete each
one safely and according to
schedule. A good example is the
unloading of the carrier Mega Trust
that arrived at the port on December
1st, 2013, carrying two LNG train
modules – at 5520 and 1409 tons
each. After the ship’s berthing and
removal of sea-fastenings and
grillage, Mammoet professionals
began offloading the modules with
264 axle lines of SPMT. All cargo had
to undergo two days of QMS before
transport to the site, where the
modules were lifted and aligned with
previously installed modules. As soon
as their position was perfect, each
module was jacked down and ready
for integration – well within the
available timeframe.
Mammoet will ultimately handle
400,000 tons of modules for Gorgon.
Mammoet’s broad and unparalleled
fleet and expertise are helping
Chevron build Gorgon while keeping
Barrow Island safe and green.
Chevron has received the United
Nations Environmental Best Practice
Award for the Gorgon Project
Quarantine Management System.
Mammoet is proud to be part of this
remarkable project, for which it has
received several safety awards.
RESOURCES
CRANES
5 crawler cranes
1 PTC
TRANSPORT
600 axle lines of SPMT
CREW
170 Mammoet professionals

More Related Content

What's hot

STA Capability Statement
STA Capability StatementSTA Capability Statement
STA Capability Statement
Ross Yendle
 
RoadPacker Asia Soil Stabiliser.pdf
RoadPacker Asia Soil Stabiliser.pdfRoadPacker Asia Soil Stabiliser.pdf
RoadPacker Asia Soil Stabiliser.pdf
Jojit Balod
 
Mud Mixing plant installed onboard Trinity Supporter for NIKO
Mud Mixing plant installed onboard Trinity Supporter for NIKOMud Mixing plant installed onboard Trinity Supporter for NIKO
Mud Mixing plant installed onboard Trinity Supporter for NIKO
Roy Catto
 

What's hot (11)

The Valletta Waterfront Experience: Back to the Future
The Valletta Waterfront Experience: Back to the FutureThe Valletta Waterfront Experience: Back to the Future
The Valletta Waterfront Experience: Back to the Future
 
11.18-19.2014, PRESENTATION, Areva's offer for Mongolia, Remy Autebert
11.18-19.2014, PRESENTATION, Areva's offer for Mongolia, Remy Autebert11.18-19.2014, PRESENTATION, Areva's offer for Mongolia, Remy Autebert
11.18-19.2014, PRESENTATION, Areva's offer for Mongolia, Remy Autebert
 
Royal Pier Cruise Terminal (Southampton) - Terminal Outline Design report
Royal Pier Cruise Terminal (Southampton) - Terminal Outline Design reportRoyal Pier Cruise Terminal (Southampton) - Terminal Outline Design report
Royal Pier Cruise Terminal (Southampton) - Terminal Outline Design report
 
STA Capability Statement
STA Capability StatementSTA Capability Statement
STA Capability Statement
 
1ResumeS 2016
1ResumeS 20161ResumeS 2016
1ResumeS 2016
 
Attachment GK
Attachment GKAttachment GK
Attachment GK
 
RoadPacker Asia Soil Stabiliser.pdf
RoadPacker Asia Soil Stabiliser.pdfRoadPacker Asia Soil Stabiliser.pdf
RoadPacker Asia Soil Stabiliser.pdf
 
Mud Mixing plant installed onboard Trinity Supporter for NIKO
Mud Mixing plant installed onboard Trinity Supporter for NIKOMud Mixing plant installed onboard Trinity Supporter for NIKO
Mud Mixing plant installed onboard Trinity Supporter for NIKO
 
Truck Safety by CALCIMA
Truck Safety by CALCIMATruck Safety by CALCIMA
Truck Safety by CALCIMA
 
C&N Intro
C&N IntroC&N Intro
C&N Intro
 
KMOC ASIA Ltd.
KMOC ASIA Ltd.KMOC ASIA Ltd.
KMOC ASIA Ltd.
 

Similar to Gorgon-A4

gorgon-project-update-issue-29
gorgon-project-update-issue-29gorgon-project-update-issue-29
gorgon-project-update-issue-29
Brian Merritt
 
focus-on-major-new-lp-gas-facilities-around-the-globe
focus-on-major-new-lp-gas-facilities-around-the-globefocus-on-major-new-lp-gas-facilities-around-the-globe
focus-on-major-new-lp-gas-facilities-around-the-globe
Klaus Gohra
 
BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015
Blase Townsing
 
Australia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project ManagerAustralia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project Manager
Niels Asjee
 
Jurong Port Corporate Brochure (2012)
Jurong Port Corporate Brochure (2012)Jurong Port Corporate Brochure (2012)
Jurong Port Corporate Brochure (2012)
norasheilla
 
A R Ram CV 2016_04 QHSSE Rev00
A R Ram CV 2016_04 QHSSE  Rev00A R Ram CV 2016_04 QHSSE  Rev00
A R Ram CV 2016_04 QHSSE Rev00
A R Ram
 
Maritime Executive_Out of Gauge CArgo
Maritime Executive_Out of Gauge CArgoMaritime Executive_Out of Gauge CArgo
Maritime Executive_Out of Gauge CArgo
Jim Romeo
 
Maritime Executive_HMorrison
Maritime Executive_HMorrisonMaritime Executive_HMorrison
Maritime Executive_HMorrison
Jim Romeo
 
Gangavaram Port Project,India
Gangavaram Port Project,IndiaGangavaram Port Project,India
Gangavaram Port Project,India
PRABIR DATTA
 
M. Miller CV 12 winch rigger
M. Miller CV 12 winch riggerM. Miller CV 12 winch rigger
M. Miller CV 12 winch rigger
Martin Miller
 

Similar to Gorgon-A4 (20)

gorgon-project-update-issue-29
gorgon-project-update-issue-29gorgon-project-update-issue-29
gorgon-project-update-issue-29
 
Brochure CMR Marine
Brochure CMR MarineBrochure CMR Marine
Brochure CMR Marine
 
507262 (tnpa) port of durban monitor newsletter final
507262 (tnpa) port of durban monitor newsletter final507262 (tnpa) port of durban monitor newsletter final
507262 (tnpa) port of durban monitor newsletter final
 
Sal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_webSal offshore brochure_2016-05-03_web
Sal offshore brochure_2016-05-03_web
 
focus-on-major-new-lp-gas-facilities-around-the-globe
focus-on-major-new-lp-gas-facilities-around-the-globefocus-on-major-new-lp-gas-facilities-around-the-globe
focus-on-major-new-lp-gas-facilities-around-the-globe
 
BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015
 
Australia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project ManagerAustralia - Gorgon LNG Project - Deputy Project Manager
Australia - Gorgon LNG Project - Deputy Project Manager
 
Jurong Port Corporate Brochure (2012)
Jurong Port Corporate Brochure (2012)Jurong Port Corporate Brochure (2012)
Jurong Port Corporate Brochure (2012)
 
REMOTE MINES(2)
REMOTE MINES(2)REMOTE MINES(2)
REMOTE MINES(2)
 
A R Ram CV 2016_04 QHSSE Rev00
A R Ram CV 2016_04 QHSSE  Rev00A R Ram CV 2016_04 QHSSE  Rev00
A R Ram CV 2016_04 QHSSE Rev00
 
RINA_Paper
RINA_PaperRINA_Paper
RINA_Paper
 
Maritime Executive_Out of Gauge CArgo
Maritime Executive_Out of Gauge CArgoMaritime Executive_Out of Gauge CArgo
Maritime Executive_Out of Gauge CArgo
 
Maritime Executive_HMorrison
Maritime Executive_HMorrisonMaritime Executive_HMorrison
Maritime Executive_HMorrison
 
Gangavaram Port Project,India
Gangavaram Port Project,IndiaGangavaram Port Project,India
Gangavaram Port Project,India
 
Dockwiser Africa eMagazine
Dockwiser Africa eMagazineDockwiser Africa eMagazine
Dockwiser Africa eMagazine
 
brochuredeepoffshore_1_0
brochuredeepoffshore_1_0brochuredeepoffshore_1_0
brochuredeepoffshore_1_0
 
M. Miller CV 12 winch rigger
M. Miller CV 12 winch riggerM. Miller CV 12 winch rigger
M. Miller CV 12 winch rigger
 
SAL Company Brochure
SAL Company BrochureSAL Company Brochure
SAL Company Brochure
 
Power Plant Demobilisation
Power Plant DemobilisationPower Plant Demobilisation
Power Plant Demobilisation
 
ISG Pit to Ship Bulk Container Brochure 2015
ISG Pit to Ship Bulk Container Brochure 2015ISG Pit to Ship Bulk Container Brochure 2015
ISG Pit to Ship Bulk Container Brochure 2015
 

Gorgon-A4

  • 2. JAN 2014 JUNE 2013 INSTALLATION OF AMINE ABSORBER LOAD-OUT OF REACTORS Discover more on www.mammoet.com FROM SHIP TO SITE: CARE AND COMPLEXITY ON A MASSIVE SCALE. JAN 2014 SPHERE MODULE ON SITEDEC 2013 REFRIGERATION COURTYARD MODULE ON ITS WAY A Z Gorgon is the single biggest LNG investment in history. When completed, it will be one of the world’s largest liquefied natural gas plants, providing 15 million tons of LNG per year from Barrow Island, a Class A Nature Reserve in Australia. This environmentally sensitive project requires a heavy lifting and transport partner with the engineering capacity, expertise and fleet of equipment to safely manage the offloading and installation of the many modules that arrive - and without any compromise to the stringent Quarantine Management System. Chevron has approved Mammoet as their Gorgon partner for the engineered heavy lifting and transport activities. Among other qualifications, deep experience with Australian quarantine practices made Mammoet the right choice for the Gorgon team. Mammoet is responsible for lifting, transportation and installation of all modules, the biggest of which weigh as much as 6,200 tons. All tasks must be completed with no compromise to the complex Gorgon Quarantine Management System (QMS) – with some 300 procedures, checklists, and guidelines. The philosophy is simple: zero tolerance for the introduction of non-indigenous species. All Gorgon modules must undergo the QMS process. In addition, every single piece of Mammoet equipment – large and small, new and used – has to go through the same inspection. For this job, Mammoet is planning and executing hundreds of sub- projects: load-outs, load-ins, transport and installation activities. The challenge is to complete each one safely and according to schedule. A good example is the unloading of the carrier Mega Trust that arrived at the port on December 1st, 2013, carrying two LNG train modules – at 5520 and 1409 tons each. After the ship’s berthing and removal of sea-fastenings and grillage, Mammoet professionals began offloading the modules with 264 axle lines of SPMT. All cargo had to undergo two days of QMS before transport to the site, where the modules were lifted and aligned with previously installed modules. As soon as their position was perfect, each module was jacked down and ready for integration – well within the available timeframe. Mammoet will ultimately handle 400,000 tons of modules for Gorgon. Mammoet’s broad and unparalleled fleet and expertise are helping Chevron build Gorgon while keeping Barrow Island safe and green. Chevron has received the United Nations Environmental Best Practice Award for the Gorgon Project Quarantine Management System. Mammoet is proud to be part of this remarkable project, for which it has received several safety awards. RESOURCES CRANES 5 crawler cranes 1 PTC TRANSPORT 600 axle lines of SPMT CREW 170 Mammoet professionals