- Golden Star is an established gold miner in Ghana with brownfield development projects transforming its production profile.
- The Wassa underground project is progressing on schedule, with the decline developed and infrastructure installed. First production is expected in early 2016.
- Drilling at Wassa has identified potential to expand resources along strike and at depth.
- Prestea Underground has potential for high grade extensions outside the known resource, with a feasibility study underway on shrinkage mining of the West Reef zone.
The document is an investor presentation for Golden Star Resources dated June 15th. It summarizes that Golden Star has secured $150 million in financing through a gold stream and loan agreement with Royal Gold. This financing will fully fund the development of Golden Star's Wassa and Prestea underground mine projects in Ghana. The presentation outlines how this financing and the development of the underground mines is expected to significantly improve Golden Star's cost profile and production outlook over the next several years.
This document provides an annual general and special meeting disclaimer and overview of Golden Star Resources Ltd. It summarizes that Golden Star is an established gold producer in Ghana with significant infrastructure that provides operational leverage. It is also developing brownfield projects that are expected to transform its production profile and deliver ounces at lower cash operating costs. The document introduces key management and the board of directors and their relevant experience in the mining industry.
- Golden Star achieved its 2013 production guidance of 331,000 ounces of gold.
- Cost cutting initiatives helped reduce costs, with cash costs per ounce of $1,044, in line with guidance.
- Capital expenditures were significantly reduced to $102.7 million while maintaining operations.
- The company is well positioned for lower cost production in 2014 and 2015 with pushbacks nearly complete at Bogoso and the large Wassa Main pit now in production.
Golden Star is expanding production and reducing costs at its projects in Ghana. The company plans to transform into a high grade, low cost gold producer by ramping up production at its Wassa Underground and Prestea Underground projects. This is expected to improve the company's production profile, lower its cash operating costs per ounce and all-in sustaining costs per ounce. Commercial production is targeted to begin at Prestea Underground in the second half of 2017, which will further reduce costs as higher grade ore is produced.
Q1 2016 results showed that Golden Star's transition to lower-cost operations is taking effect. Cash operating costs and all-in sustaining costs declined significantly from prior periods. Production exceeded expectations and cash flow from operations was positive. A $20 million payment was received from Royal Gold per the streaming agreement and additional financing of $15 million is expected to close in May 2016.
Golden Star has transformed its strategic focus and leadership to become a stable, reliable non-refractory gold producer. Key actions include suspending high-cost refractory production, converting reserves to non-refractory ounces, and unlocking value at existing mines. At Wassa, costs have been reduced by accessing higher grades from the open pit and planned underground mine. Prestea's open pits provide non-refractory production until the underground mine starts in 2017. Fourth quarter costs per ounce fell to $715 as production shifted to only non-refractory ounces. The company is fully funded to develop Wassa and Prestea underground mines to provide long-term production and cost stability.
Golden Star reported its financial results for fiscal year 2014. Key highlights included:
- Costs and expenses declined for four consecutive quarters in 2014, with cost of sales before depreciation and amortization reduced 19% from the prior year.
- Cash operating costs per ounce declined consistently through 2014, with the fourth quarter representing the lowest costs since 2010.
- The Wassa mine in Ghana showed improved operational performance in the fourth quarter of 2014, with grade processed and gold recoveries increasing.
- At the Bogoso mine, strong operational performance continued in the fourth quarter, with improved grade and processing rates maintained despite power issues.
Golden Star is expanding gold production and reducing costs at its projects in Ghana. The company plans to commence commercial production at its Prestea Underground mine in 2016 and its Wassa Underground mine. This is expected to increase production and improve grades and costs. Golden Star also aims to strengthen its balance sheet through refinancing debt in mid-2017. The company sees exploration potential to increase mine lives at its current operations.
The document is an investor presentation for Golden Star Resources dated June 15th. It summarizes that Golden Star has secured $150 million in financing through a gold stream and loan agreement with Royal Gold. This financing will fully fund the development of Golden Star's Wassa and Prestea underground mine projects in Ghana. The presentation outlines how this financing and the development of the underground mines is expected to significantly improve Golden Star's cost profile and production outlook over the next several years.
This document provides an annual general and special meeting disclaimer and overview of Golden Star Resources Ltd. It summarizes that Golden Star is an established gold producer in Ghana with significant infrastructure that provides operational leverage. It is also developing brownfield projects that are expected to transform its production profile and deliver ounces at lower cash operating costs. The document introduces key management and the board of directors and their relevant experience in the mining industry.
- Golden Star achieved its 2013 production guidance of 331,000 ounces of gold.
- Cost cutting initiatives helped reduce costs, with cash costs per ounce of $1,044, in line with guidance.
- Capital expenditures were significantly reduced to $102.7 million while maintaining operations.
- The company is well positioned for lower cost production in 2014 and 2015 with pushbacks nearly complete at Bogoso and the large Wassa Main pit now in production.
Golden Star is expanding production and reducing costs at its projects in Ghana. The company plans to transform into a high grade, low cost gold producer by ramping up production at its Wassa Underground and Prestea Underground projects. This is expected to improve the company's production profile, lower its cash operating costs per ounce and all-in sustaining costs per ounce. Commercial production is targeted to begin at Prestea Underground in the second half of 2017, which will further reduce costs as higher grade ore is produced.
Q1 2016 results showed that Golden Star's transition to lower-cost operations is taking effect. Cash operating costs and all-in sustaining costs declined significantly from prior periods. Production exceeded expectations and cash flow from operations was positive. A $20 million payment was received from Royal Gold per the streaming agreement and additional financing of $15 million is expected to close in May 2016.
Golden Star has transformed its strategic focus and leadership to become a stable, reliable non-refractory gold producer. Key actions include suspending high-cost refractory production, converting reserves to non-refractory ounces, and unlocking value at existing mines. At Wassa, costs have been reduced by accessing higher grades from the open pit and planned underground mine. Prestea's open pits provide non-refractory production until the underground mine starts in 2017. Fourth quarter costs per ounce fell to $715 as production shifted to only non-refractory ounces. The company is fully funded to develop Wassa and Prestea underground mines to provide long-term production and cost stability.
Golden Star reported its financial results for fiscal year 2014. Key highlights included:
- Costs and expenses declined for four consecutive quarters in 2014, with cost of sales before depreciation and amortization reduced 19% from the prior year.
- Cash operating costs per ounce declined consistently through 2014, with the fourth quarter representing the lowest costs since 2010.
- The Wassa mine in Ghana showed improved operational performance in the fourth quarter of 2014, with grade processed and gold recoveries increasing.
- At the Bogoso mine, strong operational performance continued in the fourth quarter, with improved grade and processing rates maintained despite power issues.
Golden Star is expanding gold production and reducing costs at its projects in Ghana. The company plans to commence commercial production at its Prestea Underground mine in 2016 and its Wassa Underground mine. This is expected to increase production and improve grades and costs. Golden Star also aims to strengthen its balance sheet through refinancing debt in mid-2017. The company sees exploration potential to increase mine lives at its current operations.
Golden Star has entered into a financing agreement with Royal Gold and its subsidiary to provide $150 million in funding. The agreement includes a $130 million gold stream and a $20 million secured loan. The funding will be used to develop the Wassa and Prestea underground mines and fully finance Golden Star's transformation into a non-refractory gold producer. The new mines are expected to significantly improve Golden Star's cost profile and production once in operation with short timelines to first production and good free cash flow.
Golden Star is expanding production and reducing costs at its Wassa and Prestea gold mines in Ghana. Production is expected to increase to 281,000 ounces annually by 2017, a 60% rise from 2016 levels, while cash operating costs are forecast to decrease to $695 per ounce. This will be achieved through commencing production at the high grade Wassa Underground mine in early 2017 and the Prestea Underground mine in mid-2017. Capital expenditures are increasing to fund the underground development projects, which will transform Golden Star into a higher grade, lower cost producer.
Golden Star is a gold mining company with operations in Ghana. It is transforming to focus on lower cost, non-refractory mining. Its Wassa Underground and Prestea projects are expected to deliver low cost production starting in 2016, with combined cash costs below $700/oz. The projects have high internal rates of return and will leverage existing infrastructure. Golden Star aims to further reduce costs at its current operations and has potential for new discoveries to extend mine lives.
Golden Star Resources is focused on unlocking value at its existing mines in Ghana. At Wassa, the company is accessing higher grade portions of the ore body from an underground mine to supplement production from the open pit. First ore from Wassa Underground is expected in mid-2016, with commercial production in early 2017. At Prestea, open pits are currently producing while rehabilitation of the underground mine is underway to establish additional production. Prestea Underground is expected to begin production in mid-2017. The company aims to become a stable gold producer through these projects and an increased focus on operational efficiencies.
This document provides an overview of Golden Star Resources, including:
- New leadership and corporate structure implemented since 2013 to focus on existing asset base.
- Goals include becoming a stable gold producer by eliminating high-cost refractory production and converting reserves to non-refractory.
- Operations located on prolific Ashanti Gold Belt in Ghana.
- Second quarter 2016 production of 42,461 ounces was in line with expectations, with production impacted by a scheduled plant shutdown at Wassa.
Microsoft power point 2014 november investor presentationGoldenStarResources
Golden Star is transforming into a lower cost gold producer by closing its higher cost refractory operation in late 2015 and developing the Wassa underground mine. The Wassa underground PEA delivered strong results, indicating it can reduce Wassa's costs per ounce dramatically and generate average annual production of 70koz over 4.5 years at $370/oz after $40 million investment. Golden Star's expenditure of $80 million on developing Wassa and Prestea is expected to unlock significant value for shareholders by reducing the group's life of mine costs below $700/oz from 2016 onward.
Golden Star reported its Q1 2014 financial results. Gold production was 65,812 ounces, in line with expectations. Cash operating costs per ounce increased to $1,206 due to transitioning to a new pit at Wassa and lower grades and recoveries at Bogoso. Cost of sales excluding depreciation decreased to $84.3 million due to lower mining contractor expenses. Golden Star maintained its 2014 production guidance of 295,000-320,000 ounces and cash cost guidance of $950-1,000 per ounce.
Golden Star achieved its 2016 production and cost guidance across its operations. Production totaled 194,054 ounces for the year, within the guidance range. Cash operating costs per ounce were $872, in the middle of the guidance range. Capital expenditures totaled $84.4 million for the year, a 48% increase over 2015, to fund development projects including Wassa and Prestea Underground mines. Commercial production was achieved at Wassa Underground on January 1, 2017, as planned.
Golden Star plans to expand production and reduce costs at its projects in Ghana. It aims to transform into a high grade, low cost gold producer by ramping up production from its Wassa Underground and Prestea Underground projects. Wassa Underground is expected to increase production and lower costs in 2017, while Prestea Underground is targeting commercial production in mid-2017. Golden Star forecasts total production to increase 31-44% in 2017 compared to 2016, with cash operating costs expected to decrease as higher grade underground ore becomes available.
- Golden Star operates two producing gold mines in Ghana - Wassa and Bogoso - with three processing plants and total annual capacity of 7 million tonnes.
- In 2013, Golden Star produced 331,000 ounces of gold at a cash cost of $1,049 per ounce, achieving its production and cost guidance.
- For 2014, Golden Star guidance is 295,000 to 320,000 ounces of gold at a cash cost of $950 to $1,000 per ounce and all-in sustaining costs of $1,150 to $1,200 per ounce.
Expanding Production and Reducing Costs at Golden Star's projects. Golden Star plans to expand production and reduce costs by developing two underground mines, Wassa Underground and Prestea Underground. This is expected to transform Golden Star's production and cost profiles, with production forecast to increase 60% between 2016 and 2019 while cash operating costs and AISC decline. Golden Star is on track to achieve its 2016 guidance and the underground development projects are advancing as planned, with infrastructure in place at Wassa Underground and stoping commenced in the third quarter.
Golden Star Resources Ltd. is a gold mining company focused on its two underground mining operations in Ghana - Wassa Underground and Prestea Underground. The presentation provides an operational and financial overview of Golden Star, including 2018 production guidance of 230,000-255,000 ounces of gold at an AISC of $850-950 per ounce. It highlights recent drilling results from Wassa Underground that indicate the deposit may be larger than previously estimated. The presentation also outlines Golden Star's $6.6 million exploration budget and plans to test for resource expansions and new underground targets near its existing operations.
- Aurico Gold reported financial results for Q3 2014 with revenue of $73.5 million, a 36% increase from Q3 2013, due to higher gold production and sales.
- Gold production was 57,037 ounces, a 48% increase from the prior year, driven by the ramp up of operations at the Young-Davidson mine.
- Cash costs per ounce decreased 17% at Young-Davidson from the previous quarter and the mine is expected to generate positive cash flow by the end of 2014.
AuRico Gold reported financial results for Q1 2015 with the following highlights:
- Solid production of 54,027 ounces at total cash costs of $696/ounce.
- Young-Davidson and El Chanate mines performed well with production on track.
- Underground development at Young-Davidson advanced as planned with productivity and costs improving.
- The company announced a merger with Alamos Gold to create a leading intermediate gold producer.
Golden Star provides guidance for 2018, focusing on generating cash flow. Production is expected to be between 230,000-255,000 ounces at an AISC of $850-950 per ounce. Capital expenditures are budgeted at $36.5 million. Operations will focus on the high margin underground mines at Wassa and Prestea. Wassa Underground is expected to continue ramping up production in 2018. Commercial production has been achieved at Prestea Underground and step-out drilling indicates potential to increase resources.
Golden Star reported Q1 2018 gold production of 57,616 ounces, with production from Wassa Underground exceeding expectations at 35,506 ounces. Wassa Underground grade was 4.54 g/t Au, a 12% increase from Q4 2017. Golden Star is on track to achieve 2018 consolidated guidance of 230,000-255,000 ounces. Recent drilling at Wassa Underground doubled the inferred mineral resource to 5.2 million ounces and extended mineralization down-plunge, indicating further upside potential.
Dgc 15 11_10 - nbf-tsx canadian miners conferenceDetourGold
Detour Gold Corporation is Canada's intermediate gold producer. In Q3 2015, Detour Lake Mine produced 106,125 ounces of gold at total cash costs of $942/ounce and all-in sustaining costs of $1,071/ounce. For full-year 2015, Detour Lake Mine expects gold production between 475,000-525,000 ounces at total cash costs between $780-$850/ounce and all-in sustaining costs between $1,050-$1,150/ounce. Detour Gold will focus its life of mine plan update on a lower risk operational profile with a mining rate reduction and higher plant throughput capacity while adding the nearby Block A deposit as a second feed source starting in 2018.
Golden Star provides guidance for 2018 of producing 230,000-255,000 ounces of gold at an all-in sustaining cost of $850-950 per ounce. Capital expenditures are budgeted at $36.5 million. Wassa Underground is expected to produce 137,000-142,000 ounces at a cash operating cost of $600-650 per ounce. Prestea Underground is targeting commercial production in February 2018 and is expected to produce 93,000-113,000 ounces at an all-in sustaining cost of $740-880 per ounce. Drilling continues to extend mineralization at both underground mines.
1. Detour Gold Corporation is a Canadian gold mining company and intermediate gold producer presenting at the Scotiabank Mining Conference in Toronto.
2. The presentation discusses Detour Gold's 2015 production guidance, opportunities to optimize operations at its Detour Lake Mine in Ontario, and notes that Detour Gold represents a unique investment opportunity as Canada's largest gold producer not controlled by a senior mining company.
3. Forward-looking statements are provided, subject to various risks and uncertainties that could cause actual results to differ materially. Non-IFRS financial measures are also referenced to provide additional information to investors.
This corporate presentation provides an overview of Detour Gold Corporation as an intermediate Canadian gold producer. Some key highlights from 2016 include producing 394,253 ounces of gold at an all-in sustaining cost of $960 per ounce sold and reducing debt levels by 28%. The presentation discusses preliminary guidance for 2017 which forecasts gold production of 540,000-590,000 ounces at an AISC of $1,050-1,150 per ounce sold. It also provides an update on exploration prospects including the prospective Zone 58N and advancing work on the West Detour project.
The document discusses plans to expand production and reduce costs at Prestea Underground. It provides a history of the mine, outlines upgrades that have been completed to rehabilitate mine infrastructure like the central shaft and winder, and procurement of mining equipment. It discusses the development sequence and Alimak mining method. Future plans are to extend mining of the West Reef zone, identify new targets in the Main Reef, and investigate underground targets at Bondaye and Tuapim.
This document discusses Golden Star Resources Ltd., a gold mining company operating in Ghana. It provides an overview of the company's leadership changes since 2013 which have brought in a new board and management with operational, development and finance expertise. It outlines the strategic shift to focus on the company's existing asset base by becoming a stable, predictable non-refractory gold producer and unlocking additional value. It also provides brief highlights on the company's Q2 2016 operational results, including gold production numbers from its Wassa and Prestea mines in Ghana.
Golden Star has entered into a financing agreement with Royal Gold and its subsidiary to provide $150 million in funding. The agreement includes a $130 million gold stream and a $20 million secured loan. The funding will be used to develop the Wassa and Prestea underground mines and fully finance Golden Star's transformation into a non-refractory gold producer. The new mines are expected to significantly improve Golden Star's cost profile and production once in operation with short timelines to first production and good free cash flow.
Golden Star is expanding production and reducing costs at its Wassa and Prestea gold mines in Ghana. Production is expected to increase to 281,000 ounces annually by 2017, a 60% rise from 2016 levels, while cash operating costs are forecast to decrease to $695 per ounce. This will be achieved through commencing production at the high grade Wassa Underground mine in early 2017 and the Prestea Underground mine in mid-2017. Capital expenditures are increasing to fund the underground development projects, which will transform Golden Star into a higher grade, lower cost producer.
Golden Star is a gold mining company with operations in Ghana. It is transforming to focus on lower cost, non-refractory mining. Its Wassa Underground and Prestea projects are expected to deliver low cost production starting in 2016, with combined cash costs below $700/oz. The projects have high internal rates of return and will leverage existing infrastructure. Golden Star aims to further reduce costs at its current operations and has potential for new discoveries to extend mine lives.
Golden Star Resources is focused on unlocking value at its existing mines in Ghana. At Wassa, the company is accessing higher grade portions of the ore body from an underground mine to supplement production from the open pit. First ore from Wassa Underground is expected in mid-2016, with commercial production in early 2017. At Prestea, open pits are currently producing while rehabilitation of the underground mine is underway to establish additional production. Prestea Underground is expected to begin production in mid-2017. The company aims to become a stable gold producer through these projects and an increased focus on operational efficiencies.
This document provides an overview of Golden Star Resources, including:
- New leadership and corporate structure implemented since 2013 to focus on existing asset base.
- Goals include becoming a stable gold producer by eliminating high-cost refractory production and converting reserves to non-refractory.
- Operations located on prolific Ashanti Gold Belt in Ghana.
- Second quarter 2016 production of 42,461 ounces was in line with expectations, with production impacted by a scheduled plant shutdown at Wassa.
Microsoft power point 2014 november investor presentationGoldenStarResources
Golden Star is transforming into a lower cost gold producer by closing its higher cost refractory operation in late 2015 and developing the Wassa underground mine. The Wassa underground PEA delivered strong results, indicating it can reduce Wassa's costs per ounce dramatically and generate average annual production of 70koz over 4.5 years at $370/oz after $40 million investment. Golden Star's expenditure of $80 million on developing Wassa and Prestea is expected to unlock significant value for shareholders by reducing the group's life of mine costs below $700/oz from 2016 onward.
Golden Star reported its Q1 2014 financial results. Gold production was 65,812 ounces, in line with expectations. Cash operating costs per ounce increased to $1,206 due to transitioning to a new pit at Wassa and lower grades and recoveries at Bogoso. Cost of sales excluding depreciation decreased to $84.3 million due to lower mining contractor expenses. Golden Star maintained its 2014 production guidance of 295,000-320,000 ounces and cash cost guidance of $950-1,000 per ounce.
Golden Star achieved its 2016 production and cost guidance across its operations. Production totaled 194,054 ounces for the year, within the guidance range. Cash operating costs per ounce were $872, in the middle of the guidance range. Capital expenditures totaled $84.4 million for the year, a 48% increase over 2015, to fund development projects including Wassa and Prestea Underground mines. Commercial production was achieved at Wassa Underground on January 1, 2017, as planned.
Golden Star plans to expand production and reduce costs at its projects in Ghana. It aims to transform into a high grade, low cost gold producer by ramping up production from its Wassa Underground and Prestea Underground projects. Wassa Underground is expected to increase production and lower costs in 2017, while Prestea Underground is targeting commercial production in mid-2017. Golden Star forecasts total production to increase 31-44% in 2017 compared to 2016, with cash operating costs expected to decrease as higher grade underground ore becomes available.
- Golden Star operates two producing gold mines in Ghana - Wassa and Bogoso - with three processing plants and total annual capacity of 7 million tonnes.
- In 2013, Golden Star produced 331,000 ounces of gold at a cash cost of $1,049 per ounce, achieving its production and cost guidance.
- For 2014, Golden Star guidance is 295,000 to 320,000 ounces of gold at a cash cost of $950 to $1,000 per ounce and all-in sustaining costs of $1,150 to $1,200 per ounce.
Expanding Production and Reducing Costs at Golden Star's projects. Golden Star plans to expand production and reduce costs by developing two underground mines, Wassa Underground and Prestea Underground. This is expected to transform Golden Star's production and cost profiles, with production forecast to increase 60% between 2016 and 2019 while cash operating costs and AISC decline. Golden Star is on track to achieve its 2016 guidance and the underground development projects are advancing as planned, with infrastructure in place at Wassa Underground and stoping commenced in the third quarter.
Golden Star Resources Ltd. is a gold mining company focused on its two underground mining operations in Ghana - Wassa Underground and Prestea Underground. The presentation provides an operational and financial overview of Golden Star, including 2018 production guidance of 230,000-255,000 ounces of gold at an AISC of $850-950 per ounce. It highlights recent drilling results from Wassa Underground that indicate the deposit may be larger than previously estimated. The presentation also outlines Golden Star's $6.6 million exploration budget and plans to test for resource expansions and new underground targets near its existing operations.
- Aurico Gold reported financial results for Q3 2014 with revenue of $73.5 million, a 36% increase from Q3 2013, due to higher gold production and sales.
- Gold production was 57,037 ounces, a 48% increase from the prior year, driven by the ramp up of operations at the Young-Davidson mine.
- Cash costs per ounce decreased 17% at Young-Davidson from the previous quarter and the mine is expected to generate positive cash flow by the end of 2014.
AuRico Gold reported financial results for Q1 2015 with the following highlights:
- Solid production of 54,027 ounces at total cash costs of $696/ounce.
- Young-Davidson and El Chanate mines performed well with production on track.
- Underground development at Young-Davidson advanced as planned with productivity and costs improving.
- The company announced a merger with Alamos Gold to create a leading intermediate gold producer.
Golden Star provides guidance for 2018, focusing on generating cash flow. Production is expected to be between 230,000-255,000 ounces at an AISC of $850-950 per ounce. Capital expenditures are budgeted at $36.5 million. Operations will focus on the high margin underground mines at Wassa and Prestea. Wassa Underground is expected to continue ramping up production in 2018. Commercial production has been achieved at Prestea Underground and step-out drilling indicates potential to increase resources.
Golden Star reported Q1 2018 gold production of 57,616 ounces, with production from Wassa Underground exceeding expectations at 35,506 ounces. Wassa Underground grade was 4.54 g/t Au, a 12% increase from Q4 2017. Golden Star is on track to achieve 2018 consolidated guidance of 230,000-255,000 ounces. Recent drilling at Wassa Underground doubled the inferred mineral resource to 5.2 million ounces and extended mineralization down-plunge, indicating further upside potential.
Dgc 15 11_10 - nbf-tsx canadian miners conferenceDetourGold
Detour Gold Corporation is Canada's intermediate gold producer. In Q3 2015, Detour Lake Mine produced 106,125 ounces of gold at total cash costs of $942/ounce and all-in sustaining costs of $1,071/ounce. For full-year 2015, Detour Lake Mine expects gold production between 475,000-525,000 ounces at total cash costs between $780-$850/ounce and all-in sustaining costs between $1,050-$1,150/ounce. Detour Gold will focus its life of mine plan update on a lower risk operational profile with a mining rate reduction and higher plant throughput capacity while adding the nearby Block A deposit as a second feed source starting in 2018.
Golden Star provides guidance for 2018 of producing 230,000-255,000 ounces of gold at an all-in sustaining cost of $850-950 per ounce. Capital expenditures are budgeted at $36.5 million. Wassa Underground is expected to produce 137,000-142,000 ounces at a cash operating cost of $600-650 per ounce. Prestea Underground is targeting commercial production in February 2018 and is expected to produce 93,000-113,000 ounces at an all-in sustaining cost of $740-880 per ounce. Drilling continues to extend mineralization at both underground mines.
1. Detour Gold Corporation is a Canadian gold mining company and intermediate gold producer presenting at the Scotiabank Mining Conference in Toronto.
2. The presentation discusses Detour Gold's 2015 production guidance, opportunities to optimize operations at its Detour Lake Mine in Ontario, and notes that Detour Gold represents a unique investment opportunity as Canada's largest gold producer not controlled by a senior mining company.
3. Forward-looking statements are provided, subject to various risks and uncertainties that could cause actual results to differ materially. Non-IFRS financial measures are also referenced to provide additional information to investors.
This corporate presentation provides an overview of Detour Gold Corporation as an intermediate Canadian gold producer. Some key highlights from 2016 include producing 394,253 ounces of gold at an all-in sustaining cost of $960 per ounce sold and reducing debt levels by 28%. The presentation discusses preliminary guidance for 2017 which forecasts gold production of 540,000-590,000 ounces at an AISC of $1,050-1,150 per ounce sold. It also provides an update on exploration prospects including the prospective Zone 58N and advancing work on the West Detour project.
The document discusses plans to expand production and reduce costs at Prestea Underground. It provides a history of the mine, outlines upgrades that have been completed to rehabilitate mine infrastructure like the central shaft and winder, and procurement of mining equipment. It discusses the development sequence and Alimak mining method. Future plans are to extend mining of the West Reef zone, identify new targets in the Main Reef, and investigate underground targets at Bondaye and Tuapim.
This document discusses Golden Star Resources Ltd., a gold mining company operating in Ghana. It provides an overview of the company's leadership changes since 2013 which have brought in a new board and management with operational, development and finance expertise. It outlines the strategic shift to focus on the company's existing asset base by becoming a stable, predictable non-refractory gold producer and unlocking additional value. It also provides brief highlights on the company's Q2 2016 operational results, including gold production numbers from its Wassa and Prestea mines in Ghana.
Golden Star Resources released its Q2 2014 financial results. Some key points:
- Revenue and production decreased from Q1 due to fewer ounces sold. Costs also decreased.
- Cash operating costs per ounce remained consistent with Q1. The company is focused on reducing costs further.
- Guidance for 2014 was revised down due to the slower-than-expected start to the year. Production is now expected to be 260,000-280,000 ounces.
Golden Star is expanding production and reducing costs at its Wassa and Prestea gold mines in Ghana. Production is expected to increase to 281,000 ounces annually by 2017, a 60% rise from 2016 levels, while cash operating costs are forecast to decrease to $695 per ounce. This will be achieved through commencing production at the high grade Wassa Underground mine in early 2017 and the Prestea Underground mine in mid-2017. Capital expenditures are increasing to fund the underground development projects, which are expected to significantly increase production and reduce operating costs going forward.
Golden Star Resources is focused on unlocking value at its existing mines in Ghana. At Wassa, the company is accessing higher grade portions of the ore body from an underground mine to supplement production from the open pit. First ore from Wassa Underground is expected in mid-2016, with commercial production in early 2017. At Prestea, open pits are currently producing while rehabilitation of the underground mine is underway to establish additional production. Prestea Underground is expected to begin production in mid-2017. The company aims to become a stable gold producer through these projects and an increased focus on operational efficiencies.
Golden Star reported its Q3 2015 financial results. Key highlights included suspending high-cost refractory operations, commencing mining development at Prestea Underground and Wassa Underground, and achieving $75 million of $150 million in funding which improved liquidity and allowed retirement of debt. Cost reduction efforts such as optimizing mining and processing operations led to decreases in mine operating expenses and cash operating costs compared to previous quarters.
Golden Star Resources is a gold mining company operating mines in Ghana. In Q1 2014, production was 65,812 ounces in line with expectations. Costs are decreasing with lower mining contractor expenses. The company is focused on growing production from lower cost, non-refractory ore sources. This includes pursuing underground mining at the Wassa mine, which could increase production and grades while lowering costs per ounce. Drilling continues to show resource growth potential at Wassa.
Golden Star is expanding production and reducing costs at its Wassa and Prestea gold mines in Ghana. Wassa underground production has commenced, which is expected to increase annual production to approximately 281,000 ounces per year and lower cash operating costs to $695 per ounce by 2017. Prestea underground is also in development, with commercial production expected by mid-2017, which will further boost production and reduce costs. Exploration continues to show potential to increase reserves at both mines through additional drilling.
- Golden Star Resources Ltd. is an established gold mining company operating in Ghana with existing infrastructure providing operational leverage for its brownfield development projects which are transforming its production profile.
- The company has successfully financed its development projects at a reduced cost of capital and is on track to deliver ounces at a cash operating cost of $750 per ounce by the end of 2016.
- Golden Star has an experienced management team and board with extensive experience in Ghana and international mining.
Golden Star Resources Ltd. aims to transform into a high-grade, low-cost gold producer by expanding production and reducing costs at its projects in Ghana. It plans to achieve this through increasing production from its Wassa Underground and Prestea Underground mines, which are expected to improve the company's production profile, costs, and cash flows. Golden Star also sees exploration upside from increasing reserves and resources at its projects to extend mine lives. The company believes this strategy could help increase its share price over time as it transforms into a lower-cost, African-focused mid-tier gold producer.
- The document discusses Golden Star's plans to expand production and reduce costs at its projects in Ghana through underground mining techniques.
- It highlights the exploration upside potential to increase mine lives at existing operations and the experience of management in project delivery.
- Key milestones in the company's transformation include commercial production from the Wassa Underground expected in mid-2017 and from the Prestea Underground also expected in mid-2017.
Golden Star is expanding production and reducing costs at its Wassa and Prestea mines in Ghana. Production is expected to increase to an average of 281,000 ounces annually from 2017 onwards. Cash operating costs are forecast to decrease as higher grade ore is accessed at Wassa Underground and Prestea Underground ramps up. Exploration drilling will target expanding reserves and mine lives at both operations.
Golden Star plans to expand production and reduce costs by ramping up its underground mines at Wassa and Prestea. This will transform the company into a higher grade, lower cost gold producer. Golden Star provided production and cost guidance for 2017, forecasting a 31-44% increase in gold production compared to 2016. Exploration drilling will focus on increasing reserves to extend the mine lives at Wassa and Prestea.
This document provides an overview of Detour Gold Corporation as an intermediate gold producer in Canada. It begins with standard forward-looking statements and disclaimers. It then notes that Detour Gold operates the Detour Lake mine in Canada, which provides exposure to the Canadian dollar. As the largest gold mine in Canada not controlled by a senior gold producer, Detour Gold presents a unique investment opportunity as a growing intermediate producer. The document highlights Detour Gold's 2015 production guidance which positions it as the #2 gold producer and #1 in reserves among Canadian producers.
This document provides an overview and investment opportunity for Detour Gold Corporation, a Canadian gold mining company. It begins with standard forward-looking statements and disclaimers. It then presents Detour Gold as having a unique investment opportunity as Canada's largest gold producer not controlled by a senior mining company, with its large-scale, long-life Detour Lake Mine located in a mining-friendly jurisdiction. The document highlights Detour Gold's growing production and cash flow profile, as well as opportunities to further optimize operations.
Golden Star is expanding production and reducing costs at its projects in Ghana. The company is transforming into a high grade, low cost gold producer through its Wassa Underground and Prestea Underground projects. In the second quarter of 2017, Golden Star achieved its fifth consecutive quarter of production growth, delivering 64,176 ounces of gold from multiple ore sources. Operating costs continue to decline as the company transitions away from refractory ore processing.
This corporate presentation provides an overview of Detour Gold Corporation as an intermediate Canadian gold producer. Key highlights from 2016 include gold production of 394,253 ounces at an all-in sustaining cost of $960 per ounce sold and earnings from mine operations of $90 million. The presentation discusses Q3 2016 operating results and costs, preliminary 2017 guidance, the Campbell Pit plan for 2017, a focus on advancing the prospective Zone 58N, and safety performance.
- Detour Gold is a Canadian gold mining company and intermediate gold producer.
- In 2016, Detour Gold expects to produce between 540,000-590,000 ounces of gold at total cash costs between $675-750 per ounce sold and all-in sustaining costs between $840-940 per ounce sold.
- In Q1 2016, Detour Gold produced 127,136 ounces of gold and sold 137,608 ounces at total cash costs of $637 per ounce sold and all-in sustaining costs of $824 per ounce sold.
Similar to Golden star investor presentation - sept 2015 (10)
Golden Star Resources provides a summary of its Q1 2018 production results and plans for the rest of 2018. Key highlights include:
- Q1 2018 gold production of 57,616oz, with Wassa complex contributing 35,506oz and Prestea complex 22,110oz.
- Stronger than expected production from Wassa Underground of 12% higher grade than Q4 2017.
- Costs are expected to reduce through 2018 as underground production increases.
- $6.6M exploration budget aims to expand resources at Wassa Underground and Prestea Underground and test 5 new targets.
- Operational improvements expected to strengthen Prestea Underground performance in Q2 2018.
Golden Star reported Q1 2018 gold production of 57,616 ounces, with stronger than expected production from its Wassa Underground mine. Costs are expected to reduce over the course of 2018 as underground production increases. Golden Star's 2018 exploration budget is $6.6 million, focusing on expanding resources at Wassa Underground and Prestea Underground, as well as investigating five new underground targets with potential to increase production and extend mine lives.
Golden Star reported Q1 2018 production results, with total gold production of 57,616 ounces. Production at the Wassa complex was 35,506 ounces, while Prestea complex production was 22,110 ounces. Wassa Underground mine performance exceeded expectations, with a 12% increase in grade and average mining rate of 2,400 tonnes per day. Costs are expected to reduce over the course of 2018 as underground production increases, though Q1 costs per ounce were higher than anticipated due to challenges at Prestea Underground. Golden Star reiterated its full-year 2018 production and cost guidance.
Golden Star achieved its 2017 gold production guidance of 267,565 ounces. Production increased 38% compared to 2016 due to higher output from its Wassa and Prestea mines in Ghana. Cash operating costs and all-in sustaining costs per ounce for 2017 were below guidance and decreased from 2016, driven by a focus on underground mining at higher grades. Golden Star is forecasting further cost reductions in 2018 as production shifts entirely to underground ore at Wassa and Prestea, with guidance of 230,000-255,000 ounces at costs of $850-950 per ounce.
1) Golden Star Resources provides a snapshot of its operations in Q3 2017, including increased gold production and lower costs. Production guidance for 2017 remains on track.
2) Drilling results from Wassa Underground extended the B Shoot zone to the north and south, indicating potential to increase short and long-term production.
3) Prestea Underground achieved a milestone with its first stoping ore blasted in September 2017 as the high grade underground mine ramps up.
Golden Star's Wassa Gold Mine in Ghana includes an open pit mine and underground mine. In Q3 2017, production from the Wassa Underground mine increased to 15,877 ounces, accounting for 50% of Wassa's total gold production. Golden Star plans to transition Wassa to an underground-only operation in 2018 in order to focus on higher grade ounces from underground at a target rate of 2,700 to 3,000 tonnes per day. Exploration and infrastructure expansion at the Wassa Underground mine has the potential to further increase production beyond 2020.
Golden Star conducted a site visit to its Wassa Gold Mine in Ghana in November 2017. Wassa currently mines and processes ore from both an open pit and underground mine. Production is ramping up at the Wassa Underground mine, which is expected to account for all mining at Wassa in 2018 in order to focus on higher grade underground ounces. Exploration and infrastructure expansion opportunities exist to further increase underground production over the next several years.
Golden Star Resources Ltd. provides guidance for 2017 including an AISC of $970-1,070 per ounce and production of 255,000-280,000 ounces. Key assets include the Wassa Underground and Prestea Underground mines in Ghana, containing total mineral reserves of 1.9 million ounces and resources of 4.4 million ounces. The company had $25.9 million in cash as of June 30, 2017 and a $69.3 million capital expenditure budget for 2017. Golden Star has an experienced management team led by President and CEO Sam Coetzer to oversee its Ghanaian operations.
Bienestar Financiero al servicio de su jubilación anticipada
Pago de su 🏡
Estudio de sus hijos
Directamente a tu cuenta bancaria
Con Tesorería Auditoria Jurídica comercial
Administración de carteras
Apalancamiento Financiero
Desarrollo de tu marca personal
Acceso a Desarrollo de varias industrias
Cuentas bancarias
Estructuras Físicas en USA y en América Central
Avalado por Bolcomer
Puesto de Bolsa Comercial
Turismo
Y mucho más
Link de registro
https://business.myinfinity.global/maurod8/
https://therusnetwork.com/
Contacto:
https://goo.su/pzm1fja
1. I N V E S T O R P R E S E N T A T I O N
0 9 . 1 5
Investor Presentation August 20151
2. DISCLAIMER AND OTHER MATTERS
SAFE HARBOR: Some statements contained in this presentation are forward-looking statements or forward-looking information (collectively, “forward-looking
statements”) within the meaning of the Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. Investors are cautioned that forward-
looking statements are inherently uncertain and involve risks and uncertainties that could cause actual results to differ materially. Such statements include comments
regarding: average cash operating costs per ounce over the life of mine and timing for achieving such costs; capital savings identified in the Prestea Underground studies;
reductions in mine operating expenses in the second half of 2015; the Company being fully financed for development at a reduced cost of capital; the rise in total costs,
and improved efficiencies that reduce unit and per ounce costs; Wassa grade forecasts and cash operating costs over the remainder 2015; reductions in accounts payable
over the next 24 months; the improvement in the Company’s cost profile once the underground mines are in production; the benefits of the stream and loan transaction;
Golden Star transforming into a non-refractory miner with a declining cash cost profile; the timing for the development of and first production and commercial production
from the underground mines; plans for deeper drilling at Prestea Underground to increase daily tonnage and expand the mineral resource; and the timing of a feasibility
study at Prestea. Factors that could cause actual results to differ materially include timing of and unexpected events at the Bogoso oxide and sulfide processing plants
and/or at the Wassa processing plant; variations in ore grade, tonnes mined, crushed or milled; variations in relative amounts of refractory, non-refractory and transition
ores; delay or failure to receive board or government approvals and permits; construction delays; the availability and cost of electrical power; timing and availability of
external financing on acceptable terms; technical, permitting, mining or processing issues, including difficulties in establishing the infrastructure for Wassa Underground,
inconsistent power supplies, plant and/or equipment failures and an inability to obtain supplies and materials on reasonable terms (including pricing) or at all; changes in
U.S. and Canadian securities markets; and fluctuations in gold price and input costs and general economic conditions. There can be no assurance that future developments
affecting the Company will be those anticipated by management. Please refer to the discussion of these and other factors in our Annual Information Form for the year
ended December 31, 2014 filed on SEDAR at www.sedar.com. The forecasts contained in this presentation constitute management's current estimates, as of the date of
this presentation, with respect to the matters covered thereby. We expect that these estimates will change as new information is received and that actual results will vary
from these estimates, possibly by material amounts. While we may elect to update these estimates at any time, we do not undertake to update any estimate at any
particular time or in response to any particular event. Investors and others should not assume that any forecasts in this presentation represent management's estimate as
of any date other than the date of this presentation.
NON-GAAP FINANCIAL MEASURES: In this presentation, we use the terms "cash operating cost per ounce" or “CoC per ounce” and "all-in sustaining cost per ounce“ or
“AISC per ounce”. These terms should be considered as Non-GAAP Financial Measures as defined in applicable Canadian and United States securities laws and should not
be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP. "Cash operating cost per ounce" for a period is equal to the
cost of sales excluding depreciation and amortization for the period less royalties and production taxes, minus the cash component of metals inventory net realizable value
adjustments and severance charges divided by the number of ounces of gold sold during the period. "All-in sustaining costs per ounce" commences with cash operating
costs and then adds sustaining capital expenditures, corporate general and administrative costs, mine site exploratory drilling and greenfield evaluation costs and
environmental rehabilitation costs, divided by the number of ounces of gold sold during the period. This measure seeks to represent the total costs of producing gold from
operations. These measures are not representative of all cash expenditures as they do not include income tax payments or interest costs. These measures are not
necessarily indicative of operating profit or cash flow from operations as would be determined under International Financial Reporting Standards. Changes in numerous
factors including, but not limited to, mining rates, milling rates, gold grade, gold recovery, and the costs of labor, consumables and mine site general and administrative
activities can cause these measures to increase or decrease. We believe that these measures are the same or similar to the measures of other gold mining companies, but
may not be comparable to similarly titled measures in every instance. In order to indicate to stakeholders the Company's earnings excluding the non-cash (gain)/loss on
the fair value of debentures, non-cash impairment charges and severance charges, the Company calculates adjusted net loss attributable to Golden Star shareholders" and
"adjusted net loss per share attributable to Golden Star shareholders" to supplement the condensed interim consolidated financial statements.
INFORMATION: The information contained in this presentation has been obtained by Golden Star from its own records and from other sources deemed reliable, however
no representation or warranty is made as to its accuracy or completeness. The technical information relating to Golden Star's material properties disclosed herein is based
upon technical reports prepared and filed pursuant to National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and other publicly available
information regarding the Company, including the following: (i) “NI 43-101 Technical Report on a Feasibility Study of the Wassa Open Pit Mine and Underground Project in
Ghana” effective December 31, 2014; (ii) “NI 43-101 Technical Report on Resources and Reserves, Golden Star Resources Ltd., Bogoso Prestea Gold Mine, Ghana”
effective December 31, 2013, and (iii) “NI 43-101 Technical Report on Preliminary Economic Assessment of Shrinkage Mining of the West Reef Resource, Prestea
Underground Mine, Ghana” effective December 18, 2014. Additional information is included in Golden Star's Annual Information Form for the year ended December 31,
2014 which is filed on SEDAR. Mineral Reserves were prepared under the supervision of Dr. Martin Raffield, Senior Vice President Technical Services for the Company. Dr.
Raffield is a "Qualified Person" as defined by NI 43-101. The Qualified Person reviewing and validating the estimation of the Mineral Resources is S. Mitchel Wasel, Golden
Star Resources Vice President of Exploration.
CURRENCY: All monetary amounts refer to United States dollars unless otherwise indicated.
2 Investor Presentation September 2015
3. INVESTING IN PROFITABLE GROWTH
— Established producing gold miner with extensive experience in
Ghana
— Existing infrastructure provides significant operational leverage
— Brownfield low-risk development projects are transforming group
production profile
— Successfully financed for development at reduced cost of capital
— On track to deliver ounces at cash operating cost of $750 per
ounce over LOM by 2016
3 Investor Presentation September 2015
4. MANAGEMENT AND BOARD
Sam Coetzer, President and CEO
Appointed CEO in 2013 after joining in
2011 as COO. Sam is a mining engineer
and member of the World Gold Council.
He has 27 years of international
experience with Kinross, Xstrata, Xstrata
Coal and Placer Dome.
André van Niekerk, EVP and CFO
André joined in 2006 and spent 5 years in
Ghana as head of finance and business
operations, whereafter he was appointed
Group Controller. He was appointed CFO in
2014. Prior to joining Golden Star, André
spent 6 years with KPMG
Daniel Owiredu, EVP and COO
Daniel was appointed COO in 2013, after
joining Golden Star in 2006 as VP, Ghana
Operations. He has 20 years of experience
in West African mining. Most recently, he
was Deputy COO for AngloGold where he
managed construction and operation of the
Bibiani, Siguiri and Obuasi mines.
Tim Baker, Chairman
Appointed Chairman in January 2013. Tim
recently served as the COO of Kinross. He
is a geologist with over 30 years of global
project development and operational
experience in Chile, Tanzania, US,
Venezuela, Kenya and Liberia.
Tony Jensen, Director
Tony has 25 years of mining experience and
is CEO of Royal Gold. Prior to joining Royal
Gold, he was the Mine GM of Cortez and
spent 18 years with Placer Dome. Tony has
extensive experience in the US and Chile
where he held several senior management
positions.
Anu Dhir, Director
Anu is the MD of Miniqs, a private group
that develops resource projects. She is a
Director of Atlatsa Resources, Frontier
Rare Earths and Energulf Resources. Prior
to founding Miniqs, Anu was VP Corporate
Development and Company Secretary at
Katanga.
Craig Nelson, Director
Craig is a geologist with 30 years of mining
experience. He was Founder, CEO of Avanti
Mining. Formerly, Craig was EVP Exploration
of Gold Fields; Founder, CEO and Chairman
of the Metallica Resources and held
numerous strategic positions at Lac
Minerals.
Rob Doyle, Director
Rob has 30 years of mining experience.
Recently, he was Founder and CEO of
Medoro Resources. Prior to this, he served
as CFO of Pacific Stratus Energy, Coalcorp
Mining and Bolivar Gold Corp. Currently, Rob
serves as a Director of Mandalay Resources
and Detour Gold
Bill Yeates, Director
Bill is one of the founding partners of Hein
& Assoc where he served on the ExCo and
was their National Director of Auditing and
Accounting. Bill has 40 years of auditing
experience with public companies in
extractive industries.
Angela Parr, VP IR & Corp. Affairs
Angela joined in September 2013. She has
over ten years of experience in the natural
resources sector, across sub-Saharan
Africa, most recently in the West African
gold mining sector.
5. (1) Includes US$52.8M of 5% Convertible Debentures at fair value
(2) As accessed on Sept 15, 2015 from NYSE Connect
(3) Before pay off of Ecobank I loan on Aug 3, 2015
Major Shareholders2
Liao Family 16%
Sentry Select Capital Corp. 11.7%
Earth Resources 2.7%
Renaissance Technologies 2.1%
Millennium Management LLC 1.1%
Share Price (Last close) (US$) (as of Sept 14, 2015) 19cents
Shares Outstanding 259.4M
Market Capitalization (US$) 49M
Cash and Equivalents (US$) (June 30, 2015) 21M
Total Debt (US$)1,3 (June 30, 2015) 127M
Enterprise Value (US$) 155M
Daily Average Volume
TSX: 70K
NYSE MKT: 823K
CAPITAL MARKET STATISTICS
5
— Listed on NYSE MKT, TSX and Ghana Stock Exchange
Investor Presentation September 2015
7. DELIVERING ON STRATEGY
7 Investor Presentation September 2015
— Favour operating margin over total ounces produced
— 150,000 oz of Bogoso production replaced with 80,000 high margin Prestea oz’s
— 1.2M oz high grade free milling ounces added to Mineral Resources at Wassa
— High cost refractory ounces removed from Mineral Reserves
— Leverage off existing infrastructure
— IRR on projects in excess of 70%* achieved through operational leverage
— Capex per ounce for both projects in lowest quartile for West Africa
— Reduce costs at operations through behavioural change and productivity
enhancements
— Mine operating expenses continue downward trend
— Disciplined focus on return on capital
— Investment in development drilling extended Wassa’s LOM and increased grade
— Refined development plan for Prestea delivers better IRR
— Two year process secured financing at lowest cost of capital
*Assumption of a gold price of $1,200 per ounce used in these calculations. For further critical assumptions used in these assessments, please refer to the reports titled “NI 43-101 Technical
Report on a Preliminary Economic Assessment of the Wassa Open Pit Mine and Underground Project in Ghana” and “NI 43-101 Technical Report on Preliminary Economic Assessment of Shrinkage
Mining of the West Reef Resource, Prestea Underground Mine, Ghana” both of which are filed on SEDAR.
8. — Acquired in 2002, in operation as open
pit mine since 2005
— Historically mined smaller oxide pits,
consolidated into large pit in 2013
— Free milling ore with high recoveries
— Large mine license area with 6 km of
lease along strike
— 2.7mtpa CIL processing plant
— 500m from Wassa Main pit
— Running at high availability
— Recently enhanced to increase
throughput & recoveries on fresh rock
— 2015 production of 110-115,000 oz at
cash operating cost of $860-990/oz
forecast
WASSA ESTABLISHED AS LOW COST OPEN PIT MINE
Investor Presentation September 20158
9. WASSA FEASIBILITY STUDY RESULTS MARCH 2015
INVESTMENT
MINING
Long hole stoping below
existing open pit
PROCESSING
Minor upgrades to
existing Wassa
processing plant
SUPPORT
INFRASTRUCTURE
Fully in place
CAPEX $39M
FIRST GOLD H1 2016
*Assumption of a gold price of $1,200 per ounce used in these calculations. For further critical assumptions used in these assessments, please refer to the reports titled “NI 43-101 Technical
Report on a Preliminary Economic Assessment of the Wassa Open Pit Mine and Underground Project in Ghana” and “NI 43-101 Technical Report on Preliminary Economic Assessment of Shrinkage
Mining of the West Reef Resource, Prestea Underground Mine, Ghana” both of which are filed on SEDAR.
RETURN
COC PER OZ $780
AISC PER OZ $938
IRR 83%
NPV5% $176M
PAY BACK PERIOD 3.25 years
9 Investor Presentation September 2015
10. — Mining equipment arrived on site
— First blast of decline in July 2015,
106m of decline development to date
— Electrical infrastructure, including
4MVA generator capacity, installed
— Construction of support infrastructure
on target
— $3.4M spent in Q2, further $10.8M
forecast for H2 2015
— Expectations for early production
from first stopes increasing
— First production expected early
2016
WASSA UNDERGROUND PROGRESSING TO SCHEDULE
10
11. FURTHER EXPLORATION UPSIDE AT WASSA
11 Investor Presentation September 2015
Nov’14 EOM Pit
BSDD342
10.7m @ 30.1g/t
BSDD348
16.9m @ 4.7g/t
BSDD335
6.3m @ 8.5g/t
BSDD333
9.7m @ 6.5g/t
BSDD347
54.1m @
4.2g/t
$1,200 Pit Design
BSDD331
17.3m @
3.9g/t
BSDD330
13.9m @
15.6g/t
BSDD328
8.6m @ 3.2g/t
BSDD344
78.9m @ 5.3g/t
BSDD347
7.5m @ 15.7g/t
BSDD290BD1
39.4m @ 9.0g/t
BSDD033
7.6m @ 14.7g/t
BSDD181
22.1m @ 29.8g/t
— Anomalies indicate mineralized trend continues 6 km south of last step out fence - deeper
drilling will be conducted to the south
— Multiple high grade folds at surface that remain untested at depth down plunge
— Possibility of large parallel shoot emerging from recent drilling
12. — Underground mine since late 1900’s,
9M oz of production, acquired 2002
and placed on care and maintenance
— 19 g/t Au orebody with excellent
potential for high grade extensions
outside known resource
— Two surface and two internal shafts
operational, levels developed to 600m
— Drilling identified and defined
West Reef mineralized zone, subject
of ongoing Feasibility Study
— Undeveloped surface deposits at
Prestea South, 2 km from
underground mine with Mineral
Reserve of 122k oz at 2.6 g/t
— Dedicated haul road 15 kms to Bogoso
processing plants
12
PRESTEA MINES HAS POTENTIAL FOR NUMEROUS ORE SOURCES
Investor Presentation September 2015
13. PRESTEA UNDERGROUND PEA RESULTS
INVESTMENT
MINING Shrinkage mining of West Reef
on existing levels 17 and 24
PROCESSING
Modifications to be made to
front end of existing
Bogoso processing plant
SUPPORT
INFRASTRUCTURE
15km haul road
improvements required
CAPEX Initial capex $40M
to get into production
FIRST GOLD First gold expected
late 2016
*Assumption of a gold price of $1,200 per ounce used in these calculations. For further critical assumptions used in these assessments, please refer to the reports titled “NI 43-101 Technical
Report on Preliminary Economic Assessment of Shrinkage Mining of the West Reef Resource, Prestea Underground Mine, Ghana” which is filed on SEDAR.
Investor Presentation September 2015
RETURN
COC PER OZ $370
AISC PER OZ $518
IRR 72%*
NPV5% $121M*
PAY BACK PERIOD 2.5 years*
13
14. PRESTEA RETURNS BEING ENHANCED
— Permits for mining at surface to south of
Prestea secured
— Mining in oxide pits has commenced,
processing and first gold has been poured
— Free digging and free milling ore with high
recoveries
— Underground Feasibility Study progressed
— Potential for significant Mineral Resource
development
— Opportunities for capital efficiency identified
— Rehabilitation of main underground mining
levels continues, $6.6M spent year to date
— Development plans accelerated post
fundraising – capex for H2 2015 revised up
$20M
15. PRESTEA RESOURCE DEVELOPMENT PROMISING
— Exploration strategy aimed at increasing daily tonnage - resource conversion up/down
plunge and along extension of the West Reef orebody
— Significant Main Reef upside at depth below the current workings in West Reef
— Exploration potential along 9 km of strike length and to a depth of 1.4 km on three
mineralized vein systems
Investor Presentation September 201515
West Reef-
Crosscut
Target
Bondaye
Deeps Drill
hole
Beta Pit
West Reef
Stoping
16. LARGEST LAND TRACT WITH SUBSTANTIAL RESOURCE POTENTIAL
Investor Presentation September 201516
— Wassa Underground Reserve based on Indicated Resources in the
B Shoot, additional 1M oz of Inferred Resources defined to the
south and ore body is open down plunge
— Parallel to B shoot, the F Shoot is emerging as new zone
accessible from current planned Wassa Underground
development
— Prestea Underground West Reef target remains open down dip,
recent resource model based on additional drilling expected to
expand this Mineral Resource and Reserver
— Prestea Underground Main Reef remains relatively untested
below 30 level and will be drill tested once ventilation enhanced
— Drilling ongoing on targets adjacent to Prestea South,
expectations are this will extend the mine life of oxide mining
beyond 2016
17. MINE PRODUCTION AND COST PROFILES
17
* Development of projects dependent on positive study results
Investor Presentation September 2015
$400
$450
$500
$550
$600
$650
$700
$750
$800
$850
-
50,000
100,000
150,000
200,000
250,000
300,000
350,000
2016 2017 2018 2019 2020
$/oz
Ounces
Wassa Prestea Cash Operating Costs per Oz.
— Golden Star is transforming to a non-refractory miner with a declining cash
cost profile
— Largest land package on Ashanti Goldbelt provides potential for new ore
sources to add near and long term production and further reduce costs
18. TRANSFORMATIONAL GOLD STREAM AND LOAN AGREEMENT CLOSED
— Long term financing partnership
entered into with Royal Gold
— Aggregate proceeds from Royal
Gold and subsidiary of $150M
— Gold stream of $130M:
—Upfront payment of $40M received,
further $90M in payments to be
received by end Q3 2016
—207,500 oz delivered at 20% of spot
price
—3% of production at 30% of spot in
perpetuity thereafter
— Four year $20M secured term loan
note received, interest rate linked
to gold price
18 Investor Presentation September 2015
RGLD
Stream
$130M
RGI Loan
$20M
Wassa
$39M
Ecobank
Debt
$38M
Sources of Funds Uses of Funds
Prestea
$40M
Working Cap and
General Purposes
$33M
19. — Mine operating expenses continue to reduce, further reduction
in H2 2015
— Lower than expected grade combined with reduced processing
capacity at Bogoso refractory operations impacted unit costs
— Wassa costs on track to meet FY 2015 guidance
— FY 2015 Group cash operating costs per ounce revised to
$955-1,050
COSTS AND EXPENSES TRACKING DOWNWARDS
19 Investor Presentation September 2015
Mine Operating Expenses ($ M)
$1,200
$1,326 $1,252
Costs per Ounce ($)
20. RESPONDING TO CHANGING MARKET DYNAMICS
1. Advancing transition into lower cost mining
—Fast tracking Prestea Underground development decision
—Rapid move to start mining in higher grade Prestea South
—Decision taken to suspend refractory mining earlier than initially
planned
2. Balance sheet stabilization and derisking
—Reduce high cost debt with repayment of $38M Ecobank I loan
—Reduced cost of capital with funding from Royal Gold
3. Planning for longer term market pressure
—Optimising Wassa Main pit for $1,000 gold price
—Targeting further 20% unit cost reductions in Wassa Open Pit mining
20 Investor Presentation September 2015
21. Commercial
production
levels
reached
underground
Construction
of exploration
decline
commences
First
stopes
reached
TIMELINE TO DELIVERY
21 Investor Presentation September 2015
* Development of projects dependent on positive study results
WASSA
PRESTEA*
Mining of
surface pits
commences
Q4’15
First
production
from
underground
First
production
from Prestea
South
Q3’15July 2015
Optimal
processing
methodology
for Prestea
Underground
identified
Q4’15
First
production
from
underground
stopes
Q4’16
July 2015 Q2’16 Q3’16
PEA on
underground
mining at
Wassa
complete
Establish
Wassa
Main pit
Updated
Mineral
Resource
estimate for
Wassa
Q3’14Q2’14
Revised PEA
for Prestea
Underground
Q3’14Q2’14
Feasibility
study
completed
22. Investment Case
Established gold mining company with
15 years of production history in Ghana
Successfully reduced overall operating
costs over last two years
Project pipeline to deliver low cost
ounces in the near future
Largest land package on the Ashanti
Gold belt
Low political risk in a stable African
mining jurisdiction
Significant exploration & development
upside
Offers investors leveraged, un-hedged
exposure to the gold price