The document is a utilization chart showing the planning utilization, operation utilization, and overall tester utilization for the Fusion FT system across various weeks. It shows the utilization percentages ranging from 0% to 100% over time. A second similar chart is shown for the Fusion WT system. Below this is a list of 4 actions being taken in 2004 to plan for improvements to the system, such as adding a check to gauge alignment and having a trial run to improve failures.
3. 2004 Actions Planning for System
1. Add one item in check list of PM, Use gauge to check & re-align docking.
(Done at WK412 WTFs.)
2. PECHF will have a trial on Fusion for PECHF high failures improvements.
(Ongoing)
3. OM6357 “Stuck-at ” problem caused by register during production.
(Ongoing)
4. SMS, Open “data_login” function for analysis SMS failure during SMS
calibration (Done WK412.)
5. SMS rev 02 & 03 ex-change because of higher failure rates
(Ongoing “exchange by fail)
Semiconductors, ATO-PSK, Promotion Candidate Overview