Project: 10FP17, ACME - Prototype Cryo Data Logger Development
Report Title: Cost, Budget, Earned Value ($), Quad Charts
    Report Date: 3/31/2012

                                     Narrative Summary and Highlights
         Schedule - Based on critical path analysis, this project is behind schedule by 3 weeks, declining slightly, and is predicted to finish 3 weeks                                                   Trend /
      behind schedule, and holding steady. Caution is advised given the following assessment of WBS 3.1.5.                                                                               Metric           % Comp        Variance
         Poor schedule performance on WBS 3.1.5, "Firmware Development" has put it on the critical path. All 5 weeks of float have been                 Schedule:        SPI(t):         0.95                               NA        Holding steady
      consumed. The team is struggling to implement a new RTOS and ethernet core. The team is bringing in an expert from the RTOS vendor to                 ES(t), AD(t) (wks):         19            22    33%             (3) wks   Declining slightly
      help address these issues and finish Firmware development. Lesson learned - dig deper for risks during the planning phase and mitigate                   BAC(t), EAC(t):    12/01/12      12/18/12                    (3) wks   Holding steady
      the risk with budget, reserve, and adequate/expert resources.                                                                                      BTC(t), ETC(t) (wks):         35.0          37.5   NA         NA
         Strong schedule performance on WBS 3.1.4, "Software Development" has removed it from the critical path. Performance will continue                 TSPI(t) [BAC, EAC]:         1.09          1.06   NA         NA
                                                                                                                                                        Cost:           CPI($):          0.95                          NA             Holding steady
      to be monitored in case it needs to be tracked back to the critical path.
                                                                                                                                                                  EV($), AC($): $ 548,331 $ 574,405         49%         ($26,074)     Improving slightly
         Cost - Cost performance reveals that the project is slightly over budget and improving slightly. Caution is advised given the struggles
                                                                                                                                                              BAC($), EAC($): $ 1,115,316 $ 1,144,148                   ($28,832)     Improving slightly
      mentioned above on WBS 3.1.5, which may have a ripple effect on overall cost performance. The entire project team has been advised to
                                                                                                                                                               BTC($), ETC($): $ 540,911 $ 569,742          NA         NA
      watch their budgets closely and to seek efficiencies to mitigate possible ripples.
                                                                                                                                                          TCPI($) [BAC, EAC]:         1.05          1.02    NA         NA


                                                                                            Schedule Summary                                                       Cost Summary ($)
                                                                       % Work                                                                   Cumulative to Date                                Last 4 Weeks
 Pg   Chart Title                                                       Comp         BAC(t)   EAC(t)                SPI(t)      BAC         EAC          EV             AC          CPI     EV          AC                                                 CPI
 1    Summary and Highlights                                             NA           NA       NA                    NA         NA          NA           NA             NA          NA      NA          NA                                                 NA
 1    Table of Contents                                                  NA           NA       NA                    NA         NA          NA           NA             NA          NA      NA          NA                                                 NA
 3    Labor Summary                                                      NA           NA       NA                    NA         NA          NA           NA             NA          NA      NA          NA                                                 NA
 4    Critical Path - Schedule Analysis                                  35%        12/01/12 12/18/12                  0.95 $ 321,790 $ 365,516 $ 112,693 $ 131,189                  0.86 $ 16,545 $ 24,598                                                 0.67
 5    Rollup - Project 10FP17                                            49%        12/08/12 11/30/12                  1.00 $ 1,115,316 $ 1,144,148 $ 548,331 $ 574,405              0.95 $ 97,956 $ 86,821                                                 1.13
 6     Rollup - WBS 1.0, PM, PC, and PE                                 40%         12/01/12 12/01/12                 1.00 $ 404,840 $ 429,440 $ 160,540 $ 172,268                   0.93 $ 27,920 $ 28,103                                                 0.99
 7        WBS: 1.1, Program Management                                    40%         12/01/12      12/01/12            1.00 $        139,200 $          163,172 $          55,200 $          66,543            0.83 $      9,600 $           9,178          1.05
 8        WBS: 1.2, Program Control                                       40%         12/01/12      12/01/12            1.00 $         18,850 $           20,393 $           7,475 $           8,173            0.91 $      1,300 $           1,219          1.07
 9        WBS: 1.3, Project Engineering                                   40%         12/01/12      12/01/12            1.00 $        246,790 $          245,875 $          97,865 $          97,552            1.00 $     17,020 $          17,706          0.96
10      Rollup - WBS 2.0, Material, Travel, and ODCs                     75%        12/08/12       08/27/12            1.48     $      89,300 $           88,394 $          66,983 $          71,756          0.93     $    5,390 $          4,323          1.25
 11       WBS: 2.1, Material                                              77%         12/08/12      05/03/12            2.53 $          84,500 $          82,945 $          65,100 $          69,323            0.94 $      4,700 $           4,323          1.09
 12       WBS: 2.2, Travel                                                39%         10/13/12      09/23/12            1.38 $           4,800 $           6,299 $           1,883 $           2,433            0.77 $        690 $             -
13      Rollup - WBS 3.0, NRE                                            52%        12/01/12 12/01/12                  1.00 $        621,176 $          631,418 $         320,808 $         330,381           0.97 $       64,646 $         54,395          1.19
14       Rollup - WBS 3.1, Design Engineering                            73%        06/23/12 06/23/12                  1.00 $        433,328 $          440,080 $         314,598 $         322,919           0.97 $       62,116 $         51,410          1.21
 15         WBS: 3.1.1, HW Development - CI#1                             90%         04/14/12      03/29/12            1.00    $      55,193     $       64,965     $      49,674     $      54,706            0.91   $    8,831     $       5,659          1.56
 16         WBS: 3.1.2, HW Development - CI#2                             72%         05/19/12      06/19/12            0.85    $      52,768     $       58,719     $      37,993     $      42,546            0.89   $    9,498     $       4,052          2.34
 17         WBS: 3.1.3, HW Development - CI#3                             75%         06/23/12      06/06/12            1.18    $      58,782     $       49,154     $      44,087     $      37,609            1.17   $   11,756     $       3,959          2.97
 18         WBS: 3.1.4, SW Development                                    75%         06/23/12      05/28/12            1.14    $     152,625     $      122,182     $     114,469     $      95,225            1.20   $   27,473     $      17,847          1.54
 19         WBS: 3.1.5, FW Development                                    60%         05/19/12      06/19/12            0.85    $     113,960     $      154,740     $      68,376     $      92,834            0.74   $    4,558     $      19,893          0.23
 20       Rollup - WBS 3.2, Prototype Production                         45%         05/26/12      05/26/12            1.00 $          13,800 $           15,821 $           6,210 $           7,461           0.83 $       2,530 $          2,985           0.85

© 2012 SCOBEN Data Solutions. All rights reserved.                                                                         Page 1 of 27                                                                                                                    4/4/2012
Schedule Summary                                                            Cost Summary ($)
                                                     % Work                                                               Cumulative to Date                                          Last 4 Weeks
 Pg Chart Title                                       Comp    BAC(t)     EAC(t)       SPI(t)           BAC          EAC            EV              AC             CPI        EV             AC       CPI
 21      WBS: 3.2.1, Production - CI#1                100%    03/17/12   03/17/12        1.13 $           4,600 $     5,144 $        4,600 $          5,144         0.89 $    1,380 $        1,178     1.17
 22      WBS: 3.2.2, Production - CI#2                 30%    04/21/12   04/21/12        1.00 $           4,600 $     4,807 $        1,380 $          1,571         0.88 $      920 $        1,060     0.87
 23      WBS: 3.2.3, Production - CI#3                 5%     05/26/12   05/26/12        1.00 $           4,600 $     5,116 $          230 $            746         0.31 $      230 $          746     0.31
 24     Rollup - WBS 3.3, System Integration          0%      08/18/12   08/18/12                 $     85,248 $     85,248 $          -       $        -                $        -    $      -
 25     Rollup - WBS 3.4, System Ver. and Qual.       0%      12/01/12   12/01/12                 $     88,800 $     88,800 $          -       $        -                $        -    $      -
 26      WBS: 3.4.1, System Verification              0%      09/22/12   09/22/12                 $      29,600 $    29,600 $          -       $        -                $        -    $       -
 27      WBS: 3.4.2, Environmental Qualification      0%      12/01/12   12/01/12                 $      59,200 $    59,200 $          -       $        -                $        -    $       -




© 2012 SCOBEN Data Solutions. All rights reserved.                                             Page 2 of 27                                                                                          4/4/2012
Labor Summary for 10FP17
          Report Date:   3/31/2012

 Sorted by Name                                                                     Sorted by WBS
                                                     Hrs for w/e Cumulative                                                   Hrs for w/e Cumulative
 Name                     Cost Acct       WBS        3/31/2012 to Date Hrs       WBS        Cost Acct      Name               3/31/2012 to Date Hrs
 Braun, Ryan              10FP17.3.1.2   3.1.2                        106      1.1          10FP17.1.1     Pujols, Albert             20       580
 Braun, Ryan              10FP17.3.1.3   3.1.3                         75      1.2          10FP17.1.2     Rollins, Jimmy              4       114
 Cabrera, Miguel          10FP17.3.1.3   3.1.3                        293      1.3          10FP17.1.3     Uggla, Dan                 40       854
 Ethier, Andre            10FP17.3.1.4   3.1.4               14       319      3.1.1        10FP17.3.1.1   Kershaw, Clayton           33       312
 Ethier, Andre            10FP17.3.1.5   3.1.5               27       418      3.1.1        10FP17.3.1.1   Kinsler, Ian                7        71
 Fielder, Prince          10FP17.3.2.1   3.2.1                        131      3.1.1        10FP17.3.1.1   Mauer, Joe                           27
 Fielder, Prince          10FP17.3.2.2   3.2.2                7        40      3.1.1        10FP17.3.1.1   Scherzer, Max                       170
 Fielder, Prince          10FP17.3.2.3   3.2.3                6        12      3.1.2        10FP17.3.1.2   Braun, Ryan                         106
 Kershaw, Clayton         10FP17.3.1.1   3.1.1               33       312      3.1.2        10FP17.3.1.2   Kershaw, Clayton                     19
 Kershaw, Clayton         10FP17.3.1.2   3.1.2                         19      3.1.2        10FP17.3.1.2   Kinsler, Ian                        295
 Kershaw, Clayton         10FP17.3.1.3   3.1.3                         12      3.1.3        10FP17.3.1.3   Braun, Ryan                          75
 Kinsler, Ian             10FP17.3.1.1   3.1.1                7        71      3.1.3        10FP17.3.1.3   Cabrera, Miguel                     293
 Kinsler, Ian             10FP17.3.1.2   3.1.2                        295      3.1.3        10FP17.3.1.3   Kershaw, Clayton                     12
 Lincecum, Tim            10FP17.3.2.3   3.2.3                           7     3.1.4        10FP17.3.1.4   Ethier, Andre              14       319
 Mauer, Joe               10FP17.3.1.1   3.1.1                         27      3.1.4        10FP17.3.1.4   Rodriguez, Alex            26       476
 Mauer, Joe               10FP17.3.1.5   3.1.5                7       192      3.1.5        10FP17.3.1.5   Ethier, Andre              27       418
 Rodriguez, Alex          10FP17.3.1.4   3.1.4               26       476      3.1.5        10FP17.3.1.5   Mauer, Joe                  7       192
 Rollins, Jimmy           10FP17.1.2     1.2                  4       114      3.1.5        10FP17.3.1.5   Scherzer, Max                        98
 Scherzer, Max            10FP17.3.1.1   3.1.1                        170      3.1.5        10FP17.3.1.5   Weaver, Jered               6       118
 Scherzer, Max            10FP17.1.3     3.1.5                         98      3.2.1        10FP17.3.2.1   Fielder, Prince                     131
 Pujols, Albert           10FP17.1.3     1.1                 20       580      3.2.2        10FP17.3.2.2   Fielder, Prince             7        40
 Uggla, Dan               10FP17.1.3     1.3                 40       854      3.2.3        10FP17.3.2.3   Fielder, Prince             6        12
 Weaver, Jered            10FP17.3.1.5   3.1.5                6       118      3.2.3        10FP17.3.2.3   Lincecum, Tim                          7

 TOTAL                                                    197        4739                                                          197        4739




© 2012 SCOBEN Data Solutions. All rights reserved.                   Page 3 of 27                                                            4/4/2012
Project: 10FP17, ACME - Prototype Cryo Data Logger Development
                          Chart Title: Critical Path - Schedule Analysis                                                                                                                                                         Planned Start/End Date: 10/29/11       12/01/12
                           Qualifiers: WBS: *, Dept: *, RU 1: *, RU 2: *, RU 3: CP
Cost, Budget, EV Trends                                                                                                                                              Schedule Performance
                                              $400.0                                                      $9.0                                                                              2.0                                                                        02/15/13
                                  Thousands




                                                                                                                        Thousands
                                                                                                          $8.0                                                                              1.8                                                                        01/26/13
                                              $350.0




                                                                                                                                                                                                                                                                                   Predicted Completion, EAC(t)
                                                                                                                                                                                                                                                                                    Planned Completion, BAC(t)
                                                                                                          $7.0                                                                              1.6
                                              $300.0                                                                                                                                                                                                                   01/06/13




                                                                                                                                                                Performance Index, SPI(t)
Cost Cumulative (Line Graph)




                                                                                                                                  Cost per Period (Bar Graph)
                                                                                                                                                                                            1.4
                                                                                                          $6.0
                                              $250.0                                                                                                                                        1.2                                                                        12/17/12
                                                                                                          $5.0
                                              $200.0                                                                                                                                        1.0                                                                        11/27/12
                                                                                                          $4.0
                                                                                                                                                                                            0.8                                                                        11/07/12
                                              $150.0
                                                                                                          $3.0
                                                                                                                                                                                            0.6
                                              $100.0                                                                                                                                                                                                                   10/18/12
                                                                                                          $2.0                                                                              0.4
                                               $50.0                                                      $1.0                                                                              0.2                                                                        09/28/12

                                                $0.0                                                      $0.0                                                                              0.0                                                                        09/08/12




                                                                                                                                                                                                   12/10/11
                                                                                                                                                                                                   12/17/11
                                                                                                                                                                                                   12/24/11
                                                                                                                                                                                                   12/31/11
                                                                                                                                                                                                   01/07/12
                                                                                                                                                                                                   01/14/12
                                                                                                                                                                                                   01/21/12
                                                                                                                                                                                                   01/28/12
                                                                                                                                                                                                   02/04/12
                                                                                                                                                                                                   02/11/12
                                                                                                                                                                                                   02/18/12
                                                                                                                                                                                                   02/25/12
                                                                                                                                                                                                   03/03/12
                                                                                                                                                                                                   03/10/12
                                                                                                                                                                                                   03/17/12
                                                                                                                                                                                                   03/24/12
                                                                                                                                                                                                   03/31/12
                                                                                                                                                                                                   04/07/12
                                                                                                                                                                                                   04/14/12
                                                                                                                                                                                                   04/21/12
                                                                                                                                                                                                   04/28/12
                                                                                                                                                                                                   05/05/12
                                                                                                                                                                                                   05/12/12
                                                                                                                                                                                                   05/19/12
                                                                                                                                                                                                   05/26/12
                                                                                                                                                                                                   06/02/12
                                                       12/10/11
                                                       12/17/11
                                                       12/24/11
                                                       12/31/11
                                                       01/07/12
                                                       01/14/12
                                                       01/21/12
                                                       01/28/12
                                                       02/04/12
                                                       02/11/12
                                                       02/18/12
                                                       02/25/12
                                                       03/03/12
                                                       03/10/12
                                                       03/17/12
                                                       03/24/12
                                                       03/31/12
                                                       04/07/12
                                                       04/14/12
                                                       04/21/12
                                                       04/28/12
                                                       05/05/12
                                                       05/12/12
                                                       05/19/12
                                                       05/26/12
                                                       06/02/12
                                                                        Status Date                                                                                                                                              Status Date
                                                 Planned Value (PV)      Actual Costs (AC)   PV (Cumulative)
                                                 AC (Cumulative)         EV (Cumulative)     Current BAC                                                                                                        SPI(t)                      EAC(t)                     BAC(t)
                                                 Predicted EAC 1
Cost Performance                                                                                                                                                     Project/Task Health Dashboard



                                                                                                                Planned Completion, BAC($) Thousands
                                     2.0                                                           $600                                                                                                                                                      Trend /
                                     1.8                                                                                                                                                                                                Metric               % Comp        Variance
      Performance Index, CPI($)




                                     1.6
                                                                                                   $500                                                                                           Schedule:        SPI(t):               0.95                                 NA
                                                                                                               Predicted Completion, EAC($)                                                           ES(t), AD(t) (wks):               19            22      33%              (3) wks
                                     1.4
                                                                                                   $400                                                                                                  BAC(t), EAC(t):         12/01/12        12/18/12                      (3) wks
                                     1.2                                                                                                                                                           BTC(t), ETC(t) (wks):              35.0           37.5      NA        NA
                                     1.0                                                           $300                                                                                              TSPI(t) [BAC, EAC]:              1.09           1.06      NA        NA
                                     0.8                                                                                                                                                          Hours:          CPI(h):                0.88                            NA
                                                                                                   $200                                                                                                    EV(h), AC(h):            1,082            1,225    32%           (143) hrs
                                     0.6
                                                                                                                                                                                                        BAC(h), EAC(h):             3,385            3,746                  (361) hrs
                                     0.4                                                                                                                                                                BTC(h), ETC(h):             2,160            2,521     NA        NA
                                                                                                   $100
                                     0.2                                                                                                                                                            TCPI(h) [BAC, EAC]:              1.07             1.01     NA        NA
                                     0.0                                                           $0                                                                                             Cost:           CPI($):                0.86                            NA
                                                                                                                                                                                                                                           00
                                                 12/10/11
                                                 12/17/11
                                                 12/24/11
                                                 12/31/11
                                                 01/07/12
                                                 01/14/12
                                                 01/21/12
                                                 01/28/12
                                                 02/04/12
                                                 02/11/12
                                                 02/18/12
                                                 02/25/12
                                                 03/03/12
                                                 03/10/12
                                                 03/17/12
                                                 03/24/12
                                                 03/31/12
                                                 04/07/12
                                                 04/14/12
                                                 04/21/12
                                                 04/28/12
                                                 05/05/12
                                                 05/12/12
                                                 05/19/12
                                                 05/26/12
                                                 06/02/12




                                                                                                                                                                                                            EV($), AC($):    $   112,693 $       131,189      35%         ($18,496)
                                                                                                                                                                                                        BAC($), EAC($):      $   321,790 $       365,516                  ($43,726)
                                                                                                                                                                                                         BTC($), ETC($):     $   190,601 $       234,327       NA        NA
                                                                                                                                                                                                    TCPI($) [BAC, EAC]:              1.10           1.01       NA        NA
                                                                      Status Date
                                                                                                                                                                                                            Commits($):      $        -                        NA        NA
                                                             CPI($)            EAC($)          BAC($)
                                                                                                                                                                                                  Labor Rates (BC, AC):      $      99.93 $       104.23       NA         ($4.30)


© 2012 SCOBEN Data Solutions. All rights reserved.                                                                  Page 4 of 27                                                                                                                                                  4/4/2012
Project: 10FP17, ACME - Prototype Cryo Data Logger Development
                          Chart Title: Rollup - Project 10FP17                                                                                                                                                                    Planned Start/End Date: 10/15/11    12/08/12
                           Qualifiers: WBS: *, Dept: *, RU 1: *, RU 2: *, RU 3: *
Cost, Budget, EV Trends                                                                                                                                               Schedule Performance
                                           $1,400.0                                                        $35.0                                                                             2.0                                                                     02/05/13
                               Thousands




                                                                                                                                Thousands
                                                                                                                                                                                             1.8                                                                     01/26/13
                                           $1,200.0                                                        $30.0




                                                                                                                                                                                                                                                                                 Predicted Completion, EAC(t)
                                                                                                                                                                                                                                                                                  Planned Completion, BAC(t)
                                                                                                                                                                                             1.6                                                                     01/16/13




                                                                                                                                                                 Performance Index, SPI(t)
Cost Cumulative (Line Graph)




                                           $1,000.0                                                        $25.0




                                                                                                                                   Cost per Period (Bar Graph)
                                                                                                                                                                                             1.4                                                                     01/06/13
                                                                                                                                                                                             1.2                                                                     12/27/12
                                             $800.0                                                        $20.0
                                                                                                                                                                                             1.0                                                                     12/17/12
                                             $600.0                                                        $15.0
                                                                                                                                                                                             0.8                                                                     12/07/12

                                             $400.0                                                        $10.0                                                                             0.6                                                                     11/27/12
                                                                                                                                                                                             0.4                                                                     11/17/12
                                             $200.0                                                        $5.0
                                                                                                                                                                                             0.2                                                                     11/07/12
                                                 $0.0                                                      $0.0                                                                              0.0                                                                     10/28/12




                                                                                                                                                                                                    12/10/11
                                                                                                                                                                                                    12/17/11
                                                                                                                                                                                                    12/24/11
                                                                                                                                                                                                    12/31/11
                                                                                                                                                                                                    01/07/12
                                                                                                                                                                                                    01/14/12
                                                                                                                                                                                                    01/21/12
                                                                                                                                                                                                    01/28/12
                                                                                                                                                                                                    02/04/12
                                                                                                                                                                                                    02/11/12
                                                                                                                                                                                                    02/18/12
                                                                                                                                                                                                    02/25/12
                                                                                                                                                                                                    03/03/12
                                                                                                                                                                                                    03/10/12
                                                                                                                                                                                                    03/17/12
                                                                                                                                                                                                    03/24/12
                                                                                                                                                                                                    03/31/12
                                                                                                                                                                                                    04/07/12
                                                                                                                                                                                                    04/14/12
                                                                                                                                                                                                    04/21/12
                                                                                                                                                                                                    04/28/12
                                                                                                                                                                                                    05/05/12
                                                                                                                                                                                                    05/12/12
                                                                                                                                                                                                    05/19/12
                                                                                                                                                                                                    05/26/12
                                                                                                                                                                                                    06/02/12
                                                        12/10/11
                                                        12/17/11
                                                        12/24/11
                                                        12/31/11
                                                        01/07/12
                                                        01/14/12
                                                        01/21/12
                                                        01/28/12
                                                        02/04/12
                                                        02/11/12
                                                        02/18/12
                                                        02/25/12
                                                        03/03/12
                                                        03/10/12
                                                        03/17/12
                                                        03/24/12
                                                        03/31/12
                                                        04/07/12
                                                        04/14/12
                                                        04/21/12
                                                        04/28/12
                                                        05/05/12
                                                        05/12/12
                                                        05/19/12
                                                        05/26/12
                                                        06/02/12
                                                                         Status Date                                                                                                                                               Status Date
                                                  Planned Value (PV)      Actual Costs (AC)   PV (Cumulative)
                                                  AC (Cumulative)         EV (Cumulative)     Current BAC                                                                                                        SPI(t)                      EAC(t)                  BAC(t)
                                                  Predicted EAC 1
Cost Performance                                                                                                                                                      Project/Task Health Dashboard



                                                                                                                 Planned Completion, BAC($) Thousands
                                           2.0                                                      $1,800                                                                                                                                                 Trend /
                                           1.8                                                      $1,600                                                                                                                                Metric           % Comp        Variance
      Performance Index, CPI($)




                                           1.6
                                                                                                                                                                                                   Schedule:        SPI(t):               1.00                              NA
                                                                                                                Predicted Completion, EAC($)
                                                                                                    $1,400
                                                                                                                                                                                                       ES(t), AD(t) (wks):               24            24    40%             0 wks
                                           1.4
                                                                                                    $1,200                                                                                                BAC(t), EAC(t):          12/08/12      11/30/12                    1 wks
                                           1.2                                                                                                                                                      BTC(t), ETC(t) (wks):               36.0          35.0   NA        NA
                                                                                                    $1,000
                                           1.0                                                                                                                                                        TSPI(t) [BAC, EAC]:               1.00          1.01   NA        NA
                                                                                                    $800                                                                                           Hours:          CPI(h):                0.94                         NA
                                           0.8
                                                                                                    $600                                                                                                    EV(h), AC(h):             4,477         4,739    44%          (262) hrs
                                           0.6
                                                                                                                                                                                                         BAC(h), EAC(h):             10,165       10,611                  (446) hrs
                                           0.4                                                      $400
                                                                                                                                                                                                         BTC(h), ETC(h):              5,426         5,872    NA        NA
                                           0.2                                                      $200                                                                                             TCPI(h) [BAC, EAC]:               1.05          1.01    NA        NA
                                           0.0                                                      $0                                                                                             Cost:           CPI($):                0.95                         NA
                                                  12/10/11
                                                  12/17/11
                                                  12/24/11
                                                  12/31/11
                                                  01/07/12
                                                  01/14/12
                                                  01/21/12
                                                  01/28/12
                                                  02/04/12
                                                  02/11/12
                                                  02/18/12
                                                  02/25/12
                                                  03/03/12
                                                  03/10/12
                                                  03/17/12
                                                  03/24/12
                                                  03/31/12
                                                  04/07/12
                                                  04/14/12
                                                  04/21/12
                                                  04/28/12
                                                  05/05/12
                                                  05/12/12
                                                  05/19/12
                                                  05/26/12
                                                  06/02/12




                                                                                                                                                                                                             EV($), AC($):    $     548,331 $ 574,405        49%        ($26,074)
                                                                                                                                                                                                         BAC($), EAC($):      $   1,115,316 $ 1,144,148                 ($28,832)
                                                                                                                                                                                                          BTC($), ETC($):     $     540,911 $ 569,742        NA        NA
                                                                                                                                                                                                     TCPI($) [BAC, EAC]:               1.05          1.02    NA        NA
                                                                       Status Date
                                                                                                                                                                                                             Commits($):      $       4,773                  NA        NA
                                                              CPI($)            EAC($)          BAC($)
                                                                                                                                                                                                   Labor Rates (BC, AC):      $      109.56 $     110.69     NA         ($1.13)


© 2012 SCOBEN Data Solutions. All rights reserved.                                                                   Page 5 of 27                                                                                                                                               4/4/2012
Project: 10FP17, ACME - Prototype Cryo Data Logger Development
                          Chart Title: Rollup - WBS 1.0, PM, PC, and PE                                                                                                                                                          Planned Start/End Date: 10/15/11       12/01/12
                           Qualifiers: WBS: *, Dept: *, RU 1: 1.0, RU 2: *, RU 3: *
Cost, Budget, EV Trends                                                                                                                                              Schedule Performance
                                              $500.0                                                      $9.0                                                                              2.0                                                                        12/07/12
                                  Thousands




                                                                                                                        Thousands
                                              $450.0                                                      $8.0                                                                              1.8




                                                                                                                                                                                                                                                                                   Predicted Completion, EAC(t)
                                                                                                                                                                                                                                                                       12/02/12




                                                                                                                                                                                                                                                                                    Planned Completion, BAC(t)
                                              $400.0                                                      $7.0                                                                              1.6




                                                                                                                                                                Performance Index, SPI(t)
Cost Cumulative (Line Graph)




                                                                                                                                  Cost per Period (Bar Graph)
                                              $350.0                                                                                                                                        1.4
                                                                                                          $6.0                                                                                                                                                         11/27/12
                                              $300.0                                                                                                                                        1.2
                                                                                                          $5.0
                                              $250.0                                                                                                                                        1.0                                                                        11/22/12
                                                                                                          $4.0
                                              $200.0                                                                                                                                        0.8
                                                                                                          $3.0                                                                                                                                                         11/17/12
                                              $150.0                                                                                                                                        0.6
                                              $100.0                                                      $2.0                                                                              0.4
                                                                                                                                                                                                                                                                       11/12/12
                                               $50.0                                                      $1.0                                                                              0.2
                                                $0.0                                                      $0.0                                                                              0.0                                                                        11/07/12




                                                                                                                                                                                                   12/10/11
                                                                                                                                                                                                   12/17/11
                                                                                                                                                                                                   12/24/11
                                                                                                                                                                                                   12/31/11
                                                                                                                                                                                                   01/07/12
                                                                                                                                                                                                   01/14/12
                                                                                                                                                                                                   01/21/12
                                                                                                                                                                                                   01/28/12
                                                                                                                                                                                                   02/04/12
                                                                                                                                                                                                   02/11/12
                                                                                                                                                                                                   02/18/12
                                                                                                                                                                                                   02/25/12
                                                                                                                                                                                                   03/03/12
                                                                                                                                                                                                   03/10/12
                                                                                                                                                                                                   03/17/12
                                                                                                                                                                                                   03/24/12
                                                                                                                                                                                                   03/31/12
                                                                                                                                                                                                   04/07/12
                                                                                                                                                                                                   04/14/12
                                                                                                                                                                                                   04/21/12
                                                                                                                                                                                                   04/28/12
                                                                                                                                                                                                   05/05/12
                                                                                                                                                                                                   05/12/12
                                                                                                                                                                                                   05/19/12
                                                                                                                                                                                                   05/26/12
                                                                                                                                                                                                   06/02/12
                                                       12/10/11
                                                       12/17/11
                                                       12/24/11
                                                       12/31/11
                                                       01/07/12
                                                       01/14/12
                                                       01/21/12
                                                       01/28/12
                                                       02/04/12
                                                       02/11/12
                                                       02/18/12
                                                       02/25/12
                                                       03/03/12
                                                       03/10/12
                                                       03/17/12
                                                       03/24/12
                                                       03/31/12
                                                       04/07/12
                                                       04/14/12
                                                       04/21/12
                                                       04/28/12
                                                       05/05/12
                                                       05/12/12
                                                       05/19/12
                                                       05/26/12
                                                       06/02/12
                                                                        Status Date                                                                                                                                              Status Date
                                                 Planned Value (PV)      Actual Costs (AC)   PV (Cumulative)
                                                 AC (Cumulative)         EV (Cumulative)     Current BAC                                                                                                        SPI(t)                      EAC(t)                     BAC(t)
                                                 Predicted EAC 1
Cost Performance                                                                                                                                                     Project/Task Health Dashboard



                                                                                                                Planned Completion, BAC($) Thousands
                                     2.0                                                           $460                                                                                                                                                      Trend /
                                     1.8                                                                                                                                                                                                Metric               % Comp       Variance
                                                                                                   $450
      Performance Index, CPI($)




                                     1.6
                                                                                                                                                                                                  Schedule:        SPI(t):               1.00                                 NA
                                                                                                   $440        Predicted Completion, EAC($)                                                           ES(t), AD(t) (wks):               24            24      41%              0 wks
                                     1.4
                                                                                                                                                                                                         BAC(t), EAC(t):         12/01/12        12/01/12                      0 wks
                                     1.2                                                           $430
                                                                                                                                                                                                   BTC(t), ETC(t) (wks):              35.0           35.0      NA        NA
                                     1.0                                                           $420                                                                                              TSPI(t) [BAC, EAC]:              1.00           1.00      NA        NA
                                     0.8                                                                                                                                                          Hours:          CPI(h):                0.92                            NA
                                                                                                   $410
                                                                                                                                                                                                           EV(h), AC(h):            1,426            1,548    40%           (122) hrs
                                     0.6
                                                                                                   $400                                                                                                 BAC(h), EAC(h):             3,596            3,851                  (255) hrs
                                     0.4                                                                                                                                                                BTC(h), ETC(h):             2,048            2,303     NA        NA
                                     0.2                                                           $390
                                                                                                                                                                                                    TCPI(h) [BAC, EAC]:              1.06             1.01     NA        NA
                                     0.0                                                           $380                                                                                           Cost:           CPI($):                0.93                            NA
                                                 12/10/11
                                                 12/17/11
                                                 12/24/11
                                                 12/31/11
                                                 01/07/12
                                                 01/14/12
                                                 01/21/12
                                                 01/28/12
                                                 02/04/12
                                                 02/11/12
                                                 02/18/12
                                                 02/25/12
                                                 03/03/12
                                                 03/10/12
                                                 03/17/12
                                                 03/24/12
                                                 03/31/12
                                                 04/07/12
                                                 04/14/12
                                                 04/21/12
                                                 04/28/12
                                                 05/05/12
                                                 05/12/12
                                                 05/19/12
                                                 05/26/12
                                                 06/02/12




                                                                                                                                                                                                            EV($), AC($):    $   160,540 $       172,268      40%         ($11,728)
                                                                                                                                                                                                        BAC($), EAC($):      $   404,840 $       429,440                  ($24,600)
                                                                                                                                                                                                         BTC($), ETC($):     $   232,572 $       257,171       NA        NA
                                                                                                                                                                                                    TCPI($) [BAC, EAC]:              1.05           1.01       NA        NA
                                                                      Status Date
                                                                                                                                                                                                            Commits($):      $        -                        NA        NA
                                                             CPI($)            EAC($)          BAC($)
                                                                                                                                                                                                  Labor Rates (BC, AC):      $    112.58 $        111.52       NA          $1.06


© 2012 SCOBEN Data Solutions. All rights reserved.                                                                  Page 6 of 27                                                                                                                                                  4/4/2012
Project: 10FP17, ACME - Prototype Cryo Data Logger Development
                          Chart Title: WBS: 1.1, Program Management                                                                                                                                                              Planned Start/End Date: 10/15/11    12/01/12
                           Qualifiers: WBS: 1.1, Dept: *, RU 1: *, RU 2: *, RU 3: *
Cost, Budget, EV Trends                                                                                                                                              Schedule Performance
                                              $180.0                                                      $4.0                                                                              2.0                                                                     12/07/12
                                  Thousands




                                                                                                                        Thousands
                                              $160.0                                                                                                                                        1.8
                                                                                                          $3.5




                                                                                                                                                                                                                                                                                Predicted Completion, EAC(t)
                                                                                                                                                                                                                                                                    12/02/12




                                                                                                                                                                                                                                                                                 Planned Completion, BAC(t)
                                              $140.0                                                                                                                                        1.6
                                                                                                          $3.0




                                                                                                                                                                Performance Index, SPI(t)
Cost Cumulative (Line Graph)




                                                                                                                                  Cost per Period (Bar Graph)
                                                                                                                                                                                            1.4
                                              $120.0                                                                                                                                                                                                                11/27/12
                                                                                                          $2.5                                                                              1.2
                                              $100.0
                                                                                                          $2.0                                                                              1.0                                                                     11/22/12
                                               $80.0
                                                                                                                                                                                            0.8
                                                                                                          $1.5
                                               $60.0                                                                                                                                                                                                                11/17/12
                                                                                                                                                                                            0.6
                                                                                                          $1.0
                                               $40.0                                                                                                                                        0.4
                                                                                                                                                                                                                                                                    11/12/12
                                               $20.0                                                      $0.5                                                                              0.2
                                                $0.0                                                      $0.0                                                                              0.0                                                                     11/07/12




                                                                                                                                                                                                   12/10/11
                                                                                                                                                                                                   12/17/11
                                                                                                                                                                                                   12/24/11
                                                                                                                                                                                                   12/31/11
                                                                                                                                                                                                   01/07/12
                                                                                                                                                                                                   01/14/12
                                                                                                                                                                                                   01/21/12
                                                                                                                                                                                                   01/28/12
                                                                                                                                                                                                   02/04/12
                                                                                                                                                                                                   02/11/12
                                                                                                                                                                                                   02/18/12
                                                                                                                                                                                                   02/25/12
                                                                                                                                                                                                   03/03/12
                                                                                                                                                                                                   03/10/12
                                                                                                                                                                                                   03/17/12
                                                                                                                                                                                                   03/24/12
                                                                                                                                                                                                   03/31/12
                                                                                                                                                                                                   04/07/12
                                                                                                                                                                                                   04/14/12
                                                                                                                                                                                                   04/21/12
                                                                                                                                                                                                   04/28/12
                                                                                                                                                                                                   05/05/12
                                                                                                                                                                                                   05/12/12
                                                                                                                                                                                                   05/19/12
                                                                                                                                                                                                   05/26/12
                                                                                                                                                                                                   06/02/12
                                                       12/10/11
                                                       12/17/11
                                                       12/24/11
                                                       12/31/11
                                                       01/07/12
                                                       01/14/12
                                                       01/21/12
                                                       01/28/12
                                                       02/04/12
                                                       02/11/12
                                                       02/18/12
                                                       02/25/12
                                                       03/03/12
                                                       03/10/12
                                                       03/17/12
                                                       03/24/12
                                                       03/31/12
                                                       04/07/12
                                                       04/14/12
                                                       04/21/12
                                                       04/28/12
                                                       05/05/12
                                                       05/12/12
                                                       05/19/12
                                                       05/26/12
                                                       06/02/12
                                                                        Status Date                                                                                                                                              Status Date
                                                 Planned Value (PV)      Actual Costs (AC)   PV (Cumulative)
                                                 AC (Cumulative)         EV (Cumulative)     Current BAC                                                                                                        SPI(t)                     EAC(t)                   BAC(t)
                                                 Predicted EAC 1
Cost Performance                                                                                                                                                     Project/Task Health Dashboard



                                                                                                                Planned Completion, BAC($) Thousands
                                     2.0                                                           $250                                                                                                                                                  Trend /
                                     1.8                                                                                                                                                                                                Metric           % Comp        Variance
      Performance Index, CPI($)




                                     1.6                                                           $200
                                                                                                                                                                                                  Schedule:        SPI(t):               1.00                              NA
                                                                                                               Predicted Completion, EAC($)                                                           ES(t), AD(t) (wks):               24           24    41%              0 wks
                                     1.4
                                                                                                                                                                                                         BAC(t), EAC(t):         12/01/12      12/01/12                     0 wks
                                     1.2                                                           $150                                                                                            BTC(t), ETC(t) (wks):              35.0          35.0   NA         NA
                                     1.0                                                                                                                                                             TSPI(t) [BAC, EAC]:              1.00          1.00   NA         NA
                                     0.8                                                           $100                                                                                           Hours:          CPI(h):                0.79                         NA
                                                                                                                                                                                                           EV(h), AC(h):              460           580    40%           (120) hrs
                                     0.6
                                                                                                                                                                                                        BAC(h), EAC(h):             1,160         1,411                  (251) hrs
                                     0.4                                                           $50                                                                                                  BTC(h), ETC(h):               580           831    NA         NA
                                     0.2                                                                                                                                                            TCPI(h) [BAC, EAC]:              1.21          1.02    NA         NA
                                     0.0                                                           $0                                                                                             Cost:           CPI($):                0.83                         NA
                                                 12/10/11
                                                 12/17/11
                                                 12/24/11
                                                 12/31/11
                                                 01/07/12
                                                 01/14/12
                                                 01/21/12
                                                 01/28/12
                                                 02/04/12
                                                 02/11/12
                                                 02/18/12
                                                 02/25/12
                                                 03/03/12
                                                 03/10/12
                                                 03/17/12
                                                 03/24/12
                                                 03/31/12
                                                 04/07/12
                                                 04/14/12
                                                 04/21/12
                                                 04/28/12
                                                 05/05/12
                                                 05/12/12
                                                 05/19/12
                                                 05/26/12
                                                 06/02/12




                                                                                                                                                                                                            EV($), AC($):    $    55,200 $      66,543     40%         ($11,343)
                                                                                                                                                                                                        BAC($), EAC($):      $   139,200 $ 163,172                     ($23,972)
                                                                                                                                                                                                         BTC($), ETC($):     $    72,657 $      96,628     NA         NA
                                                                                                                                                                                                    TCPI($) [BAC, EAC]:              1.16          1.02    NA         NA
                                                                      Status Date
                                                                                                                                                                                                            Commits($):      $        -                    NA         NA
                                                             CPI($)            EAC($)          BAC($)
                                                                                                                                                                                                  Labor Rates (BC, AC):      $    120.00 $      114.73     NA           $5.27


© 2012 SCOBEN Data Solutions. All rights reserved.                                                                  Page 7 of 27                                                                                                                                               4/4/2012
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report
Format for EVM Report

More Related Content

Viewers also liked

Measuring The Effectiveness Of Evm
Measuring The Effectiveness Of EvmMeasuring The Effectiveness Of Evm
Measuring The Effectiveness Of Evm
bhurless
 
Functional UI testing of Adobe Flex RIA
Functional UI testing of Adobe Flex RIAFunctional UI testing of Adobe Flex RIA
Functional UI testing of Adobe Flex RIA
Viktor Gamov
 
Dance Ability
Dance AbilityDance Ability
Dance Ability
Anabel Barboza
 
WebSockets: The Current State of the Most Valuable HTML5 API for Java Developers
WebSockets: The Current State of the Most Valuable HTML5 API for Java DevelopersWebSockets: The Current State of the Most Valuable HTML5 API for Java Developers
WebSockets: The Current State of the Most Valuable HTML5 API for Java Developers
Viktor Gamov
 
Testing Flex RIAs for NJ Flex user group
Testing Flex RIAs for NJ Flex user groupTesting Flex RIAs for NJ Flex user group
Testing Flex RIAs for NJ Flex user group
Viktor Gamov
 
NEOUPA Remote Usability Studies
NEOUPA Remote Usability StudiesNEOUPA Remote Usability Studies
NEOUPA Remote Usability Studies
jaholmes2
 
JavaOne 2013: «Java and JavaScript - Shaken, Not Stirred»
JavaOne 2013: «Java and JavaScript - Shaken, Not Stirred»JavaOne 2013: «Java and JavaScript - Shaken, Not Stirred»
JavaOne 2013: «Java and JavaScript - Shaken, Not Stirred»
Viktor Gamov
 
2010 Economic Summit accomplishments
2010 Economic Summit accomplishments2010 Economic Summit accomplishments
2010 Economic Summit accomplishments
City of Johnson City
 
2009 Economic Summit Accomplishments
2009 Economic Summit Accomplishments2009 Economic Summit Accomplishments
2009 Economic Summit Accomplishments
City of Johnson City
 
Accomplishments 2011
Accomplishments 2011Accomplishments 2011
Accomplishments 2011
City of Johnson City
 
Smart
SmartSmart
Structure in Basic Web Design
Structure in Basic Web DesignStructure in Basic Web Design
Structure in Basic Web Design
waschmunk
 
[JokerConf] Верхом на реактивных стримах, 10/13/2016
[JokerConf] Верхом на реактивных стримах, 10/13/2016[JokerConf] Верхом на реактивных стримах, 10/13/2016
[JokerConf] Верхом на реактивных стримах, 10/13/2016
Viktor Gamov
 
Danis Concarneau 2016
Danis Concarneau 2016Danis Concarneau 2016
Danis Concarneau 2016
Bruno Danis
 

Viewers also liked (14)

Measuring The Effectiveness Of Evm
Measuring The Effectiveness Of EvmMeasuring The Effectiveness Of Evm
Measuring The Effectiveness Of Evm
 
Functional UI testing of Adobe Flex RIA
Functional UI testing of Adobe Flex RIAFunctional UI testing of Adobe Flex RIA
Functional UI testing of Adobe Flex RIA
 
Dance Ability
Dance AbilityDance Ability
Dance Ability
 
WebSockets: The Current State of the Most Valuable HTML5 API for Java Developers
WebSockets: The Current State of the Most Valuable HTML5 API for Java DevelopersWebSockets: The Current State of the Most Valuable HTML5 API for Java Developers
WebSockets: The Current State of the Most Valuable HTML5 API for Java Developers
 
Testing Flex RIAs for NJ Flex user group
Testing Flex RIAs for NJ Flex user groupTesting Flex RIAs for NJ Flex user group
Testing Flex RIAs for NJ Flex user group
 
NEOUPA Remote Usability Studies
NEOUPA Remote Usability StudiesNEOUPA Remote Usability Studies
NEOUPA Remote Usability Studies
 
JavaOne 2013: «Java and JavaScript - Shaken, Not Stirred»
JavaOne 2013: «Java and JavaScript - Shaken, Not Stirred»JavaOne 2013: «Java and JavaScript - Shaken, Not Stirred»
JavaOne 2013: «Java and JavaScript - Shaken, Not Stirred»
 
2010 Economic Summit accomplishments
2010 Economic Summit accomplishments2010 Economic Summit accomplishments
2010 Economic Summit accomplishments
 
2009 Economic Summit Accomplishments
2009 Economic Summit Accomplishments2009 Economic Summit Accomplishments
2009 Economic Summit Accomplishments
 
Accomplishments 2011
Accomplishments 2011Accomplishments 2011
Accomplishments 2011
 
Smart
SmartSmart
Smart
 
Structure in Basic Web Design
Structure in Basic Web DesignStructure in Basic Web Design
Structure in Basic Web Design
 
[JokerConf] Верхом на реактивных стримах, 10/13/2016
[JokerConf] Верхом на реактивных стримах, 10/13/2016[JokerConf] Верхом на реактивных стримах, 10/13/2016
[JokerConf] Верхом на реактивных стримах, 10/13/2016
 
Danis Concarneau 2016
Danis Concarneau 2016Danis Concarneau 2016
Danis Concarneau 2016
 

Similar to Format for EVM Report

Jdsu
JdsuJdsu
Jdsu
flipwedge
 
Macquarie - BlueStone Resources Report
Macquarie - BlueStone Resources ReportMacquarie - BlueStone Resources Report
Macquarie - BlueStone Resources Report
MomentumPR
 
Tcw
TcwTcw
Tcw
kanith0
 
Levelized Cost Of Electricity For Cpv Paper Nishikawa
Levelized Cost Of Electricity For Cpv Paper NishikawaLevelized Cost Of Electricity For Cpv Paper Nishikawa
Levelized Cost Of Electricity For Cpv Paper Nishikawa
warlor
 
ANZ Bank - Structural Headwinds
ANZ Bank - Structural Headwinds ANZ Bank - Structural Headwinds
ANZ Bank - Structural Headwinds
George Gabriel
 
Concor ru2 qfy2011-201010
Concor ru2 qfy2011-201010Concor ru2 qfy2011-201010
Concor ru2 qfy2011-201010
Angel Broking
 
Areva t&d ru1 qcy2010-260410
Areva t&d ru1 qcy2010-260410Areva t&d ru1 qcy2010-260410
Areva t&d ru1 qcy2010-260410
Angel Broking
 
Bvn scotiabank
Bvn scotiabankBvn scotiabank
Bvn scotiabank
gro77
 
Mackie Research: Northern Graphite - Lifting Target on Spherical Graphite News
Mackie Research: Northern Graphite - Lifting Target on Spherical Graphite NewsMackie Research: Northern Graphite - Lifting Target on Spherical Graphite News
Mackie Research: Northern Graphite - Lifting Target on Spherical Graphite News
Graphite Graphite
 
ABG Shipyard
ABG Shipyard ABG Shipyard
ABG Shipyard
Angel Broking
 
ONGC
ONGCONGC
GDL
GDLGDL
Appendix
AppendixAppendix
Appendix
AToshach
 
2324
23242324
2324
yo9889
 
CCXG Global Forum September 2017, BGD Accounting within the NDC cycle by Jae ...
CCXG Global Forum September 2017, BGD Accounting within the NDC cycle by Jae ...CCXG Global Forum September 2017, BGD Accounting within the NDC cycle by Jae ...
CCXG Global Forum September 2017, BGD Accounting within the NDC cycle by Jae ...
OECD Environment
 
Finolex Cables
Finolex CablesFinolex Cables
Finolex Cables
Angel Broking
 
Butts estimating facilitiespm challenge2012
Butts estimating facilitiespm challenge2012Butts estimating facilitiespm challenge2012
Butts estimating facilitiespm challenge2012
NASAPMC
 
Sun TV
Sun TVSun TV
Gail india event update - 200410
Gail india   event update - 200410Gail india   event update - 200410
Gail india event update - 200410
Angel Broking
 
Areva TD
Areva TDAreva TD
Areva TD
Angel Broking
 

Similar to Format for EVM Report (20)

Jdsu
JdsuJdsu
Jdsu
 
Macquarie - BlueStone Resources Report
Macquarie - BlueStone Resources ReportMacquarie - BlueStone Resources Report
Macquarie - BlueStone Resources Report
 
Tcw
TcwTcw
Tcw
 
Levelized Cost Of Electricity For Cpv Paper Nishikawa
Levelized Cost Of Electricity For Cpv Paper NishikawaLevelized Cost Of Electricity For Cpv Paper Nishikawa
Levelized Cost Of Electricity For Cpv Paper Nishikawa
 
ANZ Bank - Structural Headwinds
ANZ Bank - Structural Headwinds ANZ Bank - Structural Headwinds
ANZ Bank - Structural Headwinds
 
Concor ru2 qfy2011-201010
Concor ru2 qfy2011-201010Concor ru2 qfy2011-201010
Concor ru2 qfy2011-201010
 
Areva t&d ru1 qcy2010-260410
Areva t&d ru1 qcy2010-260410Areva t&d ru1 qcy2010-260410
Areva t&d ru1 qcy2010-260410
 
Bvn scotiabank
Bvn scotiabankBvn scotiabank
Bvn scotiabank
 
Mackie Research: Northern Graphite - Lifting Target on Spherical Graphite News
Mackie Research: Northern Graphite - Lifting Target on Spherical Graphite NewsMackie Research: Northern Graphite - Lifting Target on Spherical Graphite News
Mackie Research: Northern Graphite - Lifting Target on Spherical Graphite News
 
ABG Shipyard
ABG Shipyard ABG Shipyard
ABG Shipyard
 
ONGC
ONGCONGC
ONGC
 
GDL
GDLGDL
GDL
 
Appendix
AppendixAppendix
Appendix
 
2324
23242324
2324
 
CCXG Global Forum September 2017, BGD Accounting within the NDC cycle by Jae ...
CCXG Global Forum September 2017, BGD Accounting within the NDC cycle by Jae ...CCXG Global Forum September 2017, BGD Accounting within the NDC cycle by Jae ...
CCXG Global Forum September 2017, BGD Accounting within the NDC cycle by Jae ...
 
Finolex Cables
Finolex CablesFinolex Cables
Finolex Cables
 
Butts estimating facilitiespm challenge2012
Butts estimating facilitiespm challenge2012Butts estimating facilitiespm challenge2012
Butts estimating facilitiespm challenge2012
 
Sun TV
Sun TVSun TV
Sun TV
 
Gail india event update - 200410
Gail india   event update - 200410Gail india   event update - 200410
Gail india event update - 200410
 
Areva TD
Areva TDAreva TD
Areva TD
 

Format for EVM Report

  • 1. Project: 10FP17, ACME - Prototype Cryo Data Logger Development Report Title: Cost, Budget, Earned Value ($), Quad Charts Report Date: 3/31/2012 Narrative Summary and Highlights Schedule - Based on critical path analysis, this project is behind schedule by 3 weeks, declining slightly, and is predicted to finish 3 weeks Trend / behind schedule, and holding steady. Caution is advised given the following assessment of WBS 3.1.5. Metric % Comp Variance Poor schedule performance on WBS 3.1.5, "Firmware Development" has put it on the critical path. All 5 weeks of float have been Schedule: SPI(t): 0.95 NA Holding steady consumed. The team is struggling to implement a new RTOS and ethernet core. The team is bringing in an expert from the RTOS vendor to ES(t), AD(t) (wks): 19 22 33% (3) wks Declining slightly help address these issues and finish Firmware development. Lesson learned - dig deper for risks during the planning phase and mitigate BAC(t), EAC(t): 12/01/12 12/18/12 (3) wks Holding steady the risk with budget, reserve, and adequate/expert resources. BTC(t), ETC(t) (wks): 35.0 37.5 NA NA Strong schedule performance on WBS 3.1.4, "Software Development" has removed it from the critical path. Performance will continue TSPI(t) [BAC, EAC]: 1.09 1.06 NA NA Cost: CPI($): 0.95 NA Holding steady to be monitored in case it needs to be tracked back to the critical path. EV($), AC($): $ 548,331 $ 574,405 49% ($26,074) Improving slightly Cost - Cost performance reveals that the project is slightly over budget and improving slightly. Caution is advised given the struggles BAC($), EAC($): $ 1,115,316 $ 1,144,148 ($28,832) Improving slightly mentioned above on WBS 3.1.5, which may have a ripple effect on overall cost performance. The entire project team has been advised to BTC($), ETC($): $ 540,911 $ 569,742 NA NA watch their budgets closely and to seek efficiencies to mitigate possible ripples. TCPI($) [BAC, EAC]: 1.05 1.02 NA NA Schedule Summary Cost Summary ($) % Work Cumulative to Date Last 4 Weeks Pg Chart Title Comp BAC(t) EAC(t) SPI(t) BAC EAC EV AC CPI EV AC CPI 1 Summary and Highlights NA NA NA NA NA NA NA NA NA NA NA NA 1 Table of Contents NA NA NA NA NA NA NA NA NA NA NA NA 3 Labor Summary NA NA NA NA NA NA NA NA NA NA NA NA 4 Critical Path - Schedule Analysis 35% 12/01/12 12/18/12 0.95 $ 321,790 $ 365,516 $ 112,693 $ 131,189 0.86 $ 16,545 $ 24,598 0.67 5 Rollup - Project 10FP17 49% 12/08/12 11/30/12 1.00 $ 1,115,316 $ 1,144,148 $ 548,331 $ 574,405 0.95 $ 97,956 $ 86,821 1.13 6 Rollup - WBS 1.0, PM, PC, and PE 40% 12/01/12 12/01/12 1.00 $ 404,840 $ 429,440 $ 160,540 $ 172,268 0.93 $ 27,920 $ 28,103 0.99 7 WBS: 1.1, Program Management 40% 12/01/12 12/01/12 1.00 $ 139,200 $ 163,172 $ 55,200 $ 66,543 0.83 $ 9,600 $ 9,178 1.05 8 WBS: 1.2, Program Control 40% 12/01/12 12/01/12 1.00 $ 18,850 $ 20,393 $ 7,475 $ 8,173 0.91 $ 1,300 $ 1,219 1.07 9 WBS: 1.3, Project Engineering 40% 12/01/12 12/01/12 1.00 $ 246,790 $ 245,875 $ 97,865 $ 97,552 1.00 $ 17,020 $ 17,706 0.96 10 Rollup - WBS 2.0, Material, Travel, and ODCs 75% 12/08/12 08/27/12 1.48 $ 89,300 $ 88,394 $ 66,983 $ 71,756 0.93 $ 5,390 $ 4,323 1.25 11 WBS: 2.1, Material 77% 12/08/12 05/03/12 2.53 $ 84,500 $ 82,945 $ 65,100 $ 69,323 0.94 $ 4,700 $ 4,323 1.09 12 WBS: 2.2, Travel 39% 10/13/12 09/23/12 1.38 $ 4,800 $ 6,299 $ 1,883 $ 2,433 0.77 $ 690 $ - 13 Rollup - WBS 3.0, NRE 52% 12/01/12 12/01/12 1.00 $ 621,176 $ 631,418 $ 320,808 $ 330,381 0.97 $ 64,646 $ 54,395 1.19 14 Rollup - WBS 3.1, Design Engineering 73% 06/23/12 06/23/12 1.00 $ 433,328 $ 440,080 $ 314,598 $ 322,919 0.97 $ 62,116 $ 51,410 1.21 15 WBS: 3.1.1, HW Development - CI#1 90% 04/14/12 03/29/12 1.00 $ 55,193 $ 64,965 $ 49,674 $ 54,706 0.91 $ 8,831 $ 5,659 1.56 16 WBS: 3.1.2, HW Development - CI#2 72% 05/19/12 06/19/12 0.85 $ 52,768 $ 58,719 $ 37,993 $ 42,546 0.89 $ 9,498 $ 4,052 2.34 17 WBS: 3.1.3, HW Development - CI#3 75% 06/23/12 06/06/12 1.18 $ 58,782 $ 49,154 $ 44,087 $ 37,609 1.17 $ 11,756 $ 3,959 2.97 18 WBS: 3.1.4, SW Development 75% 06/23/12 05/28/12 1.14 $ 152,625 $ 122,182 $ 114,469 $ 95,225 1.20 $ 27,473 $ 17,847 1.54 19 WBS: 3.1.5, FW Development 60% 05/19/12 06/19/12 0.85 $ 113,960 $ 154,740 $ 68,376 $ 92,834 0.74 $ 4,558 $ 19,893 0.23 20 Rollup - WBS 3.2, Prototype Production 45% 05/26/12 05/26/12 1.00 $ 13,800 $ 15,821 $ 6,210 $ 7,461 0.83 $ 2,530 $ 2,985 0.85 © 2012 SCOBEN Data Solutions. All rights reserved. Page 1 of 27 4/4/2012
  • 2. Schedule Summary Cost Summary ($) % Work Cumulative to Date Last 4 Weeks Pg Chart Title Comp BAC(t) EAC(t) SPI(t) BAC EAC EV AC CPI EV AC CPI 21 WBS: 3.2.1, Production - CI#1 100% 03/17/12 03/17/12 1.13 $ 4,600 $ 5,144 $ 4,600 $ 5,144 0.89 $ 1,380 $ 1,178 1.17 22 WBS: 3.2.2, Production - CI#2 30% 04/21/12 04/21/12 1.00 $ 4,600 $ 4,807 $ 1,380 $ 1,571 0.88 $ 920 $ 1,060 0.87 23 WBS: 3.2.3, Production - CI#3 5% 05/26/12 05/26/12 1.00 $ 4,600 $ 5,116 $ 230 $ 746 0.31 $ 230 $ 746 0.31 24 Rollup - WBS 3.3, System Integration 0% 08/18/12 08/18/12 $ 85,248 $ 85,248 $ - $ - $ - $ - 25 Rollup - WBS 3.4, System Ver. and Qual. 0% 12/01/12 12/01/12 $ 88,800 $ 88,800 $ - $ - $ - $ - 26 WBS: 3.4.1, System Verification 0% 09/22/12 09/22/12 $ 29,600 $ 29,600 $ - $ - $ - $ - 27 WBS: 3.4.2, Environmental Qualification 0% 12/01/12 12/01/12 $ 59,200 $ 59,200 $ - $ - $ - $ - © 2012 SCOBEN Data Solutions. All rights reserved. Page 2 of 27 4/4/2012
  • 3. Labor Summary for 10FP17 Report Date: 3/31/2012 Sorted by Name Sorted by WBS Hrs for w/e Cumulative Hrs for w/e Cumulative Name Cost Acct WBS 3/31/2012 to Date Hrs WBS Cost Acct Name 3/31/2012 to Date Hrs Braun, Ryan 10FP17.3.1.2 3.1.2 106 1.1 10FP17.1.1 Pujols, Albert 20 580 Braun, Ryan 10FP17.3.1.3 3.1.3 75 1.2 10FP17.1.2 Rollins, Jimmy 4 114 Cabrera, Miguel 10FP17.3.1.3 3.1.3 293 1.3 10FP17.1.3 Uggla, Dan 40 854 Ethier, Andre 10FP17.3.1.4 3.1.4 14 319 3.1.1 10FP17.3.1.1 Kershaw, Clayton 33 312 Ethier, Andre 10FP17.3.1.5 3.1.5 27 418 3.1.1 10FP17.3.1.1 Kinsler, Ian 7 71 Fielder, Prince 10FP17.3.2.1 3.2.1 131 3.1.1 10FP17.3.1.1 Mauer, Joe 27 Fielder, Prince 10FP17.3.2.2 3.2.2 7 40 3.1.1 10FP17.3.1.1 Scherzer, Max 170 Fielder, Prince 10FP17.3.2.3 3.2.3 6 12 3.1.2 10FP17.3.1.2 Braun, Ryan 106 Kershaw, Clayton 10FP17.3.1.1 3.1.1 33 312 3.1.2 10FP17.3.1.2 Kershaw, Clayton 19 Kershaw, Clayton 10FP17.3.1.2 3.1.2 19 3.1.2 10FP17.3.1.2 Kinsler, Ian 295 Kershaw, Clayton 10FP17.3.1.3 3.1.3 12 3.1.3 10FP17.3.1.3 Braun, Ryan 75 Kinsler, Ian 10FP17.3.1.1 3.1.1 7 71 3.1.3 10FP17.3.1.3 Cabrera, Miguel 293 Kinsler, Ian 10FP17.3.1.2 3.1.2 295 3.1.3 10FP17.3.1.3 Kershaw, Clayton 12 Lincecum, Tim 10FP17.3.2.3 3.2.3 7 3.1.4 10FP17.3.1.4 Ethier, Andre 14 319 Mauer, Joe 10FP17.3.1.1 3.1.1 27 3.1.4 10FP17.3.1.4 Rodriguez, Alex 26 476 Mauer, Joe 10FP17.3.1.5 3.1.5 7 192 3.1.5 10FP17.3.1.5 Ethier, Andre 27 418 Rodriguez, Alex 10FP17.3.1.4 3.1.4 26 476 3.1.5 10FP17.3.1.5 Mauer, Joe 7 192 Rollins, Jimmy 10FP17.1.2 1.2 4 114 3.1.5 10FP17.3.1.5 Scherzer, Max 98 Scherzer, Max 10FP17.3.1.1 3.1.1 170 3.1.5 10FP17.3.1.5 Weaver, Jered 6 118 Scherzer, Max 10FP17.1.3 3.1.5 98 3.2.1 10FP17.3.2.1 Fielder, Prince 131 Pujols, Albert 10FP17.1.3 1.1 20 580 3.2.2 10FP17.3.2.2 Fielder, Prince 7 40 Uggla, Dan 10FP17.1.3 1.3 40 854 3.2.3 10FP17.3.2.3 Fielder, Prince 6 12 Weaver, Jered 10FP17.3.1.5 3.1.5 6 118 3.2.3 10FP17.3.2.3 Lincecum, Tim 7 TOTAL 197 4739 197 4739 © 2012 SCOBEN Data Solutions. All rights reserved. Page 3 of 27 4/4/2012
  • 4. Project: 10FP17, ACME - Prototype Cryo Data Logger Development Chart Title: Critical Path - Schedule Analysis Planned Start/End Date: 10/29/11 12/01/12 Qualifiers: WBS: *, Dept: *, RU 1: *, RU 2: *, RU 3: CP Cost, Budget, EV Trends Schedule Performance $400.0 $9.0 2.0 02/15/13 Thousands Thousands $8.0 1.8 01/26/13 $350.0 Predicted Completion, EAC(t) Planned Completion, BAC(t) $7.0 1.6 $300.0 01/06/13 Performance Index, SPI(t) Cost Cumulative (Line Graph) Cost per Period (Bar Graph) 1.4 $6.0 $250.0 1.2 12/17/12 $5.0 $200.0 1.0 11/27/12 $4.0 0.8 11/07/12 $150.0 $3.0 0.6 $100.0 10/18/12 $2.0 0.4 $50.0 $1.0 0.2 09/28/12 $0.0 $0.0 0.0 09/08/12 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 Status Date Status Date Planned Value (PV) Actual Costs (AC) PV (Cumulative) AC (Cumulative) EV (Cumulative) Current BAC SPI(t) EAC(t) BAC(t) Predicted EAC 1 Cost Performance Project/Task Health Dashboard Planned Completion, BAC($) Thousands 2.0 $600 Trend / 1.8 Metric % Comp Variance Performance Index, CPI($) 1.6 $500 Schedule: SPI(t): 0.95 NA Predicted Completion, EAC($) ES(t), AD(t) (wks): 19 22 33% (3) wks 1.4 $400 BAC(t), EAC(t): 12/01/12 12/18/12 (3) wks 1.2 BTC(t), ETC(t) (wks): 35.0 37.5 NA NA 1.0 $300 TSPI(t) [BAC, EAC]: 1.09 1.06 NA NA 0.8 Hours: CPI(h): 0.88 NA $200 EV(h), AC(h): 1,082 1,225 32% (143) hrs 0.6 BAC(h), EAC(h): 3,385 3,746 (361) hrs 0.4 BTC(h), ETC(h): 2,160 2,521 NA NA $100 0.2 TCPI(h) [BAC, EAC]: 1.07 1.01 NA NA 0.0 $0 Cost: CPI($): 0.86 NA 00 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 EV($), AC($): $ 112,693 $ 131,189 35% ($18,496) BAC($), EAC($): $ 321,790 $ 365,516 ($43,726) BTC($), ETC($): $ 190,601 $ 234,327 NA NA TCPI($) [BAC, EAC]: 1.10 1.01 NA NA Status Date Commits($): $ - NA NA CPI($) EAC($) BAC($) Labor Rates (BC, AC): $ 99.93 $ 104.23 NA ($4.30) © 2012 SCOBEN Data Solutions. All rights reserved. Page 4 of 27 4/4/2012
  • 5. Project: 10FP17, ACME - Prototype Cryo Data Logger Development Chart Title: Rollup - Project 10FP17 Planned Start/End Date: 10/15/11 12/08/12 Qualifiers: WBS: *, Dept: *, RU 1: *, RU 2: *, RU 3: * Cost, Budget, EV Trends Schedule Performance $1,400.0 $35.0 2.0 02/05/13 Thousands Thousands 1.8 01/26/13 $1,200.0 $30.0 Predicted Completion, EAC(t) Planned Completion, BAC(t) 1.6 01/16/13 Performance Index, SPI(t) Cost Cumulative (Line Graph) $1,000.0 $25.0 Cost per Period (Bar Graph) 1.4 01/06/13 1.2 12/27/12 $800.0 $20.0 1.0 12/17/12 $600.0 $15.0 0.8 12/07/12 $400.0 $10.0 0.6 11/27/12 0.4 11/17/12 $200.0 $5.0 0.2 11/07/12 $0.0 $0.0 0.0 10/28/12 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 Status Date Status Date Planned Value (PV) Actual Costs (AC) PV (Cumulative) AC (Cumulative) EV (Cumulative) Current BAC SPI(t) EAC(t) BAC(t) Predicted EAC 1 Cost Performance Project/Task Health Dashboard Planned Completion, BAC($) Thousands 2.0 $1,800 Trend / 1.8 $1,600 Metric % Comp Variance Performance Index, CPI($) 1.6 Schedule: SPI(t): 1.00 NA Predicted Completion, EAC($) $1,400 ES(t), AD(t) (wks): 24 24 40% 0 wks 1.4 $1,200 BAC(t), EAC(t): 12/08/12 11/30/12 1 wks 1.2 BTC(t), ETC(t) (wks): 36.0 35.0 NA NA $1,000 1.0 TSPI(t) [BAC, EAC]: 1.00 1.01 NA NA $800 Hours: CPI(h): 0.94 NA 0.8 $600 EV(h), AC(h): 4,477 4,739 44% (262) hrs 0.6 BAC(h), EAC(h): 10,165 10,611 (446) hrs 0.4 $400 BTC(h), ETC(h): 5,426 5,872 NA NA 0.2 $200 TCPI(h) [BAC, EAC]: 1.05 1.01 NA NA 0.0 $0 Cost: CPI($): 0.95 NA 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 EV($), AC($): $ 548,331 $ 574,405 49% ($26,074) BAC($), EAC($): $ 1,115,316 $ 1,144,148 ($28,832) BTC($), ETC($): $ 540,911 $ 569,742 NA NA TCPI($) [BAC, EAC]: 1.05 1.02 NA NA Status Date Commits($): $ 4,773 NA NA CPI($) EAC($) BAC($) Labor Rates (BC, AC): $ 109.56 $ 110.69 NA ($1.13) © 2012 SCOBEN Data Solutions. All rights reserved. Page 5 of 27 4/4/2012
  • 6. Project: 10FP17, ACME - Prototype Cryo Data Logger Development Chart Title: Rollup - WBS 1.0, PM, PC, and PE Planned Start/End Date: 10/15/11 12/01/12 Qualifiers: WBS: *, Dept: *, RU 1: 1.0, RU 2: *, RU 3: * Cost, Budget, EV Trends Schedule Performance $500.0 $9.0 2.0 12/07/12 Thousands Thousands $450.0 $8.0 1.8 Predicted Completion, EAC(t) 12/02/12 Planned Completion, BAC(t) $400.0 $7.0 1.6 Performance Index, SPI(t) Cost Cumulative (Line Graph) Cost per Period (Bar Graph) $350.0 1.4 $6.0 11/27/12 $300.0 1.2 $5.0 $250.0 1.0 11/22/12 $4.0 $200.0 0.8 $3.0 11/17/12 $150.0 0.6 $100.0 $2.0 0.4 11/12/12 $50.0 $1.0 0.2 $0.0 $0.0 0.0 11/07/12 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 Status Date Status Date Planned Value (PV) Actual Costs (AC) PV (Cumulative) AC (Cumulative) EV (Cumulative) Current BAC SPI(t) EAC(t) BAC(t) Predicted EAC 1 Cost Performance Project/Task Health Dashboard Planned Completion, BAC($) Thousands 2.0 $460 Trend / 1.8 Metric % Comp Variance $450 Performance Index, CPI($) 1.6 Schedule: SPI(t): 1.00 NA $440 Predicted Completion, EAC($) ES(t), AD(t) (wks): 24 24 41% 0 wks 1.4 BAC(t), EAC(t): 12/01/12 12/01/12 0 wks 1.2 $430 BTC(t), ETC(t) (wks): 35.0 35.0 NA NA 1.0 $420 TSPI(t) [BAC, EAC]: 1.00 1.00 NA NA 0.8 Hours: CPI(h): 0.92 NA $410 EV(h), AC(h): 1,426 1,548 40% (122) hrs 0.6 $400 BAC(h), EAC(h): 3,596 3,851 (255) hrs 0.4 BTC(h), ETC(h): 2,048 2,303 NA NA 0.2 $390 TCPI(h) [BAC, EAC]: 1.06 1.01 NA NA 0.0 $380 Cost: CPI($): 0.93 NA 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 EV($), AC($): $ 160,540 $ 172,268 40% ($11,728) BAC($), EAC($): $ 404,840 $ 429,440 ($24,600) BTC($), ETC($): $ 232,572 $ 257,171 NA NA TCPI($) [BAC, EAC]: 1.05 1.01 NA NA Status Date Commits($): $ - NA NA CPI($) EAC($) BAC($) Labor Rates (BC, AC): $ 112.58 $ 111.52 NA $1.06 © 2012 SCOBEN Data Solutions. All rights reserved. Page 6 of 27 4/4/2012
  • 7. Project: 10FP17, ACME - Prototype Cryo Data Logger Development Chart Title: WBS: 1.1, Program Management Planned Start/End Date: 10/15/11 12/01/12 Qualifiers: WBS: 1.1, Dept: *, RU 1: *, RU 2: *, RU 3: * Cost, Budget, EV Trends Schedule Performance $180.0 $4.0 2.0 12/07/12 Thousands Thousands $160.0 1.8 $3.5 Predicted Completion, EAC(t) 12/02/12 Planned Completion, BAC(t) $140.0 1.6 $3.0 Performance Index, SPI(t) Cost Cumulative (Line Graph) Cost per Period (Bar Graph) 1.4 $120.0 11/27/12 $2.5 1.2 $100.0 $2.0 1.0 11/22/12 $80.0 0.8 $1.5 $60.0 11/17/12 0.6 $1.0 $40.0 0.4 11/12/12 $20.0 $0.5 0.2 $0.0 $0.0 0.0 11/07/12 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 Status Date Status Date Planned Value (PV) Actual Costs (AC) PV (Cumulative) AC (Cumulative) EV (Cumulative) Current BAC SPI(t) EAC(t) BAC(t) Predicted EAC 1 Cost Performance Project/Task Health Dashboard Planned Completion, BAC($) Thousands 2.0 $250 Trend / 1.8 Metric % Comp Variance Performance Index, CPI($) 1.6 $200 Schedule: SPI(t): 1.00 NA Predicted Completion, EAC($) ES(t), AD(t) (wks): 24 24 41% 0 wks 1.4 BAC(t), EAC(t): 12/01/12 12/01/12 0 wks 1.2 $150 BTC(t), ETC(t) (wks): 35.0 35.0 NA NA 1.0 TSPI(t) [BAC, EAC]: 1.00 1.00 NA NA 0.8 $100 Hours: CPI(h): 0.79 NA EV(h), AC(h): 460 580 40% (120) hrs 0.6 BAC(h), EAC(h): 1,160 1,411 (251) hrs 0.4 $50 BTC(h), ETC(h): 580 831 NA NA 0.2 TCPI(h) [BAC, EAC]: 1.21 1.02 NA NA 0.0 $0 Cost: CPI($): 0.83 NA 12/10/11 12/17/11 12/24/11 12/31/11 01/07/12 01/14/12 01/21/12 01/28/12 02/04/12 02/11/12 02/18/12 02/25/12 03/03/12 03/10/12 03/17/12 03/24/12 03/31/12 04/07/12 04/14/12 04/21/12 04/28/12 05/05/12 05/12/12 05/19/12 05/26/12 06/02/12 EV($), AC($): $ 55,200 $ 66,543 40% ($11,343) BAC($), EAC($): $ 139,200 $ 163,172 ($23,972) BTC($), ETC($): $ 72,657 $ 96,628 NA NA TCPI($) [BAC, EAC]: 1.16 1.02 NA NA Status Date Commits($): $ - NA NA CPI($) EAC($) BAC($) Labor Rates (BC, AC): $ 120.00 $ 114.73 NA $5.27 © 2012 SCOBEN Data Solutions. All rights reserved. Page 7 of 27 4/4/2012