The document summarizes a proposed project by Sierra Pacific Power Company (NV Energy) to rebuild and upgrade the Lahontan Substation on Reclamation-managed land in Nevada. The existing substation is beyond its useful life. The proposed project would involve constructing a new substation 200 feet from the existing one, upgrading equipment, building a new access road, and realigning transmission lines. An environmental assessment found the project would have minor, localized impacts but no significant effects on resources such as vegetation, wildlife, water, and cultural/historic sites. The Bureau of Reclamation approved the project and found it would not significantly affect the human environment.
US Court of Appeals for DC - EarthReports v Federal Energy Regulatory Commiss...Marcellus Drilling News
A decision by the U.S. Court of Appeals for the District of Columbia. Big Green groups, including the Sierra Club, the Chesapeake Climate Action Network, the Patuxent Riverkeeper, EarthReports Inc. and Earthjustice, colluded together to sue in federal appeals court to try and stop the Cove Point, Maryland LNG export project by claiming the Federal Energy Regulatory Commission should not have approved it. The court rejected their claim.
New Construction Stormwater Regulation in MinnesotaDan Schleck
Attorney Dan Schleck makes a presentation to the Builders Association of the Twin Cities (BATC) on new construction stormwater permitting and regulation in Minnesota
Range Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPAMarcellus Drilling News
A voluntary plan created and submitted by Range Resources to the Pennsylvania Dept. of Environmental Protection to permanently close (and restore) the Yeager wastewater impoundment (i.e. open pond) site in Amwell Township, located in Washington County, PA. The plan was tweaked by the DEP to require Range to test for certain compounds underneath the two liners in the impoundment--liners that, according to Range, had holes in both layers.
US Court of Appeals for DC - EarthReports v Federal Energy Regulatory Commiss...Marcellus Drilling News
A decision by the U.S. Court of Appeals for the District of Columbia. Big Green groups, including the Sierra Club, the Chesapeake Climate Action Network, the Patuxent Riverkeeper, EarthReports Inc. and Earthjustice, colluded together to sue in federal appeals court to try and stop the Cove Point, Maryland LNG export project by claiming the Federal Energy Regulatory Commission should not have approved it. The court rejected their claim.
New Construction Stormwater Regulation in MinnesotaDan Schleck
Attorney Dan Schleck makes a presentation to the Builders Association of the Twin Cities (BATC) on new construction stormwater permitting and regulation in Minnesota
Range Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPAMarcellus Drilling News
A voluntary plan created and submitted by Range Resources to the Pennsylvania Dept. of Environmental Protection to permanently close (and restore) the Yeager wastewater impoundment (i.e. open pond) site in Amwell Township, located in Washington County, PA. The plan was tweaked by the DEP to require Range to test for certain compounds underneath the two liners in the impoundment--liners that, according to Range, had holes in both layers.
California Coastal Commission revised staff report - Beach Chalet fieldsSFOceanEdge
This original Staff Report for the Beach Chalet presented the case for NOT approving the project. However, after intense political pressure was exerted on the Commission by leading California politicians, the report was rewritten to support destroying the environment at the end of Golden Gate Park and at Ocean Beach, San Francisco.
To learn more about this damaging project, go to www.sfoceanedge.org. Also view the video on youtube called Beach Chalet Fields Renovation, to see the beauty of this area that will be destroyed.
Be sure to download and read the full report. The crossed-out language is the original staff reporting, supporting protecting Golden Gate Park and Ocean Beach from over 7 acres of artificial turf and 150,000 watts of stadium lighting, that will be lighted until 10:00 pm every night of the year.
LCW Restoration Plan & EIR- Public Workshop #2TidalInlfluence
This presentation was presented at the second public workshop to familiarize the public with the consulting team's Draft Optimized Restoration Design. Members of the public were then able to ask questions and give feedback about the design of the 4 different project areas.
MITIGATION BANKING IS BAD!
My Opponent, Kick the Cannon, has been very negative of my Business with Wetland Mitigation Banking. However, did you know, that in 2017, The City of Winter Springs received a permit to IMPACT 0.63 Acres of Direct Wetland Impacts for the construction of several NEW FEATURES at TORCASO PARK!?
The City purchased 0.147 UMAM Credits which provided 2.5 Acres of Wetland Mitigation Credits from Torcaso Park from Lake Jesup Mitigation Tract.
Within the SJRWMD Technical Staff Report it actually states that the elimination or reduction of impacts was not required for the 0.63-acre direct impacts to W1 because the ecological value of the functions provided by the area of wetland to be adversely affected is low, and the proposed mitigation will provide greater long term ecological value than the area of wetland to be adversely affected, pursuant to Section 10.2.1.2(a.) ERP A.H. Volume I.
If you want to learn more about mitigation banking industry, please visit https://mitigationbankinginc.com/
Positive Declaration for Pilgrim Pipeline from NY DEC & Thruway AuthorityMarcellus Drilling News
A document instruction the proposed Pilgrim Pipeline, which is really two pipelines (one heading south from Albany to NJ carrying Bakken oil, the other north from NJ to Albany carrying gasoline and other refined products) will need to complete a full environmental review before the project will be considered. Both anti-fossil fuel freaks and the pipeline builders welcomed the news (strangely).
California Coastal Commission revised staff report - Beach Chalet fieldsSFOceanEdge
This original Staff Report for the Beach Chalet presented the case for NOT approving the project. However, after intense political pressure was exerted on the Commission by leading California politicians, the report was rewritten to support destroying the environment at the end of Golden Gate Park and at Ocean Beach, San Francisco.
To learn more about this damaging project, go to www.sfoceanedge.org. Also view the video on youtube called Beach Chalet Fields Renovation, to see the beauty of this area that will be destroyed.
Be sure to download and read the full report. The crossed-out language is the original staff reporting, supporting protecting Golden Gate Park and Ocean Beach from over 7 acres of artificial turf and 150,000 watts of stadium lighting, that will be lighted until 10:00 pm every night of the year.
LCW Restoration Plan & EIR- Public Workshop #2TidalInlfluence
This presentation was presented at the second public workshop to familiarize the public with the consulting team's Draft Optimized Restoration Design. Members of the public were then able to ask questions and give feedback about the design of the 4 different project areas.
MITIGATION BANKING IS BAD!
My Opponent, Kick the Cannon, has been very negative of my Business with Wetland Mitigation Banking. However, did you know, that in 2017, The City of Winter Springs received a permit to IMPACT 0.63 Acres of Direct Wetland Impacts for the construction of several NEW FEATURES at TORCASO PARK!?
The City purchased 0.147 UMAM Credits which provided 2.5 Acres of Wetland Mitigation Credits from Torcaso Park from Lake Jesup Mitigation Tract.
Within the SJRWMD Technical Staff Report it actually states that the elimination or reduction of impacts was not required for the 0.63-acre direct impacts to W1 because the ecological value of the functions provided by the area of wetland to be adversely affected is low, and the proposed mitigation will provide greater long term ecological value than the area of wetland to be adversely affected, pursuant to Section 10.2.1.2(a.) ERP A.H. Volume I.
If you want to learn more about mitigation banking industry, please visit https://mitigationbankinginc.com/
Positive Declaration for Pilgrim Pipeline from NY DEC & Thruway AuthorityMarcellus Drilling News
A document instruction the proposed Pilgrim Pipeline, which is really two pipelines (one heading south from Albany to NJ carrying Bakken oil, the other north from NJ to Albany carrying gasoline and other refined products) will need to complete a full environmental review before the project will be considered. Both anti-fossil fuel freaks and the pipeline builders welcomed the news (strangely).
Mountain Valley Pipeline, Analysis of Environmental IssuesJacqueline Tkac
The following report addresses the impacts of highest concern from residential community members as well as the scientific community. The primary focus of the report is on environmental impacts, especially relating to karst topography, but also addresses four non-environmental concerns of significant importance. These include economic issues, eminent domain, Appalachian culture, and community engagement. Our conclusions are based on a set of ten recommendations to the Federal Energy Regulatory Commission (FERC) and Mountain Valley Pipeline (MVP), LLC that outline the need for oversight, mitigation, community engagement, and cumulative impact analysis. The approval of the Mountain Valley Pipeline should be contingent on these recommendations.
NY DEC Letter Refusing to Grant Stream Crossing Permits for Constitution Pipe...Marcellus Drilling News
A totally bogus BS letter refusing to grant stream crossing permits for the much-needed Constitution Pipeline in New York State. Gov. Andrew Cuomo instructed the Dept. of Environmental Conservation to refuse the permits on political grounds--and this letter is the bogus excuses the DEC made up in order to cover Cuomo's political dictatorial decision.
3. FONSI LO-2012-1023 July 2014
1
Background and Purpose and Need
The Bureau of Reclamation (Reclamation) Lahontan Basin Office has evaluated the potential
environmental consequences of the construction of a new substation, and abandonment and
removal of the existing substation by Sierra Pacific Power Company dba NV Energy (NV
Energy) on Reclamation-managed land. The project is called the Lahontan Substation Rebuild
and Upgrade Project (Project). The existing Lahontan Substation was constructed in the 1950s
and is beyond its useful life. The substation is the primary source for customers in the Fallon,
Nevada, area as well as the Naval Air Station, and brings geothermal generation into
NV Energy’s system from the Stillwater, Nevada area. Upgrades to the substation are necessary
to more reliably serve NV Energy’s customers. The need for the Proposed Action is to bring the
Lahontan Substation facilities up-to-date and get them operating in a reliable fashion, and
authorization and issuance of a license is needed for the construction of a new substation on
Reclamation-managed lands.
In accordance with the National Environmental Policy Act (NEPA), an Environmental
Assessment (EA) was prepared for the utilization of Reclamation-managed land. The EA
considered two alternatives: the Proposed Action and the No-Action Alternative. The EA was
prepared by NV Energy under the direction of Reclamation.
In addition to the NEPA, actions of Reclamation are guided by a number of statutes, regulations,
and agreements, including Endangered Species Act (ESA), Clean Water Act, National Historic
Preservation Act (NHPA), and other pertinent state, local, or county regulations. Opportunities
were provided for public review of and comment on the EA. Scoping letters for the EA were
mailed to interested parties and the Fallon Paiute-Shoshone Tribe of west-central Nevada on
October 24, 2013. The letter announced the preparation of an EA and requested comments on
the proposed Project. Reclamation reviewed and considered all comments received.
Alternatives Including Proposed Action
No-Action Alternative
Under the No-Action Alternative, Reclamation would not approve NV Energy’s SF-299
Application for the construction of a new substation. The existing substation would remain in
use, no new substation facilities would be constructed, and reliability of the electrical service to
the Fallon, Nevada area and the Naval Air Station may diminish over time.
Proposed Action
The Proposed Action is to issue a license for NV Energy’s SF-299 Application for the
construction of a new substation, which would be adjacent to the existing Lahontan Substation
on lands under Reclamation’s jurisdiction, located in Churchill County, Nevada. The Project
would consist of rebuilding the Lahontan Substation approximately 200 feet to the northeast of
the existing site, and would involve the installation of a 4.5/7.5 Million Volt-Amperes (MVA)
regulator, seven 69-kilovolt (kV) circuit breakers, a 69-kV circuit switcher, instrument
transformers, service transformers, switches, capacitor bank, new control enclosure to
accommodate new protection panels, new remote terminal unit (RTU), and telecom
4. FONSI LO-2012-1023 July 2014
2
infrastructure, including fiber optic cables. In addition to the substation components, NV Energy
proposes to construct a new 200-foot access road and to realign six 60-kV transmission lines.
The 60-kV transmission line realignments would require the removal of approximately
18 existing wood single-pole structures and the placement of approximately five new wood
single-pole tangent structures and 12 new wood single-pole angle structures. Ground
disturbance for the proposed Project would include approximately 14.8 acres of construction
disturbance. Of those 14.8 acres, approximately 2.3 acres would be permanent ground
disturbance for the substation site, 200 feet of access road, and approximately 17 new structure
locations.
The existing Lahontan Substation would be deconstructed and removed, however the perimeter
fence and gravel surface would be left for use as a storage area by the Nevada Division of State
Parks. Deconstruction of the existing substation would include the removal of the above-ground
equipment. Concrete and steel foundations would be left in place along with the existing gravel
surface and perimeter fencing. Oil spills on the existing site would be cleaned by removing
contaminated soil.
Findings
Based on the attached EA, Reclamation finds that the Proposed Action will not significantly
affect the quality of the human environment. The attached EA describes the existing
environmental resources in the Project area, evaluates the effects of the No Action and Proposed
Action Alternatives on the resources, and proposes measures to avoid, minimize, or mitigate any
adverse effects. This EA was prepared in accordance with the NEPA (42 United States Code
4321-4347), Council of Environmental Quality Regulations for implementing the procedural
requirements of the NEPA (40 Code of Federal Regulations [CFR] 1500–1508), and the
Department of the Interior NEPA regulations (43 CFR Part 46).
Effects on several environmental resources were examined and any adverse impacts are minor
and restricted to short-term, localized events. No significant effects were identified for any
resource. This analysis is provided in the attached EA, and the analysis in the EA is hereby
incorporated by reference.
Cultural and Archaeological Resources
Reclamation identified one historic property within the area of potential effect (APE), the Fallon
Cutoff segment (CrNV-03-5419), and multiple historic properties adjacent to the APE and
related to the Newlands Project (Lahontan Dam and Power Plant, Truckee Canal, Lahontan Dam
government camp, and Lahontan City). Although located within the Project APE, the Fallon
Cutoff segment would not be adversely affected by the Project. Indirect effects, largely visual in
nature, are considered to be minimal given the amount of development in the area and the fact
that power transmission infrastructure has long been an element of the local landscape as well as
a subordinate component of the Newlands Project.
Reclamation initiated consultation with the Nevada State Preservation Office (SHPO) by letter
and SHPO responded July 22, 2014, concurring with Reclamation’s determination of no adverse
effect to historic properties. The proposed action will not have significant impacts on properties
5. FONSI LO-2012-1023 July 2014
3
listed, or eligible for listing, on the National Register of Historic Places and will result in no
adverse effect to historic properties pursuant to 36 CFR Part 800.5(a)(1).
Indian Trust Assets
No land or trust income resources would be affected by the Proposed Action, as there are no trust
assets in the proximity of the Project.
Indian Sacred Sites
There will be no impacts that would adversely affect the physical integrity of Indian Sacred Sites
and that access to, or ceremonial use of such sites would not be restricted because there are no
known sites within the project area.
Geologic Hazards, Mineral Resources, and Soil Resources
The Project site does not include any mineral resource locations; therefore, there would be no
Project-associated impacts on these resources. The potential for geologic hazards, such as
earthquakes, that could impact the Project site is low. Effects on soil resources are linked to
ground-disturbing activities that would be closely associated with vegetation clearing and
grading of the substation site, access road, and transmission-pole locations. Proper mitigation
measures would be required during construction of the Proposed Action in order to avoid or
minimize damage resulting from erosion and to prevent acceleration of soil erosion beyond
natural levels.
Land Use and Recreation
The Proposed Action presents a minimal direct-land-use impact within the study area because
the Project site, access road, and transmission structure locations are located on land that is
currently vacant and adjacent to the existing substation site and transmission lines. Minimal
changes to recreational opportunities would result through the implementation of the Proposed
Action.
Vegetation and Special-Status Plants
There will be approximately 14.8 acres of temporary ground disturbance and of the 14.8 acres,
2.3 acres of permanent ground disturbance of native Intermountain Basins Mixed Salt Desert
Scrub would occur to allow for construction of the proposed substation, access road, and
transmission lines. Intermountain Basins Mixed Salt Desert Scrub is a regionally abundant
vegetation community with relatively low species diversity. Riparian and wetland vegetation
within the Project site boundary would not be affected by the Proposed Action.
No special-status plants would be affected by the Proposed Action. The single Sagebrush Cholla
observed within the site boundary is not located in an area that would be disturbed as a result of
the Proposed Action.
6. FONSI LO-2012-1023 July 2014
4
Visual Resources
Impacts to scenic quality are anticipated to be low/moderate for the Proposed Action because of
existing structures and access roads. Impacts to viewers, including recreation, travelers, and
residents, are anticipated to be low to moderate for the Project.
Water Resources
The likelihood for the Proposed Action to impact surface water or groundwater quality is
minimal.
Wildlife and Special-Status Wildlife
Approximately 14.8 acres of native vegetation would be temporarily disturbed under the
Proposed Action. Although some wildlife would be present, the low diversity and productivity
of vegetation within the Project site does not support a high diversity of wildlife species. The
extent of temporary and permanent disturbance associated with the Project is not anticipated to
affect local or regional populations of any species.
Special-status bat species are anticipated to primarily forage along the Carson River and nearby
wetlands, rather than the low-productivity vegetation within the site boundary. The Pale
Kangaroo Mouse and special-status birds may occur within the site boundary. Preconstruction
surveys for Pale Kangaroo Mouse burrows would indicate whether avoidance or relocation
would be recommended. Preconstruction nesting bird surveys would take place prior to any
construction activities during the nesting season, typically from March through August.
Air Quality and Noise
Project construction activities would produce fugitive dust and engine emissions. Ground
disturbing activities that would result in fugitive dust include site preparation for the new
substation site, erecting new transmission structures, removing existing transmission structures,
and removing equipment from the existing substation site. Emissions from construction engines
and fugitive dust would be short term and occur during the six months of construction activities.
Best management practices (BMPs), such as watering during ground disturbing activities, would
reduce impacts to air quality.
Climate Change
The Project would produce greenhouse gases during the approximately six-month period of
construction, through vehicle and equipment fuel burning, and are not expected to produce
appreciable cumulative effects to greenhouse gas emissions.
Environmental Justice
Environmental justice is not affected by the Proposed Action, because there are no
disproportionately high and adverse effects on minority or low-income populations.
7. FONSI LO-2012-1023 July 2014
5
Cumulative Effects
Impacts to cultural and archaeological resources could occur if unanticipated discoveries were
made during construction activities, however, based on the detailed Class III cultural inventory,
cultural resource impacts are anticipated to be insignificant. Visual impacts are related to the
introduction of new facilities into the landscape, ground disturbance, the presence of existing
facilities, and sensitive viewers. Cumulative impacts from the Project would be reduced because
the new facilities would replace existing facilities, and there are similar types of industrial and
utility facilities in the area of influence. Based on the relatively small permanent ground
disturbance (2.3 acres), the temporary construction activity period, and the use of BMPs,
cumulative impacts to soil resources, land use, recreation, vegetation, water resources, wildlife,
air quality and noise, and climate change are expected to be minimal.
Consultation and Coordination
This section describes the consultation and coordination activities Reclamation has carried out
with interested agencies, organizations, tribes, and individuals while preparing the EA. The
NEPA and Council on Environmental Quality (CEQ) regulations require the public’s
involvement in the decision-making process, as well as allow for full environmental disclosure.
Copies of the letters and the mailing list are included as an appendix to the EA.
Scoping letters for the EA were mailed to interested parties and tribes on October 24, 2013. The
letter announced the preparation of an EA and requested comments on the proposed Project.
One comment letter was received during Scoping from the National Park Service (NPS). The
comment provided by the NPS National Trails Intermountain Region Archaeologist verified the
location of the California National Historic Trail in relation to the Project, called attention to
additional potential cultural resources within the Project vicinity, and noted that any trail remnant
in that area would have likely been destroyed by previous development.
The Draft EA was provided for a 15-day public review and comment period on May 14, 2014 at
www.usbr.gov/mp, at the Churchill County Library, and at the Bureau of Reclamation, Lahontan
Basin Area Office which is located in Carson City, Nevada. A news release was issued and
notice of availability was sent to those on the mailing list. No new comments were received
during the comment period.
Decision
Based on the analysis of the environmental impacts, as described in the Final EA and on
thorough review of public comments received, Reclamation has determined that implementing
the Proposed Action will not have a significant impact on the quality of the human environment
or the natural resources of the area. A Finding of No Significant Impact is justified for the
Proposed Action. Therefore, an environmental impact statement is not necessary to further
analyze the environmental effects of the Proposed Action.