SlideShare a Scribd company logo
Amritanshu Kumar
(GET)
Training Mentor: M. Ramakrishna
Plant : Hosur
Final Year Review
Unit II’s Electrical Work
Project Mentor : M. Ramakrishna
Project Guide : Nitin Saxena
End to End supervision of all HT/LT electrical works
 Lighting work of Unit II
Studying Feasibility of Solar On Grid Model in Plant
Overview about Unit II’s Electrical
Status
Total Contract Load:- 950 KVA with 3 phase supply at 415 V
Transformer:- 2000 KVA (11KV/440V)
DG Sets:- Two of 500 KVA each & one of 365 KVA along with synchronizing Panel
Unit II’s SLD :-
MAIN SLD.pdf
Methodology Adopted
• Job Assigned :-
 To look after end to end all HT/LT works along with maintaining all quality and
safety standards
 To take initiatives towards adopting some new models in electrical like in
lighting, new development etc..
• Methodology adopted :-
• Made electrical log book to track day to
day work as well as material’s flow
• To keep crisp communication with
contractor to smoothen all electrical
processes
• To validate all electrical works are as per
TNEB norms
Unit II’s Electrical Works
HT Side Works LT Side Works
1. DP Structure Erection 1.LT Panel Room Work
2. HT Cable Laying 2.MCC Panel Room
Work
3. RMG Unit Installation 3. LT Room to MCC
Room Cable Laying
4. VCB Panel Installation 4. All Light fittings job
5. Transformer Installation 5. All internal cabling
• Examples of HT/LT Side work:-
DP Structure Erection (HT Work)
Motor Cable Laying (LT Work)
Learnings LT Cables
PCC Panel
DG Earthing
Saving Through Value Engineering
Item Description
New Purchase Value
(Lacs)
Reconditioning Value
(Lacs)
Savings
(Lacs)
2000 KVA Transformer 20 4.5 15.5
HT switch (near transformer) 14 0.5 13.5
PCC panel 36 16.5 19.5
SSB panel 2.5 1.15 1.35
Capacitor panel 2.5 0.95 1.55
Switchgears 17.5 6.25 11.25
Transformer yard fencing 1 0.25 0.75
Old LT Cables re use 5 0 5
Total expenditure in Rs –Lacs 98.5 30.1 68.4
Savings through Value Engineering (Electrical) :- 68.4
Lacs
Before & After Pictures
BEFORE AFTER
DP Structure Area
HT Cable Laying
Work
Before & After Pictures
BEFORE AFTER
LT / PCC Room
MCC Room
Before & After Pictures
BEFORE AFTER
Lighting Works
Transformer Installation
• Learnings
 Transformer various parts and
associated parts like OLTC, RTCC
 Transformer Oil Filtration process
 Various test performed before
transformer installation
• Findings
During insulation test, we found
that insulation of LT side was
malfunctioning
However, later faulty insulators
were removed with healthier ones
and test certificate was obtained on
above
LT’s Insulator
2000 KVA Transformer
Unit II’s Lighting Works
• Methodology Adopted
 Our objective was to fit lighting system which should have following features :-
1. Low Power Consumption & Better Life
2. Better Efficacy and CRI
3. Optimum Price
 So we decided to go for combination of LED & T5 lights in order to achieve
optimum quality and cost
• Advantages of LED lights
1.Energy savings between 40%-80% and have life up to 5 times than normal lights.
2.Efficacy level is above 100 in both LED & T5 Lights and LED has best CRI
Savings & Learnings
• Savings
 Apart from our electrical contractor, parallel we also took quotes from other two
vendors and thus able to bring down lighting price from our contractor.
• Lighting Techno Commercial Sheet :-
• Total Savings after negotiations 3.62 lacs
• Learnings
 Knowledge about various types of light, their working principles, features
 Brief Overview about designing of Light fixtures
 Learnt about Solar Lights & it’s working
Microsoft Excel
97-2003 Worksheet
Lighting Fixture
S. No. Area Light Type Description Watt Quantity
1 HARPIC MFG AREA LED
Totally enclosed LED Tubes + LED 2X2 Luminaire
with IP65 Protection
32/39 16 +8
2 LIIZOL & COLIN-Mfg LED Totally enclosed LED Tube 39 16
3 HARPIC FILLING AREA LED
LED 2X2 Luminaire suitable for Recessed on
Grid / POP ceiling with IP65 Protection
32 16
4 LIZOL & COLIN FILLING LED
LED 2X2 Luminaire suitable for Recessed on
Grid / POP ceiling
32 28
5 ALPLA Plant T5 T5 Highbay enclosed type (4X32W) 128 74
6 Packaging Area T5 T5 Highbay enclosed type (4X32W) 128 10
7 FG Store Area
Metal Halide
+T5
Flood Light + T5 Highbay enclosed type (4X32W) 250/128 6+5
8 Quality Lab LED
LED 2X2 Luminaire suitable for Recessed on
Grid / POP ceiling
32 20
9 Street Light Metal Halide Mercury Halide with IP66 Protection 150 15
10 Solar Light LED
26W LED street light with 100W Solar panel, 12
V 80AH Voltamp Make Battery & 20 feet GI Pole
26 5
Lighting Contd..
Harpic Filling Area Harpic Mfg. Area
Street Light
Quality Lab
SolarStreetLight
Solar Auto-Grid Project
Energy Cost has Increased by
about 93 %
• About Solar On Grid Project :-
Works on principle of Net Metering System
Can Install Solar Panel Grid either on roof top or
ground
Have life of about 25 years with very less
degradation in it’s efficiency
Maintenance free operation
Levellized Cost Of Electricity (Solar) is
between Rs 5-6
Solar Auto-Grid Project Contd..
• Hosur Plant Potential
 Each KW of Solar Panel can generate about 5 Units per day and require about
100 Sq. Feet of area
 In Unit II, we are having roof top area of about 2000 sq. mts above LT Panel
room while having land availability of about 5600 sq. mts on the south west
• Work Progress on Solar On-Grid
 Already talked with three vendors and we decided to 1st
install 30 KW of Solar
Panel Grid System as a pilot project
 Techno Commercial Sheet :-
 Cost Of Installation :- Rs. 25 lacs
 Payback Period :- Rs. 5 years
Microsoft Excel
97-2003 Worksheet
Benefits & Learnings
• Benefits
• Learnings
Learnt about Solar On Grid System, working
principle etc..
Knowledge about various types of solar panels,
their features etc..
Factory Procurement & Planning
Project Guide : M. Shujauddin
 Learnings about Procurement & Logistic various functioning
 Project on RM & PM Planning of Unit II
Learnings
• Steps Involved In material movement inside Plant
Learnings
• Various documents required for FG transfer
For Stock Transfer For FG Sales
1. Stock Transfer Copy 1. Sales Invoice Copy
2. Excise Invoice Copy 2. Delivery Challan/Gate Pass
3. Delivery Challan/Gate Pass 3. Road Permit
4. Form JJ ( By TN Govt.)
5. Road Permit
RM PM Planning (Unit II)
• Why needed ??
 As to start production in Unit II, we need to have a system to manage the
RM/PM stocks as per our production plan
 A Planning sheet was need to be developed which gives all RM/PM
requirements as per no. of cases to be produced as per plan.
 Products going to be manufactured under Unit II
1. Harpic (Harpic Power Opti Thick)
2. Lizol (Pine, Citrus, Lavender, Sandal, Floral)
3. Colin (Colin Blue)
Methodology Adopted
Microsoft Excel
Worksheet
Microsoft Excel
97-2003 Worksheet
Learnings & Outcomes
 Learnings
 Basic knowledge about master BOM & Bulk BOM
 Knowledge regarding terms like scrap factor, why to include it etc..
 Brief overview about how production planning is done
 Outcomes
 On the basis of RM/PM planning sheet made, RM/PM requirement (for July-
Dec’15) as per our tentative production plan was forecasted
 Forecasted sheet validate the logic used behind RM/PM planning sheet
formation
Factory HR
Project Guide : Pavan Kumar
 Learnings about various Factory & Labour Laws
 Job Description & Skill Matrix formation for Unit II
Job Description & Skill Matrix
Making
• Job Description Sheet
 To carry out various operations inside Unit II, new requirement was required &
accordingly Job Description for various post were made.
 JDs were made for the following posts:-
1. Trainee Associate – Electrical
2. Trainee Associate – Mechanical
3. Trainee Associate – Production
4. IPQC (Contractual)
5. DG & LT Room (Contractual)
6. RODM Plant (Contractual)
7. Unskilled labours (Contractual)
Microsoft Excel
97-2003 Worksheet
Job Description & Skill Matrix
Making
• Skill Matrix Making
 To evaluate the performance of all operators, chemist in nearby future; skill
matrix was made
 Color Coding system is used to show the performance of each individual as it
makes skill matrix tracking lot easier and simpler
 Whole Unit II operators and chemist performance figure was summarized on
single sheet
Microsoft Excel
97-2003 Worksheet
Contract Labour Act 1970
Employees Provident Fund Act 1952
Rates Of Contribution
Scheme Employee’s Employers Central Govt.
PF 12 % 3.67 % NIL
EDLI NIL 0.5 % NIL
PS NIL 8.33 % 1.16 %
Employees State Insurance Act 1948
Factories Act 1948
Factory Act 1948
• Audit Findings
 A certified doctor must visit the plant twice in a week, eight times a month but only
3 visit in a month is taking place
 One qualified & trained dresser cum compounder on duty throughout working
period not available
 In safety practices, plant’s level of safety is up to the mark & every process is
going as per standard safety procedure
 In welfare section & working hour of adults all process are carrying out through
standard procedure
 Person below 18 years are not allowed to work, so employment of young person
not applicable
Microsoft Excel
Worksheet
Thanks

More Related Content

What's hot

Gurpreet singh (MEP services manager with 9.8 year Exp)
Gurpreet singh (MEP services manager with 9.8 year Exp)Gurpreet singh (MEP services manager with 9.8 year Exp)
Gurpreet singh (MEP services manager with 9.8 year Exp)Gurpreet Singh
 
J010316164
J010316164J010316164
J010316164
IOSR Journals
 
Deep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building StandardsDeep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building Standards
SustainableEnergyAut
 
Uhde Shedden Project Undertaken
Uhde Shedden Project UndertakenUhde Shedden Project Undertaken
Uhde Shedden Project UndertakenMichael Macek
 
Greener Greater Building Plan Overview
Greener Greater Building Plan Overview Greener Greater Building Plan Overview
Greener Greater Building Plan Overview
REBNY
 
Examples of NZEB in the Public Sector by John Furlong
Examples of NZEB in the Public Sector by John FurlongExamples of NZEB in the Public Sector by John Furlong
Examples of NZEB in the Public Sector by John Furlong
SustainableEnergyAut
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Abdul Alim Dewan
 
NZEB Office Building including renewable energy ratio calculation orla coyle
NZEB Office Building including renewable energy ratio calculation  orla coyleNZEB Office Building including renewable energy ratio calculation  orla coyle
NZEB Office Building including renewable energy ratio calculation orla coyle
SustainableEnergyAut
 
VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCE
VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCEVIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCE
VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCEvijayabaskar v
 
MPC Tuning Based On Desired Frequency Domain Closed Loop Response
MPC Tuning Based On Desired Frequency Domain Closed Loop ResponseMPC Tuning Based On Desired Frequency Domain Closed Loop Response
MPC Tuning Based On Desired Frequency Domain Closed Loop Response
Ryvo Octaviano
 
Fabic in Schools by Niall Lowther
Fabic in Schools by Niall LowtherFabic in Schools by Niall Lowther
Fabic in Schools by Niall Lowther
SustainableEnergyAut
 
Tuning PID Controller Parameters for Load Frequency Control Considering Syste...
Tuning PID Controller Parameters for Load Frequency Control Considering Syste...Tuning PID Controller Parameters for Load Frequency Control Considering Syste...
Tuning PID Controller Parameters for Load Frequency Control Considering Syste...
IJERA Editor
 

What's hot (20)

CV-Project Manager
CV-Project ManagerCV-Project Manager
CV-Project Manager
 
Gurpreet singh (MEP services manager with 9.8 year Exp)
Gurpreet singh (MEP services manager with 9.8 year Exp)Gurpreet singh (MEP services manager with 9.8 year Exp)
Gurpreet singh (MEP services manager with 9.8 year Exp)
 
J010316164
J010316164J010316164
J010316164
 
Behnam Nikouei resume
Behnam Nikouei resumeBehnam Nikouei resume
Behnam Nikouei resume
 
Deep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building StandardsDeep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building Standards
 
Uhde Shedden Project Undertaken
Uhde Shedden Project UndertakenUhde Shedden Project Undertaken
Uhde Shedden Project Undertaken
 
Greener Greater Building Plan Overview
Greener Greater Building Plan Overview Greener Greater Building Plan Overview
Greener Greater Building Plan Overview
 
Examples of NZEB in the Public Sector by John Furlong
Examples of NZEB in the Public Sector by John FurlongExamples of NZEB in the Public Sector by John Furlong
Examples of NZEB in the Public Sector by John Furlong
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017
 
MOHAN_Final
MOHAN_FinalMOHAN_Final
MOHAN_Final
 
NZEB Office Building including renewable energy ratio calculation orla coyle
NZEB Office Building including renewable energy ratio calculation  orla coyleNZEB Office Building including renewable energy ratio calculation  orla coyle
NZEB Office Building including renewable energy ratio calculation orla coyle
 
VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCE
VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCEVIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCE
VIJAYABASKAR_ELECTRICAL _8YEARS_EXPERIENCE
 
MPC Tuning Based On Desired Frequency Domain Closed Loop Response
MPC Tuning Based On Desired Frequency Domain Closed Loop ResponseMPC Tuning Based On Desired Frequency Domain Closed Loop Response
MPC Tuning Based On Desired Frequency Domain Closed Loop Response
 
Resume
ResumeResume
Resume
 
CV_Poliarco,Romeo
CV_Poliarco,RomeoCV_Poliarco,Romeo
CV_Poliarco,Romeo
 
Resume140515
Resume140515Resume140515
Resume140515
 
cv ehab
cv ehabcv ehab
cv ehab
 
Fabic in Schools by Niall Lowther
Fabic in Schools by Niall LowtherFabic in Schools by Niall Lowther
Fabic in Schools by Niall Lowther
 
mandal
mandalmandal
mandal
 
Tuning PID Controller Parameters for Load Frequency Control Considering Syste...
Tuning PID Controller Parameters for Load Frequency Control Considering Syste...Tuning PID Controller Parameters for Load Frequency Control Considering Syste...
Tuning PID Controller Parameters for Load Frequency Control Considering Syste...
 

Viewers also liked

Secrecion vaginal flujo vaginal expo
Secrecion vaginal  flujo vaginal expoSecrecion vaginal  flujo vaginal expo
Secrecion vaginal flujo vaginal expo
moranjane
 
Flora vaginal
Flora vaginalFlora vaginal
Flora vaginal
miguel soledispa
 
Sample Work - Lush "Hope Soap" advertising proposal (student project)
Sample Work - Lush "Hope Soap" advertising proposal (student project)Sample Work - Lush "Hope Soap" advertising proposal (student project)
Sample Work - Lush "Hope Soap" advertising proposal (student project)
Evangeline Fan
 
Dettol
DettolDettol

Viewers also liked (7)

Consumer Behaviour
Consumer BehaviourConsumer Behaviour
Consumer Behaviour
 
Comp constaller2
Comp constaller2Comp constaller2
Comp constaller2
 
Secrecion vaginal flujo vaginal expo
Secrecion vaginal  flujo vaginal expoSecrecion vaginal  flujo vaginal expo
Secrecion vaginal flujo vaginal expo
 
Flora vaginal
Flora vaginalFlora vaginal
Flora vaginal
 
Sample Work - Lush "Hope Soap" advertising proposal (student project)
Sample Work - Lush "Hope Soap" advertising proposal (student project)Sample Work - Lush "Hope Soap" advertising proposal (student project)
Sample Work - Lush "Hope Soap" advertising proposal (student project)
 
Dettol
DettolDettol
Dettol
 
Diarrhea ppt
Diarrhea pptDiarrhea ppt
Diarrhea ppt
 

Similar to Final Year Review

Presentation for Industrial Training
Presentation for Industrial TrainingPresentation for Industrial Training
Presentation for Industrial Training
Abudzarwan Wan
 
Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...
Bowman Power
 
KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016sfact
 
Team 2 Final Presentation 12-7 download
Team 2 Final Presentation 12-7 downloadTeam 2 Final Presentation 12-7 download
Team 2 Final Presentation 12-7 downloadCassandra A. Appleton
 
Cmdi,ranchi p pt
Cmdi,ranchi p ptCmdi,ranchi p pt
Cmdi,ranchi p pt
Abhishek Kumar
 
Kerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum VitaeKerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum VitaeKerry Ow Buland
 
IBL Presentation rev FINAL
IBL Presentation rev FINALIBL Presentation rev FINAL
IBL Presentation rev FINALDion Botha
 
ARITRA_GHOSH_Resume_Updtd
ARITRA_GHOSH_Resume_UpdtdARITRA_GHOSH_Resume_Updtd
ARITRA_GHOSH_Resume_UpdtdAritra Ghosh
 
ZERO ENERGY BUILDING; DESIGN AND SIMULATION
ZERO ENERGY BUILDING; DESIGN AND SIMULATIONZERO ENERGY BUILDING; DESIGN AND SIMULATION
ZERO ENERGY BUILDING; DESIGN AND SIMULATION
IRJET Journal
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
Sandro Suzart
 

Similar to Final Year Review (20)

Presentation for Industrial Training
Presentation for Industrial TrainingPresentation for Industrial Training
Presentation for Industrial Training
 
Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...Developing a new generation of energy efficiency products for reciprocating e...
Developing a new generation of energy efficiency products for reciprocating e...
 
KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016KE House Solar Project Highlights Dec 2016
KE House Solar Project Highlights Dec 2016
 
ECBC Training_02-Scope Admin
ECBC Training_02-Scope AdminECBC Training_02-Scope Admin
ECBC Training_02-Scope Admin
 
Team 2 Final Presentation 12-7 download
Team 2 Final Presentation 12-7 downloadTeam 2 Final Presentation 12-7 download
Team 2 Final Presentation 12-7 download
 
Mid Year Review
Mid Year ReviewMid Year Review
Mid Year Review
 
Tanaji Update new
Tanaji Update newTanaji Update new
Tanaji Update new
 
Cmdi,ranchi p pt
Cmdi,ranchi p ptCmdi,ranchi p pt
Cmdi,ranchi p pt
 
PECL PROJECTS
PECL PROJECTSPECL PROJECTS
PECL PROJECTS
 
Kerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum VitaeKerry Ow Buland - Curriculum Vitae
Kerry Ow Buland - Curriculum Vitae
 
IBL Presentation rev FINAL
IBL Presentation rev FINALIBL Presentation rev FINAL
IBL Presentation rev FINAL
 
chiranjeevi_resumlatest-2016.new
chiranjeevi_resumlatest-2016.newchiranjeevi_resumlatest-2016.new
chiranjeevi_resumlatest-2016.new
 
RSR LATEST TRESUME
RSR LATEST TRESUMERSR LATEST TRESUME
RSR LATEST TRESUME
 
ajay cv new (3)
ajay cv new (3)ajay cv new (3)
ajay cv new (3)
 
CNJ Career Path
CNJ Career PathCNJ Career Path
CNJ Career Path
 
ARITRA_GHOSH_Resume_Updtd
ARITRA_GHOSH_Resume_UpdtdARITRA_GHOSH_Resume_Updtd
ARITRA_GHOSH_Resume_Updtd
 
ZERO ENERGY BUILDING; DESIGN AND SIMULATION
ZERO ENERGY BUILDING; DESIGN AND SIMULATIONZERO ENERGY BUILDING; DESIGN AND SIMULATION
ZERO ENERGY BUILDING; DESIGN AND SIMULATION
 
Update profile 2015
Update profile 2015Update profile 2015
Update profile 2015
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
 
Resume- Plant Manager- Harish
Resume- Plant Manager- HarishResume- Plant Manager- Harish
Resume- Plant Manager- Harish
 

Final Year Review

  • 1. Amritanshu Kumar (GET) Training Mentor: M. Ramakrishna Plant : Hosur Final Year Review
  • 2. Unit II’s Electrical Work Project Mentor : M. Ramakrishna Project Guide : Nitin Saxena End to End supervision of all HT/LT electrical works  Lighting work of Unit II Studying Feasibility of Solar On Grid Model in Plant
  • 3. Overview about Unit II’s Electrical Status Total Contract Load:- 950 KVA with 3 phase supply at 415 V Transformer:- 2000 KVA (11KV/440V) DG Sets:- Two of 500 KVA each & one of 365 KVA along with synchronizing Panel Unit II’s SLD :- MAIN SLD.pdf
  • 4. Methodology Adopted • Job Assigned :-  To look after end to end all HT/LT works along with maintaining all quality and safety standards  To take initiatives towards adopting some new models in electrical like in lighting, new development etc.. • Methodology adopted :- • Made electrical log book to track day to day work as well as material’s flow • To keep crisp communication with contractor to smoothen all electrical processes • To validate all electrical works are as per TNEB norms
  • 5. Unit II’s Electrical Works HT Side Works LT Side Works 1. DP Structure Erection 1.LT Panel Room Work 2. HT Cable Laying 2.MCC Panel Room Work 3. RMG Unit Installation 3. LT Room to MCC Room Cable Laying 4. VCB Panel Installation 4. All Light fittings job 5. Transformer Installation 5. All internal cabling • Examples of HT/LT Side work:- DP Structure Erection (HT Work) Motor Cable Laying (LT Work)
  • 6. Learnings LT Cables PCC Panel DG Earthing
  • 7. Saving Through Value Engineering Item Description New Purchase Value (Lacs) Reconditioning Value (Lacs) Savings (Lacs) 2000 KVA Transformer 20 4.5 15.5 HT switch (near transformer) 14 0.5 13.5 PCC panel 36 16.5 19.5 SSB panel 2.5 1.15 1.35 Capacitor panel 2.5 0.95 1.55 Switchgears 17.5 6.25 11.25 Transformer yard fencing 1 0.25 0.75 Old LT Cables re use 5 0 5 Total expenditure in Rs –Lacs 98.5 30.1 68.4 Savings through Value Engineering (Electrical) :- 68.4 Lacs
  • 8. Before & After Pictures BEFORE AFTER DP Structure Area HT Cable Laying Work
  • 9. Before & After Pictures BEFORE AFTER LT / PCC Room MCC Room
  • 10. Before & After Pictures BEFORE AFTER Lighting Works
  • 11. Transformer Installation • Learnings  Transformer various parts and associated parts like OLTC, RTCC  Transformer Oil Filtration process  Various test performed before transformer installation • Findings During insulation test, we found that insulation of LT side was malfunctioning However, later faulty insulators were removed with healthier ones and test certificate was obtained on above LT’s Insulator 2000 KVA Transformer
  • 12. Unit II’s Lighting Works • Methodology Adopted  Our objective was to fit lighting system which should have following features :- 1. Low Power Consumption & Better Life 2. Better Efficacy and CRI 3. Optimum Price  So we decided to go for combination of LED & T5 lights in order to achieve optimum quality and cost • Advantages of LED lights 1.Energy savings between 40%-80% and have life up to 5 times than normal lights. 2.Efficacy level is above 100 in both LED & T5 Lights and LED has best CRI
  • 13. Savings & Learnings • Savings  Apart from our electrical contractor, parallel we also took quotes from other two vendors and thus able to bring down lighting price from our contractor. • Lighting Techno Commercial Sheet :- • Total Savings after negotiations 3.62 lacs • Learnings  Knowledge about various types of light, their working principles, features  Brief Overview about designing of Light fixtures  Learnt about Solar Lights & it’s working Microsoft Excel 97-2003 Worksheet
  • 14. Lighting Fixture S. No. Area Light Type Description Watt Quantity 1 HARPIC MFG AREA LED Totally enclosed LED Tubes + LED 2X2 Luminaire with IP65 Protection 32/39 16 +8 2 LIIZOL & COLIN-Mfg LED Totally enclosed LED Tube 39 16 3 HARPIC FILLING AREA LED LED 2X2 Luminaire suitable for Recessed on Grid / POP ceiling with IP65 Protection 32 16 4 LIZOL & COLIN FILLING LED LED 2X2 Luminaire suitable for Recessed on Grid / POP ceiling 32 28 5 ALPLA Plant T5 T5 Highbay enclosed type (4X32W) 128 74 6 Packaging Area T5 T5 Highbay enclosed type (4X32W) 128 10 7 FG Store Area Metal Halide +T5 Flood Light + T5 Highbay enclosed type (4X32W) 250/128 6+5 8 Quality Lab LED LED 2X2 Luminaire suitable for Recessed on Grid / POP ceiling 32 20 9 Street Light Metal Halide Mercury Halide with IP66 Protection 150 15 10 Solar Light LED 26W LED street light with 100W Solar panel, 12 V 80AH Voltamp Make Battery & 20 feet GI Pole 26 5
  • 15. Lighting Contd.. Harpic Filling Area Harpic Mfg. Area Street Light Quality Lab SolarStreetLight
  • 16. Solar Auto-Grid Project Energy Cost has Increased by about 93 % • About Solar On Grid Project :- Works on principle of Net Metering System Can Install Solar Panel Grid either on roof top or ground Have life of about 25 years with very less degradation in it’s efficiency Maintenance free operation Levellized Cost Of Electricity (Solar) is between Rs 5-6
  • 17. Solar Auto-Grid Project Contd.. • Hosur Plant Potential  Each KW of Solar Panel can generate about 5 Units per day and require about 100 Sq. Feet of area  In Unit II, we are having roof top area of about 2000 sq. mts above LT Panel room while having land availability of about 5600 sq. mts on the south west • Work Progress on Solar On-Grid  Already talked with three vendors and we decided to 1st install 30 KW of Solar Panel Grid System as a pilot project  Techno Commercial Sheet :-  Cost Of Installation :- Rs. 25 lacs  Payback Period :- Rs. 5 years Microsoft Excel 97-2003 Worksheet
  • 18. Benefits & Learnings • Benefits • Learnings Learnt about Solar On Grid System, working principle etc.. Knowledge about various types of solar panels, their features etc..
  • 19. Factory Procurement & Planning Project Guide : M. Shujauddin  Learnings about Procurement & Logistic various functioning  Project on RM & PM Planning of Unit II
  • 20. Learnings • Steps Involved In material movement inside Plant
  • 21. Learnings • Various documents required for FG transfer For Stock Transfer For FG Sales 1. Stock Transfer Copy 1. Sales Invoice Copy 2. Excise Invoice Copy 2. Delivery Challan/Gate Pass 3. Delivery Challan/Gate Pass 3. Road Permit 4. Form JJ ( By TN Govt.) 5. Road Permit
  • 22. RM PM Planning (Unit II) • Why needed ??  As to start production in Unit II, we need to have a system to manage the RM/PM stocks as per our production plan  A Planning sheet was need to be developed which gives all RM/PM requirements as per no. of cases to be produced as per plan.  Products going to be manufactured under Unit II 1. Harpic (Harpic Power Opti Thick) 2. Lizol (Pine, Citrus, Lavender, Sandal, Floral) 3. Colin (Colin Blue)
  • 24. Learnings & Outcomes  Learnings  Basic knowledge about master BOM & Bulk BOM  Knowledge regarding terms like scrap factor, why to include it etc..  Brief overview about how production planning is done  Outcomes  On the basis of RM/PM planning sheet made, RM/PM requirement (for July- Dec’15) as per our tentative production plan was forecasted  Forecasted sheet validate the logic used behind RM/PM planning sheet formation
  • 25. Factory HR Project Guide : Pavan Kumar  Learnings about various Factory & Labour Laws  Job Description & Skill Matrix formation for Unit II
  • 26. Job Description & Skill Matrix Making • Job Description Sheet  To carry out various operations inside Unit II, new requirement was required & accordingly Job Description for various post were made.  JDs were made for the following posts:- 1. Trainee Associate – Electrical 2. Trainee Associate – Mechanical 3. Trainee Associate – Production 4. IPQC (Contractual) 5. DG & LT Room (Contractual) 6. RODM Plant (Contractual) 7. Unskilled labours (Contractual) Microsoft Excel 97-2003 Worksheet
  • 27. Job Description & Skill Matrix Making • Skill Matrix Making  To evaluate the performance of all operators, chemist in nearby future; skill matrix was made  Color Coding system is used to show the performance of each individual as it makes skill matrix tracking lot easier and simpler  Whole Unit II operators and chemist performance figure was summarized on single sheet Microsoft Excel 97-2003 Worksheet
  • 29. Employees Provident Fund Act 1952 Rates Of Contribution Scheme Employee’s Employers Central Govt. PF 12 % 3.67 % NIL EDLI NIL 0.5 % NIL PS NIL 8.33 % 1.16 %
  • 32. Factory Act 1948 • Audit Findings  A certified doctor must visit the plant twice in a week, eight times a month but only 3 visit in a month is taking place  One qualified & trained dresser cum compounder on duty throughout working period not available  In safety practices, plant’s level of safety is up to the mark & every process is going as per standard safety procedure  In welfare section & working hour of adults all process are carrying out through standard procedure  Person below 18 years are not allowed to work, so employment of young person not applicable Microsoft Excel Worksheet