PROJECT MANAGEMENT
ONLINE INTEGRATION OF BLOOD BANKS
P R E S E N T E D TO
Honorable Sir Mehboob ul Haq
Faculty member of Management Sciences,
Iqra University,
Quetta Campus
P R E S E N T E R S
Muti ur Rehman Khan Lodhi – 4463
Arshad Hussain Mengal - 4467
Salman Shakir - 4657
Ibrar Khan – 4385
Students of Master In Business Administration,
Iqra University,
Quetta Campus
12th of January, 2011
Acknowledgement
• We would like to show great esteem and
deference to Honorable Sir Mehboob ul Haq, to
make it possible for us to have spectacles to
see and understand the matter with
different ideas and outcomes. He gave us a
new way of brainstorming on the various
matters as project manager.
RISKS AND CONTINGENCY PLAN
ESTIMATIONS
PROCESS BREAKDOWN STRUCTURE
WORK BREAKDOWN STRCUTURE
SCOPE OF THE PROJECT
CONTENTS
PRIORITY MATRIX
• PERFORMANCE
• Very Important as helps in
future growth and
continuation
• TIME AND COST
• Negotiable
• Limited variation can
be acceptable
SCOPE OF THE PROJECT
• OBJECTIVES
– To establish an online integrated blood banks database
and information system which will be designed to facilitate
the requirements of customers in Quetta city with the
collaboration of various blood banks.
– As well as developing an online platform for the donors to
make their donations to be utilized efficiently.
SCOPE OF THE PROJECT
• DELIVERABLES
– A database system with an online platform which will
integrate all the blood banks at a single place to
acknowledge the need of blood in timely manner.
– A website which will help to develop coordination
between Blood Banks, Customers, and Donors.
– It will help the customers to reach to their specified blood
groups without roaming all over the city as well as to trace
out the nearest place.
SCOPE OF THE PROJECT
• DELIVERABLES (Continued)
– It will help to the blood banks to maintain their stock on the
basis of better forecasting method in term of requirement.
– The project will also play its role in the society to aware the
public about the healthy blood.
SCOPE OF THE PROJECT
• MILESTONES
– Technical Requirements
– Convincing all the blood banks to integrate on our system.
– Locating the center point for our setup.
– Implementation of database and integration with all
available blood banks.
– Designing and launching of website.
– Promotions will be covered up to fifteen hospitals.
SCOPE OF THE PROJECT
• TECHNICAL REQUIREMENTS
– Well equipped setup with high configuration server.
– Well skilled two personnel having sound knowledge about
database and website maintenance.
– Fully Converged local area network within the setup so the
upgrading the website with database can be easy.
– Affiliation with laboratories and hospitals for attestation of
donor’s blood.
SCOPE OF THE PROJECT
• TECHNICAL REQUIREMENTS (Continued)
– Security implementation on website and database system.
– Remote access to database and web portal for
administrators.
– Backup of information available on database system as
well as a tool for restoration, if required.
– UPS for smooth running of database system.
SCOPE OF THE PROJECT
• LIMITATIONS AND EXCLUSIONS
– Initially working geographically within the premises of
Quetta City and nearby areas.
– Blood donors must be in between of eighteen years to fifty
years of age.
– We can facilitate our customer only in case that we have
the required blood in our database system, else wise, the
customer would not be entertained.
SCOPE OF THE PROJECT
• CUSTOMER REVIEWS / FEED BACK
– Website
– contacts details
– phone calls
– Post box number
WORK/ PROCESS
BREAKDOWN
STRUCTURE
WORKBREAKDOWN
STRUCTURE
1
ONLINE BLOOD
BANK
1.1
BLOOD BANK
1.1.1
Analysis
1.1.2
Negotiation
1.1.3
Agreement
2.1
DATABASE
2.1.1
Analysis
2.1.2
Design
2.1.3
Coding
2.1.4
Testing
2.1.5
Implementation
3.1
WEBSITE
3.1.1
Design Approval
3.1.2
Development
3.1.3
Integration with
database
3.1.4
Launch
4.1
SETUP
4.1.1
Location
4.1.2
Computers &
Accessories
4.1.3
Furniture
4.1.4
Network
Implementation
4.1.5
Internet Access
5.1
PROMOTION
5.1.1
Media
5.1.1.1
Electronic
Media
5.1.1.2
Print Media
LEVELS
1
2
3
4
5
6
1.1 BLOOD BANKS
ANALYSIS NEGOTIATION AGREEMENT
2.1 DATABASE DEVELOPMENT
ANALYSIS
DESIGN
CODING
TESTING
IMPLEMENTATION
3.1 WEBSITE
Company Logo
INTEGRATION
WITH DATABASE
DEVELOPMENT
DESIGN APPROVAL
LAUNCH
Design Sample
* Secondary Information
4.1 SETUP
SETUP
INTERNET
CONNECTION
LOCATION
NETWORK
IMPLEMENTATION
FURNITURE
COMPUTERS
AND ACCESSORIES
5.1 PROMOTION
• MEDIA
• ELECTRONIC MEDIA
• Facebook - Twitter
• PRINT MEDIA
Tasks Arshad Ibrar Mati Salman Out sourced
1. BLOOD BANK
ANALYSIS A R
NEGOTIATION R A
AGREEMENT R A
2. DATA BASE
ANALYSIS A R
DESIGN A R
CODING A R
TESTING R A
IMPLEMENTATION S S R
3. WEBSITE
DESIGN APPROVAL R A
DEVELOPMENT A R
INTEGRATION WITH DATABASE A R
LAUNCH R R S S R
4. SETUP
LOCATION A R
COMPUTER & ACCESSORIES A R
FURNITURE R A A
INTERNET CONNECTION R A
NETWORKING IMPLEMENTATION R A
5.PROMOTION
PRINT MEDIA A R
ELECTRONIC MEDIA A R
RESPONSIBILITYMATRIX
COSTESTIMATION
1
ONLINE BLOOD BANK
(Rs: 320,000)
1.1
BLOOD BANK
(Rs: 15,000)
1.1.1
Analysis
1.1.2
Negotiation
1.1.4
Agreement
2.1
DATABASE
(Rs: 36,000)
2.1.1
Analysis
2.1.2
Design
2.1.3
Coding
(Rs: 16,000)
2.1.4
Testing
2.1.5
Implementation
(20,000)
3.1
WEBSITE
(Rs: 40,000)
3.1.1
Design Approval
3.1.2
Development
(Rs: 15,000)
3.1.3
Integration with
database
3.1.4
Launch
(Rs: 20,000)
4.1
SETUP
(Rs: 179,000)
4.1.1
Location
(Rs: 115,000)
4.1.2
Computers &
Accessories
(Rs: 40,000)
4.1.3
Furniture
(Rs: 12,000)
4.1.4
Network
Implementation
(Rs: 10,000)
4.1.5
Internet Access
(Rs: 2000)
5.1
PROMOTION
(Rs: 50,000)
5.1.1
Media
(Rs: 50,000)
5.1.1.1
Electronic Media
(Rs: 30,000)
5.1.1.2
Print Media
(20,000)
TIMEESTIMATION
1
ONLINE BLOOD BANK
(175 Days)
1.1
BLOOD BANK
(42 Days)
1.1.1
Analysis
(7 Days)
1.1.2
Negotiation
(15 Days)
1.1.4
Agreement
(20 Days)
2.1
DATABASE
(38 Days)
2.1.1
Analysis
(3 Days)
2.1.2
Design
(7 Days)
2.1.3
Coding
(25 Days)
2.1.4
Testing
(2 Days)
2.1.5
Implementation
(1 Day)
3.1
WEBSITE
(44 Days)
3.1.1
Design Approval
(3 Days)
3.1.2
Development
(30 Days)
3.1.3
Integration with
database
(10 Days)
3.1.4
Launch
(1 Day)
4.1
SETUP
(37 Days)
4.1.1
Location
(10 Days)
4.1.2
Computers &
Accessories
(7 Days)
4.1.3
Furniture
(2 Days)
4.1.4
Network
Implementation
(4 Days)
4.1.5
Internet Access
(14 Days)
5.1
PROMOTION
(14 Days)
5.1.1
Media
(14 Days)
5.1.1.1
Electronic Media
(7 Days)
5.1.1.2
Print Media
(7 Days)
RISKS RELATED TO PROJECT
• PROJECT
• Future Financial Obligations
• Time Frame not be met?
• BLOOD BANKS
• Will they associate with system?
• If they do no have Electronic Record System?
• Technical Expertise?
• Influence to be a part of project, How?
• If not accepting to Agreement Signing?
• DATABASE
– Design not fulfilling the needs
– Backup of data in case of crash
– Upgrade of database in percept of coding without losing
data
– Responsibility on data leaking
– Cost Reduction
– Energy short fall and impact on stake holders
RISKS RELATED TO PROJECT
• WEBSITE
– Design
– Integration
– Cost of web/Expensive procedure
– Completion in time
– Web launching ceremony
RISKS RELATED TO PROJECT
• SETUP / CENTER POINT
– Location Availability
– Rent more than expected
– Chances of theft and stealing
– Database Malfunctioning
– Furniture Cost
– Network Implements
– Internet Facility
RISKS RELATED TO PROJECT
• PROMOTION
– Minimization of Cost, how?
– Electronic Media, how to afford that?
– Inability to pass message to target customers
– How to brought someone onboard for promotional
activities?
RISKS RELATED TO PROJECT
• PROJECT
– Project Sponsor Meetings
– Blood Bank Suppliers Confidence and trust building
• BLOOD BANK
– New Business opportunity. Only manage the data of donors.
– Training by one of our employees
– Good for welfare purpose and business. Facts and figures of
Quetta blood market.
– ULEMA statements on rewards by nature’s perspective
– Single table arrangements for all blood banks
CONTINGENCY PLAN
• DATABASE
– Analysis phase personnel hired
– ISA Server as third party backup is expensive
– Agreement with developers and ability of layout to
enhance future capabilities.
– Administrators would have to follow our terms and
conditions
– Dividing various responsibilities within team members as per
through our expertise.
– UPS or generator in extreme cases
CONTINGENCY PLAN
• WEBSITE
– Continuous upgradation and stakeholder feedback
– DOTnet Framework
– Expertise by us on known processes
– The time of launching ceremony with buffer
CONTINGENCY PLAN
• SETUP
– Near Imdad Chowk or Civil Hospital Quetta
– Turn towards Zarghoon Road
– Watchmen
– Resolution of server
– China furniture from Lahore Market
– Dialup or Vfone
CONTINGENCY PLAN
• PROMOTION
– Publishing an article
– Attracting journalists
– Non profit organization charity
– Cable TV ads
– High traffic websites
– Online forums
– Badges
CONTINGENCY PLAN
• COST
– Total = Rs.350,000/-
– WBS = Rs.320,000/-
– Contingency Reserves = Rs.15000/-
• TIME
– 1 year
– But try to launch a project within 6 months
• Evaluation and Assessment of Performance
– Time Buffer of 1 month
CONTINGENCY RESERVES
FUTURE PLANS
• Expending Geographically
– Out from Quetta (To major parts of Balochistan)
• Time frame expansion
– Plans depend on feedbacks from customers and
stakeholders.
• Sponsor required
– For future operations
Project Management of Online Integration of Blood Banks
Project Management of Online Integration of Blood Banks

More Related Content

Viewers also liked

Good governance & good enough governance
Good governance & good enough governanceGood governance & good enough governance
Good governance & good enough governanceRahat ul Aain
 
Central Asia Slides
Central Asia SlidesCentral Asia Slides
Central Asia SlidesEric Castro
 
How best can you finance your business
How best can you finance your businessHow best can you finance your business
How best can you finance your businessTanzil Al Gazmir
 
Business Finance Fund 2013
Business Finance Fund 2013Business Finance Fund 2013
Business Finance Fund 2013Keith Williams
 
Scope of Financial Management
Scope of Financial Management Scope of Financial Management
Scope of Financial Management Manu Thakur
 
IBM Global Finance - Building strong IT Business Cases in the New Economic World
IBM Global Finance - Building strong IT Business Cases in the New Economic WorldIBM Global Finance - Building strong IT Business Cases in the New Economic World
IBM Global Finance - Building strong IT Business Cases in the New Economic WorldVincent Kwon
 
Modern Finance Tour London May 2016
Modern Finance Tour London May 2016Modern Finance Tour London May 2016
Modern Finance Tour London May 2016BlackLine
 

Viewers also liked (11)

Good governance & good enough governance
Good governance & good enough governanceGood governance & good enough governance
Good governance & good enough governance
 
Hdi calculation
Hdi calculationHdi calculation
Hdi calculation
 
Central Asia Slides
Central Asia SlidesCentral Asia Slides
Central Asia Slides
 
Ppt ft 1
Ppt ft 1Ppt ft 1
Ppt ft 1
 
How best can you finance your business
How best can you finance your businessHow best can you finance your business
How best can you finance your business
 
Business Finance Fund 2013
Business Finance Fund 2013Business Finance Fund 2013
Business Finance Fund 2013
 
Time to embrace new opportunities - MBA Finance
Time to embrace new opportunities   - MBA FinanceTime to embrace new opportunities   - MBA Finance
Time to embrace new opportunities - MBA Finance
 
Business Financing Options Workshop Batesville July
Business Financing Options Workshop Batesville JulyBusiness Financing Options Workshop Batesville July
Business Financing Options Workshop Batesville July
 
Scope of Financial Management
Scope of Financial Management Scope of Financial Management
Scope of Financial Management
 
IBM Global Finance - Building strong IT Business Cases in the New Economic World
IBM Global Finance - Building strong IT Business Cases in the New Economic WorldIBM Global Finance - Building strong IT Business Cases in the New Economic World
IBM Global Finance - Building strong IT Business Cases in the New Economic World
 
Modern Finance Tour London May 2016
Modern Finance Tour London May 2016Modern Finance Tour London May 2016
Modern Finance Tour London May 2016
 

Similar to Project Management of Online Integration of Blood Banks

Similar to Project Management of Online Integration of Blood Banks (20)

Migrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer Story
Migrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer StoryMigrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer Story
Migrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer Story
 
Subrat K Panigrahi Resume
Subrat K Panigrahi ResumeSubrat K Panigrahi Resume
Subrat K Panigrahi Resume
 
Srinivasalu R CV
Srinivasalu R  CVSrinivasalu R  CV
Srinivasalu R CV
 
Srinivasalu R CV
Srinivasalu R  CVSrinivasalu R  CV
Srinivasalu R CV
 
Ahmed Alkokah_CV_VerMay2016
Ahmed Alkokah_CV_VerMay2016Ahmed Alkokah_CV_VerMay2016
Ahmed Alkokah_CV_VerMay2016
 
Victor Holderby - Project Manger
Victor Holderby - Project MangerVictor Holderby - Project Manger
Victor Holderby - Project Manger
 
Himmelrich 8-2015
Himmelrich 8-2015Himmelrich 8-2015
Himmelrich 8-2015
 
Akram_Resume_ETL_Informatica
Akram_Resume_ETL_InformaticaAkram_Resume_ETL_Informatica
Akram_Resume_ETL_Informatica
 
IT, Network System Engineer
IT, Network System EngineerIT, Network System Engineer
IT, Network System Engineer
 
LaMima Gilbert Lewis PM
LaMima Gilbert Lewis PMLaMima Gilbert Lewis PM
LaMima Gilbert Lewis PM
 
Puneet Verma CV
Puneet Verma CVPuneet Verma CV
Puneet Verma CV
 
MitchRESUME 02_22_2016
MitchRESUME 02_22_2016MitchRESUME 02_22_2016
MitchRESUME 02_22_2016
 
Sumalatha_Kalugotla
Sumalatha_KalugotlaSumalatha_Kalugotla
Sumalatha_Kalugotla
 
Hossam ali cv_2018
Hossam ali cv_2018Hossam ali cv_2018
Hossam ali cv_2018
 
CV
CVCV
CV
 
AssetNet
AssetNetAssetNet
AssetNet
 
AssetNet
AssetNetAssetNet
AssetNet
 
Krishnan Ramachandran
Krishnan RamachandranKrishnan Ramachandran
Krishnan Ramachandran
 
Ryan Stewart CV
Ryan Stewart CVRyan Stewart CV
Ryan Stewart CV
 
Adel eid ali resume
Adel eid ali resumeAdel eid ali resume
Adel eid ali resume
 

More from Muti ur Rahman Khan Lodhi (8)

Presentation on corporate frauds
Presentation on corporate fraudsPresentation on corporate frauds
Presentation on corporate frauds
 
Presentation on corp frauds
Presentation on corp fraudsPresentation on corp frauds
Presentation on corp frauds
 
Metro, A Presentation of Production Management
Metro, A Presentation of Production ManagementMetro, A Presentation of Production Management
Metro, A Presentation of Production Management
 
Final presentation of mm
Final presentation of mmFinal presentation of mm
Final presentation of mm
 
Final presentation about icf
Final presentation about icfFinal presentation about icf
Final presentation about icf
 
Final project marketing
Final project marketingFinal project marketing
Final project marketing
 
Self Management Skills
Self Management SkillsSelf Management Skills
Self Management Skills
 
Learning Styles
Learning StylesLearning Styles
Learning Styles
 

Project Management of Online Integration of Blood Banks

  • 1.
  • 3. P R E S E N T E D TO Honorable Sir Mehboob ul Haq Faculty member of Management Sciences, Iqra University, Quetta Campus P R E S E N T E R S Muti ur Rehman Khan Lodhi – 4463 Arshad Hussain Mengal - 4467 Salman Shakir - 4657 Ibrar Khan – 4385 Students of Master In Business Administration, Iqra University, Quetta Campus 12th of January, 2011
  • 4. Acknowledgement • We would like to show great esteem and deference to Honorable Sir Mehboob ul Haq, to make it possible for us to have spectacles to see and understand the matter with different ideas and outcomes. He gave us a new way of brainstorming on the various matters as project manager.
  • 5. RISKS AND CONTINGENCY PLAN ESTIMATIONS PROCESS BREAKDOWN STRUCTURE WORK BREAKDOWN STRCUTURE SCOPE OF THE PROJECT CONTENTS
  • 6. PRIORITY MATRIX • PERFORMANCE • Very Important as helps in future growth and continuation • TIME AND COST • Negotiable • Limited variation can be acceptable
  • 7. SCOPE OF THE PROJECT • OBJECTIVES – To establish an online integrated blood banks database and information system which will be designed to facilitate the requirements of customers in Quetta city with the collaboration of various blood banks. – As well as developing an online platform for the donors to make their donations to be utilized efficiently.
  • 8. SCOPE OF THE PROJECT • DELIVERABLES – A database system with an online platform which will integrate all the blood banks at a single place to acknowledge the need of blood in timely manner. – A website which will help to develop coordination between Blood Banks, Customers, and Donors. – It will help the customers to reach to their specified blood groups without roaming all over the city as well as to trace out the nearest place.
  • 9. SCOPE OF THE PROJECT • DELIVERABLES (Continued) – It will help to the blood banks to maintain their stock on the basis of better forecasting method in term of requirement. – The project will also play its role in the society to aware the public about the healthy blood.
  • 10. SCOPE OF THE PROJECT • MILESTONES – Technical Requirements – Convincing all the blood banks to integrate on our system. – Locating the center point for our setup. – Implementation of database and integration with all available blood banks. – Designing and launching of website. – Promotions will be covered up to fifteen hospitals.
  • 11. SCOPE OF THE PROJECT • TECHNICAL REQUIREMENTS – Well equipped setup with high configuration server. – Well skilled two personnel having sound knowledge about database and website maintenance. – Fully Converged local area network within the setup so the upgrading the website with database can be easy. – Affiliation with laboratories and hospitals for attestation of donor’s blood.
  • 12. SCOPE OF THE PROJECT • TECHNICAL REQUIREMENTS (Continued) – Security implementation on website and database system. – Remote access to database and web portal for administrators. – Backup of information available on database system as well as a tool for restoration, if required. – UPS for smooth running of database system.
  • 13. SCOPE OF THE PROJECT • LIMITATIONS AND EXCLUSIONS – Initially working geographically within the premises of Quetta City and nearby areas. – Blood donors must be in between of eighteen years to fifty years of age. – We can facilitate our customer only in case that we have the required blood in our database system, else wise, the customer would not be entertained.
  • 14. SCOPE OF THE PROJECT • CUSTOMER REVIEWS / FEED BACK – Website – contacts details – phone calls – Post box number
  • 16. WORKBREAKDOWN STRUCTURE 1 ONLINE BLOOD BANK 1.1 BLOOD BANK 1.1.1 Analysis 1.1.2 Negotiation 1.1.3 Agreement 2.1 DATABASE 2.1.1 Analysis 2.1.2 Design 2.1.3 Coding 2.1.4 Testing 2.1.5 Implementation 3.1 WEBSITE 3.1.1 Design Approval 3.1.2 Development 3.1.3 Integration with database 3.1.4 Launch 4.1 SETUP 4.1.1 Location 4.1.2 Computers & Accessories 4.1.3 Furniture 4.1.4 Network Implementation 4.1.5 Internet Access 5.1 PROMOTION 5.1.1 Media 5.1.1.1 Electronic Media 5.1.1.2 Print Media LEVELS 1 2 3 4 5 6
  • 17. 1.1 BLOOD BANKS ANALYSIS NEGOTIATION AGREEMENT
  • 19. 3.1 WEBSITE Company Logo INTEGRATION WITH DATABASE DEVELOPMENT DESIGN APPROVAL LAUNCH
  • 22. 5.1 PROMOTION • MEDIA • ELECTRONIC MEDIA • Facebook - Twitter • PRINT MEDIA
  • 23. Tasks Arshad Ibrar Mati Salman Out sourced 1. BLOOD BANK ANALYSIS A R NEGOTIATION R A AGREEMENT R A 2. DATA BASE ANALYSIS A R DESIGN A R CODING A R TESTING R A IMPLEMENTATION S S R 3. WEBSITE DESIGN APPROVAL R A DEVELOPMENT A R INTEGRATION WITH DATABASE A R LAUNCH R R S S R 4. SETUP LOCATION A R COMPUTER & ACCESSORIES A R FURNITURE R A A INTERNET CONNECTION R A NETWORKING IMPLEMENTATION R A 5.PROMOTION PRINT MEDIA A R ELECTRONIC MEDIA A R RESPONSIBILITYMATRIX
  • 24. COSTESTIMATION 1 ONLINE BLOOD BANK (Rs: 320,000) 1.1 BLOOD BANK (Rs: 15,000) 1.1.1 Analysis 1.1.2 Negotiation 1.1.4 Agreement 2.1 DATABASE (Rs: 36,000) 2.1.1 Analysis 2.1.2 Design 2.1.3 Coding (Rs: 16,000) 2.1.4 Testing 2.1.5 Implementation (20,000) 3.1 WEBSITE (Rs: 40,000) 3.1.1 Design Approval 3.1.2 Development (Rs: 15,000) 3.1.3 Integration with database 3.1.4 Launch (Rs: 20,000) 4.1 SETUP (Rs: 179,000) 4.1.1 Location (Rs: 115,000) 4.1.2 Computers & Accessories (Rs: 40,000) 4.1.3 Furniture (Rs: 12,000) 4.1.4 Network Implementation (Rs: 10,000) 4.1.5 Internet Access (Rs: 2000) 5.1 PROMOTION (Rs: 50,000) 5.1.1 Media (Rs: 50,000) 5.1.1.1 Electronic Media (Rs: 30,000) 5.1.1.2 Print Media (20,000)
  • 25. TIMEESTIMATION 1 ONLINE BLOOD BANK (175 Days) 1.1 BLOOD BANK (42 Days) 1.1.1 Analysis (7 Days) 1.1.2 Negotiation (15 Days) 1.1.4 Agreement (20 Days) 2.1 DATABASE (38 Days) 2.1.1 Analysis (3 Days) 2.1.2 Design (7 Days) 2.1.3 Coding (25 Days) 2.1.4 Testing (2 Days) 2.1.5 Implementation (1 Day) 3.1 WEBSITE (44 Days) 3.1.1 Design Approval (3 Days) 3.1.2 Development (30 Days) 3.1.3 Integration with database (10 Days) 3.1.4 Launch (1 Day) 4.1 SETUP (37 Days) 4.1.1 Location (10 Days) 4.1.2 Computers & Accessories (7 Days) 4.1.3 Furniture (2 Days) 4.1.4 Network Implementation (4 Days) 4.1.5 Internet Access (14 Days) 5.1 PROMOTION (14 Days) 5.1.1 Media (14 Days) 5.1.1.1 Electronic Media (7 Days) 5.1.1.2 Print Media (7 Days)
  • 26. RISKS RELATED TO PROJECT • PROJECT • Future Financial Obligations • Time Frame not be met? • BLOOD BANKS • Will they associate with system? • If they do no have Electronic Record System? • Technical Expertise? • Influence to be a part of project, How? • If not accepting to Agreement Signing?
  • 27. • DATABASE – Design not fulfilling the needs – Backup of data in case of crash – Upgrade of database in percept of coding without losing data – Responsibility on data leaking – Cost Reduction – Energy short fall and impact on stake holders RISKS RELATED TO PROJECT
  • 28. • WEBSITE – Design – Integration – Cost of web/Expensive procedure – Completion in time – Web launching ceremony RISKS RELATED TO PROJECT
  • 29. • SETUP / CENTER POINT – Location Availability – Rent more than expected – Chances of theft and stealing – Database Malfunctioning – Furniture Cost – Network Implements – Internet Facility RISKS RELATED TO PROJECT
  • 30. • PROMOTION – Minimization of Cost, how? – Electronic Media, how to afford that? – Inability to pass message to target customers – How to brought someone onboard for promotional activities? RISKS RELATED TO PROJECT
  • 31. • PROJECT – Project Sponsor Meetings – Blood Bank Suppliers Confidence and trust building • BLOOD BANK – New Business opportunity. Only manage the data of donors. – Training by one of our employees – Good for welfare purpose and business. Facts and figures of Quetta blood market. – ULEMA statements on rewards by nature’s perspective – Single table arrangements for all blood banks CONTINGENCY PLAN
  • 32. • DATABASE – Analysis phase personnel hired – ISA Server as third party backup is expensive – Agreement with developers and ability of layout to enhance future capabilities. – Administrators would have to follow our terms and conditions – Dividing various responsibilities within team members as per through our expertise. – UPS or generator in extreme cases CONTINGENCY PLAN
  • 33. • WEBSITE – Continuous upgradation and stakeholder feedback – DOTnet Framework – Expertise by us on known processes – The time of launching ceremony with buffer CONTINGENCY PLAN
  • 34. • SETUP – Near Imdad Chowk or Civil Hospital Quetta – Turn towards Zarghoon Road – Watchmen – Resolution of server – China furniture from Lahore Market – Dialup or Vfone CONTINGENCY PLAN
  • 35. • PROMOTION – Publishing an article – Attracting journalists – Non profit organization charity – Cable TV ads – High traffic websites – Online forums – Badges CONTINGENCY PLAN
  • 36. • COST – Total = Rs.350,000/- – WBS = Rs.320,000/- – Contingency Reserves = Rs.15000/- • TIME – 1 year – But try to launch a project within 6 months • Evaluation and Assessment of Performance – Time Buffer of 1 month CONTINGENCY RESERVES
  • 37. FUTURE PLANS • Expending Geographically – Out from Quetta (To major parts of Balochistan) • Time frame expansion – Plans depend on feedbacks from customers and stakeholders. • Sponsor required – For future operations