OK kids,We’re gonna
paint the garage floor.
Everyone off the couch
and in the garage with
smiles on your little faces
V7
1/24
Dad’s gonna “program manage” your efforts to a
successful outcome using Event Based Scheduling
10 November 2006
+
Core Problem of all Project’s
n Collecting project costs is relatively easy
n Obtaining real physical progress status of ongoing activities is
much more difficult
n This is the 90% syndrome – or in some cases the 80% syndrome
n When physical progress is reported by the activity owners,without a
way to cross check of the achievement – true progress is often hidden
n Om many cases progress is equated to the passage of time and
consumption of money
n Replacing this progress–oriented reporting with deliverables–
oriented reporting is the starting point of real performance
management – an authentic,trusted and verifiable performance
measurement
1 Nov 06V7
2/24
Failed or underperforming projects are more common than not. Learning how to address one of the
problems found in troubled projects is the topic of this Brown Bag session
+
Themes of Event Based Scheduling
n Progress is measured by the completion of Significant
Accomplishments (SA)
n The evidence of this progress is provided by the
Accomplishment Criteria (AC)
n Task progress is only measured as 0% or 100%. No partial
credit,no percent complete – either its done or it’s not done,
either we’ve accomplished our accomplishment or we haven’t
n The “architecture”of the project describes the increasing value
maturity of the deliverables through the completion of the
Significant Accomplishments
n Defining what “done” looks like and scheduling backward,
tells us when we should have started the project
1 Nov 06V7
3/24
+
Events For Our Family Garage
Project
n When asked to “make a plan,” our first impulse is to make a list for all the
work to be performed.Here’s a list of the garage floor painting work …
n All our sports “stuff” cleaned up
n Get the garage floor washed and dried
n Put down epoxy sealer and let it dry
n Paint the car stalls
n Put everything back
n Park the cars and close the doors
n Let’s just focus on item #1
1 Nov 06V7
4/24
Events are celebratory occasions, where a collection of Significant Accomplishments has been
“accomplished” with measurable outcomes, judged by the Accomplishment Criteria for the work
performed
+
First Some Definitions
n Event – A major transition point in the project. The place
where the maturity of the deliverables can be assessed to
determine if we should proceed to the next step
n Significant Accomplishment – An interim, critical, or discrete
activity that must be completed prior to an Event
n Accomplishment Criteria – A measurable indicator of the
evidence that increased maturity or progress has been made
towards a Significant Accomplishment
n Task – The work performed in support of accomplishments
and their criteria
1 Nov 06V7
5/24
There are some new terms we’ll need to use when we’re speaking in the “Event Based
Scheduling” vocabulary
+
Get“stuff” Cleaned Up Event
n It needs a finite duration
n There needs to be a clear and concise definition “cleaned
up”
n Measures of success need to be defined
n When we reach the logical stopping point when “all” the
stuff is cleaned up – Mom says its time for lunch is not a very
good measure of success
n There are clear and concise benefits to getting to this point
n We could stop here and still havebenefits
1 Nov 06V7
6/24
Let’s look at the details of our first Event
– “all the sports stuff cleaned up”
+
Event:“All the stuff cleaned up”–
Let’s Eat
n Significant Accomplishment (SA)
n Interim, critical or discrete activity required to complete prior to
an event
n All Baseball Equipment Located and collected for storage
n Accomplishment Criteria (AC)
n Measurableindicators of evidence that demonstrates the
achievement of maturity or progress in an activity
n Bats, gloves, pads, and uniforms placed in their labeled bags and
hung on hooks
1 Nov 06V7
7/24
A Significant Accomplishment (SA) is getting all the baseball gear into bags, hung on the wall, bats in
a bag, and batting helmets in their racks
+
Significant Accomplishment (SA)
n SA:Baseball Equipment Stored
in Assigned Location
n The Accomplishment Criteria
for completing this Significant
Accomplishment includes:
n Location for each baseball
item identified
n Pads, balls, hats gloves
located, sorted, and placed
in a pile of like stuff
n Bats located and loaded into
a single bat bag
n Equipment bags located,
emptied of food, drinks, and
mice droppings
1 Nov 06V7
8/24
The Significant Accomplishment of getting all the Baseball gear into bags is measured
by the completion of the Accomplishment Criteria
+
Accomplishment Criteria (AC)
n AC: Locations defined for each identified item
n Tasks to complete the AC include:
n Labeling all bags with their contents
n Cleaning the bags
n Determining if the bag can hold the equipment
n Finding new bags, if there is not enough room in the current ones
1 Nov 06V7
9/24
Accomplishment Criteria (AC) is the Exit Criteria for the work performed by the Tasks. When all
the work is done, the AC is 100% complete
+
Project Management According to
Yogi†
n Planning
n You’ve got to be very careful if
you don’t know where you’re
going,because you might not
get there
n Communicating
n I didn’t really say everything I
said
n Decision Making
n If you come to a fork in the
road, take it
n Measuring progress
n You’d better cut the pizza in
four pieces,because I’m not
hungry enough to eat six
n Executing
n Think? How the hell are you
gonna think and hit at the
same time?
n Managing
n You can observe a lot just by
watching
n Meeting deadlines
n I knew I was going to take the
wrong train,so I left early
n Closeout
n This is like déjà vu all over
again
1 Nov 06V7
10/24
† “Yogi Berra, PMP,” Ralph Sacco, Computer World, October 23, 2006, pp. 44
+
OK,Enough Baseball
Let’s have a business
example that moves us
from the old world of time
and cost measurement to
the new world of
accomplishments and exit
criteria
1 Nov 06 V7
11/24
+
Provisioning a New Employee
1 Nov 06V7
12/24
Human ResourcesNew Employee Ready to Work
Insurance
Orientation
Laptop Account Setup
Charge account setup
Information Technology
Finance
Buying authority
Supply Chain Management
Significant Accomplishments
Project Event
New Employee
Ready for Work
Project Event
New Employee
Arrives
A new employee arrives. What needs to happen before she can be productive? How can we measure
the progress toward being productive?
+
Structure of the Event Based
Schedule
1 Nov 06V7
13/24
Business StrategyBusiness Strategy
Process StepProcess Step
WBS Element or
Subsystem
EventsEvents
TasksTasks
Accomplishments
CriteriaCriteria
Significant
Accomplishments
(SA)
Accomplishment
Criteria (AC)
SubsystemSubsystem
State of the
Project
State of the
Project
State of the
Capability
State of the
Process
Demonstrates
Maturity
Identifies
End Item
How
Defines
Customer/Program
Direction
Program/Team
Direction
Team Direction
Performance
Team Status
Team Status
Something
Completed
Effort
Expended
DeliverablesDeliverables
+
Describing “Done” in a Single
Phrase
1 Nov 06V7
14/24
Perform
Work
MaturityMaturity
Adjective
ActionAction
Verb
ProvisioningFinal
CapabilityCapability
Noun
Desktop
Demonstrates
Maturity End Item
“A01B02a: Preliminary Month End Close of the General Ledger Complete ”“A01B02a: Final Desktop Provisioning of New Employee Complete”
Step in the Process
StateState
Verb
Complete
Closure
State
+
One More Review of Our New
Terminology
n Events – define the state of the project
n Significant Accomplishments –demonstrate the state of the
capability
n This is the assessment of maturity of the deliverable at a point in
time
n Accomplishment Criteria – demonstrates the state of the
process
n Task – describes the effort required to complete the
Accomplishment Criteria
1 Nov 06V7
15/24
The terms of Event Based Scheduling need to be repeated over and over. This helps replace our
temporal progress thinking with event maturity thinking
+
And Some More Detail Of These
Terms
n A Significant Accomplishment describes …
n A desired result
n A discrete step in a process
n A description of an interrelationship
n An Accomplishment Criteria describes …
n Completed work effort
n Activities that confirm the value
n Completion of critical activities
1 Nov 06V7
16/24
+
AC’s are the Central Elements of
the Plan
n Define the measure by which an Accomplishment (SA) is considered
“done”
n Terms like:complete,delivered,closed have no“units of measure”in
the context of a Significant Accomplishment (SA) are weak and open to
interpretation
n Terms that use …
n Measures of completion – 80% of training materials published
n Counts of available items – 75% of entry forms approved
n Fidelity of a design – 90% of Use Cases converted to UML
n Error bounds – network performance within ±12%
n Performance parameters – backup duration £allowable window
n Maturity parameters – successful conversation completed 3 times
n … are stronger definitions of the Exit Criteria
1 Nov 06V7
17/24
Defining the Accomplishment Criteria is the hard part. But they are the key to success in Event Based
Scheduling, since they are the measures of “done”
+
Primary Motivation – Avoid This
Meeting!
n Project management is
not about forecasting the
future
n Project Management is
about understanding
risks that impact the
future
n Project Management is
about making visible
what “done” looks like
n Project Management is
about staying ahead of
risk the curve
1 Nov 06V7
18/24
Would you please elaborate on “Then Something Bad Happened”
+
Nine Principles of Project
Management
n Systematic and integrative planning
– maximum influence comes early in
the project
n Timely decisions adjusted to
uncertainty – objectives first,the
means to fulfill next
n Isolation and Absorption of Risk –
organize project elements to
maintain stability and isolate
undesired results
n Leadership is Both Inward and
Outward – leadership copes with
uncertainty, management copes with
complexity
n Teamwork – emphasize cooperation
rather than risk allocation
n Overlapping Phases – pay great
attention to pre–existing
activities
n Simple Procedures – prevent re–
invention,contribute to
cooperation,and establish
internal stability
n Intensive Communication – fit
the intensity and mode of
communication to the situation
n Systematic Monitoring –
identifying and correcting small
problems is easy,identifying
large problems is easy,
correcting them is hard
1 Nov 06V7
19/24
Event Based Scheduling is the basis for these Nine Principles (or any other favorite principles of
project management)
+
An Event Based Schedule
1 Nov 06V7
20/24
Event
Significant
Accomplishment
Accomplishment
Criteria
Tasks
Here’s an example of a project that rolls out Microsoft Project Server™
+
Our Working Example
n Event – Phase A/B of the enterprise
project server deployment is
complete
n All the deliverables,activities to
deliver those deliverables,and
the criteria by which those
deliverables were measured have
been completed
n Significant Accomplishment – the
Governance and Review Groups
have been established
n There are 2 “exit criteria”
shown representing the
“evidence” that these review
groups have been established
n The completion of these “exit
criteria” is a clear and concise
measure of progress
n Accomplishment Criteria –
Design Proof of Concept
Complete
n Each AC is the “exit
criteria” for the collection of
tasks (work) performed in the
schedule and is the criteria
for judging the completion
and the resulting maturity of
the work effort
n Tasks
n Each task participates in the
completion of the AC
n No partial completion of the
task is allowed in the
completion of the AC
n A strict parent child
relationship is used for all
relationships 1 Nov 06V7
21/24
Constructing an Event Based Schedule is more work than just writing down the list of tasks and linking
them in a network. That’s easy The result makes visible what Done looks like in ways no list of
connected tasks ever can.
+
We Did It On Time, On Budget, On
Spec?
n If we know ahead of time what
done looks like …
n … we measure can progress
toward done in technical
performance units of measure
that describe the increasing
maturity and value of the
deliverables,rather than
consumption of time and
resources.
n Then we can tell our
customers – with a straight
face – how much value we’
ve created for their
investment, how much work
remains, an estimate of when
we’ll be done, and an estimate
of how much it will cost when
we’re done.
n If we use Event Based
Scheduling, progress can be
measured in terms understood
by all the participants –
consumer and supplier – in
units of measure of “done”
1 Nov 06V7
22/24
+
Our Garage Project Is A Success …
1 Nov 06V7
23/24
A Job Well DoneAnd The Kids Are Happy, with …
+
n Poinephobia - An
abnormal, persistent fear of
punishment
n Enissophobia – a fear
having committed an
unpardonable sin or
criticism
n Decidophobia – a fear of
making decisions
n Atychipohbia – a fear of
failure
1 Nov 06V7
24/24
But first,what are those words in the sign two slides back?
1 Nov 06V7
25/24

More Related Content

Similar to Event Based Scheduling Brown Bag

Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bagGlen Alleman
 
Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bagGlen Alleman
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based PlanningGlen Alleman
 
General Project Management 2003
General Project Management 2003General Project Management 2003
General Project Management 2003Sidewinder2011
 
OpEx-8D-Problem-Solving-Process-ASQ-Overview.pdf
OpEx-8D-Problem-Solving-Process-ASQ-Overview.pdfOpEx-8D-Problem-Solving-Process-ASQ-Overview.pdf
OpEx-8D-Problem-Solving-Process-ASQ-Overview.pdfDeepakMore54
 
From Lean Six Sigma to Strategy Execution...
From Lean Six Sigma to Strategy Execution...From Lean Six Sigma to Strategy Execution...
From Lean Six Sigma to Strategy Execution...Grant Crow
 
A Gentle Introduction to Deliverables Based Planning
A Gentle Introduction to Deliverables Based PlanningA Gentle Introduction to Deliverables Based Planning
A Gentle Introduction to Deliverables Based PlanningGlen Alleman
 
Project Management How To
Project Management How ToProject Management How To
Project Management How Tokellyfrey
 
SUCCESS STORY: Reducing Activity Planning Lead Time by 81%
SUCCESS STORY: Reducing Activity Planning Lead Time by 81%SUCCESS STORY: Reducing Activity Planning Lead Time by 81%
SUCCESS STORY: Reducing Activity Planning Lead Time by 81%GoLeanSixSigma.com
 
Parametric project metrics
Parametric project metricsParametric project metrics
Parametric project metricsGlen Alleman
 
LLCprocessimprovement
LLCprocessimprovementLLCprocessimprovement
LLCprocessimprovementslidewayne
 
Project assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedProject assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedTerje Sæbø
 
Art of Project Management - Make Things Done On Time
Art of Project Management - Make Things Done On TimeArt of Project Management - Make Things Done On Time
Art of Project Management - Make Things Done On Timecalvinbiz0514
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
5 Project Management Steps to Boost Company Success (1).pdf
5 Project Management Steps to Boost Company Success (1).pdf5 Project Management Steps to Boost Company Success (1).pdf
5 Project Management Steps to Boost Company Success (1).pdfeducationedge.ca
 
Six Sigma Green Belt Training Part 4
Six Sigma Green Belt Training Part 4Six Sigma Green Belt Training Part 4
Six Sigma Green Belt Training Part 4Skillogic Solutions
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)Glen Alleman
 

Similar to Event Based Scheduling Brown Bag (20)

Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bag
 
Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bag
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based Planning
 
General Project Management 2003
General Project Management 2003General Project Management 2003
General Project Management 2003
 
OpEx-8D-Problem-Solving-Process-ASQ-Overview.pdf
OpEx-8D-Problem-Solving-Process-ASQ-Overview.pdfOpEx-8D-Problem-Solving-Process-ASQ-Overview.pdf
OpEx-8D-Problem-Solving-Process-ASQ-Overview.pdf
 
From Lean Six Sigma to Strategy Execution...
From Lean Six Sigma to Strategy Execution...From Lean Six Sigma to Strategy Execution...
From Lean Six Sigma to Strategy Execution...
 
A Gentle Introduction to Deliverables Based Planning
A Gentle Introduction to Deliverables Based PlanningA Gentle Introduction to Deliverables Based Planning
A Gentle Introduction to Deliverables Based Planning
 
Project Management How To
Project Management How ToProject Management How To
Project Management How To
 
SUCCESS STORY: Reducing Activity Planning Lead Time by 81%
SUCCESS STORY: Reducing Activity Planning Lead Time by 81%SUCCESS STORY: Reducing Activity Planning Lead Time by 81%
SUCCESS STORY: Reducing Activity Planning Lead Time by 81%
 
Project Management
Project ManagementProject Management
Project Management
 
Parametric project metrics
Parametric project metricsParametric project metrics
Parametric project metrics
 
Executing Successful Projects
Executing  Successful  ProjectsExecuting  Successful  Projects
Executing Successful Projects
 
LLCprocessimprovement
LLCprocessimprovementLLCprocessimprovement
LLCprocessimprovement
 
Project assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expectedProject assurance - make sure your projects delivers as expected
Project assurance - make sure your projects delivers as expected
 
Art of Project Management - Make Things Done On Time
Art of Project Management - Make Things Done On TimeArt of Project Management - Make Things Done On Time
Art of Project Management - Make Things Done On Time
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
5 Project Management Steps to Boost Company Success (1).pdf
5 Project Management Steps to Boost Company Success (1).pdf5 Project Management Steps to Boost Company Success (1).pdf
5 Project Management Steps to Boost Company Success (1).pdf
 
Six Sigma Green Belt Training Part 4
Six Sigma Green Belt Training Part 4Six Sigma Green Belt Training Part 4
Six Sigma Green Belt Training Part 4
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)
 
Pm1011 stockton 3hr 2014
Pm1011 stockton 3hr 2014Pm1011 stockton 3hr 2014
Pm1011 stockton 3hr 2014
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Recently uploaded

What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 

Recently uploaded (20)

What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 

Event Based Scheduling Brown Bag

  • 1. + Event Based Scheduling OK kids,We’re gonna paint the garage floor. Everyone off the couch and in the garage with smiles on your little faces V7 1/24 Dad’s gonna “program manage” your efforts to a successful outcome using Event Based Scheduling 10 November 2006
  • 2. + Core Problem of all Project’s n Collecting project costs is relatively easy n Obtaining real physical progress status of ongoing activities is much more difficult n This is the 90% syndrome – or in some cases the 80% syndrome n When physical progress is reported by the activity owners,without a way to cross check of the achievement – true progress is often hidden n Om many cases progress is equated to the passage of time and consumption of money n Replacing this progress–oriented reporting with deliverables– oriented reporting is the starting point of real performance management – an authentic,trusted and verifiable performance measurement 1 Nov 06V7 2/24 Failed or underperforming projects are more common than not. Learning how to address one of the problems found in troubled projects is the topic of this Brown Bag session
  • 3. + Themes of Event Based Scheduling n Progress is measured by the completion of Significant Accomplishments (SA) n The evidence of this progress is provided by the Accomplishment Criteria (AC) n Task progress is only measured as 0% or 100%. No partial credit,no percent complete – either its done or it’s not done, either we’ve accomplished our accomplishment or we haven’t n The “architecture”of the project describes the increasing value maturity of the deliverables through the completion of the Significant Accomplishments n Defining what “done” looks like and scheduling backward, tells us when we should have started the project 1 Nov 06V7 3/24
  • 4. + Events For Our Family Garage Project n When asked to “make a plan,” our first impulse is to make a list for all the work to be performed.Here’s a list of the garage floor painting work … n All our sports “stuff” cleaned up n Get the garage floor washed and dried n Put down epoxy sealer and let it dry n Paint the car stalls n Put everything back n Park the cars and close the doors n Let’s just focus on item #1 1 Nov 06V7 4/24 Events are celebratory occasions, where a collection of Significant Accomplishments has been “accomplished” with measurable outcomes, judged by the Accomplishment Criteria for the work performed
  • 5. + First Some Definitions n Event – A major transition point in the project. The place where the maturity of the deliverables can be assessed to determine if we should proceed to the next step n Significant Accomplishment – An interim, critical, or discrete activity that must be completed prior to an Event n Accomplishment Criteria – A measurable indicator of the evidence that increased maturity or progress has been made towards a Significant Accomplishment n Task – The work performed in support of accomplishments and their criteria 1 Nov 06V7 5/24 There are some new terms we’ll need to use when we’re speaking in the “Event Based Scheduling” vocabulary
  • 6. + Get“stuff” Cleaned Up Event n It needs a finite duration n There needs to be a clear and concise definition “cleaned up” n Measures of success need to be defined n When we reach the logical stopping point when “all” the stuff is cleaned up – Mom says its time for lunch is not a very good measure of success n There are clear and concise benefits to getting to this point n We could stop here and still havebenefits 1 Nov 06V7 6/24 Let’s look at the details of our first Event – “all the sports stuff cleaned up”
  • 7. + Event:“All the stuff cleaned up”– Let’s Eat n Significant Accomplishment (SA) n Interim, critical or discrete activity required to complete prior to an event n All Baseball Equipment Located and collected for storage n Accomplishment Criteria (AC) n Measurableindicators of evidence that demonstrates the achievement of maturity or progress in an activity n Bats, gloves, pads, and uniforms placed in their labeled bags and hung on hooks 1 Nov 06V7 7/24 A Significant Accomplishment (SA) is getting all the baseball gear into bags, hung on the wall, bats in a bag, and batting helmets in their racks
  • 8. + Significant Accomplishment (SA) n SA:Baseball Equipment Stored in Assigned Location n The Accomplishment Criteria for completing this Significant Accomplishment includes: n Location for each baseball item identified n Pads, balls, hats gloves located, sorted, and placed in a pile of like stuff n Bats located and loaded into a single bat bag n Equipment bags located, emptied of food, drinks, and mice droppings 1 Nov 06V7 8/24 The Significant Accomplishment of getting all the Baseball gear into bags is measured by the completion of the Accomplishment Criteria
  • 9. + Accomplishment Criteria (AC) n AC: Locations defined for each identified item n Tasks to complete the AC include: n Labeling all bags with their contents n Cleaning the bags n Determining if the bag can hold the equipment n Finding new bags, if there is not enough room in the current ones 1 Nov 06V7 9/24 Accomplishment Criteria (AC) is the Exit Criteria for the work performed by the Tasks. When all the work is done, the AC is 100% complete
  • 10. + Project Management According to Yogi† n Planning n You’ve got to be very careful if you don’t know where you’re going,because you might not get there n Communicating n I didn’t really say everything I said n Decision Making n If you come to a fork in the road, take it n Measuring progress n You’d better cut the pizza in four pieces,because I’m not hungry enough to eat six n Executing n Think? How the hell are you gonna think and hit at the same time? n Managing n You can observe a lot just by watching n Meeting deadlines n I knew I was going to take the wrong train,so I left early n Closeout n This is like déjà vu all over again 1 Nov 06V7 10/24 † “Yogi Berra, PMP,” Ralph Sacco, Computer World, October 23, 2006, pp. 44
  • 11. + OK,Enough Baseball Let’s have a business example that moves us from the old world of time and cost measurement to the new world of accomplishments and exit criteria 1 Nov 06 V7 11/24
  • 12. + Provisioning a New Employee 1 Nov 06V7 12/24 Human ResourcesNew Employee Ready to Work Insurance Orientation Laptop Account Setup Charge account setup Information Technology Finance Buying authority Supply Chain Management Significant Accomplishments Project Event New Employee Ready for Work Project Event New Employee Arrives A new employee arrives. What needs to happen before she can be productive? How can we measure the progress toward being productive?
  • 13. + Structure of the Event Based Schedule 1 Nov 06V7 13/24 Business StrategyBusiness Strategy Process StepProcess Step WBS Element or Subsystem EventsEvents TasksTasks Accomplishments CriteriaCriteria Significant Accomplishments (SA) Accomplishment Criteria (AC) SubsystemSubsystem State of the Project State of the Project State of the Capability State of the Process Demonstrates Maturity Identifies End Item How Defines Customer/Program Direction Program/Team Direction Team Direction Performance Team Status Team Status Something Completed Effort Expended DeliverablesDeliverables
  • 14. + Describing “Done” in a Single Phrase 1 Nov 06V7 14/24 Perform Work MaturityMaturity Adjective ActionAction Verb ProvisioningFinal CapabilityCapability Noun Desktop Demonstrates Maturity End Item “A01B02a: Preliminary Month End Close of the General Ledger Complete ”“A01B02a: Final Desktop Provisioning of New Employee Complete” Step in the Process StateState Verb Complete Closure State
  • 15. + One More Review of Our New Terminology n Events – define the state of the project n Significant Accomplishments –demonstrate the state of the capability n This is the assessment of maturity of the deliverable at a point in time n Accomplishment Criteria – demonstrates the state of the process n Task – describes the effort required to complete the Accomplishment Criteria 1 Nov 06V7 15/24 The terms of Event Based Scheduling need to be repeated over and over. This helps replace our temporal progress thinking with event maturity thinking
  • 16. + And Some More Detail Of These Terms n A Significant Accomplishment describes … n A desired result n A discrete step in a process n A description of an interrelationship n An Accomplishment Criteria describes … n Completed work effort n Activities that confirm the value n Completion of critical activities 1 Nov 06V7 16/24
  • 17. + AC’s are the Central Elements of the Plan n Define the measure by which an Accomplishment (SA) is considered “done” n Terms like:complete,delivered,closed have no“units of measure”in the context of a Significant Accomplishment (SA) are weak and open to interpretation n Terms that use … n Measures of completion – 80% of training materials published n Counts of available items – 75% of entry forms approved n Fidelity of a design – 90% of Use Cases converted to UML n Error bounds – network performance within ±12% n Performance parameters – backup duration £allowable window n Maturity parameters – successful conversation completed 3 times n … are stronger definitions of the Exit Criteria 1 Nov 06V7 17/24 Defining the Accomplishment Criteria is the hard part. But they are the key to success in Event Based Scheduling, since they are the measures of “done”
  • 18. + Primary Motivation – Avoid This Meeting! n Project management is not about forecasting the future n Project Management is about understanding risks that impact the future n Project Management is about making visible what “done” looks like n Project Management is about staying ahead of risk the curve 1 Nov 06V7 18/24 Would you please elaborate on “Then Something Bad Happened”
  • 19. + Nine Principles of Project Management n Systematic and integrative planning – maximum influence comes early in the project n Timely decisions adjusted to uncertainty – objectives first,the means to fulfill next n Isolation and Absorption of Risk – organize project elements to maintain stability and isolate undesired results n Leadership is Both Inward and Outward – leadership copes with uncertainty, management copes with complexity n Teamwork – emphasize cooperation rather than risk allocation n Overlapping Phases – pay great attention to pre–existing activities n Simple Procedures – prevent re– invention,contribute to cooperation,and establish internal stability n Intensive Communication – fit the intensity and mode of communication to the situation n Systematic Monitoring – identifying and correcting small problems is easy,identifying large problems is easy, correcting them is hard 1 Nov 06V7 19/24 Event Based Scheduling is the basis for these Nine Principles (or any other favorite principles of project management)
  • 20. + An Event Based Schedule 1 Nov 06V7 20/24 Event Significant Accomplishment Accomplishment Criteria Tasks Here’s an example of a project that rolls out Microsoft Project Server™
  • 21. + Our Working Example n Event – Phase A/B of the enterprise project server deployment is complete n All the deliverables,activities to deliver those deliverables,and the criteria by which those deliverables were measured have been completed n Significant Accomplishment – the Governance and Review Groups have been established n There are 2 “exit criteria” shown representing the “evidence” that these review groups have been established n The completion of these “exit criteria” is a clear and concise measure of progress n Accomplishment Criteria – Design Proof of Concept Complete n Each AC is the “exit criteria” for the collection of tasks (work) performed in the schedule and is the criteria for judging the completion and the resulting maturity of the work effort n Tasks n Each task participates in the completion of the AC n No partial completion of the task is allowed in the completion of the AC n A strict parent child relationship is used for all relationships 1 Nov 06V7 21/24 Constructing an Event Based Schedule is more work than just writing down the list of tasks and linking them in a network. That’s easy The result makes visible what Done looks like in ways no list of connected tasks ever can.
  • 22. + We Did It On Time, On Budget, On Spec? n If we know ahead of time what done looks like … n … we measure can progress toward done in technical performance units of measure that describe the increasing maturity and value of the deliverables,rather than consumption of time and resources. n Then we can tell our customers – with a straight face – how much value we’ ve created for their investment, how much work remains, an estimate of when we’ll be done, and an estimate of how much it will cost when we’re done. n If we use Event Based Scheduling, progress can be measured in terms understood by all the participants – consumer and supplier – in units of measure of “done” 1 Nov 06V7 22/24
  • 23. + Our Garage Project Is A Success … 1 Nov 06V7 23/24 A Job Well DoneAnd The Kids Are Happy, with …
  • 24. + n Poinephobia - An abnormal, persistent fear of punishment n Enissophobia – a fear having committed an unpardonable sin or criticism n Decidophobia – a fear of making decisions n Atychipohbia – a fear of failure 1 Nov 06V7 24/24 But first,what are those words in the sign two slides back?