A large food manufacturer was losing a significant amount of heat energy from its steam boiler and pipework, resulting in high energy costs and safety risks. ERIKS conducted a non-disruptive steam audit to identify issues. They found that inadequate insulation on the pipework was causing heat loss and increased energy usage. ERIKS and partner Enersol Flomar installed a custom insulation solution on the boiler and pipework within two weeks with no production interruption. This insulation solution reduced energy consumption and saved the customer over £13,500 per year with a 12 month payback period.