AL WORKSTO DESIGN THE ELECTRICESSENTIAL FACTORS
1. All rooms identification in English & Arabic
2. All design as per MEW latest regulation.
3. Design Electrical load at least 20% more for future.
4. Legend & mounting height is according to MEW standard.
5. Furniture layout drawing is require to ensure numbers and location of power outlet.
6. False ceiling drawing is required to confirm the light fitting type & fixing method.
7. Minimum 25cm clearance in between A/C duct & false ceiling to install light fitting.
8. Each floor need separate electrical rooms with suitable dimension for panels
9. Sub-station layout design drawing should have approval from MEW.
10. Transformers room will be in between HT & LT rooms to easy cables entry.
11. Design calculation of capacitor banks and space required 2x2m for each one in LT room.
12. Separate suitable riser or shaft for electrical cables from LT panel to all feeders.
13. Parallel cables are required instead of higher size cables.
14. Maximum load of MSB should not exceed 200kw & DB 25kw.
15. MSBs and DBs have 25% breakers spare for future.
16. Cable trays have 20% free space for future cables.
17. A/C and Mechanical equipments load schedules sheet.
18. Voltage drop calculation from LT panel upto DBs and S/Fs for each cables
19. Light fitting type and control should be suitable as per rooms & users application
20. Lux calculation should be as per MEW illumination level.
21. Busbar rating should be 25% more than main incoming breaker.
22. Earth layout drawing showing location of Earth Pit.
23. All panels should be inside electrical room.
24. Generator should be prime rating with 20% future load.
25. Space between Generators base and walls should be one meter for cables trench and motors installation.
26. Under- ground fuel tank and daily fuel tank capacity approved by KNPC & KFB.
27. Telephone design drawing should be approved from ministry of communication.
28. Fire Alarm design drawing should be approved from KFB.
29. All pumps motors, Lifts, and Smoke Fans power supply from Generators.
30. All Pumps motors, Lifts, Fresh Air Fans and Smoke Fans should be protected by AVA+ ELRs.
(Eng. Mohammed Atahar Ali)
Planning section (Electrical & Low voltage)
Engineering Affairs Dept.

More Related Content

Viewers also liked

Electrical System Design Initial
Electrical System Design InitialElectrical System Design Initial
Electrical System Design InitialMohammed Atahar Ali
 
ELECTRICAL DESIGN ENGINEER - RESUME
ELECTRICAL DESIGN ENGINEER -  RESUMEELECTRICAL DESIGN ENGINEER -  RESUME
ELECTRICAL DESIGN ENGINEER - RESUMEVEERABHARATHI MUNI
 
Electrical Standard Products Catalogue
Electrical Standard Products CatalogueElectrical Standard Products Catalogue
Electrical Standard Products CatalogueLarsen & Toubro E & A
 
design electrical engineer cv
design electrical engineer cvdesign electrical engineer cv
design electrical engineer cvsaryhasabadly
 

Viewers also liked (6)

Electrical System Design Initial
Electrical System Design InitialElectrical System Design Initial
Electrical System Design Initial
 
Transformer
TransformerTransformer
Transformer
 
ELECTRICAL DESIGN ENGINEER - RESUME
ELECTRICAL DESIGN ENGINEER -  RESUMEELECTRICAL DESIGN ENGINEER -  RESUME
ELECTRICAL DESIGN ENGINEER - RESUME
 
ELECTRICAL ENGINEER CV
ELECTRICAL ENGINEER CVELECTRICAL ENGINEER CV
ELECTRICAL ENGINEER CV
 
Electrical Standard Products Catalogue
Electrical Standard Products CatalogueElectrical Standard Products Catalogue
Electrical Standard Products Catalogue
 
design electrical engineer cv
design electrical engineer cvdesign electrical engineer cv
design electrical engineer cv
 

Similar to Electrical design fo Ministry Awqaf.

Seektronics.com 64 skills about switching power supply design
Seektronics.com 64 skills about switching power supply designSeektronics.com 64 skills about switching power supply design
Seektronics.com 64 skills about switching power supply designPaddyWang4
 
Advances in Ceramic Capacitors
Advances in Ceramic CapacitorsAdvances in Ceramic Capacitors
Advances in Ceramic CapacitorsRandall Ghany
 
Cable size available guidelines network design
Cable size available guidelines network designCable size available guidelines network design
Cable size available guidelines network designManikandan Mani
 
Indian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyIndian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyMahesh Chandra Manav
 
Utility Basic Details in Ahmedabad Railway Station Re Development.pptx
Utility Basic Details in Ahmedabad Railway Station Re Development.pptxUtility Basic Details in Ahmedabad Railway Station Re Development.pptx
Utility Basic Details in Ahmedabad Railway Station Re Development.pptxMoturiVinodKumar
 
Project List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerProject List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerReza Shah Abadi
 
Project List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerProject List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerReza Shah Abadi
 
A Project Report On MINI INVERTER 12V TO 220V
A Project Report On MINI INVERTER 12V TO 220VA Project Report On MINI INVERTER 12V TO 220V
A Project Report On MINI INVERTER 12V TO 220VJoe Andelija
 
Small_Cabin_PV_Design
Small_Cabin_PV_DesignSmall_Cabin_PV_Design
Small_Cabin_PV_DesignJames Koehler
 
Offshore Converters for Multimegawatt Wind Turbines
Offshore Converters for Multimegawatt Wind TurbinesOffshore Converters for Multimegawatt Wind Turbines
Offshore Converters for Multimegawatt Wind TurbinesIngeteam Wind Energy
 
Prefabricated compact transformer
Prefabricated compact transformerPrefabricated compact transformer
Prefabricated compact transformerJoeChueng
 
17416 industrial electrical system-i
17416 industrial electrical system-i17416 industrial electrical system-i
17416 industrial electrical system-isoni_nits
 
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working modelgiriraj bairwa
 
Learn how EMC simulation can be used as an up-front design tool
Learn how EMC simulation can be used as an up-front design tool Learn how EMC simulation can be used as an up-front design tool
Learn how EMC simulation can be used as an up-front design tool Torben Haagh
 

Similar to Electrical design fo Ministry Awqaf. (20)

Seektronics.com 64 skills about switching power supply design
Seektronics.com 64 skills about switching power supply designSeektronics.com 64 skills about switching power supply design
Seektronics.com 64 skills about switching power supply design
 
11.docx
11.docx11.docx
11.docx
 
Advances in Ceramic Capacitors
Advances in Ceramic CapacitorsAdvances in Ceramic Capacitors
Advances in Ceramic Capacitors
 
Advances in Ceramic Capacitors
Advances in Ceramic CapacitorsAdvances in Ceramic Capacitors
Advances in Ceramic Capacitors
 
Cable size available guidelines network design
Cable size available guidelines network designCable size available guidelines network design
Cable size available guidelines network design
 
Indian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyIndian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periorty
 
Utility Basic Details in Ahmedabad Railway Station Re Development.pptx
Utility Basic Details in Ahmedabad Railway Station Re Development.pptxUtility Basic Details in Ahmedabad Railway Station Re Development.pptx
Utility Basic Details in Ahmedabad Railway Station Re Development.pptx
 
PROJECT ENGINEER- ELECTRICAL._L
PROJECT ENGINEER-  ELECTRICAL._LPROJECT ENGINEER-  ELECTRICAL._L
PROJECT ENGINEER- ELECTRICAL._L
 
Project List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerProject List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical Enginner
 
Project List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical EnginnerProject List 1.3-May21,16- Substation Electrical Enginner
Project List 1.3-May21,16- Substation Electrical Enginner
 
A Project Report On MINI INVERTER 12V TO 220V
A Project Report On MINI INVERTER 12V TO 220VA Project Report On MINI INVERTER 12V TO 220V
A Project Report On MINI INVERTER 12V TO 220V
 
Small_Cabin_PV_Design
Small_Cabin_PV_DesignSmall_Cabin_PV_Design
Small_Cabin_PV_Design
 
Ijecet 06 09_011
Ijecet 06 09_011Ijecet 06 09_011
Ijecet 06 09_011
 
Offshore Converters for Multimegawatt Wind Turbines
Offshore Converters for Multimegawatt Wind TurbinesOffshore Converters for Multimegawatt Wind Turbines
Offshore Converters for Multimegawatt Wind Turbines
 
Mohd_Anwarulla
Mohd_AnwarullaMohd_Anwarulla
Mohd_Anwarulla
 
avi
aviavi
avi
 
Prefabricated compact transformer
Prefabricated compact transformerPrefabricated compact transformer
Prefabricated compact transformer
 
17416 industrial electrical system-i
17416 industrial electrical system-i17416 industrial electrical system-i
17416 industrial electrical system-i
 
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working model
 
Learn how EMC simulation can be used as an up-front design tool
Learn how EMC simulation can be used as an up-front design tool Learn how EMC simulation can be used as an up-front design tool
Learn how EMC simulation can be used as an up-front design tool
 

Electrical design fo Ministry Awqaf.

  • 1. AL WORKSTO DESIGN THE ELECTRICESSENTIAL FACTORS 1. All rooms identification in English & Arabic 2. All design as per MEW latest regulation. 3. Design Electrical load at least 20% more for future. 4. Legend & mounting height is according to MEW standard. 5. Furniture layout drawing is require to ensure numbers and location of power outlet. 6. False ceiling drawing is required to confirm the light fitting type & fixing method. 7. Minimum 25cm clearance in between A/C duct & false ceiling to install light fitting. 8. Each floor need separate electrical rooms with suitable dimension for panels 9. Sub-station layout design drawing should have approval from MEW. 10. Transformers room will be in between HT & LT rooms to easy cables entry. 11. Design calculation of capacitor banks and space required 2x2m for each one in LT room. 12. Separate suitable riser or shaft for electrical cables from LT panel to all feeders. 13. Parallel cables are required instead of higher size cables. 14. Maximum load of MSB should not exceed 200kw & DB 25kw. 15. MSBs and DBs have 25% breakers spare for future. 16. Cable trays have 20% free space for future cables. 17. A/C and Mechanical equipments load schedules sheet. 18. Voltage drop calculation from LT panel upto DBs and S/Fs for each cables 19. Light fitting type and control should be suitable as per rooms & users application 20. Lux calculation should be as per MEW illumination level. 21. Busbar rating should be 25% more than main incoming breaker. 22. Earth layout drawing showing location of Earth Pit. 23. All panels should be inside electrical room. 24. Generator should be prime rating with 20% future load. 25. Space between Generators base and walls should be one meter for cables trench and motors installation. 26. Under- ground fuel tank and daily fuel tank capacity approved by KNPC & KFB. 27. Telephone design drawing should be approved from ministry of communication. 28. Fire Alarm design drawing should be approved from KFB. 29. All pumps motors, Lifts, and Smoke Fans power supply from Generators. 30. All Pumps motors, Lifts, Fresh Air Fans and Smoke Fans should be protected by AVA+ ELRs. (Eng. Mohammed Atahar Ali) Planning section (Electrical & Low voltage) Engineering Affairs Dept.