The document describes a pilot project in Nafplio, Greece to treat and reuse wastewater from a fruit processing plant. A mobile pilot plant was installed to extract high-value compounds from the wastewater using adsorption and subcritical water extraction. The residual wastewater would then be treated using an advanced oxidation process and a small bioreactor platform for polishing before being reused for irrigation or discharged. Laboratory experiments were conducted to test the individual technologies and the pilot units have been installed and are operational, with the goal of achieving 100% water reuse and a 90% reduction in freshwater use.
The document discusses two operational demo cases in Nafplio, Greece. The first case involves reusing wastewater from a fruit processing plant through a hybrid adsorption/SubCritical Water Extraction process to extract high-value compounds for reuse. The treated wastewater will then be further polished and reused for irrigation. The second case involves recovering antioxidants from the wastewater through adsorption and extraction processes. Laboratory experiments showed these processes can recover 50-70% of polyphenols. Pilot plants for both cases have been designed and are being constructed to test the technologies at a larger scale.
This document summarizes the operational demo cases for CS4 Nafplio in Greece. Pilot wastewater treatment and recovery technologies are being implemented at a fruit processing plant to treat wastewater onsite for irrigation reuse. Laboratory experiments show the technologies effectively remove organic matter and recover high-value compounds. The pilot system has been installed and initial results are promising, with the goal of 100% water reuse for irrigation and reducing freshwater use by 90%.
This document discusses the status of various operational demo cases for the CS5 Lleida project. It summarizes the progress of Subtask 1.3.2, which involves anaerobic pretreatment of brewery wastewater and electricity production via solid-oxide fuel cell. The key technologies being tested are an anaerobic membrane bioreactor, an electrostimulated anaerobic reactor, and a solid oxide fuel cell. Pilot-scale tests indicate these technologies could produce biogas and electricity from wastewater at target capacities while advancing the technologies from TRL 7 to 9.
This document discusses the status of a project involving wastewater treatment and energy production at a brewery in Lleida, Spain. It describes using an anaerobic membrane bioreactor and electrostimulated anaerobic reactor to produce biogas from brewery wastewater, and a solid oxide fuel cell to generate electricity from the biogas. The systems are in various stages, with the anaerobic membrane bioreactor currently commissioning and expected to produce 20,000 cubic meters of biogas per year. The project aims to foster circular economy practices through energy recovery from wastewater.
The document summarizes a pilot project in Kalundborg, Denmark that is testing novel membrane treatment technologies to produce high-quality water for reuse from municipal wastewater effluent. Two pilot plants were constructed to test a conventional ultrafiltration membrane versus a novel tight ultrafiltration membrane, followed by reverse osmosis. The goals are to increase water reuse, reduce energy usage, and explore nutrient/product recovery. Water quality data and pilot performance will be evaluated under different treatment scenarios to assess water production and fouling prevention. Videos of the operating pilot plants are available online. The project is on schedule, with the pilots now operational.
The document provides details about operational demo cases for CS5 Lleida. It summarizes the status and progress of various subtasks involving new technologies to improve wastewater treatment and resource recovery at the Lleida brewery. These include a pilot system for water reuse using NF, RO and AOP/UV (subtask 1.2.5), an AnMBR and SOFC for energy production from wastewater (subtask 1.3.2), and plans for an ELSAR reactor. The NF, RO and SOFC systems are currently being installed and commissioned, while the ELSAR awaits building permits. Photos show the installed treatment systems and design drawings.
The document describes the operational demo cases for CS7 Tain. It discusses several subtasks involving new technologies to treat and reuse distillery wastewater, including: 1) reverse osmosis to treat anaerobically digested wastewater for reuse, 2) heat recovery from treated wastewater, and 3) ammonia recovery via air stripping and struvite precipitation. Laboratory experiments and pilot demonstrations are underway or planned for various subtasks. The timelines indicate some delays but still sufficient time to complete the work by the end of the project.
The document discusses several operational demo cases for treating and recycling distillery wastewater in Tain, Scotland. It summarizes the status of various subtasks involving reverse osmosis (RO) treatment, heat recovery, and nutrient recovery through struvite precipitation and ammonia stripping. Laboratory and pilot experiments have been conducted on RO, stripping columns are in use, and initial results are promising for reducing water and energy usage through treatment and reuse.
The document discusses two operational demo cases in Nafplio, Greece. The first case involves reusing wastewater from a fruit processing plant through a hybrid adsorption/SubCritical Water Extraction process to extract high-value compounds for reuse. The treated wastewater will then be further polished and reused for irrigation. The second case involves recovering antioxidants from the wastewater through adsorption and extraction processes. Laboratory experiments showed these processes can recover 50-70% of polyphenols. Pilot plants for both cases have been designed and are being constructed to test the technologies at a larger scale.
This document summarizes the operational demo cases for CS4 Nafplio in Greece. Pilot wastewater treatment and recovery technologies are being implemented at a fruit processing plant to treat wastewater onsite for irrigation reuse. Laboratory experiments show the technologies effectively remove organic matter and recover high-value compounds. The pilot system has been installed and initial results are promising, with the goal of 100% water reuse for irrigation and reducing freshwater use by 90%.
This document discusses the status of various operational demo cases for the CS5 Lleida project. It summarizes the progress of Subtask 1.3.2, which involves anaerobic pretreatment of brewery wastewater and electricity production via solid-oxide fuel cell. The key technologies being tested are an anaerobic membrane bioreactor, an electrostimulated anaerobic reactor, and a solid oxide fuel cell. Pilot-scale tests indicate these technologies could produce biogas and electricity from wastewater at target capacities while advancing the technologies from TRL 7 to 9.
This document discusses the status of a project involving wastewater treatment and energy production at a brewery in Lleida, Spain. It describes using an anaerobic membrane bioreactor and electrostimulated anaerobic reactor to produce biogas from brewery wastewater, and a solid oxide fuel cell to generate electricity from the biogas. The systems are in various stages, with the anaerobic membrane bioreactor currently commissioning and expected to produce 20,000 cubic meters of biogas per year. The project aims to foster circular economy practices through energy recovery from wastewater.
The document summarizes a pilot project in Kalundborg, Denmark that is testing novel membrane treatment technologies to produce high-quality water for reuse from municipal wastewater effluent. Two pilot plants were constructed to test a conventional ultrafiltration membrane versus a novel tight ultrafiltration membrane, followed by reverse osmosis. The goals are to increase water reuse, reduce energy usage, and explore nutrient/product recovery. Water quality data and pilot performance will be evaluated under different treatment scenarios to assess water production and fouling prevention. Videos of the operating pilot plants are available online. The project is on schedule, with the pilots now operational.
The document provides details about operational demo cases for CS5 Lleida. It summarizes the status and progress of various subtasks involving new technologies to improve wastewater treatment and resource recovery at the Lleida brewery. These include a pilot system for water reuse using NF, RO and AOP/UV (subtask 1.2.5), an AnMBR and SOFC for energy production from wastewater (subtask 1.3.2), and plans for an ELSAR reactor. The NF, RO and SOFC systems are currently being installed and commissioned, while the ELSAR awaits building permits. Photos show the installed treatment systems and design drawings.
The document describes the operational demo cases for CS7 Tain. It discusses several subtasks involving new technologies to treat and reuse distillery wastewater, including: 1) reverse osmosis to treat anaerobically digested wastewater for reuse, 2) heat recovery from treated wastewater, and 3) ammonia recovery via air stripping and struvite precipitation. Laboratory experiments and pilot demonstrations are underway or planned for various subtasks. The timelines indicate some delays but still sufficient time to complete the work by the end of the project.
The document discusses several operational demo cases for treating and recycling distillery wastewater in Tain, Scotland. It summarizes the status of various subtasks involving reverse osmosis (RO) treatment, heat recovery, and nutrient recovery through struvite precipitation and ammonia stripping. Laboratory and pilot experiments have been conducted on RO, stripping columns are in use, and initial results are promising for reducing water and energy usage through treatment and reuse.
The document discusses an operational demo case in Rosignano, Italy. It describes the current wastewater treatment situation and objectives to improve it using local by-products. Laboratory and pilot testing was conducted on activated hydrochar made from hydrochar, a waste product. Testing showed the hydrochar had higher COD and diclofenac removal rates than commercial activated carbon. By-products from local industries were also tested for softening, coagulation and flocculation, reducing COD and minerals. A pilot system was constructed using the hydrochar and is scheduled to be operational in June 2022 to further test and optimize the solutions. The timeline aims to have start-up results by month 19 and best practices identified by month 25
This document summarizes a pilot project testing novel membrane treatments for water reuse from municipal wastewater treatment plants in Kalundborg, Denmark. The project aims to produce high-quality water using ultrafiltration or nanofiltration followed by reverse osmosis to increase water recycling. Pilot plants are operating two treatment trains - one with a conventional ultrafiltration membrane and one with a novel ultra-tight ultrafiltration membrane. The pilots aim to compare membrane performance in preventing fouling and producing water suitable for reuse. Initial results indicate the task is progressing on schedule despite issues with pre-treatment options due to energy supply problems.
This document discusses an operational demo case for a wastewater treatment plant in Lleida, Spain. It describes:
1) The existing wastewater treatment process and sludge management.
2) Objectives to implement more sustainable solutions through membrane technologies and water reuse.
3) Progress on a subtask to reuse brewery wastewater as process water through nanofiltration, reverse osmosis, and advanced oxidation processes. Pilot systems have been set up and tested to produce water meeting quality standards for reuse.
This document discusses the operational demo cases for the CS3 site in Rosignano, Italy. It summarizes the status of Subtask 1.4.2, which aims to use by-products from local industries for wastewater treatment. Laboratory and pilot tests show that activated hydrochar produced better adsorption results for COD and diclofenac removal compared to commercial activated carbon. Pilot systems for adsorption, advanced oxidation, and clariflocculation are being constructed and tested to further improve wastewater treatment using local by-products.
The document discusses an operational demo case in Rosignano, Italy. It describes the current wastewater treatment situation and objectives to improve it using local by-products. Pilot systems are being tested using adsorption columns with activated hydrochar and an AOP pilot plant. Initial results show reductions in COD and fluorescence indicators. The timeline outlines progress made so far and plans to complete pilot experiments and share best practices for material recovery.
D1.2-Demonstrator Case Study Karmiel/ShafdanDrKristineJung
The document describes two operational demo cases in Israel - Karmiel and Shafdan. In Karmiel, an advanced anaerobic treatment process is used to produce biogas from municipal and olive mill wastewater. The system is operational and achieving its targets. In Shafdan, a new system combines anaerobic biofilm treatment with membrane filtration and activated carbon to produce biogas from agro-industrial wastewater. Laboratory experiments show initial biogas production. The system is also now operational. A separate process in Karmiel aims to recover polyphenols from olive mill wastewater using resin adsorption columns. Laboratory experiments indicate over 40% recovery is possible.
D1.2-Demonstrator Case Study Karmiel/ShafdanDrKristineJung
The document summarizes the operational demo cases for CS6 Shafdan & Karmiel. It describes the baseline technologies and ultimate solutions being tested at the Karmiel and Shafdan WWTPs. For Karmiel, an advanced anaerobic treatment process is producing biogas from municipal and olive mill wastewater, and lab experiments are recovering polyphenols from olive mill wastewater. At Shafdan, an anaerobic biofilm reactor combined with membrane filtration and activated carbon is being constructed to produce biogas from agro-industrial wastewater. Both projects are progressing on schedule with pilot systems operational or nearing operation.
The document discusses a pilot project in Tarragona, Spain that aims to increase reclaimed water availability for a petrochemical complex by 20%. It involves upgrading an existing water resource recovery plant (WRRP) and future industrial wastewater treatment plant (iWWTP) using new technologies like ultrafiltration, reverse osmosis, membrane distillation, and zeolite adsorption. Bench and pilot tests of these technologies have been completed. The pilot plant is now operational and being monitored to test the technologies and achieve the goal of reducing fresh water usage.
The document describes several operational demo cases for the CS7 Tain site. It summarizes the objectives, status, and timelines for multiple subtasks involving new technologies:
1) An RO system to treat distillery wastewater for internal water reuse, with a design capacity of 1 m3/d. The system is detailed designed and parts have been ordered.
2) A heat recovery system using heat exchangers to recover heat from treated distillery wastewater and reduce energy demands. The design is complete and parts have been ordered.
3) A two-stage system to recover nutrients from distillery wastewater involving struvite precipitation followed by ammonia stripping. The design is finished
This document discusses a case study in Tarragona, Spain to increase reclaimed water availability using new technologies. The current water resource plant and upcoming industrial wastewater treatment plant were described. The objectives are to increase reclaimed water production by 20% through membrane distillation, reverse osmosis, and ammonia removal via zeolite adsorption. Bench and pilot testing have been completed, with a pilot plant scheduled to operate starting in June 2022 to test ultrafiltration, reverse osmosis, and membrane distillation. The goal is to validate these new technologies and increase circular water usage at the petrochemical complex.
D1.2-Demonstrator Case Study Nieuw PrinsenlandDrKristineJung
The document discusses two operational demo cases for the Ultimate project. For subtask 1.2.2, laboratory experiments are being conducted to optimize water reclamation from agricultural wastewater using electrodialysis. A pilot plant is being constructed and is expected to be operational by October 2022. For subtask 1.4.1, laboratory experiments aim to recover nutrients from wastewater through selective ion removal using electrodialysis. A pilot plant for nutrient recovery is also being constructed.
D1.2-Demonstrator Case Study Nieuw PrinsenlandDrKristineJung
The document discusses two operational demo cases for the Ultimate project. For subtask 1.2.2, laboratory experiments are optimizing water reclamation from agricultural wastewater using electrodialysis. Results show 60% reduction in salts. A pilot plant will be operational in September 2022 to test the solutions. For subtask 1.4.1, the same electrodialysis process is being used to recover nutrients like potassium, nitrogen, and calcium from wastewater. Laboratory experiments show over 55% recovery of various nutrients. Both pilot plants are on track to start operations and validate the technologies.
D1.2-Demonstrator Case Study Nieuw PrinsenlandDrKristineJung
The document discusses pilot projects at Coöperatieve Tuinbouw Water Zuivering de Vlot wastewater treatment plant to optimize water reclamation and nutrient recovery from greenhouse wastewater. Laboratory and pilot-scale experiments are being conducted to selectively remove sodium and concentrate nutrients using electrodialysis. Initial results show 60% reduction in salt content and over 50% recovery of potassium, nitrogen and other nutrients. The pilots have been constructed and are operational, with the goal of validating the technologies to treat 0.1 m3/day of water and recover nutrients at a technical readiness level of 6 by the end of the projects.
D1.2-Demonstrator Case Study Karmiel/ShafdanDrKristineJung
This document describes two operational demo cases in Israel: Karmiel and Shafdan. In Karmiel, an advanced anaerobic treatment (AAT) system is processing municipal and olive mill wastewater to produce biogas. The AAT system has been constructed and is operational. In Shafdan, an anaerobic biofilm treatment membrane bioreactor (AnBTMBR) system combining AAT with activated carbon and membrane filtration has been constructed and started operation in August 2022, with sampling beginning in December 2022. The document provides details on the systems, including design, targets, status updates, operational procedures, and timeline updates for each location.
D1.2-Demonstrator Case Study Saint-Maurice l´ExilDrKristineJung
The document discusses plans to develop pilot systems to recover sulfur from flue gas and wastewater treatment effluent at a chemical platform in Roussillon, France. A laboratory pilot plant is under construction to test sulfur recovery methods from flue gas involving condensation, dust cleaning, and scrubbing. Tests are also being prepared to recover sulfur from effluent using electrolytic oxidation, flocculation, or precipitation. An industrial pilot plant will then be built and connected to the site to further test sulfur recovery at scale. The overall goal is to develop sustainable solutions to recover 80% of sulfur from both streams and advance them to a technology readiness level of 6.
D1.2-Demonstrator Case Study Saint-Maurice l´ExilDrKristineJung
The document discusses plans to recover sulfur from flue gas and wastewater treatment plant effluent at a chemical platform in Roussillon, France. A laboratory pilot plant is under construction to test sulfur recovery techniques from flue gas using condensation, dust cleaning and scrubbing. Tests are also being prepared to recover sulfur from effluent using electrolytic oxidation, flocculation or precipitation. An industrial pilot plant will then be built to apply the optimal techniques identified from the laboratory testing to recover 80% of the sulfur from both sources. The status of the subtask is provided, including timelines showing the laboratory pilot becoming operational in June 2022 and plans for the industrial pilot in November 2022.
SaltGae Project: results achieved and demo sites.SALTGAEProject
This document summarizes a stakeholder event for the Saltgae Project, which received funding from the European Union's Horizon 2020 Innovation Action programme. The project aims to develop a modular technology platform for efficiently treating saline wastewater with organic loads. The event provided an overview of the project objectives, structure, scientific approach and challenges. It also described the project's pilot sites in Ljubljana and Israel and discussed preliminary tests on sludge valorization, biomass valorization, and effluent valorization.
D1.2-Demonstrator Case Study Karmiel/ShafdanDrKristineJung
This document describes the operational demo cases for CS6 at the Karmiel and Shafdan wastewater treatment plants. It provides status updates on multiple subtasks involving advanced anaerobic treatment and biogas production, as well as recovery of high-value products from olive mill wastewater. The advanced anaerobic treatment systems at both sites are now operational, including an immobilized high-rate reactor at Karmiel and an anaerobic biofilm membrane bioreactor at Shafdan. Pilot-scale systems are also operational for polyphenol recovery from olive mill wastewater at Karmiel using adsorption and extraction. Laboratory experiments show promising results for biogas production and polyphenol removal.
This document discusses a pilot project to increase reclaimed water availability for an industrial complex in Tarragona, Spain. The project involves testing new technologies at a wastewater treatment plant and future industrial wastewater treatment plant to polish wastewater and produce additional reclaimed water. Bench scale experiments were completed with various technologies like ultrafiltration, reverse osmosis, and membrane distillation. A pilot plant was ordered to test ultrafiltration, reverse osmosis, and zeolite adsorption. The pilot system is scheduled to be operational in September 2022 to evaluate increasing reclaimed water production by at least 20% with lower energy demand.
We have compiled the most important slides from each speaker's presentation. This year’s compilation, available for free, captures the key insights and contributions shared during the DfMAy 2024 conference.
The document discusses an operational demo case in Rosignano, Italy. It describes the current wastewater treatment situation and objectives to improve it using local by-products. Laboratory and pilot testing was conducted on activated hydrochar made from hydrochar, a waste product. Testing showed the hydrochar had higher COD and diclofenac removal rates than commercial activated carbon. By-products from local industries were also tested for softening, coagulation and flocculation, reducing COD and minerals. A pilot system was constructed using the hydrochar and is scheduled to be operational in June 2022 to further test and optimize the solutions. The timeline aims to have start-up results by month 19 and best practices identified by month 25
This document summarizes a pilot project testing novel membrane treatments for water reuse from municipal wastewater treatment plants in Kalundborg, Denmark. The project aims to produce high-quality water using ultrafiltration or nanofiltration followed by reverse osmosis to increase water recycling. Pilot plants are operating two treatment trains - one with a conventional ultrafiltration membrane and one with a novel ultra-tight ultrafiltration membrane. The pilots aim to compare membrane performance in preventing fouling and producing water suitable for reuse. Initial results indicate the task is progressing on schedule despite issues with pre-treatment options due to energy supply problems.
This document discusses an operational demo case for a wastewater treatment plant in Lleida, Spain. It describes:
1) The existing wastewater treatment process and sludge management.
2) Objectives to implement more sustainable solutions through membrane technologies and water reuse.
3) Progress on a subtask to reuse brewery wastewater as process water through nanofiltration, reverse osmosis, and advanced oxidation processes. Pilot systems have been set up and tested to produce water meeting quality standards for reuse.
This document discusses the operational demo cases for the CS3 site in Rosignano, Italy. It summarizes the status of Subtask 1.4.2, which aims to use by-products from local industries for wastewater treatment. Laboratory and pilot tests show that activated hydrochar produced better adsorption results for COD and diclofenac removal compared to commercial activated carbon. Pilot systems for adsorption, advanced oxidation, and clariflocculation are being constructed and tested to further improve wastewater treatment using local by-products.
The document discusses an operational demo case in Rosignano, Italy. It describes the current wastewater treatment situation and objectives to improve it using local by-products. Pilot systems are being tested using adsorption columns with activated hydrochar and an AOP pilot plant. Initial results show reductions in COD and fluorescence indicators. The timeline outlines progress made so far and plans to complete pilot experiments and share best practices for material recovery.
D1.2-Demonstrator Case Study Karmiel/ShafdanDrKristineJung
The document describes two operational demo cases in Israel - Karmiel and Shafdan. In Karmiel, an advanced anaerobic treatment process is used to produce biogas from municipal and olive mill wastewater. The system is operational and achieving its targets. In Shafdan, a new system combines anaerobic biofilm treatment with membrane filtration and activated carbon to produce biogas from agro-industrial wastewater. Laboratory experiments show initial biogas production. The system is also now operational. A separate process in Karmiel aims to recover polyphenols from olive mill wastewater using resin adsorption columns. Laboratory experiments indicate over 40% recovery is possible.
D1.2-Demonstrator Case Study Karmiel/ShafdanDrKristineJung
The document summarizes the operational demo cases for CS6 Shafdan & Karmiel. It describes the baseline technologies and ultimate solutions being tested at the Karmiel and Shafdan WWTPs. For Karmiel, an advanced anaerobic treatment process is producing biogas from municipal and olive mill wastewater, and lab experiments are recovering polyphenols from olive mill wastewater. At Shafdan, an anaerobic biofilm reactor combined with membrane filtration and activated carbon is being constructed to produce biogas from agro-industrial wastewater. Both projects are progressing on schedule with pilot systems operational or nearing operation.
The document discusses a pilot project in Tarragona, Spain that aims to increase reclaimed water availability for a petrochemical complex by 20%. It involves upgrading an existing water resource recovery plant (WRRP) and future industrial wastewater treatment plant (iWWTP) using new technologies like ultrafiltration, reverse osmosis, membrane distillation, and zeolite adsorption. Bench and pilot tests of these technologies have been completed. The pilot plant is now operational and being monitored to test the technologies and achieve the goal of reducing fresh water usage.
The document describes several operational demo cases for the CS7 Tain site. It summarizes the objectives, status, and timelines for multiple subtasks involving new technologies:
1) An RO system to treat distillery wastewater for internal water reuse, with a design capacity of 1 m3/d. The system is detailed designed and parts have been ordered.
2) A heat recovery system using heat exchangers to recover heat from treated distillery wastewater and reduce energy demands. The design is complete and parts have been ordered.
3) A two-stage system to recover nutrients from distillery wastewater involving struvite precipitation followed by ammonia stripping. The design is finished
This document discusses a case study in Tarragona, Spain to increase reclaimed water availability using new technologies. The current water resource plant and upcoming industrial wastewater treatment plant were described. The objectives are to increase reclaimed water production by 20% through membrane distillation, reverse osmosis, and ammonia removal via zeolite adsorption. Bench and pilot testing have been completed, with a pilot plant scheduled to operate starting in June 2022 to test ultrafiltration, reverse osmosis, and membrane distillation. The goal is to validate these new technologies and increase circular water usage at the petrochemical complex.
D1.2-Demonstrator Case Study Nieuw PrinsenlandDrKristineJung
The document discusses two operational demo cases for the Ultimate project. For subtask 1.2.2, laboratory experiments are being conducted to optimize water reclamation from agricultural wastewater using electrodialysis. A pilot plant is being constructed and is expected to be operational by October 2022. For subtask 1.4.1, laboratory experiments aim to recover nutrients from wastewater through selective ion removal using electrodialysis. A pilot plant for nutrient recovery is also being constructed.
D1.2-Demonstrator Case Study Nieuw PrinsenlandDrKristineJung
The document discusses two operational demo cases for the Ultimate project. For subtask 1.2.2, laboratory experiments are optimizing water reclamation from agricultural wastewater using electrodialysis. Results show 60% reduction in salts. A pilot plant will be operational in September 2022 to test the solutions. For subtask 1.4.1, the same electrodialysis process is being used to recover nutrients like potassium, nitrogen, and calcium from wastewater. Laboratory experiments show over 55% recovery of various nutrients. Both pilot plants are on track to start operations and validate the technologies.
D1.2-Demonstrator Case Study Nieuw PrinsenlandDrKristineJung
The document discusses pilot projects at Coöperatieve Tuinbouw Water Zuivering de Vlot wastewater treatment plant to optimize water reclamation and nutrient recovery from greenhouse wastewater. Laboratory and pilot-scale experiments are being conducted to selectively remove sodium and concentrate nutrients using electrodialysis. Initial results show 60% reduction in salt content and over 50% recovery of potassium, nitrogen and other nutrients. The pilots have been constructed and are operational, with the goal of validating the technologies to treat 0.1 m3/day of water and recover nutrients at a technical readiness level of 6 by the end of the projects.
D1.2-Demonstrator Case Study Karmiel/ShafdanDrKristineJung
This document describes two operational demo cases in Israel: Karmiel and Shafdan. In Karmiel, an advanced anaerobic treatment (AAT) system is processing municipal and olive mill wastewater to produce biogas. The AAT system has been constructed and is operational. In Shafdan, an anaerobic biofilm treatment membrane bioreactor (AnBTMBR) system combining AAT with activated carbon and membrane filtration has been constructed and started operation in August 2022, with sampling beginning in December 2022. The document provides details on the systems, including design, targets, status updates, operational procedures, and timeline updates for each location.
D1.2-Demonstrator Case Study Saint-Maurice l´ExilDrKristineJung
The document discusses plans to develop pilot systems to recover sulfur from flue gas and wastewater treatment effluent at a chemical platform in Roussillon, France. A laboratory pilot plant is under construction to test sulfur recovery methods from flue gas involving condensation, dust cleaning, and scrubbing. Tests are also being prepared to recover sulfur from effluent using electrolytic oxidation, flocculation, or precipitation. An industrial pilot plant will then be built and connected to the site to further test sulfur recovery at scale. The overall goal is to develop sustainable solutions to recover 80% of sulfur from both streams and advance them to a technology readiness level of 6.
D1.2-Demonstrator Case Study Saint-Maurice l´ExilDrKristineJung
The document discusses plans to recover sulfur from flue gas and wastewater treatment plant effluent at a chemical platform in Roussillon, France. A laboratory pilot plant is under construction to test sulfur recovery techniques from flue gas using condensation, dust cleaning and scrubbing. Tests are also being prepared to recover sulfur from effluent using electrolytic oxidation, flocculation or precipitation. An industrial pilot plant will then be built to apply the optimal techniques identified from the laboratory testing to recover 80% of the sulfur from both sources. The status of the subtask is provided, including timelines showing the laboratory pilot becoming operational in June 2022 and plans for the industrial pilot in November 2022.
SaltGae Project: results achieved and demo sites.SALTGAEProject
This document summarizes a stakeholder event for the Saltgae Project, which received funding from the European Union's Horizon 2020 Innovation Action programme. The project aims to develop a modular technology platform for efficiently treating saline wastewater with organic loads. The event provided an overview of the project objectives, structure, scientific approach and challenges. It also described the project's pilot sites in Ljubljana and Israel and discussed preliminary tests on sludge valorization, biomass valorization, and effluent valorization.
D1.2-Demonstrator Case Study Karmiel/ShafdanDrKristineJung
This document describes the operational demo cases for CS6 at the Karmiel and Shafdan wastewater treatment plants. It provides status updates on multiple subtasks involving advanced anaerobic treatment and biogas production, as well as recovery of high-value products from olive mill wastewater. The advanced anaerobic treatment systems at both sites are now operational, including an immobilized high-rate reactor at Karmiel and an anaerobic biofilm membrane bioreactor at Shafdan. Pilot-scale systems are also operational for polyphenol recovery from olive mill wastewater at Karmiel using adsorption and extraction. Laboratory experiments show promising results for biogas production and polyphenol removal.
This document discusses a pilot project to increase reclaimed water availability for an industrial complex in Tarragona, Spain. The project involves testing new technologies at a wastewater treatment plant and future industrial wastewater treatment plant to polish wastewater and produce additional reclaimed water. Bench scale experiments were completed with various technologies like ultrafiltration, reverse osmosis, and membrane distillation. A pilot plant was ordered to test ultrafiltration, reverse osmosis, and zeolite adsorption. The pilot system is scheduled to be operational in September 2022 to evaluate increasing reclaimed water production by at least 20% with lower energy demand.
We have compiled the most important slides from each speaker's presentation. This year’s compilation, available for free, captures the key insights and contributions shared during the DfMAy 2024 conference.
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTjpsjournal1
The rivalry between prominent international actors for dominance over Central Asia's hydrocarbon
reserves and the ancient silk trade route, along with China's diplomatic endeavours in the area, has been
referred to as the "New Great Game." This research centres on the power struggle, considering
geopolitical, geostrategic, and geoeconomic variables. Topics including trade, political hegemony, oil
politics, and conventional and nontraditional security are all explored and explained by the researcher.
Using Mackinder's Heartland, Spykman Rimland, and Hegemonic Stability theories, examines China's role
in Central Asia. This study adheres to the empirical epistemological method and has taken care of
objectivity. This study analyze primary and secondary research documents critically to elaborate role of
china’s geo economic outreach in central Asian countries and its future prospect. China is thriving in trade,
pipeline politics, and winning states, according to this study, thanks to important instruments like the
Shanghai Cooperation Organisation and the Belt and Road Economic Initiative. According to this study,
China is seeing significant success in commerce, pipeline politics, and gaining influence on other
governments. This success may be attributed to the effective utilisation of key tools such as the Shanghai
Cooperation Organisation and the Belt and Road Economic Initiative.
6th International Conference on Machine Learning & Applications (CMLA 2024)ClaraZara1
6th International Conference on Machine Learning & Applications (CMLA 2024) will provide an excellent international forum for sharing knowledge and results in theory, methodology and applications of on Machine Learning & Applications.
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...IJECEIAES
Climate change's impact on the planet forced the United Nations and governments to promote green energies and electric transportation. The deployments of photovoltaic (PV) and electric vehicle (EV) systems gained stronger momentum due to their numerous advantages over fossil fuel types. The advantages go beyond sustainability to reach financial support and stability. The work in this paper introduces the hybrid system between PV and EV to support industrial and commercial plants. This paper covers the theoretical framework of the proposed hybrid system including the required equation to complete the cost analysis when PV and EV are present. In addition, the proposed design diagram which sets the priorities and requirements of the system is presented. The proposed approach allows setup to advance their power stability, especially during power outages. The presented information supports researchers and plant owners to complete the necessary analysis while promoting the deployment of clean energy. The result of a case study that represents a dairy milk farmer supports the theoretical works and highlights its advanced benefits to existing plants. The short return on investment of the proposed approach supports the paper's novelty approach for the sustainable electrical system. In addition, the proposed system allows for an isolated power setup without the need for a transmission line which enhances the safety of the electrical network
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELgerogepatton
As digital technology becomes more deeply embedded in power systems, protecting the communication
networks of Smart Grids (SG) has emerged as a critical concern. Distributed Network Protocol 3 (DNP3)
represents a multi-tiered application layer protocol extensively utilized in Supervisory Control and Data
Acquisition (SCADA)-based smart grids to facilitate real-time data gathering and control functionalities.
Robust Intrusion Detection Systems (IDS) are necessary for early threat detection and mitigation because
of the interconnection of these networks, which makes them vulnerable to a variety of cyberattacks. To
solve this issue, this paper develops a hybrid Deep Learning (DL) model specifically designed for intrusion
detection in smart grids. The proposed approach is a combination of the Convolutional Neural Network
(CNN) and the Long-Short-Term Memory algorithms (LSTM). We employed a recent intrusion detection
dataset (DNP3), which focuses on unauthorized commands and Denial of Service (DoS) cyberattacks, to
train and test our model. The results of our experiments show that our CNN-LSTM method is much better
at finding smart grid intrusions than other deep learning algorithms used for classification. In addition,
our proposed approach improves accuracy, precision, recall, and F1 score, achieving a high detection
accuracy rate of 99.50%.
Advanced control scheme of doubly fed induction generator for wind turbine us...IJECEIAES
This paper describes a speed control device for generating electrical energy on an electricity network based on the doubly fed induction generator (DFIG) used for wind power conversion systems. At first, a double-fed induction generator model was constructed. A control law is formulated to govern the flow of energy between the stator of a DFIG and the energy network using three types of controllers: proportional integral (PI), sliding mode controller (SMC) and second order sliding mode controller (SOSMC). Their different results in terms of power reference tracking, reaction to unexpected speed fluctuations, sensitivity to perturbations, and resilience against machine parameter alterations are compared. MATLAB/Simulink was used to conduct the simulations for the preceding study. Multiple simulations have shown very satisfying results, and the investigations demonstrate the efficacy and power-enhancing capabilities of the suggested control system.
2. 2
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Nafplio
Lead partner:
Other partners:
3. 3
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Situation before Ultimate
Argolida area:
- increasing water demand for irrigation
- high-water consumption of the fruit processing industry
great pressure on regional aquifer
Alberta S.A has a primary treatment unit of about 20 m3/h capacity:
- high production periods (Nov.-Mar. & Aug.-Oct.): 3500 m3 WW/d
- other months: 500 m3 WW/d
- treatment unit consists of a series of tank:
Raw wastewater tank → Rotostrainer →Less solids tank → equalization/ homogeneous
tank → Neutralization tank → Pre Sedimentation tank → Aeration tank → Flocculation tank
→ Final sedimentation tank → Final tank of treated water → Central treatment unit of local
water authority (DEYARM)
Aim of the Ultimate solutions (after the implementation of the additional pilot wastewater
treatment process):
to achieve lower organic burden in the final effluent,
compliant to limits specified by the local water management authority
either for disposal to the local final treatment unit,
either for irrigation
or for reuse in the production procedure of Alberta S.A.
4. 4
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Objectives of the Ultimate solutions
5. 5
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Objectives of the Ultimate solutions
Ultimate aims to address the various issues involved in fresh-water management and reduce
wastewater disposal cost. Thus, different techniques are to be implemented to guarantee a
sustainable management of the end-of-the-pipe wastewater effluents derived from the food
industry, and also to prevent the losses of inorganic and organic pollutants to the
environment, making it easier to recycle/reuse the purified water.
The activities in ULTIMATE target both the recovery of various inorganic and organic
contaminants from the processing water and the reuse of the purified water. In Alberta’s fruit
processing plant, a mobile pilot plant will demonstrate a hybrid adsorption / SubCritical Water
Extraction (SCWE) process to extract high value-added compounds, such as antioxidants from
the wastewater. Residual wastewater will be treated in pilot-scale by an AOP before polishing in
an on-site Small Bioreactor Platform (SBP) for reuse in irrigation or discharge into the municipal
WWTP to reduce operational costs. The extracted compounds will be assessed for their use by
Alberta making “fortified juice” with antioxidant properties, increasing the value of their product,
but also by selling the extract to the food-supplement sector.
6. 6
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Subtask 1.2.4 Status/progress
Baseline technology: no water reuse so far
TRL: 57
Ultimate solution to foster circular economy:
Capacity: 10 m³/d
Status/progress:
• detailed design completed
• The unit has been installed in Nafplio and is operational
Subtask: 1.2.4 Reuse of fruit processing wastewater in Nafplio
Quantifiable target: Ambition beyond the project: 100% water reuse for irrigation; >90% reduction of freshwater
through water reuse
7. 7
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Pictures/videos of the new technologies
Subtask: 1.2.4 Reuse of fruit processing wastewater in Nafplio
Unit installation video
The unit installed in Nafplio
Sensors
SBP capsules
TOC analyzer
Dossing pumps
8. 8
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Operational procedures and methodologies
Subtask: 1.2.4 Reuse of fruit processing wastewater in Nafplio
9. 9
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Results of laboratory experiments
Subtask: 1.2.4 Reuse of fruit processing wastewater in Nafplio
Advanced Oxidation Process (AOP)
• GtG has developed 2 AOP reactors
• Annular reactor: a tube with a high intensity UV
lamp where the wastewater flows through
• Solar reactor: made of quartz glass tubes and
performs under solar light. It has been proven to
effectively degrade our model compound
0
0.2
0.4
0.6
0.8
1
1.2
0 1000 2000 3000 4000
Remaining
content
of
model
compound
Irrandiance(W/m^2)
Solar
Reactor
Solar reactor: low OpEx as there are no energy costs, but to achieve the
contact time needed for degradation you need either huge area of glasses
either extremely low flow, these are obstacles for a pilot unit
Annular reactor: operates with UV lamps and shorter contact time is
needed
10. 10
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Results of laboratory experiments
Subtask: 1.2.4 Reuse of fruit processing wastewater in Nafplio
Pretreatment steps- Orange by-product
Paper
Filtration
Adsorption
Coagulation
TOC (mg/L)
Orange by-product 1950
Filtrate (paper filtration) 1810
Solution after adsorption 1400
Coagulation supernatant 1005
11. 11
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Results of laboratory experiments
Subtask: 1.2.4 Reuse of fruit processing wastewater in Nafplio
Results of the individual technologies
• Coagulant effectively removes TSS
• The adsorption of VAC is more efficient if it goes prior to any
chemical process Minor change in our initial design
12. 12
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Pictures of the pilot units
Subtask: 1.2.4 Reuse of fruit processing wastewater in Nafplio
Adsorption of polyphenols AOP: solar reactor
AOP: Annular reactor
13. 13
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Subtask 1.2.4 – Timeline
Pilot system (filtration, AOP and SBP) is operational since M24 (May 2022)
Legend
Task/Subtask
Activity as planned
Postponed activity
Delay of activity
Subtask: 1.2.4 Reuse of fruit processing wastewater in Nafplio
T1.2.4 - Reuse of fruit processing wastewater in Nafplio
Baseline conditions assessed MS05 D1.1
Design of pilot system MS09
Laboratory experiments MS15
Pilot system operational (Filtration, AOP, SBP) MS15 +6M D1.2 + 0M
Start-up & results MS19 D1.9
Best practices for water recycling D1.3
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M1
M2
M3
M4
M5
YEAR 5
YEAR 4
YEAR 1 YEAR 2 YEAR 3
2020 2021 2022 2023 2024
14. 14
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Subtask 1.4.3 Status/progress
Baseline technology: No recovery
TRL: 5 7
Ultimate solution to foster circular economy:
Capacity: 10 m³/d
Status/progress:
• Lab scale experiments completed
• Pilot unit constructed and in operation
Subtask: 1.4.3 Recovery of high-added-value compounds (antioxidants) in Nafplio
Quantifiable target: Recovery of polyphenols: 50-70%
15. 15
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
Subtask: 1.4.3 Recovery of high-added-value compounds (antioxidants) in Nafplio
CS4: Pictures/videos of the new technologies
Static adsorption
Lab scale – Dynamic adsorption
16. 16
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
Subtask: 1.4.3 Recovery of high-added-value compounds (antioxidants) in Nafplio
CS4: Operational procedures and methodologies
17. 17
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
Subtask: 1.4.3 Recovery of high-added-value compounds (antioxidants) in Nafplio
CS4: Results of the laboratory experiments
0.
3.5
7.
10.5
14.
0 15 30 45 60 75
adsorption
capacity
Q
(mg/g)
t (min)
0.1g
0.2g
0.5g
1.0g
y = -0,0195x + 2,9041
R² = 0,9964
y = -0,0208x + 2,6424
R² = 0,9802
y = -0,0197x + 2,3111
R² = 0,9701
0.
0.75
1.5
2.25
3.
3.75
0 15 30 45 60 75
lnQe
t (min)
0.1 g
0.2 g
0.5 g
maximum adsorptive
capacity (Q): 23 g of
polyphenols per kg of
resin for the FPX 66
resin
Static
Adsorption
Dynamic
Adsorption
0
35
70
105
140
0. 125. 250. 375. 500.
C
phenols
(mg/L)
Bed Volums (BV)
2.5 ml/min
5ml/min
The breakthrough
curves showed that
1.7 m3 of wastewater
can be treated per kg
of resin per 10 cycles
18. 18
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Results of the laboratory experiments
Subtask: 1.4.3 Recovery of high-added-value compounds (antioxidants) in Nafplio
•Static extraction experiments were
performed employing hot water and
organic solvents
•Water-methanol mixture (50:50 b.v.)
yielded 69% polyphenols recovery
•Currently working on dynamic
extraction experiments,
•Aiming to optimise:
• experimental conditions and
• solvent recovery and reuse
strategy
19. 19
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Pictures of the pilot units
Subtask: 1.4.3 Recovery of high-added-value compounds (antioxidants) in Nafplio
Adsorption of polyphenols Supercritical water extraction
20. 20
The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
CS4: Subtask 1.4.3 – Timeline
Pilot system operational since November 2022 (M30)
Subtask: 1.4.3 Recovery of high-added-value compounds (antioxidants) in Nafplio
Legend
Task/Subtask
Activity as planned
Postponed activity
Delay of activity
Extension of activity
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
M1
M2
M3
M4
M5
YEAR 5
YEAR 4
YEAR 1 YEAR 2 YEAR 3
2020 2021 2022 2023 2024
T1.4.3 - Recovery of high added-value compounds
(antioxidants) in Nafplio
Baseline conditions assessed MS05 D1.1
Design of pilot system MS09
Laboratory experiments MS15
Pilot system operational MS15 +12M D1.2 + 6M
Start-up & results MS19 +2M D1.9 + 4M
Best practices for material recovery D1.5
21. The project leading to this application has received funding from the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 869318
d.iossifidis@greenerthangreen.co
CS4 Contacts
m.touloupi@greenerthangreen.co