This letter from Crown Hydro, LLC to the Federal Energy Regulatory Commission requests that the FERC continue to hold license termination proceedings in abeyance. Crown Hydro has been working to obtain local site control for its hydroelectric project from the Minneapolis Parks & Recreation Board, but the Board has been unwilling to provide access. However, the Minnesota legislature is expected to pass a bill during an upcoming special session that would preempt the Board and provide Crown Hydro the necessary site control. Crown Hydro asks for more time to allow the legislative process to play out before the FERC takes any action to terminate its license.