2. Rationale
“Subproject proposals submitted by Cities and
Municipalities amounting to PhP15 million and below,
shall be submitted to the DILG Provincial Director.
Within two (2) days upon receipt of the proposal, the
DILG Provincial Director shall endorse said proposal
to the PAMANA Provincial Technical Working Group
(PTWG), constituted under the Provincial Peace and
Order Council (PPOC), for review and
evaluation/appraisal.”
Section I-B-B.5-f, PAMANA-DILG Fund Guidelines
DILG-OPAPP JMC No. 2, s. 2014
3. Provincial Peace and Order
Council Technical Working Group
(PTWG)
C.1 The PAMANA TWG constituted under the RPOC and
PPOC shall:
a. Review and evaluate/appraise subproject proposals
submitted at their levels
b. Conduct the site visits and field validation to further
assess the feasibility of the proposed subproject
c. Recommend for approval/disapproval the LGU
subproject proposals to the DILG Regional Director
d. Provide support to OPAPP in monitoring the
implementation of the subprojects under the Fund
Roles/ Responsibilities/ Functions
Section III-C, PAMANA-DILG Fund Guidelines
DILG-OPAPP JMC No. 2, s. 2014
4. Provincial Peace and Order
Council Technical Working Group
(PTWG)
C.2 Members of the R/PTWG shall be composed of a maximum
of seven (7) technical personnel from among the member
agencies represented in the R/PPOC. With the varying types
and nature of proposed subprojects, NEDA and other
relevant sector agencies may be invited.
However, it is acknowledged that the multisector nature of the
proposed subprojects would require a variety of experts. The
concerned TWG may then resort to invitation of
representatives of other R/PPOC members as resource
persons/experts in the evaluation meetings/site validation
visits.
Roles/ Responsibilities/ Functions
Section III-C, PAMANA-DILG Fund Guidelines
DILG-OPAPP JMC No. 2, s. 2014
5. Provincial Peace and Order
Council Technical Working Group
(PTWG)
C.3 NCIP representative shall be invited as additional
member to the R/PTWG if the proposed subproject is
situated in an ancestral domain or will directly affect
Indigenous People. This will ensure consideration of
Indigenous People’s concerns in the subproject
appraisal process that could facilitate securing of the
Free Prior and Informed Consent (FPIC) or any
appropriate clearances.
Roles/ Responsibilities/ Functions
Section III-C, PAMANA-DILG Fund Guidelines
DILG-OPAPP JMC No. 2, s. 2014
6. Provincial Peace and Order
Council Technical Working Group
(PTWG)
C.4 The PTWG shall be chaired by the DILG Provincial
Director.
C.5 The Chairman of the RTWG shall be designated by
the
RPOC.
Roles/ Responsibilities/ Functions
Section III-C, PAMANA-DILG Fund Guidelines
DILG-OPAPP JMC No. 2, s. 2014