The document discusses guidelines for managing geotechnical risks in design-build transportation projects. The key findings from supporting research are: 1) There is a need for owners and contractors to align their approach to managing geotechnical risks in design-build projects; and 2) The disconnect between owners and contractors on who owns geotechnical risk leads to unnecessary contingencies that increase costs. The guidelines recommend mitigating risks by encouraging early collaboration between owners and contractors to develop a mutually agreed risk allocation plan. This aims to address the challenge that design-build projects often lack sufficient time to fully characterize site conditions before construction begins.
Infrastructure and Design Build ContractingWagner College
This monograph was written for Wagner College's Hugh L. Carey Institute for Government Reform in August 2020 by Peter J. Kiernan, of counsel at Schiff Hardin in New York. Kiernan previously served as counsel to New York Gov. David Paterson, counsel to the deputy mayor for finance of the City of New York, and chief counsel to the New York State Senate Minority. As a Littauer fellow at the Kennedy School of Government at Harvard University, he wrote an analysis of the New York City fiscal crisis, which was published by Harvard. He is a graduate of John Carroll University, the Kennedy School of Government at Harvard, and Cornell Law School.
There is no “one size fits all” method to construction delivery. Each project faces a unique and often complex set of circumstances. That’s why McCarthy provides public owners with flexible and creative alternative delivery methods. Learn more about Design-Build-Finance, Public-Private Partnership, Job Order Contracting, Integrated Project Delivery, Design-Assist and Construction Management-at-Risk.
Click here for even more on construction delivery methods: www.mccarthy.com/work/delivery-methods
1/31/2021 Project Procurement
https://leocontent.umgc.edu/content/umuc/tgs/mba/mba670/2211/learning-resourcelist/project-procurement.html?ou=541222 1/2
Project Procurement
By Adrienne Watt and bpayne
The procurement effort on projects varies widely and depends on the type of project.
Often the client organization will provide procurement services on less complex projects.
In this case, the project team identifies the materials, equipment, and supplies needed by
the project and provides product specifications and a detailed delivery schedule. When
the procurement department of the parent organization provides procurement services, a
liaison from the project can help the procurement team better understand the unique
requirements of the project and the time-sensitive or critical items of the project schedule.
On larger, more complex projects, personnel are dedicated to procuring and managing the
equipment, supplies, and materials needed by the project. Because of the temporary
nature of projects, equipment, supplies, and materials are procured as part of the product
of the project or for the execution of the project. For example, the bricks procured for a
construction project would be procured for the product of the project, and the mortar
mixer would be equipment procured for the execution of the project work. At the end of
the project, equipment bought or rented for the execution of the work of the project are
sold, returned to rental organizations, or disposed of some other way.
More complex projects will typically procure through different procurement and
management methods. Commodities are common products that are purchased based on
the lowest bid. Commodities include items like concrete for building projects, office
supplies, or even lab equipment for a research project. The second type of procurement
includes products that are specified for the project. Vendors who can produce these
products bid for a contract. The awarding of a contract can include price, ability to meet
the project schedule, the fit for purpose of the product, and other considerations
important to the project.
Manufacturing a furnace for a new steel mill would be provided by a project vendor.
Equipment especially designed and built for a research project is another example. These
vendors’ performances become important parts of the project, and the project manager
Learning Resource
1/31/2021 Project Procurement
https://leocontent.umgc.edu/content/umuc/tgs/mba/mba670/2211/learning-resourcelist/project-procurement.html?ou=541222 2/2
assigns resources to coordinate the work and schedule of the vendor. The third
procurement approach is the development of one or more partners. A design firm that is
awarded the design contract for a major part of the steel mill and a research firm that is
conducting critical subparts of the research are examples of potential project partners. A
partner contributes to and is integrated into the execution p ...
1/31/2021 Project Procurement
https://leocontent.umgc.edu/content/umuc/tgs/mba/mba670/2211/learning-resourcelist/project-procurement.html?ou=541222 1/2
Project Procurement
By Adrienne Watt and bpayne
The procurement effort on projects varies widely and depends on the type of project.
Often the client organization will provide procurement services on less complex projects.
In this case, the project team identifies the materials, equipment, and supplies needed by
the project and provides product specifications and a detailed delivery schedule. When
the procurement department of the parent organization provides procurement services, a
liaison from the project can help the procurement team better understand the unique
requirements of the project and the time-sensitive or critical items of the project schedule.
On larger, more complex projects, personnel are dedicated to procuring and managing the
equipment, supplies, and materials needed by the project. Because of the temporary
nature of projects, equipment, supplies, and materials are procured as part of the product
of the project or for the execution of the project. For example, the bricks procured for a
construction project would be procured for the product of the project, and the mortar
mixer would be equipment procured for the execution of the project work. At the end of
the project, equipment bought or rented for the execution of the work of the project are
sold, returned to rental organizations, or disposed of some other way.
More complex projects will typically procure through different procurement and
management methods. Commodities are common products that are purchased based on
the lowest bid. Commodities include items like concrete for building projects, office
supplies, or even lab equipment for a research project. The second type of procurement
includes products that are specified for the project. Vendors who can produce these
products bid for a contract. The awarding of a contract can include price, ability to meet
the project schedule, the fit for purpose of the product, and other considerations
important to the project.
Manufacturing a furnace for a new steel mill would be provided by a project vendor.
Equipment especially designed and built for a research project is another example. These
vendors’ performances become important parts of the project, and the project manager
Learning Resource
1/31/2021 Project Procurement
https://leocontent.umgc.edu/content/umuc/tgs/mba/mba670/2211/learning-resourcelist/project-procurement.html?ou=541222 2/2
assigns resources to coordinate the work and schedule of the vendor. The third
procurement approach is the development of one or more partners. A design firm that is
awarded the design contract for a major part of the steel mill and a research firm that is
conducting critical subparts of the research are examples of potential project partners. A
partner contributes to and is integrated into the execution p ...
[Report] Who's protecting your blindside? Construction Management: Protectin...JLL
Risk management continues to top business agendas, being regarded as critical to succeed in today’s competitive and volatile corporate environment. However, many companies leave themselves open to significant risks in the delivery of real estate projects. Risk management continues to top business agendas, being regarded as critical to succeed in today’s competitive and volatile corporate environment. However, many companies leave themselves open to significant risks in the delivery of real estate projects.
To learn more about JLL's project and development services in APAC, please visit: http://bit.ly/1iEasVh
This deck was presented to the Pennsylvania School Boards Association (PSBA) in 2010. It addressed some commonly overlooked critical items in the planning and execution of construction projects which could improve the overall performance of the project and reduce the risk of disputes and claims.
“Investigation of Time-Cost Effectiveness on Construction Projects”IOSR Journals
Development projects undertaken in various sectors of economy and finance are building blocks of
national economy. This paper examines the time-cost effectiveness on construction projects by quantification of
16 different project performance parameters applied on 49 construction projects (both public and private sector
projects). A questionnaire was drafted to test the parameters and criteria adopted when assessing the success of construction projects. The results shows that for general group of construction projects all 16 parameters have significant impact on cost growth.
3.0 Project 2_ Developing My Brand Identity Kit.pptxtanyjahb
A personal brand exploration presentation summarizes an individual's unique qualities and goals, covering strengths, values, passions, and target audience. It helps individuals understand what makes them stand out, their desired image, and how they aim to achieve it.
Personal Brand Statement:
As an Army veteran dedicated to lifelong learning, I bring a disciplined, strategic mindset to my pursuits. I am constantly expanding my knowledge to innovate and lead effectively. My journey is driven by a commitment to excellence, and to make a meaningful impact in the world.
Infrastructure and Design Build ContractingWagner College
This monograph was written for Wagner College's Hugh L. Carey Institute for Government Reform in August 2020 by Peter J. Kiernan, of counsel at Schiff Hardin in New York. Kiernan previously served as counsel to New York Gov. David Paterson, counsel to the deputy mayor for finance of the City of New York, and chief counsel to the New York State Senate Minority. As a Littauer fellow at the Kennedy School of Government at Harvard University, he wrote an analysis of the New York City fiscal crisis, which was published by Harvard. He is a graduate of John Carroll University, the Kennedy School of Government at Harvard, and Cornell Law School.
There is no “one size fits all” method to construction delivery. Each project faces a unique and often complex set of circumstances. That’s why McCarthy provides public owners with flexible and creative alternative delivery methods. Learn more about Design-Build-Finance, Public-Private Partnership, Job Order Contracting, Integrated Project Delivery, Design-Assist and Construction Management-at-Risk.
Click here for even more on construction delivery methods: www.mccarthy.com/work/delivery-methods
1/31/2021 Project Procurement
https://leocontent.umgc.edu/content/umuc/tgs/mba/mba670/2211/learning-resourcelist/project-procurement.html?ou=541222 1/2
Project Procurement
By Adrienne Watt and bpayne
The procurement effort on projects varies widely and depends on the type of project.
Often the client organization will provide procurement services on less complex projects.
In this case, the project team identifies the materials, equipment, and supplies needed by
the project and provides product specifications and a detailed delivery schedule. When
the procurement department of the parent organization provides procurement services, a
liaison from the project can help the procurement team better understand the unique
requirements of the project and the time-sensitive or critical items of the project schedule.
On larger, more complex projects, personnel are dedicated to procuring and managing the
equipment, supplies, and materials needed by the project. Because of the temporary
nature of projects, equipment, supplies, and materials are procured as part of the product
of the project or for the execution of the project. For example, the bricks procured for a
construction project would be procured for the product of the project, and the mortar
mixer would be equipment procured for the execution of the project work. At the end of
the project, equipment bought or rented for the execution of the work of the project are
sold, returned to rental organizations, or disposed of some other way.
More complex projects will typically procure through different procurement and
management methods. Commodities are common products that are purchased based on
the lowest bid. Commodities include items like concrete for building projects, office
supplies, or even lab equipment for a research project. The second type of procurement
includes products that are specified for the project. Vendors who can produce these
products bid for a contract. The awarding of a contract can include price, ability to meet
the project schedule, the fit for purpose of the product, and other considerations
important to the project.
Manufacturing a furnace for a new steel mill would be provided by a project vendor.
Equipment especially designed and built for a research project is another example. These
vendors’ performances become important parts of the project, and the project manager
Learning Resource
1/31/2021 Project Procurement
https://leocontent.umgc.edu/content/umuc/tgs/mba/mba670/2211/learning-resourcelist/project-procurement.html?ou=541222 2/2
assigns resources to coordinate the work and schedule of the vendor. The third
procurement approach is the development of one or more partners. A design firm that is
awarded the design contract for a major part of the steel mill and a research firm that is
conducting critical subparts of the research are examples of potential project partners. A
partner contributes to and is integrated into the execution p ...
1/31/2021 Project Procurement
https://leocontent.umgc.edu/content/umuc/tgs/mba/mba670/2211/learning-resourcelist/project-procurement.html?ou=541222 1/2
Project Procurement
By Adrienne Watt and bpayne
The procurement effort on projects varies widely and depends on the type of project.
Often the client organization will provide procurement services on less complex projects.
In this case, the project team identifies the materials, equipment, and supplies needed by
the project and provides product specifications and a detailed delivery schedule. When
the procurement department of the parent organization provides procurement services, a
liaison from the project can help the procurement team better understand the unique
requirements of the project and the time-sensitive or critical items of the project schedule.
On larger, more complex projects, personnel are dedicated to procuring and managing the
equipment, supplies, and materials needed by the project. Because of the temporary
nature of projects, equipment, supplies, and materials are procured as part of the product
of the project or for the execution of the project. For example, the bricks procured for a
construction project would be procured for the product of the project, and the mortar
mixer would be equipment procured for the execution of the project work. At the end of
the project, equipment bought or rented for the execution of the work of the project are
sold, returned to rental organizations, or disposed of some other way.
More complex projects will typically procure through different procurement and
management methods. Commodities are common products that are purchased based on
the lowest bid. Commodities include items like concrete for building projects, office
supplies, or even lab equipment for a research project. The second type of procurement
includes products that are specified for the project. Vendors who can produce these
products bid for a contract. The awarding of a contract can include price, ability to meet
the project schedule, the fit for purpose of the product, and other considerations
important to the project.
Manufacturing a furnace for a new steel mill would be provided by a project vendor.
Equipment especially designed and built for a research project is another example. These
vendors’ performances become important parts of the project, and the project manager
Learning Resource
1/31/2021 Project Procurement
https://leocontent.umgc.edu/content/umuc/tgs/mba/mba670/2211/learning-resourcelist/project-procurement.html?ou=541222 2/2
assigns resources to coordinate the work and schedule of the vendor. The third
procurement approach is the development of one or more partners. A design firm that is
awarded the design contract for a major part of the steel mill and a research firm that is
conducting critical subparts of the research are examples of potential project partners. A
partner contributes to and is integrated into the execution p ...
[Report] Who's protecting your blindside? Construction Management: Protectin...JLL
Risk management continues to top business agendas, being regarded as critical to succeed in today’s competitive and volatile corporate environment. However, many companies leave themselves open to significant risks in the delivery of real estate projects. Risk management continues to top business agendas, being regarded as critical to succeed in today’s competitive and volatile corporate environment. However, many companies leave themselves open to significant risks in the delivery of real estate projects.
To learn more about JLL's project and development services in APAC, please visit: http://bit.ly/1iEasVh
This deck was presented to the Pennsylvania School Boards Association (PSBA) in 2010. It addressed some commonly overlooked critical items in the planning and execution of construction projects which could improve the overall performance of the project and reduce the risk of disputes and claims.
“Investigation of Time-Cost Effectiveness on Construction Projects”IOSR Journals
Development projects undertaken in various sectors of economy and finance are building blocks of
national economy. This paper examines the time-cost effectiveness on construction projects by quantification of
16 different project performance parameters applied on 49 construction projects (both public and private sector
projects). A questionnaire was drafted to test the parameters and criteria adopted when assessing the success of construction projects. The results shows that for general group of construction projects all 16 parameters have significant impact on cost growth.
3.0 Project 2_ Developing My Brand Identity Kit.pptxtanyjahb
A personal brand exploration presentation summarizes an individual's unique qualities and goals, covering strengths, values, passions, and target audience. It helps individuals understand what makes them stand out, their desired image, and how they aim to achieve it.
Personal Brand Statement:
As an Army veteran dedicated to lifelong learning, I bring a disciplined, strategic mindset to my pursuits. I am constantly expanding my knowledge to innovate and lead effectively. My journey is driven by a commitment to excellence, and to make a meaningful impact in the world.
The key differences between the MDR and IVDR in the EUAllensmith572606
In the European Union (EU), two significant regulations have been introduced to enhance the safety and effectiveness of medical devices – the In Vitro Diagnostic Regulation (IVDR) and the Medical Device Regulation (MDR).
https://mavenprofserv.com/comparison-and-highlighting-of-the-key-differences-between-the-mdr-and-ivdr-in-the-eu/
Business Valuation Principles for EntrepreneursBen Wann
This insightful presentation is designed to equip entrepreneurs with the essential knowledge and tools needed to accurately value their businesses. Understanding business valuation is crucial for making informed decisions, whether you're seeking investment, planning to sell, or simply want to gauge your company's worth.
Falcon stands out as a top-tier P2P Invoice Discounting platform in India, bridging esteemed blue-chip companies and eager investors. Our goal is to transform the investment landscape in India by establishing a comprehensive destination for borrowers and investors with diverse profiles and needs, all while minimizing risk. What sets Falcon apart is the elimination of intermediaries such as commercial banks and depository institutions, allowing investors to enjoy higher yields.
Affordable Stationery Printing Services in Jaipur | Navpack n PrintNavpack & Print
Looking for professional printing services in Jaipur? Navpack n Print offers high-quality and affordable stationery printing for all your business needs. Stand out with custom stationery designs and fast turnaround times. Contact us today for a quote!
[Note: This is a partial preview. To download this presentation, visit:
https://www.oeconsulting.com.sg/training-presentations]
Sustainability has become an increasingly critical topic as the world recognizes the need to protect our planet and its resources for future generations. Sustainability means meeting our current needs without compromising the ability of future generations to meet theirs. It involves long-term planning and consideration of the consequences of our actions. The goal is to create strategies that ensure the long-term viability of People, Planet, and Profit.
Leading companies such as Nike, Toyota, and Siemens are prioritizing sustainable innovation in their business models, setting an example for others to follow. In this Sustainability training presentation, you will learn key concepts, principles, and practices of sustainability applicable across industries. This training aims to create awareness and educate employees, senior executives, consultants, and other key stakeholders, including investors, policymakers, and supply chain partners, on the importance and implementation of sustainability.
LEARNING OBJECTIVES
1. Develop a comprehensive understanding of the fundamental principles and concepts that form the foundation of sustainability within corporate environments.
2. Explore the sustainability implementation model, focusing on effective measures and reporting strategies to track and communicate sustainability efforts.
3. Identify and define best practices and critical success factors essential for achieving sustainability goals within organizations.
CONTENTS
1. Introduction and Key Concepts of Sustainability
2. Principles and Practices of Sustainability
3. Measures and Reporting in Sustainability
4. Sustainability Implementation & Best Practices
To download the complete presentation, visit: https://www.oeconsulting.com.sg/training-presentations
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...BBPMedia1
Marvin neemt je in deze presentatie mee in de voordelen van non-endemic advertising op retail media netwerken. Hij brengt ook de uitdagingen in beeld die de markt op dit moment heeft op het gebied van retail media voor niet-leveranciers.
Retail media wordt gezien als het nieuwe advertising-medium en ook mediabureaus richten massaal retail media-afdelingen op. Merken die niet in de betreffende winkel liggen staan ook nog niet in de rij om op de retail media netwerken te adverteren. Marvin belicht de uitdagingen die er zijn om echt aansluiting te vinden op die markt van non-endemic advertising.
At Techbox Square, in Singapore, we're not just creative web designers and developers, we're the driving force behind your brand identity. Contact us today.
B2B payments are rapidly changing. Find out the 5 key questions you need to be asking yourself to be sure you are mastering B2B payments today. Learn more at www.BlueSnap.com.
LA HUG - Video Testimonials with Chynna Morgan - June 2024Lital Barkan
Have you ever heard that user-generated content or video testimonials can take your brand to the next level? We will explore how you can effectively use video testimonials to leverage and boost your sales, content strategy, and increase your CRM data.🤯
We will dig deeper into:
1. How to capture video testimonials that convert from your audience 🎥
2. How to leverage your testimonials to boost your sales 💲
3. How you can capture more CRM data to understand your audience better through video testimonials. 📊
Implicitly or explicitly all competing businesses employ a strategy to select a mix
of marketing resources. Formulating such competitive strategies fundamentally
involves recognizing relationships between elements of the marketing mix (e.g.,
price and product quality), as well as assessing competitive and market conditions
(i.e., industry structure in the language of economics).
"𝑩𝑬𝑮𝑼𝑵 𝑾𝑰𝑻𝑯 𝑻𝑱 𝑰𝑺 𝑯𝑨𝑳𝑭 𝑫𝑶𝑵𝑬"
𝐓𝐉 𝐂𝐨𝐦𝐬 (𝐓𝐉 𝐂𝐨𝐦𝐦𝐮𝐧𝐢𝐜𝐚𝐭𝐢𝐨𝐧𝐬) is a professional event agency that includes experts in the event-organizing market in Vietnam, Korea, and ASEAN countries. We provide unlimited types of events from Music concerts, Fan meetings, and Culture festivals to Corporate events, Internal company events, Golf tournaments, MICE events, and Exhibitions.
𝐓𝐉 𝐂𝐨𝐦𝐬 provides unlimited package services including such as Event organizing, Event planning, Event production, Manpower, PR marketing, Design 2D/3D, VIP protocols, Interpreter agency, etc.
Sports events - Golf competitions/billiards competitions/company sports events: dynamic and challenging
⭐ 𝐅𝐞𝐚𝐭𝐮𝐫𝐞𝐝 𝐩𝐫𝐨𝐣𝐞𝐜𝐭𝐬:
➢ 2024 BAEKHYUN [Lonsdaleite] IN HO CHI MINH
➢ SUPER JUNIOR-L.S.S. THE SHOW : Th3ee Guys in HO CHI MINH
➢FreenBecky 1st Fan Meeting in Vietnam
➢CHILDREN ART EXHIBITION 2024: BEYOND BARRIERS
➢ WOW K-Music Festival 2023
➢ Winner [CROSS] Tour in HCM
➢ Super Show 9 in HCM with Super Junior
➢ HCMC - Gyeongsangbuk-do Culture and Tourism Festival
➢ Korean Vietnam Partnership - Fair with LG
➢ Korean President visits Samsung Electronics R&D Center
➢ Vietnam Food Expo with Lotte Wellfood
"𝐄𝐯𝐞𝐫𝐲 𝐞𝐯𝐞𝐧𝐭 𝐢𝐬 𝐚 𝐬𝐭𝐨𝐫𝐲, 𝐚 𝐬𝐩𝐞𝐜𝐢𝐚𝐥 𝐣𝐨𝐮𝐫𝐧𝐞𝐲. 𝐖𝐞 𝐚𝐥𝐰𝐚𝐲𝐬 𝐛𝐞𝐥𝐢𝐞𝐯𝐞 𝐭𝐡𝐚𝐭 𝐬𝐡𝐨𝐫𝐭𝐥𝐲 𝐲𝐨𝐮 𝐰𝐢𝐥𝐥 𝐛𝐞 𝐚 𝐩𝐚𝐫𝐭 𝐨𝐟 𝐨𝐮𝐫 𝐬𝐭𝐨𝐫𝐢𝐞𝐬."
Kseniya Leshchenko: Shared development support service model as the way to ma...Lviv Startup Club
Kseniya Leshchenko: Shared development support service model as the way to make small projects with small budgets profitable for the company (UA)
Kyiv PMDay 2024 Summer
Website – www.pmday.org
Youtube – https://www.youtube.com/startuplviv
FB – https://www.facebook.com/pmdayconference
Kseniya Leshchenko: Shared development support service model as the way to ma...
Chap 1.pdf
1. CONTRIBUTORS
DETAILS
All downloadable National Academies titles are free to be used for personal and/or non-commercial
academic use. Users may also freely post links to our titles on this website; non-commercial academic
users are encouraged to link to the version on this website rather than distribute a downloaded PDF
to ensure that all users are accessing the latest authoritative version of the work. All other uses require
written permission. (Request Permission)
This PDF is protected by copyright and owned by the National Academy of Sciences; unless otherwise
indicated, the National Academy of Sciences retains copyright to all materials in this PDF with all rights
reserved.
Visit the National Academies Press at nap.edu and login or register to get:
– Access to free PDF downloads of thousands of publications
– 10% off the price of print publications
– Email or social media notifications of new titles related to your interests
– Special offers and discounts
SUGGESTED CITATION
BUY THIS BOOK
FIND RELATED TITLES
This PDF is available at http://nap.nationalacademies.org/25262
Guidelines for Managing Geotechnical
Risks in Design Build Projects (2018)
80 pages | 8.5 x 11 | PAPERBACK
ISBN 978-0-309-39060-6 | DOI 10.17226/25262
Douglas D. Gransberg, Michael Loulakis, Ali Touran, Ghada Gad, Kevin McLain,
Shannon Sweitzer, Dominique Pittenger, Ivan Castro Nova, Ricardo Tapia Pereira,
and Milagros Pinto-Nunez; National Cooperative Highway Research Program;
Transportation Research Board; National Academies of Sciences, Engineering, and
Medicine
National Academies of Sciences, Engineering, and Medicine. 2018. Guidelines for
Managing Geotechnical Risks in Design Build Projects. Washington, DC: The
National Academies Press. https://doi.org/10.17226/25262.
2. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
3
The purpose of these guidelines is to assist public agencies in manag
ing geotechnical risk on highway construction projects that are deliv
ered using design–build (DB). They may also provide insight for users
managing projects with traditional delivery. The goal associated with
using these guidelines is to aid agencies in identifying and evaluating
opportunities that measurably reduce the levels of geotechnical uncer
tainty for both the owner and the competing design–builders, where
possible, before project advertisement and award, as well as equitably
distribute the remaining risk between the parties during contract exe
cution so that there is a positive impact on project cost and schedule.
The intended audience of the guidelines is public agencies that must
manage geotechnical risk on DB highway construction projects. This
report furnishes insight about the potential impact of geotechnical risk
in the DB context. The guidelines can be used to facilitate the DB proj
ect delivery selection process. Once the decision to use DB is made, it
also provides information for allocating the geotechnical risk between
the agency and the design–builder, as well as specific practices found
during the supporting research to be effective in managing, mitigating,
and retiring geotechnical risk.
The supporting research conducted an extensive review of state departments of transportation
(DOTs) legal, contracting, design, and construction practices to manage DB geotechnical risk.
The outcome was to frame the problem as a conflict between two characteristics of DB project
delivery. First, DOTs use DB to accelerate project delivery and, second, one of the reasons for
selecting DB is to develop a single point of responsibility for both design and construction. The
conflict comes when the time available during the preliminary engineering conducted to develop
a DB request for proposal (RFP) is insufficient to permit the agency to characterize the project’s
subsurface conditions to a reasonable degree of certainty. The ability to transfer the geotechnical
risk to the design–builder is limited because often the design–builder is charged with completing
the necessary subsurface investigations and interpreting those to develop the project’s design.
Once the DB contract is awarded, the first design elements that must be completed are those
dealing with subsurface features of work, utilities, and drainage. This further reduces the time
available for geotechnical engineering effort and often creates a situation in which early con
struction packages are started before the subsurface uncertainty can be brought to a reasonable
level. The result can be summarized as the following chain of logic:
• The bulk of U.S. construction case law demonstrates that owners find it challenging to win
differing site conditions (DSC) claims.
C H A P T E R 1
Introduction to Design–Build
Geotechnical Risk Management
The primary finding of the guidelines
supporting research is that there is a need
to achieve an aligned approach toward
managing geotechnical risks in DB
projects. The disconnect between owners
and contractors as to who owns the
geotechnical risk in DB projects creates
an overestimation of the risks that lead
to unnecessary contingencies as a mea-
sure of protection from overexposure.
Therefore, the focus moving forward is to
mitigate the geotechnical risks by encour-
aging collaboration between the parties
in a DB contract to achieve a mutually
agreed geotechnical risk allocation plan.
3. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
4 Guidelines for Managing Geotechnical Risks in Design–Build Projects
• Nevertheless, DOTs continue to rely on exculpatory language to attempt to shed geotechnical
risk in DB projects.
• The industry recognizes the risk shedding bias and perceives geotechnical risk to be much
higher than do authors of DOT DB RFPs.
• The result is the inclusion of contingencies for geotechnical risks that may not be realized,
which must logically increase the overall cost of the project.
• The solution is to align the perceptions of geotechnical risk of the DOT and the DB team early
in the process.
• The study has identified progressive DB, DB with multiple notices to proceed, and DB with
some fixed scope validation period as potential mechanisms to permit the early alignment of
geotechnical risk perceptions.
Put another way, there simply is not enough time in a typical DB project’s development cycle
to complete the geotechnical investigations necessary to reduce geotechnical uncertainty to an
acceptable level prior to awarding the DB contract. Thus, the most pragmatic way to mitigate
DB subsurface risk is to start the digging and uncover the actual site conditions on which the
project must be built as soon as practical. This can be accomplished through early contractor
involvement and joint development of the geotechnical risk profile for the DB project. The
overall objective of the guidelines is to assist agencies by furnishing potential methodologies that
permit the DOT and its industry partners to align perceptions of risks as well as their business
objectives as early as practical during the delivery of a DB transportation project.
1.1 Design–Build Project Risk Management
While the focus of the report is on geotechnical risk, it is important to be able to put that
in context of the overall risk profile for a DB project. The major change in the DB risk profile
versus design–bid–build (DBB) risk is due to the shift in design responsibility to the design–
builder. The owner’s new DB risks can result from not relinquishing the design responsibility
to the design–builder. Compounding the issue is the owner’s desire to accelerate the construc
tion schedule, which may result in construction beginning before the project’s design is 100%
complete. Since public sector DB projects often require that the design–builder commit to a
firm fixed price before the project’s design is complete, the risk that the agency’s RFP does not
adequately articulate the total scope of work is higher than DBB. Additionally, unfamiliarity
with DB contracts often leads to a proliferation of exculpatory risk shedding clauses that will
ultimately drive the competing design–builders to raise their proposed prices regardless if those
clauses are actually enforceable. The bottom line is that the winning design–builder must design
to the budget defined by its contract amount. If the agency’s oversight staff is new to DB, this is
often perceived to be cutting corners on design and construction quality on the basis of a preva
lent school of thought that believes any changes made after contract award are done to increase
the contractor’s profit margin. This issue can cause an adversarial environment to develop, in
which the risk of claims because the actual scope of work does not match the one portrayed in
the solicitation and award documents is higher.
Given the preceding discussion, the first question a DOT will want to address is whether a
given project is a good candidate for DB project delivery given the influence of geotechnical
uncertainty on the design, price, and schedule. Table 1.1 is a synopsis of project characteristics
found in the literature that would indicate that DB delivery may not be the most appropriate
approach. However, the DOT survey from supporting research also found that the decision to
use DB was rarely, if ever, influenced by the level of geotechnical risk. This brings the discus
sion back to its starting point. DOTs use DB when an aggressive delivery schedule is required;
therefore, it becomes imperative that geotechnical risk be thoughtfully managed. Given that the
4. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
Introduction to Design–Build Geotechnical Risk Management 5
subsurface risks will be the first to be realized in construction, it makes sense to give the sub
surface risks specific attention both before and after DB contract award. Additionally, the need
for the agency and the design–builder to align their perceptions of geotechnical uncertainty as
early as possible gains importance as a remedy to avoid potential disputes over DSC after
construction has commenced.
1.1.1 Geotechnical Risk in DB projects
When trying to understand risk in projects delivered by alternative methods, one must
remember that risk is a function of both individual and organizational perceptions borne by the
collective experiences of those conducting the risk analysis. Risk is measured by comparing it
with a benchmark with which the analyst is familiar. In this case, a comparison of typical geo
technical risks in DBB projects versus the change in the risk profile that occurs when the contract
is awarded for both design and construction is a logical starting point. In doing the comparison,
it is important to remember that geotechnical uncertainty is always high until the necessary sub
surface investigations and studies are complete, and the uncertainty will remain until construc
tion activities expose the actual subsurface characteristics found on the project site.
Table 1.2 provides a side-by-side comparison of geotechnical scope, schedule, and cost risks
in DBB and DB from the perspective of the owner and its construction contractor or design–
builder. Looking at the table, in most cases the decision to use DB delivery results in a shift
of many of the risks associated with design activities to the design–builder. One of the major
risks in DB is that the owner’s staff will not relinquish control over the design details that
they are used to exercising in DBB to the design–builder’s design staff. The case law review for
this guide found that when the agency becomes prescriptive in its design reviews, it usually
assumes the performance liability for the aspect that it directed to be changed. This is shown
in the Table 1.2 scope risk section, in which “direct and tacit approval of constructive changes
to geotechnical design” remains in the owner’s court in both DB and DBB. The DOTs with the
most DB experience tend to employ the use of “over-the-shoulder” design reviews to remedy
this potential issue.
In DBB delivery, the design is complete before the construction contract is awarded. The
owner assumes responsibility for accuracy of design. Most geotechnical claims fall under changes
due to differing site conditions or DSC. The FHWA mandates the use of a DSC clause for DBB
projects on federal-aid highway projects unless its use is contrary to the state law. The typical
DSC clause provides broad relief to a contractor for site conditions that differ materially from
Project Characteristic Source
• High risk of differing site conditions.
• Low probability to be able to expedite design and construction schedule.
• High possibility of change to phases of work.
Blanchard 2007
• The design must be complete to develop accurate pricing.
• The design must be complete to obtain permits and/or satisfy other third party
issues.
Gransberg et al.
2006
• Project scope is difficult to define or quantify.
• Project scope has high probability of change in permitting process.
• Missing “sound geotechnical and environmental data prior to the bid phase.”
Christensen and
Meeker 2002
• “Inability of design-stage investigation to eliminate risks from
unknown geological conditions for construction of underground
works.”
Hoek and Palmieri
1998
• Risk shedding is owner’s primary motivation for using alternative project
delivery methods.
Scheepbouwer and
Humphries 2011
Table 1.1. Project characteristics that indicate a poor candidate
for DB project delivery.
5. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
6 Guidelines for Managing Geotechnical Risks in Design–Build Projects
what is expected according to the contract documents. Thus, the risk of DSC is usually borne by
the owner in DBB projects. However, in DB, the design–builder is responsible for completing the
design and construction under a single contract. FHWA does not have a similar DSC mandate
for DB projects. Without a DSC clause, the liability for DSC becomes murky and the potential
for costly and time-consuming disputes rises.
Most RFPs require that the design–builder conduct a comprehensive geotechnical study of
the site and base the final design on the results of its own geotechnical investigation. A dilemma
arises since the geotechnical study is not conducted until the contract is awarded, and it is both
unreasonable and unrealistic to expect competing teams to gather that data at their own expense
during procurement. Thus, the agency must provide enough information about project site
conditions to permit competing teams to develop a price, forcing the DOT to furnish what is
currently available in the agency’s files and from any preliminary engineering studies. Often,
the same RFPs also include disclaimers of liability for the accuracy of geotechnical information
furnished by the owner in the RFP. As a result, when the winning design–builder encounters a
site condition that significantly differs from the owner-furnished RFP geotechnical data during
its own comprehensive investigations, a dispute may occur if the agency denies the claim, relying
on its exculpatory disclaimers.
The legal review that was conducted found two important facts that can be used to pro
vide guidance on the above-cited dilemma. First, regardless of project delivery method, the
courts rarely find for the project owner, holding that most exculpatory verbiage does not in fact
transfer the liability for unknown/undiscovered conditions. Second, when the agency fails to
disclose everything it knows about a given project’s site conditions in the DB RFP, the agency
stands in danger of having been found to have knowingly withheld information that would have
DBB Contractor/Design–Builder Owner
Geotechnical Scope Risk
DBB
Warranties and guarantees
Latent defects—workmanship
Competent geotechnical specialty
subcontractors available
Design error and omissions
Latent defects—design
Direct and tacit approval of constructive
changes to geotechnical design
DB
Design errors and omissions
Warranties and guarantees
Latent defects—design and/or
workmanship
Competent geotechnical design personnel
available
Clear geotechnical scope definition
Direct and tacit approval of constructive
changes to geotechnical design
Geotechnical design review comments and
directives
Technical review capability
Geotechnical Cost Risk
DBB
Rework
Subcontractor default
Market fluctuation after award
Redesign and resultant rework
Construction contract amount
Market fluctuation during design—material and
labor
DB
Rework
Redesign
Subcontractor default
Market fluctuation during
design—material and labor
Design–build contract amount
Prompt payment
Design–builder default
Geotechnical Schedule Risk
DBB
Contract completion date
Liquidated damages
Timely design completion
Owner furnished property delivery
DB
Delivery on approved schedule
Fast-track geotechnical rework
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
• Liquidated damages
Unrealistic schedule
Timely geotechnical design approvals on fast-
track project
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
• Owner furnished property delivery
Table 1.2. DBB versus DB geotechnical risk profiles.
6. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
Introduction to Design–Build Geotechnical Risk Management 7
materially affected bid pricing. The conclusion is clear. The owner cannot reliably shed DSC risk
and, therefore, must mitigate that risk in other ways, like including a DSC clause in their DB
contracts. The subsequent chapters in this report will furnish a number of other alternatives that
have proved to be successful.
1.1.2 Alternative Contracting Methods
This report features AASHTO best practices guidance for managing geotechnical risk in vari
ous types of DB contracts, including specific task assignments of responsibility based on the
type of contracting method and means of project execution. There are three major variations of
the DB delivery method. Those variations are based on the manner in which the award will be
determined. The general definition for DB and its variations are as follows:
• Design–Build. The system of contracting under which one entity performs both architecture/
engineering and construction under a single contract with the owner.
– Design–Build–Low Bid. The award is based on the lowest priced responsive proposal.
– Design–Build–Best Value. The award is based on the factors other than lowest proposed
price alone. The factors may include qualifications, past experience, proposed design
approach, proposed schedule, and so on.
– Design–Build–Stipulated Sum. This variant is sometimes termed “Fixed Price-Best Proposal.”
Its distinguishing feature is the absence of price competition. The owner stipulates the
maximum allowable price and essentially awards the project to the proposal that provides
the “most bang for the buck.”
DB is intended to create a single point of responsibility for design and construction, inte
grating the DB team through its internal contractual arrangements. DB also permits the
owner to evaluate the merits of multiple design solutions to the same design problem. If
the agency indicates a specific desire to optimize the geotechnical risk management strategy
in the proposed design, it will potentially receive proposals from the competing DB teams
that provide more than one approach for satisfying the project’s RFP performance criteria.
Table 1.3 shows the major advantages and disadvantages of using DB in the geotechnical risk
management context.
Alternate technical concepts (ATCs) can be included in all three DB variants. ATCs are often
referred to incorrectly as pre-award value engineering. While the result is the same (i.e., money
or timesaving changes to the baseline design are proposed, evaluated, and approved), there is
no shared savings. The agency receives the entire savings as part of the contract award price.
The definition for ATCs is as follows:
• Alternative Technical Concepts. An ATC is a specific modification of the baseline scope of
work and its attendant contract requirements in a manner that is equal to or better than the
baseline scope of work articulated in the solicitation of the project.
NCHRP Synthesis 455: Alternative Technical Concepts (2014) found
that the confidential one-on-one meetings used in “ATC submittal pro
cess was found to be an effective practice for DB projects to furnish an
opportunity to identify errors, omissions, ambiguities and to provide clari-
fications that might not be raised when all RFIs are published.” It also
found that “implementing ATCs with confidential one-on-one meet
ings effectively provides a new level of design quality control through
the involvement of the contractor in reviewing the solicitation and
design documents and identifying errors, omissions, and ambiguities.”
Hence, the ATC one-on-one meetings create an opportunity to clarify
the geotechnical risk as well as for the agency to consider changes to the
“In comparing the ATC cost benefits to
the stipends paid, Caltrans achieved a
return on investment of 156:1, mean-
ing $156 of ATCs incorporated or made
available to Caltrans for every dollar
spent on stipends.”
Ray Tritt, PE
2013
7. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
8 Guidelines for Managing Geotechnical Risks in Design–Build Projects
baseline design that it may not have found alone. As will be seen in subsequent chapters, ATCs
provide a powerful geotechnical risk management and mitigation tool for DB projects.
1.1.3 The Motivation of the Guidelines
The overarching motivation for using DB project delivery is driven by the agency’s need to
accelerate the project’s schedule. Geotechnical characterization of the site’s subsurface proper
ties is not an activity that can easily be crashed. Thus, most DB projects delay the comprehensive
geotechnical studies and reports to the post-award timeframe. This means that the contract price
is fixed and if the actual conditions significantly differ from those that can be reasonably expected
by the information provided in the RFP, a dispute may arise as to whether the changes/delays
related to differing subsurface conditions are compensable. Therefore, the primary purpose of
these guidelines is to furnish a menu of options for avoiding controversy over geotechnical risk,
based on DB practices of geotechnical risk management that have proved to be effective in the field.
These guidelines do not advocate any specific practice contained herein but rather leave it up to
the practitioner to identify those effective practices that will best apply to their specific DB project.
1.2 Project Geotechnical Risk Management Process
This section provides a brief overview of the classic project risk management process as
applied in the geotechnical context. Geotechnical risk is not just another one of the full suite of
risks that must be managed in a typical DB project. Geotechnical risk is typically the first one
Advantage Geotechnical Context
Single point of
responsibility for
both design and
construction
• Integrating subsurface risk management strategy into the project strategy facilitated
by DB internal structure.
• Reduced potential for differing site conditions delays.
• DB team can conduct subsurface utility engineering (SUE), plus utility
coordination.*
Contractor design
input
• Creates opportunities for optimizing means and methods with geotechnical
risk strategy.
• Allows DB team to evaluate alternatives to utility relocation after award, before final
design.
Fast tracking
supported
• Sequence of work can be optimized with project geotechnical risk strategy.
• Work packaging and work phases can be developed for geotechnical risk
requirements.
• Early start possible for utility relocations.
Compete different
design solutions
• Creates opportunities for optimizing DB teams’ preferred means and methods
with geotechnical risk strategy.
• Allows competing DB teams to propose alternatives to avoid geotechnical risks.
• Competing proposals can be evaluated for innovative geotechnical engineering
design and risk management strategies.
Disadvantage
Large
contingencies for
risk
• An incomplete geotechnical risk strategy forces the DB team to include
contingencies for subsurface risks and utility conflicts that might not be realized.
• Contingencies can be reduced if ATCs are used to create a pre-award dialogue to
better clarify geotechnical risk.
Loss of checks
and balances
• Frequently creates a subcontractor relationship for the designer, which may make
cost considerations after award more important than the coverage of the post-award
subsurface investigations and the quality of the geotechnical engineering.
• Often puts the general contractor between the owner and the designer, reducing
the designer’s ability to act as the owner’s advocate on geotechnical engineering
matters.
*See Standard Guidelines for the Collection and Depiction of Existing Subsurface Utility Data. (2002).
Standard CI/ASCE 38-02. American Society of Civil Engineers, Reston, Va.
Table 1.3. DB advantages and disadvantages.
8. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
Introduction to Design–Build Geotechnical Risk Management 9
encountered, the first one to be realized, and if well managed, it can be the first one retired
so that the project delivery team can focus on completing the remainder of the project.
It can be argued that geotechnical risk may also be the risk that has the highest level of
uncertainty during the pre-award phase and, as previously mentioned, cannot be transferred
in its entirety, regardless of contract language. Therefore, geotechnical risk occupies a unique
position in the project risk register because of its early occurrence and deserves to be treated
with the necessary respect and attention because of its potential impact on project cost and
schedule performance.
1.2.1 Risk Term Definitions
The definitions of following terms that relate to the risk management process are important
to understand to comprehend properly the information in this guide. These definitions come
from ISO 31000 (Lark 2015).
• Risk: Effect of uncertainty on objectives
• Risk Management: Coordinated activities to direct and control an organization with regard
to risk
• Risk Identification: Process of finding, recognizing, and describing risks
• Risk Assessment: Overall process of risk identification, risk quantification, risk analysis, and
risk evaluation
• Risk Analysis: Process to comprehend the nature of risk and determine the level of risk
• Risk Evaluation: Process of comparing the results of risk analysis with risk criteria to determine
whether the risk and/or its magnitude is acceptable or tolerable.
1.2.2 Geotechnical Term Definitions
Most DOTs have evolved their own technical jargon and the proliferation of new tech
nical terms in transportation creates confusion, making it difficult to properly interpret
agency documents. This issue is prevalent in the geotechnical arena. The guideline will use
certain geotechnical terms in a precise sense. It is important for the reader to understand the
specific definition of each of the terms to understand fully the contents of this document.
The definitions for the primary geotechnical reports that will be referenced in the synthesis
are drawn from the FHWA Technical Manual for Design and Construction of Road Tunnels—
Civil Elements (Hung et al. 2009), which draws from an American Society of Civil Engi
neers document that reports a consensus definition reached by the Underground Technical
Research Council (see Essex 2007 citation in Appendix A).
• Geotechnical Design Memoranda (GDM): “interpretive reports are used to evaluate design
alternatives, assess the impact of construction on adjacent structures and facilities, focus
on individual elements of the project, and discuss construction issues . . . the GDM may
be prepared at different stages of a project, and therefore may not accurately reflect the
final design or final contract documents. Since GDMs are used internally within the
design team and with the owner as part of the project development effort, it is not appro
priate to include GDMs as part of the contract documents.” Also termed geotechnical
interpretive report.
• Geotechnical Data Report (GDR): “a document that presents the factual subsurface data for
the project without including an interpretation of these data. The purpose of the GDR is to
compile all factual geological, geotechnical, groundwater, and other data obtained from the
geotechnical investigations for use by the various participants in the project, including the
owner, designers, contractors and third parties that may be impacted by the project. It serves
9. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
10 Guidelines for Managing Geotechnical Risks in Design–Build Projects
as a single and comprehensive source of geotechnical information obtained for the project.”
The GDR should contain the following information:
– “Descriptions of the geologic setting;
– Descriptions of the site exploration program(s);
– Logs of all borings, trenches, and other site investigations;
– Descriptions/discussions of all field and laboratory test programs; and
– Results of all field and laboratory testing.”
• Geotechnical Baseline Report (GBR): a document developed “to define the baseline conditions
on which contractors will base their bids and select their means, methods and equipment,
and that will be used as a basis for determining the merits of contractor claims of differing site
conditions during construction.” The GBR should contain the following information:
– “The amounts and distribution of different materials along the selected alignment;
– Description,strength,compressibility,grain size,and permeability of the existing materials;
– Description, strength and permeability of the ground mass as a whole;
– Groundwater levels and expected groundwater conditions, including baseline estimates of
inflows and pumping rates;
– Anticipated ground behavior, and the influence of groundwater, with regard to methods of
excavation and installation of ground support;
– Construction impacts on adjacent facilities; and
– Potential geotechnical and man-made sources of potential difficulty or hazard that could
impact construction, including the presence of faults, gas, boulders, solution cavities, exist
ing foundation piles, and the like.”
In addition to the above terms, the supporting research found that DOTs use several terms
to describe commonly practiced methods for conveying geotechnical information in DB RFPs.
They are as follows:
• Reconnaissance Report: Document that contains the results of a review of records and observa
tions from the project site.
• Geotechnical Summary Report: Document that contains the results of a review of records and
geotechnical investigation of critical areas.
• Preliminary Geotechnical Data Report: Document that contains the results of a partial geotech
nical investigation that will eventually be included in a final GDR.
1.2.3 Design–Build Term Definitions
It is also necessary to provide standard definitions for terms that relate to DB project delivery.
Those terms follow.
• Design–bid–build (DBB). The “traditional” project delivery approach where the owner com
missions a designer to prepare drawings and specifications under a design services contract,
and separately contracts for construction, by engaging a contractor through competitive
bidding or negotiation.
• Design–build(DB).Thesystemofcontractingunderwhichoneentityperformsbotharchitecture/
engineering and construction under a single contract with the owner.
• Alternative technical concepts (ATC). An ATC is a specific modification of the baseline scope
of work and its attendant contract requirements in a manner that is equal to or better than
the baseline scope of work articulated in the projects solicitation.
• Differing site conditions (DSC) clause. A contract clause designed to give a contractor cost and
time relief for: (1) subsurface or latent physical conditions encountered at the site differing
materially from those indicated in the contract; or (2) unknown physical conditions at the
site of an unusual nature differing materially from those ordinarily encountered and generally
10. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
Introduction to Design–Build Geotechnical Risk Management 11
recognized as inherent in the work provided for in the contract [U.S. Code, Differing Site
Conditions, Title 23 CFR 635.109 (2013)].
There are two types.
– Type 1 DSC. Type 1 focuses on conditions that are indicated in the contract documents.
Classic examples include (a) rock or water at different elevations than shown in the geo
technical report, (b) unknown underground utilities, and (c) soil that contains different
characteristics than identified in the contract documents.
– Type 2 DSC. Type 2 is independent from what is set forth in the contract documents
and defined by what one would reasonably expect to encounter in performing the work.
Examples of this can be soil compacting or rock fracturing differently than one would
reasonably expect.
1.2.4 The Differing Site Conditions Clause
Some owners believe that the contractor should bear the risk of DSCs. The flaw in this form
of logic is that neither the owner nor the contractor can accurately value the risk of geotechnical
unknowns. When forced to price geotechnical risk, contractors include contingencies that could
either price themselves out of the competition, or, if they do win the contract, the potential that
the contingency might be insufficient for dealing with the actual conditions. Many sophisticated
contractors will refuse to bid on a contract with unlimited DSC risk. This not only reduces
competition but also increases the risk to the owner that the winning contractor will have
underpriced the risk and may default if faced with a significant DSC for which it is liable. More
important, if the potential geotechnical risks are not realized, the owner will have overpaid for
the project, leaving the lucky contractor with a windfall.
Time has shown that owners are in the best position to accept the DSC risk and the most
common approach is to include a DSC clause in the DB contract. A landmark U.S. Claims Court
decision provided a clear explanation of the purpose of the DSC clause (Foster Construction C.A.
and Williams Brother Company, a Joint Venture, Etc. v. the United States 1970):
The purpose of the changed conditions clause is thus to take at least some of the gamble on subsurface con-
ditions out of bidding. Bidders need not weigh the cost and ease of making their own borings against the risk
of encountering an adverse subsurface, and they need not consider how large a contingency should be added
to the bid to cover the risk. They will have no windfalls and no disasters. The Government benefits from more
accurate bidding, without inflation for risks which may not eventuate. It pays for difficult subsurface work only
when it is encountered and was not indicated in the logs.
The DSC clause provides cost and time relief for: (1) subsurface or latent physical condi
tions encountered at the site differing materially from those indicated in the contract; or
(2) unknown physical conditions at the site of an unusual nature, differing materially from
those ordinarily encountered and generally recognized as inherent in the work provided for
in the contract. The owner only pays for the actual costs incurred if and when these condi
tions are actually encountered, as opposed to the unliquidated contingency for a geotechni
cal risk that may never occur.
1.3 Design–Build Project Risk Management Planning
This section presents an overview of the geotechnical risk management planning in the DB
project development and delivery. Figure 1.1 shows the generic risk assessment cycle. The figure
shows that it is a continuing process and, as a result, the DB project risk management plan must
include provisions for tracking project risks, updating the project risk register, and retiring risks
when appropriate.
11. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
12 Guidelines for Managing Geotechnical Risks in Design–Build Projects
Most agencies that use DB have their own policies and standard operating procedures for
conducting formal risk analyses on DB projects. Geotechnical, utilities, and other subsurface
risks are generally included in those documents and implementing this guide in no way alters
those procedures. The practices described are intended to provide a sharper focus on the
geotechnical risks and furnish the agency a set of tools for managing and mitigating risks due
to geotechnical uncertainty. The guide also seeks to raise the visibility of geotechnical risks
and contends that the combination of high uncertainty and the need to pursue an aggressive
schedule on DB projects warrants giving geotechnical risks special focus by pursuing a policy
of retiring geotechnical risks as early in the project as practical. Thus, the change, if there
is one, is the focus on early risk retirement as the primary geotechnical risk management
strategy.
1.3.1 Defining Geotechnical Risk Management and Risk Response
ISO 31000 defines a risk as the “effect of uncertainty on objectives” and risk management as
those “coordinated activities to direct and control an organization with regard to risk.” In this
case, the risk is that actual site conditions will be found to be different from those that were
reasonably anticipated at the time of DB contract award and establishment of the lump sum
price for the project. Its effect is the possibility of scope changes that will result in cost and sched
ule overruns. Therefore, geotechnical risk management involves coordinating the activities to
reduce the uncertainty that lead to the point where the geotechnical risk is realized or is not real
ized. These activities occur in two distinct stages. They are the activities that seek to characterize
the site conditions before DB contract award and those that occur after the contract is consum
mated. The pre-award activities involve preliminary geotechnical engineering, the development
of geotechnical information to be contained in the DB RFP, and the other activities described
in Section 1.3.3 below. The post-award activities (see Section 1.3.4) encompass the geotechnical
studies conducted as part of the final design process and early subsurface construction activities
that seek to disclose actual site conditions.
In Figure 1.1, the first step is to identify geotechnical risks. Table 1.4 is a list of 29 subsurface
risks identified by a survey of state DOT geotechnical personnel and corroborated by indus
try geotechnical engineers who work on DB teams. The subsurface risks are ranked using an
1. Risk
Identification
4. Risk
Mitigation
&
Monitoring
2. Risk
Quantification
3. Risk
Evaluation
Figure 1.1. Risk assessment process.
12. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
Introduction to Design–Build Geotechnical Risk Management 13
objective system based on survey respondent ratings of each risk’s frequency of occurrence and
impact if realized.
The three columns on the right side of Table 1.4 can be used as a checklist to ensure that the
pre-award geotechnical risk identification process includes the major common risks. The table
is not meant to be inclusive, and the risk analyst will want to ensure that agency geotechnical
engineers are consulted to determine if other project specific risks not shown in the table are
present. Once the DB project’s risk identification process is complete, the agency must deter
mine how it will respond to each risk. Classic risk management theory offers four possible
responses:
1. Avoid. This is done by removing the cause of the risk and may involve revisiting the project’s
design to determine if this response is viable.
2. Transfer. This is done in the risk allocation process and should be governed by transferring the
risk to the party that is best equipped to own the risk and deal with it effectively.This response
often involves preparing to pay the other party to own the transferred risk.
3. Mitigate. Mitigation involves reducing the probability of occurrence and/or severity of
impact of the risk to an acceptable level.Again, mitigation responses often involve additional
resources.
4. Accept. This is the final response if a given risk cannot be avoided, transferred, or mitigated.
Often this response demands the development of a contingency plan, as well as a specific
amount of contingency funds set aside to cover the risk if it will be realized.
Importance # Identified Geotechnical Risk Factors Present? Probability Impact
High
[1-10]
1 Landslides
2 Slope instability
3 Contaminated material
4 Highly compressive soils
5 Settlement of adjacent structure
6
Prediction of subsurface conditions due to
inaccessible drilling locations
7 Subsidence (subsurface voids)
8 Soft clays, organic silts, or peat
9
Consideration for public sensitivity/reaction to
excavations (parks, historic buildings, etc.)
10 Scour of bridge piers
Medium
[11-20]
11 Soft compressible soil
12 Seismic risk
13 Karst formations
14 Caverns/voids
15
Existing structures likely to be impacted by the
work (other than utilities)
16 Groundwater/water table
17 Utility conflicts
18 Lateral spreading
19 Liquefaction
20 Rock faults/fragmentation
Low
[21-29]
21 Settlement in general
22 Underground manmade debris
23 Settlement of bridge approaches
24 Presence of rock/boulders
25 Eroding/mobile ground conditions
26 Chemically reactive ground
27 Unsuitable material
28 Groundwater infiltration
29 Replace in situ material with borrowed material
Note: Based on NCHRP Project 24-44 survey.
Table 1.4. Ranked geotechnical risks.
13. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
14 Guidelines for Managing Geotechnical Risks in Design–Build Projects
Table 1.5 contains a listing of 25 geotechnical risk management tools found to be effective
during the research. The tools are grouped by stage of project development and delivery in which
they apply. The table provides the primary source of the given tool. A state abbreviation followed
by a plus sign (+) indicates that the tool was observed to be used in other states as well. A detailed
description of each tool may be found in Chapter 5.
1.3.2
Integrating the Management of Geotechnical Risk
into the Overall Project Risk Plan
In keeping with the findings of the supporting research that geotechnical risks are likely to
be the first ones realized in the post-award phase of project execution, integrating them into
the overall DB project risk register is a matter of giving the geotechnical risks elevated visibility
during the formal risk analysis. There are several ways to achieve the heightened awareness of
the geotechnical risks.
The first example is to address geotechnical risks first and determine an appropriate risk
response for each one. Then check all other risk responses to determine if they will interfere
with the geotechnical risk strategy. An example resolving other risks within the context of the
geotechnical risk profile might be a decision to relocate a given utility system that was brought
# Tool Source
Tools Used During RFP Development
1 Flexible footprint for NEPA clearance MO
2 Develop and furnish GBR in RFP WA+
3 Geotechnical conditions database VA
4 Site conditions history from property owners during right-of-way (ROW) acquisition MN
5 Prescriptive geotechnical design UT+
6 Performance specifications for post-construction performance (subsidence, etc.) MN+
Tools Used During Procurement and Award
7 Include differing site conditions clause SC+
8 Progressive DB MD
9 Request of geotechnical and/or utilities ATCs CA+
10 Define no-go zones for geotechnical ATCs UT+
11 Competitor designated boring locations UT+
12 Competitors permitted to conduct supplementary borings at own expense. MN+
13 Unit prices for contaminated material, over-excavation, etc. MT+
14 Weight geotechnical evaluation criteria MI+
15 Include life-cycle criteria in best value award scheme TX+
Tools Used During Post-Award
16 Scope validation period VA
17
Multiple notices to proceed (NTP) with one designated for geotechnical
investigation, design, and a second specifically to commence excavations,
utility work, etc.
UT
18 Contractor produced geotechnical baseline report for construction (GBR-C) OH
19 Negotiated GBR interpretation WA+
20 Differing site conditions allowance WA+
21 Contaminated material allowance MN+
22 Unforeseen utilities allowance KY
23 Assign design–builder responsibility for utility coordination TX+
24 Validate proposed life cycle elements during design CA
25 Encourage life cycle related value engineering proposals from subcontractors CA+
Table 1.5. Geotechnical risk management tools identified in the research.
14. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
Introduction to Design–Build Geotechnical Risk Management 15
into conflict by a geotechnical risk management decision to shift the alignment of the project to
avoid potentially contaminated material.
A second example comes from the Virginia DOT, where the risk response decision is to trans
fer the geotechnical risk to the design–builder and give it a 120-day scope validation period after
award to conduct its subsurface investigations and identify any potential DSC, after which DSC
claims are not permitted. If an unexpected condition is uncovered during the scope validation
period, execute a negotiated change to the project’s scope to provide the design–builder the
necessary compensation at an early point in the project to mitigate schedule and cost impacts.
A third example is Washington State DOT’s geotechnical risk acceptance clause for DB DSC,
in which the agency sets a fixed dollar limit below which the design–builder is responsible for
any DSC encountered and above which the state assumes all responsibility.
1.3.3
Geotechnical Risk Considerations During Preliminary
Engineering and Procurement
Pre-award geotechnical risk management activities involve the following:
• Identifying the primary geotechnical risks for the specific DB project.
• Conducting preliminary geotechnical information gathering to characterize the project site.
• Preparing the project’s solicitation documents [request for quotation (RFQ) and RFP].
• Providing a conduit where requests for information (RFI) can be submitted and satisfied
during procurement.
• Determining the level of interactivity that the agency will permit with competing DB teams
during proposal preparation using mechanisms like confidential one-on-one meetings, allow
ing competitors to conduct their own site borings, etc.
• Determining whether geotechnical ATCs will be permitted and, if so,
how the agency will conduct the ATC review and approval process.
Identifying the DB project’s primary geotechnical risks sets the stage
for the remaining pre-award risk management activities (Gransberg
et al. 2014). Many agencies will do this as a matter of course in the
project’s risk analysis conducted as a part of their standard DB project
development procedure. For DB projects with high geotechnical risk,
the agency needs to ensure that staff members responsible for prepar
ing the solicitation and award documents are made aware of major
geotechnical risks and make provisions to manage them in the proj
ect procurement strategy. Once geotechnical risks are identified, the
agency can determine the level of geotechnical investigation that will
be conducted during the preliminary process necessary to develop the
DB RFP’s technical content. The pre-award geotechnical investigation
activities actually range across a broad spectrum from furnishing only
the site information available in the agency’s records, with no new geo
technical data collection for the development of a GBR.
The necessary qualifications and experience criteria for the design–
builder’s geotechnical design staff and construction team fall out of
the geotechnical risk identification process and will serve as evaluation
criteria in the DB project’s RFQ. Solicitation document developers
need to maintain a pragmatic outlook as the evaluation criteria are
developed and ensure that the criteria match both the major identified
risks and the potential availability of industry team members with the
The Minnesota DOT took advantage of
ATCs in the DB project delivery on the
Hastings Bridge Replacement DB project.
The DOT received an ATC that changed
the foundation design to an innovative
column-supported fill, which not only
greatly reduced the long-term subsidence
risk but also included the installation of
instrumentation to monitor settlement
over time and an extended warranty.
The same design–builder also proposed
an innovative plan for the rapid utility
transfer from the existing to the new
service that significantly reduced the
construction schedule. All told, the
Hastings Bridge Replacement DB ATCs
significantly reduced the cost of the
project, amply demonstrating the poten-
tial for leveraging DB with ATCs to benefit
the DOT by gaining early contractor
involvement in the design during the
procurement (Gransberg et al. 2014).
15. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
16 Guidelines for Managing Geotechnical Risks in Design–Build Projects
appropriate credentials and past experience to meet them. One effective practice identified
in the research was to quantify past experience in terms of the number of projects of similar
scope, complexity, and magnitude rather than using an arbitrary number of years of similar
experience.
Experience has shown that allowing a certain amount of agency/competing DB team inter
action has a positive impact on increasing the probability of having high quality proposals that
are fully responsive to the DB project’s solicitation. Again, a spectrum of possible amounts of
interaction exists, which ranges from merely accepting and answering RFIs to confidential one-
on-one meetings to accept ATCs, discuss specific geotechnical risks, and clarify ambiguities
found in the DB RFP. It is common to permit some form of additional site investigation by the
competing DB teams. This also falls in a range from permitting each competitor to designate
locations for additional borings to be made at the agency’s expense with all new information
provided to all competitors to permitting each competitor to conduct its own preliminary inves
tigations at its own expense and not disclose the results.
1.3.4 Geotechnical Risk Considerations After Award
Once the DB contract is awarded, the focus shifts from geotechnical risk management to
completing the geotechnical engineering investigations necessary to support the design and
getting early site development packages like utilities and drainage to a point where they can
released for construction. Chapter 5 includes details on geotechnical risk management strat
egies, methods, and tools. Three of the tools (progressive DB, scope validation period, and
multiple construction notices to proceed) are designed to get the construction contractor into
the field as early as practical to uncover the subsurface conditions and determine if there are
indeed conditions that differ materially from those that would reasonably have been expected
during price proposal preparation. The use of one of those tools shifts the geotechnical engi
neering from being design-centric to construction-centric and recognizes that even the most
extensive geotechnical investigations can still miss differing conditions. Therefore, the object
of the post-award effort in this area is to expose those risks as quickly as practical at a point
earlier enough in project execution that the cost impact of their remedies is minimized and
where any schedule impacts occur at a point where the maximum project float is available to
mitigate any delays.
1.3.5 Retiring Geotechnical Risks
The ultimate goal of DB project geotechnical risk management is to eliminate the subsurface
uncertainty so geotechnical risk can be retired and the project team can focus on completing the
remainder of the project. Once a risk of any sort is retired, the line item contingency allocated
to the risk can be released for use elsewhere in the project. Since subsurface risks will be exposed
and remedied first, it makes sense to treat them differently from the remainder of the project
risks. Agencies will want to consider structuring their budget in a manner that carries a separate
lump sum geotechnical contingency that can be released once the project has reached a point
where all possible subsurface risks have been retired.
1.4 How to Use the Guidelines
The guidelines are organized into seven chapters.
1. Introduction to Design–Build Geotechnical Risk Management
2. Geotechnical Risk Identification
16. Guidelines for Managing Geotechnical Risks in Design–Build Projects
Copyright National Academy of Sciences. All rights reserved.
Introduction to Design–Build Geotechnical Risk Management 17
3. Qualitative Geotechnical Risk Analysis
4. Quantitative Geotechnical Risk Analysis
5. Geotechnical Risk Management Strategies, Methods, and Tools
6. Geotechnical Risk Monitoring, Control, and Retirement
7. Design–Build Project Geotechnical Risk Management Planning Workshop Template
There are call-out boxes that emphasize the most important findings of the research and con
tain appropriate quotations and other facts or examples of how geotechnical risk issues discussed
in the text were overcome successfully in case study projects.