Embed presentation
Download to read offline





The document provides a cost update for the Third Place Building project. The total projected cost has decreased from the original 2008 budget of $1,000,000 to a current price for completion of $797,000. The shell cost has also decreased, with the original 2008 shell budget being $500,000, and the current anticipated cost for just the shell being $300,000. There is currently $220,000 cash on hand for the building fund, leaving a $80,000 shortfall to begin Phase 1.




