BID EVALUATION PROCESS:
RECEIVING TENDERS:
1. The data for all bids received shall be maintained in a Receiving Register.
2. Return late tenders unopened to the tenderers and record their existence and time of
arrival.
3. Ensure that a clear and formal report of the tenders received is produced.
PRELIMINARY EXAMINATION OF BIDS:
4. Bids to be properly signed and accompanied by a power of attorney.
5. Bids to be accompanied by the required bid security.
6. Bids to be free of computational errors.
OPENING TENDERS:
Technical Proposal:
7. Technical Bid to be opened 30 minutes after the closing time for bid receiving, and
duly marked in receiving register.
8. The bidders/representatives of bidders should mark their attendance in the attendance
sheet, if required to be present.
9. The attendance of members of the Bid Opening Committee should be duly marked.
10. The bid envelope, as well as the bidders’ attendance sheet shall be signed by the Bid
Opening Committee members. They will sign each tender page, mentioning the date as
well.
11. The technical bids should be opened first and financial bids should be retained.
12. Covering letter of technical bid to be signed by the Committee members.
TECHNICAL EVALUATION:
13. Members of Procurement Committee or Consultant Selection Committee to be present
and to duly mark their attendance.
14. Evaluation Report to be made, with initials of each member of the Committee on all
pages and signatures on the last page.
15. Successful bidders to be short-listed.
16. Results of shortlisting to be communicated to all bidders and to be uploaded on the
Company’s as well as PPRA’s website.
17. RFPs to be given to the short listed candidates for a particular fee.
18. The Committee should technically evaluate the bids and record minutes thereof.
19. The Committee is to put forth a duly signed technical evaluation report. If there was
pre-qualification, then final report is to be brought forth the Board of Directors.
20. Based on the technical evaluation, letters should be written to technically qualifying
SAQLAIN ARSHAD & Co.
ADVOCATES & CORPORATE COUNSELS
w w w. s a q l a i n a r s h a d. c o m
Please mention our reference
In your reply:
________________________________________________________________________
65, Garden Block, New Garden Town, Lahore Pakistan
Tel: +92-42- 35884065-66 I Fax: +92-42- 35884066; Email: info@saqlainarshad.com
bidders, informing them of the date, time and venue of the financial bid opening.
Letters must also be written to the non-qualifying bidders, explaining them in writing
the reason for rejection of their bids.
OPENING TENDERS:
Financial Proposal:
21. The financial bid is to be opened at the designated date, time and venue.
22. All envelopes containing financial bids should be signed before opening and the bid
amount shall be encircled.
23. The bid amount should be read aloud. Procuring agency may also record the
proceedings in audio or video for future reference.
FINANCIAL EVALUATION:
24. The Committee is to send final evaluation report to all the technically shortlisted
candidates.
25. Evaluation price to include taxes.
26. All members of the evaluation committee and other personnel involved in any way
with the bid evaluation must be fully aware that the evaluation process up to the award
of a contract is confidential, and this confidentiality must be respected and fully
adhered to.
27. Any effort by a bidder or its agents to influence the evaluation of bids or award
decisions, including the offering or giving of bribes, gifts or other inducement, should
be reported to the evaluation committee. Such action by a bidder or its agents could
result in the invalidation of its bid and the forfeiture of its bid security.
28. Within 10 days of the bid evaluation report, the aggrieved bidders may lodge a
complaint and the Complaint Committee is to decide upon it, within 15 days of the
receipt of the complaint.
AWARDING THE CONTRACT:
29. The report for Award of Contract is to be presented before the Board of Directors after
lapse of 10 days’ grievance complaint time.
30. All terms and special conditions that apply, should be recorded in the contract
document. The contract should specify clear roles and responsibilities of both parties.
31. The contract is to be awarded to the successfully qualifying bidder, and the same is to
be updated on the PPRA website.
For any query on public procurement law, please write to us at
info@saqlainarshad.com or call on given numbers.

More Related Content

Similar to Bid evaluation process explained under PPRA laws

Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
umes manandhar
 
Bid document reverse tendering
Bid document reverse tenderingBid document reverse tendering
Bid document reverse tendering
Venkata Bhaskar Damera
 
Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”
RCREEE
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
Ritesh Kumar Baranwal
 
Bid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal PradeshBid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal Pradesh
Headway Solar
 
Public procurement rules 2004
Public procurement rules 2004Public procurement rules 2004
Public procurement rules 2004
Muhammad Ijaz Syed
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
Ganesh Bhorkade
 
Pre Qualification Disqualification as per PPRA Rules 2004.pptx
Pre Qualification Disqualification as per PPRA Rules 2004.pptxPre Qualification Disqualification as per PPRA Rules 2004.pptx
Pre Qualification Disqualification as per PPRA Rules 2004.pptx
Fayyaz Khan
 
Eoi indoor & outdoor venue branding
Eoi indoor & outdoor venue brandingEoi indoor & outdoor venue branding
Eoi indoor & outdoor venue branding
plastivision
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Joy Irman
 
Eoi fire fighting & services
Eoi  fire fighting & servicesEoi  fire fighting & services
Eoi fire fighting & services
plastivision
 
BIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptxBIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptx
benito procia
 
Eoi pr agency
Eoi pr agencyEoi pr agency
Eoi pr agency
plastivision
 
tamil nadu tenders act.pptx
tamil nadu tenders act.pptxtamil nadu tenders act.pptx
tamil nadu tenders act.pptx
Pradeep513562
 
MM FOR IIT JAMMU
MM FOR IIT JAMMU MM FOR IIT JAMMU
MM FOR IIT JAMMU
Ganesh Bhorkade
 
Tendering procedures
Tendering proceduresTendering procedures
Tendering procedures
Rotich Kimaru
 
Grinding & drilling machines bid
Grinding & drilling machines   bidGrinding & drilling machines   bid
Grinding & drilling machines bid
Charles Dick Benson N
 
StandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdfStandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdf
PSENTHILMURUGAN2
 
Eoi event activation & btl agency
Eoi event activation & btl agencyEoi event activation & btl agency
Eoi event activation & btl agency
plastivision
 
Eoi compressed air & water connection
Eoi compressed air & water connectionEoi compressed air & water connection
Eoi compressed air & water connection
plastivision
 

Similar to Bid evaluation process explained under PPRA laws (20)

Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Bid document reverse tendering
Bid document reverse tenderingBid document reverse tendering
Bid document reverse tendering
 
Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
Bid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal PradeshBid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal Pradesh
 
Public procurement rules 2004
Public procurement rules 2004Public procurement rules 2004
Public procurement rules 2004
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
 
Pre Qualification Disqualification as per PPRA Rules 2004.pptx
Pre Qualification Disqualification as per PPRA Rules 2004.pptxPre Qualification Disqualification as per PPRA Rules 2004.pptx
Pre Qualification Disqualification as per PPRA Rules 2004.pptx
 
Eoi indoor & outdoor venue branding
Eoi indoor & outdoor venue brandingEoi indoor & outdoor venue branding
Eoi indoor & outdoor venue branding
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
Eoi fire fighting & services
Eoi  fire fighting & servicesEoi  fire fighting & services
Eoi fire fighting & services
 
BIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptxBIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptx
 
Eoi pr agency
Eoi pr agencyEoi pr agency
Eoi pr agency
 
tamil nadu tenders act.pptx
tamil nadu tenders act.pptxtamil nadu tenders act.pptx
tamil nadu tenders act.pptx
 
MM FOR IIT JAMMU
MM FOR IIT JAMMU MM FOR IIT JAMMU
MM FOR IIT JAMMU
 
Tendering procedures
Tendering proceduresTendering procedures
Tendering procedures
 
Grinding & drilling machines bid
Grinding & drilling machines   bidGrinding & drilling machines   bid
Grinding & drilling machines bid
 
StandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdfStandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdf
 
Eoi event activation & btl agency
Eoi event activation & btl agencyEoi event activation & btl agency
Eoi event activation & btl agency
 
Eoi compressed air & water connection
Eoi compressed air & water connectionEoi compressed air & water connection
Eoi compressed air & water connection
 

Recently uploaded

原版定做(sheffield学位证书)英国谢菲尔德大学毕业证文凭证书原版一模一样
原版定做(sheffield学位证书)英国谢菲尔德大学毕业证文凭证书原版一模一样原版定做(sheffield学位证书)英国谢菲尔德大学毕业证文凭证书原版一模一样
原版定做(sheffield学位证书)英国谢菲尔德大学毕业证文凭证书原版一模一样
abondo3
 
Should AI hold Intellectual Property Rights?
Should AI hold Intellectual Property Rights?Should AI hold Intellectual Property Rights?
Should AI hold Intellectual Property Rights?
RoseZubler1
 
A Critical Study of ICC Prosecutor's Move on GAZA War
A Critical Study of ICC Prosecutor's Move on GAZA WarA Critical Study of ICC Prosecutor's Move on GAZA War
A Critical Study of ICC Prosecutor's Move on GAZA War
Nilendra Kumar
 
一比一原版多伦多都会大学毕业证(TMU毕业证书)学历如何办理
一比一原版多伦多都会大学毕业证(TMU毕业证书)学历如何办理一比一原版多伦多都会大学毕业证(TMU毕业证书)学历如何办理
一比一原版多伦多都会大学毕业证(TMU毕业证书)学历如何办理
woywevt
 
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
ElenaLazr2
 
一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
一比一原版(monash毕业证书)莫纳什大学毕业证如何办理一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
bzofm
 
一比一原版(uwgb毕业证书)美国威斯康星大学绿湾分校毕业证如何办理
一比一原版(uwgb毕业证书)美国威斯康星大学绿湾分校毕业证如何办理一比一原版(uwgb毕业证书)美国威斯康星大学绿湾分校毕业证如何办理
一比一原版(uwgb毕业证书)美国威斯康星大学绿湾分校毕业证如何办理
pdeehy
 
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
cadyzeo
 
一比一原版英国伦敦商学院毕业证(lbs毕业证书)如何办理
一比一原版英国伦敦商学院毕业证(lbs毕业证书)如何办理一比一原版英国伦敦商学院毕业证(lbs毕业证书)如何办理
一比一原版英国伦敦商学院毕业证(lbs毕业证书)如何办理
gedsuu
 
一比一原版(trent毕业证书)加拿大特伦特大学毕业证如何办理
一比一原版(trent毕业证书)加拿大特伦特大学毕业证如何办理一比一原版(trent毕业证书)加拿大特伦特大学毕业证如何办理
一比一原版(trent毕业证书)加拿大特伦特大学毕业证如何办理
mecyyn
 
一比一原版英国伦敦大学亚非学院毕业证(soas毕业证书)如何办理
一比一原版英国伦敦大学亚非学院毕业证(soas毕业证书)如何办理一比一原版英国伦敦大学亚非学院毕业证(soas毕业证书)如何办理
一比一原版英国伦敦大学亚非学院毕业证(soas毕业证书)如何办理
duxss
 
一比一原版朴次茅斯大学毕业证(uop毕业证)如何办理
一比一原版朴次茅斯大学毕业证(uop毕业证)如何办理一比一原版朴次茅斯大学毕业证(uop毕业证)如何办理
一比一原版朴次茅斯大学毕业证(uop毕业证)如何办理
onduyv
 
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
ymefneb
 
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
hedonxu
 
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
ayvace
 
一比一原版(glasgow毕业证书)格拉斯哥大学毕业证如何办理
一比一原版(glasgow毕业证书)格拉斯哥大学毕业证如何办理一比一原版(glasgow毕业证书)格拉斯哥大学毕业证如何办理
一比一原版(glasgow毕业证书)格拉斯哥大学毕业证如何办理
ooqzo
 
United States vs. Donald Trump Speaking Indictment
United States vs. Donald Trump Speaking IndictmentUnited States vs. Donald Trump Speaking Indictment
United States vs. Donald Trump Speaking Indictment
Todd Spodek
 
17-03 2022 -full agreement full version .pdf
17-03 2022 -full agreement full version .pdf17-03 2022 -full agreement full version .pdf
17-03 2022 -full agreement full version .pdf
ssuser0dfed9
 
Legal Research and Legal Methodology-1.pptx
Legal Research and Legal Methodology-1.pptxLegal Research and Legal Methodology-1.pptx
Legal Research and Legal Methodology-1.pptx
varalakshmillm
 
一比一原版林肯大学毕业证(lincoln毕业证)如何办理
一比一原版林肯大学毕业证(lincoln毕业证)如何办理一比一原版林肯大学毕业证(lincoln毕业证)如何办理
一比一原版林肯大学毕业证(lincoln毕业证)如何办理
fexbqa
 

Recently uploaded (20)

原版定做(sheffield学位证书)英国谢菲尔德大学毕业证文凭证书原版一模一样
原版定做(sheffield学位证书)英国谢菲尔德大学毕业证文凭证书原版一模一样原版定做(sheffield学位证书)英国谢菲尔德大学毕业证文凭证书原版一模一样
原版定做(sheffield学位证书)英国谢菲尔德大学毕业证文凭证书原版一模一样
 
Should AI hold Intellectual Property Rights?
Should AI hold Intellectual Property Rights?Should AI hold Intellectual Property Rights?
Should AI hold Intellectual Property Rights?
 
A Critical Study of ICC Prosecutor's Move on GAZA War
A Critical Study of ICC Prosecutor's Move on GAZA WarA Critical Study of ICC Prosecutor's Move on GAZA War
A Critical Study of ICC Prosecutor's Move on GAZA War
 
一比一原版多伦多都会大学毕业证(TMU毕业证书)学历如何办理
一比一原版多伦多都会大学毕业证(TMU毕业证书)学历如何办理一比一原版多伦多都会大学毕业证(TMU毕业证书)学历如何办理
一比一原版多伦多都会大学毕业证(TMU毕业证书)学历如何办理
 
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
 
一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
一比一原版(monash毕业证书)莫纳什大学毕业证如何办理一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
 
一比一原版(uwgb毕业证书)美国威斯康星大学绿湾分校毕业证如何办理
一比一原版(uwgb毕业证书)美国威斯康星大学绿湾分校毕业证如何办理一比一原版(uwgb毕业证书)美国威斯康星大学绿湾分校毕业证如何办理
一比一原版(uwgb毕业证书)美国威斯康星大学绿湾分校毕业证如何办理
 
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
 
一比一原版英国伦敦商学院毕业证(lbs毕业证书)如何办理
一比一原版英国伦敦商学院毕业证(lbs毕业证书)如何办理一比一原版英国伦敦商学院毕业证(lbs毕业证书)如何办理
一比一原版英国伦敦商学院毕业证(lbs毕业证书)如何办理
 
一比一原版(trent毕业证书)加拿大特伦特大学毕业证如何办理
一比一原版(trent毕业证书)加拿大特伦特大学毕业证如何办理一比一原版(trent毕业证书)加拿大特伦特大学毕业证如何办理
一比一原版(trent毕业证书)加拿大特伦特大学毕业证如何办理
 
一比一原版英国伦敦大学亚非学院毕业证(soas毕业证书)如何办理
一比一原版英国伦敦大学亚非学院毕业证(soas毕业证书)如何办理一比一原版英国伦敦大学亚非学院毕业证(soas毕业证书)如何办理
一比一原版英国伦敦大学亚非学院毕业证(soas毕业证书)如何办理
 
一比一原版朴次茅斯大学毕业证(uop毕业证)如何办理
一比一原版朴次茅斯大学毕业证(uop毕业证)如何办理一比一原版朴次茅斯大学毕业证(uop毕业证)如何办理
一比一原版朴次茅斯大学毕业证(uop毕业证)如何办理
 
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
 
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
 
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
 
一比一原版(glasgow毕业证书)格拉斯哥大学毕业证如何办理
一比一原版(glasgow毕业证书)格拉斯哥大学毕业证如何办理一比一原版(glasgow毕业证书)格拉斯哥大学毕业证如何办理
一比一原版(glasgow毕业证书)格拉斯哥大学毕业证如何办理
 
United States vs. Donald Trump Speaking Indictment
United States vs. Donald Trump Speaking IndictmentUnited States vs. Donald Trump Speaking Indictment
United States vs. Donald Trump Speaking Indictment
 
17-03 2022 -full agreement full version .pdf
17-03 2022 -full agreement full version .pdf17-03 2022 -full agreement full version .pdf
17-03 2022 -full agreement full version .pdf
 
Legal Research and Legal Methodology-1.pptx
Legal Research and Legal Methodology-1.pptxLegal Research and Legal Methodology-1.pptx
Legal Research and Legal Methodology-1.pptx
 
一比一原版林肯大学毕业证(lincoln毕业证)如何办理
一比一原版林肯大学毕业证(lincoln毕业证)如何办理一比一原版林肯大学毕业证(lincoln毕业证)如何办理
一比一原版林肯大学毕业证(lincoln毕业证)如何办理
 

Bid evaluation process explained under PPRA laws

  • 1. SAQLAIN ARSHAD & Co. ADVOCATES & CORPORATE COUNSELS w w w. s a q l a i n a r s h a d. c o m Please mention our reference In your reply: ________________________________________________________________________ 65, Garden Block, New Garden Town, Lahore Pakistan Tel: +92-42- 35884065-66 I Fax: +92-42- 35884066; Email: info@saqlainarshad.com BID EVALUATION PROCESS: RECEIVING TENDERS: 1. The data for all bids received shall be maintained in a Receiving Register. 2. Return late tenders unopened to the tenderers and record their existence and time of arrival. 3. Ensure that a clear and formal report of the tenders received is produced. PRELIMINARY EXAMINATION OF BIDS: 4. Bids to be properly signed and accompanied by a power of attorney. 5. Bids to be accompanied by the required bid security. 6. Bids to be free of computational errors. OPENING TENDERS: Technical Proposal: 7. Technical Bid to be opened 30 minutes after the closing time for bid receiving, and duly marked in receiving register. 8. The bidders/representatives of bidders should mark their attendance in the attendance sheet, if required to be present. 9. The attendance of members of the Bid Opening Committee should be duly marked. 10. The bid envelope, as well as the bidders’ attendance sheet shall be signed by the Bid Opening Committee members. They will sign each tender page, mentioning the date as well. 11. The technical bids should be opened first and financial bids should be retained. 12. Covering letter of technical bid to be signed by the Committee members. TECHNICAL EVALUATION: 13. Members of Procurement Committee or Consultant Selection Committee to be present and to duly mark their attendance. 14. Evaluation Report to be made, with initials of each member of the Committee on all pages and signatures on the last page. 15. Successful bidders to be short-listed. 16. Results of shortlisting to be communicated to all bidders and to be uploaded on the Company’s as well as PPRA’s website. 17. RFPs to be given to the short listed candidates for a particular fee. 18. The Committee should technically evaluate the bids and record minutes thereof. 19. The Committee is to put forth a duly signed technical evaluation report. If there was pre-qualification, then final report is to be brought forth the Board of Directors. 20. Based on the technical evaluation, letters should be written to technically qualifying
  • 2. SAQLAIN ARSHAD & Co. ADVOCATES & CORPORATE COUNSELS w w w. s a q l a i n a r s h a d. c o m Please mention our reference In your reply: ________________________________________________________________________ 65, Garden Block, New Garden Town, Lahore Pakistan Tel: +92-42- 35884065-66 I Fax: +92-42- 35884066; Email: info@saqlainarshad.com bidders, informing them of the date, time and venue of the financial bid opening. Letters must also be written to the non-qualifying bidders, explaining them in writing the reason for rejection of their bids. OPENING TENDERS: Financial Proposal: 21. The financial bid is to be opened at the designated date, time and venue. 22. All envelopes containing financial bids should be signed before opening and the bid amount shall be encircled. 23. The bid amount should be read aloud. Procuring agency may also record the proceedings in audio or video for future reference. FINANCIAL EVALUATION: 24. The Committee is to send final evaluation report to all the technically shortlisted candidates. 25. Evaluation price to include taxes. 26. All members of the evaluation committee and other personnel involved in any way with the bid evaluation must be fully aware that the evaluation process up to the award of a contract is confidential, and this confidentiality must be respected and fully adhered to. 27. Any effort by a bidder or its agents to influence the evaluation of bids or award decisions, including the offering or giving of bribes, gifts or other inducement, should be reported to the evaluation committee. Such action by a bidder or its agents could result in the invalidation of its bid and the forfeiture of its bid security. 28. Within 10 days of the bid evaluation report, the aggrieved bidders may lodge a complaint and the Complaint Committee is to decide upon it, within 15 days of the receipt of the complaint. AWARDING THE CONTRACT: 29. The report for Award of Contract is to be presented before the Board of Directors after lapse of 10 days’ grievance complaint time. 30. All terms and special conditions that apply, should be recorded in the contract document. The contract should specify clear roles and responsibilities of both parties. 31. The contract is to be awarded to the successfully qualifying bidder, and the same is to be updated on the PPRA website. For any query on public procurement law, please write to us at info@saqlainarshad.com or call on given numbers.