SlideShare a Scribd company logo
1 of 1
Download to read offline
1-877-786-7655 | WWW.STORMTEC.CA
CLIENT:
AVANTI KITSAULT MINE
LTD.
DURATION OF PROJECT:
1 MONTH
FLOW RATE:
300 GPM
CONTAMINATED:
NOT APLICABLE
DISCHARGE POINT:
AQUATIC HABITAT
EQUIPMENT:
 LFI600-LIQUID
FLOCCULENT
INJECTION UNIT
 18,000 GALLON
OPEN TOP TANKS (3)
 30HP TRANSFER
PUMP
 STF400-4 –SAND
MEDIA FILTER
AVANTI KITSAULT MINE - NW BC
Avanti Kitsault Mine Ltd. (AKML) is developing a mine
approximately 120 km north of Terrace, BC. Once in
operation, Avanti Kitsault Mine (AKM) will be one of the top
four primary producers of molybdenum in the world.
The AKM plan is envisaged as a conventional truck-and-shovel
open pit mining operation. Surface water run-off at the mine
site is being collected in a contact pond prior to discharge to a
local water stream. In order to ensure protection of the
environment, AKML selected an eco-friendly solution to
reduce the effluent turbidity.
After carrying out several tests on the water sample taken
from the contact pond, Stormtec established that 2%
chitosan-based flocculent worked extremely well in bringing
effluent turbidity to levels below 2 NTU. These tests also
allowed Stormtec to determine an effective flocculent dose
rate which enabled the customer to more accurately budget
for consumables.
The Stormtec treatment system was designed to meet the
required standards on a continuous basis and was installed
on-site in May 2015. AKM adheres to a very strict
environmental program. Therefore, in addition to the regular
tests for turbidity, field tests for residual flocculent were
carried out daily to confirm its absence in the discharge. The
project was successfully completed in June 2015 when all the
water in the contact pond was treated to continuously meet
BC Water Quality Guidelines to protect Freshwater Aquatic
Life.

More Related Content

Viewers also liked

Viewers also liked (12)

ESP
ESPESP
ESP
 
Electrostatic Precipitator
Electrostatic Precipitator Electrostatic Precipitator
Electrostatic Precipitator
 
Bs 4-sedimentation
Bs 4-sedimentationBs 4-sedimentation
Bs 4-sedimentation
 
Types of centrifuges
Types of centrifugesTypes of centrifuges
Types of centrifuges
 
Cyclone separator
Cyclone separatorCyclone separator
Cyclone separator
 
SEDIMENTATION
SEDIMENTATIONSEDIMENTATION
SEDIMENTATION
 
ESP (Electrostatic precipitator)
ESP (Electrostatic precipitator)ESP (Electrostatic precipitator)
ESP (Electrostatic precipitator)
 
Electrostatic precipitator (esp) - working function
Electrostatic precipitator (esp) - working functionElectrostatic precipitator (esp) - working function
Electrostatic precipitator (esp) - working function
 
Particle Technology- Filtration
Particle Technology- FiltrationParticle Technology- Filtration
Particle Technology- Filtration
 
Filtration and Clarification
Filtration and ClarificationFiltration and Clarification
Filtration and Clarification
 
Filtration
FiltrationFiltration
Filtration
 
Filtration
FiltrationFiltration
Filtration
 

Similar to BC - Kitsault Mine - APPROVED by AKM - October 30 2015

Canada Silver Cobalt - Corporate Presentation (May 29, 2020)
Canada Silver Cobalt - Corporate Presentation (May 29, 2020)Canada Silver Cobalt - Corporate Presentation (May 29, 2020)
Canada Silver Cobalt - Corporate Presentation (May 29, 2020)MomentumPR
 
Canada Silver Cobalt Works Presentation May 7th 2020
Canada Silver Cobalt Works Presentation May 7th 2020Canada Silver Cobalt Works Presentation May 7th 2020
Canada Silver Cobalt Works Presentation May 7th 2020MomentumPR
 
Kaz M-I for PM local content meeting_2
Kaz M-I for PM local content meeting_2Kaz M-I for PM local content meeting_2
Kaz M-I for PM local content meeting_2Berik Zh
 
San Manuel 1999 Ore Reserves Report (Draft)
San Manuel 1999 Ore Reserves Report (Draft)San Manuel 1999 Ore Reserves Report (Draft)
San Manuel 1999 Ore Reserves Report (Draft)Gary Sutton
 
UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016Charlie Bell
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
Canada cobalt-presentation-january-10-2020
Canada cobalt-presentation-january-10-2020Canada cobalt-presentation-january-10-2020
Canada cobalt-presentation-january-10-2020MomentumPR
 
Water management
Water managementWater management
Water managementSNC-Lavalin
 
Canada cobalt-presentation-january-3-2020
Canada cobalt-presentation-january-3-2020Canada cobalt-presentation-january-3-2020
Canada cobalt-presentation-january-3-2020MomentumPR
 
Angus Creek Stormwater Harvest
Angus Creek Stormwater HarvestAngus Creek Stormwater Harvest
Angus Creek Stormwater HarvestPhillip Birtles
 
Canada Cobalt-Presentation-march-10-2020
Canada Cobalt-Presentation-march-10-2020Canada Cobalt-Presentation-march-10-2020
Canada Cobalt-Presentation-march-10-2020MomentumPR
 
Sustainable Hydropower Development Alternatives for the Mekong
Sustainable Hydropower Development Alternatives for the MekongSustainable Hydropower Development Alternatives for the Mekong
Sustainable Hydropower Development Alternatives for the MekongJessicaNagtalon
 
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...Michael Hewitt, GISP
 
Rainwater Harvesting Systems - Case Studies
Rainwater Harvesting Systems - Case StudiesRainwater Harvesting Systems - Case Studies
Rainwater Harvesting Systems - Case StudiesD4Z
 
The caserones project
The caserones projectThe caserones project
The caserones projectRoberto Salas
 
Project Management Challenges in an Effluent Treatment Plant Construction
Project Management  Challenges in an Effluent Treatment Plant Construction Project Management  Challenges in an Effluent Treatment Plant Construction
Project Management Challenges in an Effluent Treatment Plant Construction PRABHASH GOKARN
 

Similar to BC - Kitsault Mine - APPROVED by AKM - October 30 2015 (20)

Mc Knight Sess13 102309
Mc Knight Sess13 102309Mc Knight Sess13 102309
Mc Knight Sess13 102309
 
Canada Silver Cobalt - Corporate Presentation (May 29, 2020)
Canada Silver Cobalt - Corporate Presentation (May 29, 2020)Canada Silver Cobalt - Corporate Presentation (May 29, 2020)
Canada Silver Cobalt - Corporate Presentation (May 29, 2020)
 
Canada Silver Cobalt Works Presentation May 7th 2020
Canada Silver Cobalt Works Presentation May 7th 2020Canada Silver Cobalt Works Presentation May 7th 2020
Canada Silver Cobalt Works Presentation May 7th 2020
 
Kaz M-I for PM local content meeting_2
Kaz M-I for PM local content meeting_2Kaz M-I for PM local content meeting_2
Kaz M-I for PM local content meeting_2
 
San Manuel 1999 Ore Reserves Report (Draft)
San Manuel 1999 Ore Reserves Report (Draft)San Manuel 1999 Ore Reserves Report (Draft)
San Manuel 1999 Ore Reserves Report (Draft)
 
UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
Canada cobalt-presentation-january-10-2020
Canada cobalt-presentation-january-10-2020Canada cobalt-presentation-january-10-2020
Canada cobalt-presentation-january-10-2020
 
Water management
Water managementWater management
Water management
 
uranium.pptx
uranium.pptxuranium.pptx
uranium.pptx
 
www homepage SBM_1
www homepage SBM_1www homepage SBM_1
www homepage SBM_1
 
Canada cobalt-presentation-january-3-2020
Canada cobalt-presentation-january-3-2020Canada cobalt-presentation-january-3-2020
Canada cobalt-presentation-january-3-2020
 
Angus Creek Stormwater Harvest
Angus Creek Stormwater HarvestAngus Creek Stormwater Harvest
Angus Creek Stormwater Harvest
 
Canada Cobalt-Presentation-march-10-2020
Canada Cobalt-Presentation-march-10-2020Canada Cobalt-Presentation-march-10-2020
Canada Cobalt-Presentation-march-10-2020
 
Sustainable Hydropower Development Alternatives for the Mekong
Sustainable Hydropower Development Alternatives for the MekongSustainable Hydropower Development Alternatives for the Mekong
Sustainable Hydropower Development Alternatives for the Mekong
 
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...
Robert Hughes and Michael Hewitt, EPCAMR, “3D Modeling of Eastern Pennsylvani...
 
Env2010 Presentation- Vancouver 2010
Env2010 Presentation- Vancouver 2010Env2010 Presentation- Vancouver 2010
Env2010 Presentation- Vancouver 2010
 
Rainwater Harvesting Systems - Case Studies
Rainwater Harvesting Systems - Case StudiesRainwater Harvesting Systems - Case Studies
Rainwater Harvesting Systems - Case Studies
 
The caserones project
The caserones projectThe caserones project
The caserones project
 
Project Management Challenges in an Effluent Treatment Plant Construction
Project Management  Challenges in an Effluent Treatment Plant Construction Project Management  Challenges in an Effluent Treatment Plant Construction
Project Management Challenges in an Effluent Treatment Plant Construction
 

BC - Kitsault Mine - APPROVED by AKM - October 30 2015

  • 1. 1-877-786-7655 | WWW.STORMTEC.CA CLIENT: AVANTI KITSAULT MINE LTD. DURATION OF PROJECT: 1 MONTH FLOW RATE: 300 GPM CONTAMINATED: NOT APLICABLE DISCHARGE POINT: AQUATIC HABITAT EQUIPMENT:  LFI600-LIQUID FLOCCULENT INJECTION UNIT  18,000 GALLON OPEN TOP TANKS (3)  30HP TRANSFER PUMP  STF400-4 –SAND MEDIA FILTER AVANTI KITSAULT MINE - NW BC Avanti Kitsault Mine Ltd. (AKML) is developing a mine approximately 120 km north of Terrace, BC. Once in operation, Avanti Kitsault Mine (AKM) will be one of the top four primary producers of molybdenum in the world. The AKM plan is envisaged as a conventional truck-and-shovel open pit mining operation. Surface water run-off at the mine site is being collected in a contact pond prior to discharge to a local water stream. In order to ensure protection of the environment, AKML selected an eco-friendly solution to reduce the effluent turbidity. After carrying out several tests on the water sample taken from the contact pond, Stormtec established that 2% chitosan-based flocculent worked extremely well in bringing effluent turbidity to levels below 2 NTU. These tests also allowed Stormtec to determine an effective flocculent dose rate which enabled the customer to more accurately budget for consumables. The Stormtec treatment system was designed to meet the required standards on a continuous basis and was installed on-site in May 2015. AKM adheres to a very strict environmental program. Therefore, in addition to the regular tests for turbidity, field tests for residual flocculent were carried out daily to confirm its absence in the discharge. The project was successfully completed in June 2015 when all the water in the contact pond was treated to continuously meet BC Water Quality Guidelines to protect Freshwater Aquatic Life.