AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS – Photo Report
• Key Plan showing the Camera positions, Click on the Icon to review respective status:
1
2
3
4
5
6
7
8
9
10 11
12 13 14
15
1617
18
19
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 01
• Aurum Villas front entrance
Key Plan
1
2
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 02
• Package I – Road WMM completed
Key Plan
1
2
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 03
• Package I – Road Kerb work in progress
Key Plan
1
2
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 04
• Package I – Waterproofing and Tiling in progress
Key Plan
1
2
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 05
• Package I – UPVC window work in progress
Key Plan
1
2
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 06
• LEFT – Package 02 RIGHT – Package 01
Key Plan
1
2
3
4
5
6
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 07
• Package II – UPVC window work in progress
Key Plan
7
8
9
10 11
12
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 08
• Package I – External painting 1st coat in progress
Key Plan
7
8
9
10 11
12
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 10
• Package II – UPVC window in progress
Key Plan
7
8
9
10 11
12
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 11
• Package II – UPVC window fixing in progress
Key Plan
7
8
9
10 11
12
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 12
• Package II – Edge villa compound wall in progress
Key Plan
7
8
9
10 11
12
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 13
• Package II – UPVC window fixing in progress
Key Plan
13 14
15
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 14
• Package II – Plastering and tile works in progress
Key Plan
13 14
15
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 15
• Package II – internal plastering and planter work in progress
Key Plan
13 14
15
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 16
• Package II – tiles and planter work in progress
Key Plan
13 14
15
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 17
• Package II – shaft plumbing work and planter work in progress
Key Plan
13 14
15
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 18
• Package II – Road work in progress
Key Plan
13 14
15
1617
18
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS Position - 19
• Package II – Tiling work in progress
Key Plan
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS LOGON PROGRESS
• Group A Villas – Electrical wall conduit work in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS LOGON PROGRESS
• Group B Villas – Waterproofing and tiling in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS LOGON PROGRESS
• Group D Villas – External plastering in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS WATER TREATMENT PLANT
• Cover slab beam reinforcement in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS RAIN WATER HARVESTING PIT
• Excavation in progress
AURUM_Photo Report - Villas
Comments :
AURUM – VILLAS MOCKUP VILLA
• Front Elevation
AURUM_Photo Report - Villas
AURUM – VILLAS Aerial View
• .
AURUM_Photo Report - Villas
AURUM – VILLAS Front Entrance
• .

Aurum - Villas Photos Aug'2016

  • 1.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS – Photo Report • Key Plan showing the Camera positions, Click on the Icon to review respective status: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1617 18 19
  • 2.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 01 • Aurum Villas front entrance Key Plan 1 2 3 4 5 6
  • 3.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 02 • Package I – Road WMM completed Key Plan 1 2 3 4 5 6
  • 4.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 03 • Package I – Road Kerb work in progress Key Plan 1 2 3 4 5 6
  • 5.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 04 • Package I – Waterproofing and Tiling in progress Key Plan 1 2 3 4 5 6
  • 6.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 05 • Package I – UPVC window work in progress Key Plan 1 2 3 4 5 6
  • 7.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 06 • LEFT – Package 02 RIGHT – Package 01 Key Plan 1 2 3 4 5 6
  • 8.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 07 • Package II – UPVC window work in progress Key Plan 7 8 9 10 11 12
  • 9.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 08 • Package I – External painting 1st coat in progress Key Plan 7 8 9 10 11 12
  • 10.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 10 • Package II – UPVC window in progress Key Plan 7 8 9 10 11 12
  • 11.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 11 • Package II – UPVC window fixing in progress Key Plan 7 8 9 10 11 12
  • 12.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 12 • Package II – Edge villa compound wall in progress Key Plan 7 8 9 10 11 12
  • 13.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 13 • Package II – UPVC window fixing in progress Key Plan 13 14 15 1617 18
  • 14.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 14 • Package II – Plastering and tile works in progress Key Plan 13 14 15 1617 18
  • 15.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 15 • Package II – internal plastering and planter work in progress Key Plan 13 14 15 1617 18
  • 16.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 16 • Package II – tiles and planter work in progress Key Plan 13 14 15 1617 18
  • 17.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 17 • Package II – shaft plumbing work and planter work in progress Key Plan 13 14 15 1617 18
  • 18.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 18 • Package II – Road work in progress Key Plan 13 14 15 1617 18
  • 19.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS Position - 19 • Package II – Tiling work in progress Key Plan
  • 20.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS LOGON PROGRESS • Group A Villas – Electrical wall conduit work in progress
  • 21.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS LOGON PROGRESS • Group B Villas – Waterproofing and tiling in progress
  • 22.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS LOGON PROGRESS • Group D Villas – External plastering in progress
  • 23.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS WATER TREATMENT PLANT • Cover slab beam reinforcement in progress
  • 24.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS RAIN WATER HARVESTING PIT • Excavation in progress
  • 25.
    AURUM_Photo Report -Villas Comments : AURUM – VILLAS MOCKUP VILLA • Front Elevation
  • 26.
    AURUM_Photo Report -Villas AURUM – VILLAS Aerial View • .
  • 27.
    AURUM_Photo Report -Villas AURUM – VILLAS Front Entrance • .