Embed presentation
Download to read offline


The document outlines the activity node diagram and critical path for building an ATC tower project. The critical path consists of activities A, B, C, D, and E which are expected to take a total of 27 weeks to complete. A delay of up to 5 weeks in designing the tower will not impact the overall project completion time since all parallel activities can still finish within the 27 week critical path.
