1. Minor finishing and roofing work remains to complete the main factory building at an estimated cost of 950,633.25 Birr, which should not obstruct plant operations.
2. Construction of the boiler room building is important for plant operations and is estimated to cost 210,000 Birr.
3. Improving roads for raw material and product transport inside the plant is important, estimated at 650,000 Birr, as the soil is clay. Strengthening the fence is also needed.