Introduction Asian Development Bank Procurement Guidelines
Table of Contents Purpose General Conditions Applicability of Guidelines Eligibility Advance Contracting and Retroactive Financing
Purpose Asian Development Bank Procurement Guidelines
Purpose Para 1.1  The purpose of these Guidelines is to inform those carrying out a project that is financed in whole or in part by a loan from the Asian Development Bank (ADB), ADB-financed grant, or ADB-administered funds,of the policies that govern the procurement of goods, works, and services (other than consultant services)required for the project.
Purpose Para 1.1  The financing agreement governs the legal relationships between the borrowerand ADB, and the Guidelines are made applicable to procurement of goods and works for the project, as provided in the agreement.  The rights and obligations of the borrower and the providers of goods and works for the project are governed by the bidding documents, and by the contracts signed by the borrower with the providers of goods and works, and not by these Guidelines or the financing agreements.  No party other than the parties to the financing agreement shall derive any rights therefrom or have any claim to the proceeds of the financing.
General Considerations Asian Development Bank Procurement Guidelines
General Considerations Para 1.2  The responsibility for the implementation of the project, and therefore for the award and administration of contracts under the project, rests with the borrower. ADB, for its part, has the obligation to ensure that the proceeds of its financing are used with due attention to considerations of economy and efficiency.
General Considerations Para 1.2 While in practice the specific procurement rules and procedures to be followed in the implementation of a project depend on the circumstances of the particular case, five basic principles generally guide ADB requirements:  subject to the qualification stated in paragraph 2.11 with regard to procurement under loans or grants from Special Funds resources, the proceeds of ADB financing can be used only for procurement of goods and works supplied from, and produced in, member countries of ADB, except in any case in which the Board of Directors determines otherwise under Article 14 (ix) of the Articles of Agreement of ADB;  the need for economy and efficiency in the implementation of the project, including the procurement of the goods and works involved;
General Considerations Para 1.2  ADB’s interest in giving all eligible bidders from developed and developing countries4 the same information and equal opportunity to compete in providing goods and works financed by ADB;  ADB’s interest in encouraging the development of domestic contracting and manufacturing industries in the country of the borrower; and  the importance of transparency in the procurement process.
General Considerations Para 1.3  Open competition is the basis for efficient public procurement. Borrowers shall select the most appropriate method for the specific procurement. In most cases, international competitive bidding (ICB), properly administered, and with the allowance for preferences for domestically manufactured goods and, where appropriate, for domestic contractors5 for works under prescribed conditions is the most appropriate method.  In most cases, therefore, ADB requires its borrowers to obtain goods, works and services through ICB open to eligible suppliers and contractors.6 Section II of these Guidelines describes the procedures for ICB.
General Considerations Para 1.4  Where ICB is not the most appropriate method of procurement, other methods of procurement may be used.  Section III describes these other methods of procurement and the circumstances under which their application would be more appropriate.  The particular methods that may be followed for procurement under a given project are provided for in the financing agreement.  The specific contracts to be financed under the project, and their method of procurement, consistent with the financing agreement, are specified in the procurement plan as indicated in paragraph 1.16 of these Guidelines.
Applicability of Guidelines  Asian Development Bank Procurement Guidelines
Applicability of Guidelines  Para 1.5  The procedures outlined in these Guidelines apply to all contracts for goods and works financed in whole or in part by ADB.7 For the procurement of those contracts for goods and works not financed by ADB, the borrower may adopt other procedures.
Applicability of Guidelines  Para 1.5 In such cases ADB shall be satisfied that the procedures to be used will fulfill the borrower’s obligations to cause the project to be carried out diligently and efficiently, and that the goods and works to be procured:  are of satisfactory quality and are compatible with the balance of the project;  will be delivered or completed in timely fashion; and  are priced so as not to affect adversely the economic and financial viability of the project.
Eligibility Asian Development Bank Procurement Guidelines
Eligibility Para 1.6  To foster competition ADB permits bidders from all eligible member countries to offer goods, works, and services for ADB-financed projects. Any conditions for participation shall be limited to those that are essential to ensure the bidder’s capability to fulfill the contract in question.
Eligibility Para 1.7  In connection with any contract to be financed in whole or in part by ADB, ADB does not permit a borrower to deny the participation of a bidder for reasons unrelated to its capability and resources to successfully perform the contract; nor does it permit a borrower to disqualify any bidder for such reasons.  Consequently, borrowers should carry out due diligence on the technical and financial qualifications of bidders to be assured of their capabilities in relation to the specific contract.
Eligibility Para 1.8  As exceptions to the foregoing:  Firms of a country or goods manufactured in a country may be excluded if, by an act of compliance with a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations, the borrower’s country prohibits any import of goods from, or payments to, a particular country, person, or entity. Where the borrower’s country prohibits payments to a particular firm or for particular goods by such an act of compliance, that firm may be excluded.
Eligibility Para 1.8  As exceptions to the foregoing:  A firm which has been engaged by the borrower to provide consulting services for the preparation or implementation of a project, and any of its affiliates, shall be disqualified from subsequently providing goods, works, or services resulting from or directly related to the firm’s consulting services for such preparation or implementation. This provision does not apply to the various firms (consultants, contractors, or suppliers) which together are performing the contractor’s obligations under a turnkey or design and build contract.
Eligibility Para 1.8  As exceptions to the foregoing:  Government-owned enterprises in the borrower’s country may participate as a bidder only if they can establish that they  are legally and financially autonomous,  operate under commercial law, and  are not dependent agencies of the borrower or sub-borrower.
Eligibility Para 1.8  As exceptions to the foregoing:  A firm or individual sanctioned by ADB in accordance with subparagraph (d) of paragraph 1.14 of these Guidelines or ADB’s Anticorruption Policy and Integrity Principles and Guidelines (both as amended from time to time), shall be ineligible to be awarded an ADB-financed or ADB-administered contract or to benefit from an ADB-financed or ADB-administered contract, financially or otherwise, during the period of time determined by ADB.
Advance Contracting and Retroactive Financing Asian Development Bank Procurement Guidelines
Advance Contracting and Retroactive Financing Para 1.9  ADB encourages borrowers to proceed with the initial steps of procurement before signing the related financing agreement. In such cases, the procurement procedures, including advertising, shall be in accordance with the Guidelines in order for the eventual contracts to be eligible for ADB financing, and ADB shall review the process used by the borrower
Advance Contracting and Retroactive Financing Para 1.9  A borrower undertakes such advance contracting at its own risk, and any concurrence by ADB with the procedures, documentation, or proposal for award does not commit ADB to finance the project in question.  If the contract is signed, reimbursement by ADB of any payments made by the borrower under the contract prior to signing the financing agreement is referred to as retroactive financing and is only permitted within the limits specified in the financing agreement.
Adb procurement guidelines   introduction1

More Related Content

What's hot

FINANCING AGREEMENT
FINANCING AGREEMENT FINANCING AGREEMENT
FINANCING AGREEMENT
Kanoon Ke Rakhwale India
 
Polaris+SB+Pool+RFP+47QTCB22R0001.pdf
Polaris+SB+Pool+RFP+47QTCB22R0001.pdfPolaris+SB+Pool+RFP+47QTCB22R0001.pdf
Polaris+SB+Pool+RFP+47QTCB22R0001.pdf
grabchetta
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Divyanshu Dayal
 
Sample of development joint venture agreement between owner of land and devel...
Sample of development joint venture agreement between owner of land and devel...Sample of development joint venture agreement between owner of land and devel...
Sample of development joint venture agreement between owner of land and devel...
Green Realtech Projects Pvt. Ltd
 
Wb procurement icb c2
Wb procurement icb c2Wb procurement icb c2
Wb procurement icb c2
Joy Irman
 
Vietnam _ Real Estate Foreign Ownership Possible Now
Vietnam _ Real Estate Foreign Ownership Possible NowVietnam _ Real Estate Foreign Ownership Possible Now
Vietnam _ Real Estate Foreign Ownership Possible Now
Dr. Oliver Massmann
 
Hitachi RFP for Janitorial FINAL
Hitachi RFP for Janitorial  FINALHitachi RFP for Janitorial  FINAL
Hitachi RFP for Janitorial FINAL
Bruce Elledge
 
16 tender document khawaja fareed university 09112017
16   tender document khawaja fareed university 0911201716   tender document khawaja fareed university 09112017
16 tender document khawaja fareed university 09112017
Salman Kharal
 
Thd garden - 2 BHK Flat in Bhiwadi
Thd garden - 2 BHK Flat in BhiwadiThd garden - 2 BHK Flat in Bhiwadi
Thd garden - 2 BHK Flat in Bhiwadi
Trehan Home Developers Pvt. Ltd.
 
Implications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbookImplications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbook
Haytham Baraka, PMP, CCP, SP, RMP,APC-RICS Candidate.
 
Agreement for Educational Services to Startups
Agreement for Educational Services to StartupsAgreement for Educational Services to Startups
Agreement for Educational Services to Startups
SV.CO
 
Vietnam Law on Tendering - Number 61 2005-QH11
Vietnam Law on Tendering - Number 61 2005-QH11Vietnam Law on Tendering - Number 61 2005-QH11
Vietnam Law on Tendering - Number 61 2005-QH11
IFAD Vietnam
 
Ppra rules knowledge thirst
Ppra rules  knowledge thirstPpra rules  knowledge thirst
Ppra rules knowledge thirst
UnsaSoomro
 
Sbd procurement of goods 6 award of contract
Sbd procurement of goods   6 award of contractSbd procurement of goods   6 award of contract
Sbd procurement of goods 6 award of contract
Joy Irman
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
Arissa Loh
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 
Sbd procurement of goods 4 submission and opening of bids
Sbd procurement of goods   4 submission and opening of bidsSbd procurement of goods   4 submission and opening of bids
Sbd procurement of goods 4 submission and opening of bids
Joy Irman
 
Eoi indoor & outdoor venue branding
Eoi indoor & outdoor venue brandingEoi indoor & outdoor venue branding
Eoi indoor & outdoor venue branding
plastivision
 
Procurement of infrastructure projects
Procurement of infrastructure projectsProcurement of infrastructure projects
Procurement of infrastructure projects
wil_mia
 
Adb procurement guidelines icb-c1
Adb procurement guidelines   icb-c1Adb procurement guidelines   icb-c1
Adb procurement guidelines icb-c1
Joy Irman
 

What's hot (20)

FINANCING AGREEMENT
FINANCING AGREEMENT FINANCING AGREEMENT
FINANCING AGREEMENT
 
Polaris+SB+Pool+RFP+47QTCB22R0001.pdf
Polaris+SB+Pool+RFP+47QTCB22R0001.pdfPolaris+SB+Pool+RFP+47QTCB22R0001.pdf
Polaris+SB+Pool+RFP+47QTCB22R0001.pdf
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
Sample of development joint venture agreement between owner of land and devel...
Sample of development joint venture agreement between owner of land and devel...Sample of development joint venture agreement between owner of land and devel...
Sample of development joint venture agreement between owner of land and devel...
 
Wb procurement icb c2
Wb procurement icb c2Wb procurement icb c2
Wb procurement icb c2
 
Vietnam _ Real Estate Foreign Ownership Possible Now
Vietnam _ Real Estate Foreign Ownership Possible NowVietnam _ Real Estate Foreign Ownership Possible Now
Vietnam _ Real Estate Foreign Ownership Possible Now
 
Hitachi RFP for Janitorial FINAL
Hitachi RFP for Janitorial  FINALHitachi RFP for Janitorial  FINAL
Hitachi RFP for Janitorial FINAL
 
16 tender document khawaja fareed university 09112017
16   tender document khawaja fareed university 0911201716   tender document khawaja fareed university 09112017
16 tender document khawaja fareed university 09112017
 
Thd garden - 2 BHK Flat in Bhiwadi
Thd garden - 2 BHK Flat in BhiwadiThd garden - 2 BHK Flat in Bhiwadi
Thd garden - 2 BHK Flat in Bhiwadi
 
Implications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbookImplications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbook
 
Agreement for Educational Services to Startups
Agreement for Educational Services to StartupsAgreement for Educational Services to Startups
Agreement for Educational Services to Startups
 
Vietnam Law on Tendering - Number 61 2005-QH11
Vietnam Law on Tendering - Number 61 2005-QH11Vietnam Law on Tendering - Number 61 2005-QH11
Vietnam Law on Tendering - Number 61 2005-QH11
 
Ppra rules knowledge thirst
Ppra rules  knowledge thirstPpra rules  knowledge thirst
Ppra rules knowledge thirst
 
Sbd procurement of goods 6 award of contract
Sbd procurement of goods   6 award of contractSbd procurement of goods   6 award of contract
Sbd procurement of goods 6 award of contract
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Sbd procurement of goods 4 submission and opening of bids
Sbd procurement of goods   4 submission and opening of bidsSbd procurement of goods   4 submission and opening of bids
Sbd procurement of goods 4 submission and opening of bids
 
Eoi indoor & outdoor venue branding
Eoi indoor & outdoor venue brandingEoi indoor & outdoor venue branding
Eoi indoor & outdoor venue branding
 
Procurement of infrastructure projects
Procurement of infrastructure projectsProcurement of infrastructure projects
Procurement of infrastructure projects
 
Adb procurement guidelines icb-c1
Adb procurement guidelines   icb-c1Adb procurement guidelines   icb-c1
Adb procurement guidelines icb-c1
 

Viewers also liked

Megan Braley Print Portfolio
Megan Braley Print PortfolioMegan Braley Print Portfolio
Megan Braley Print Portfolio
megandesign
 
3 2 pengguna anggaran
3 2 pengguna anggaran3 2 pengguna anggaran
3 2 pengguna anggaran
Joy Irman
 
Appendix 2 domestic preferences
Appendix 2   domestic preferencesAppendix 2   domestic preferences
Appendix 2 domestic preferences
Joy Irman
 
Contract for consultancy services time based - d appendix
Contract for consultancy services   time based - d appendixContract for consultancy services   time based - d appendix
Contract for consultancy services time based - d appendix
Joy Irman
 
Contract for consultancy services time based - preface
Contract for consultancy services   time based - prefaceContract for consultancy services   time based - preface
Contract for consultancy services time based - preface
Joy Irman
 
Session1
Session1Session1
Session1
Viren Kadam
 

Viewers also liked (6)

Megan Braley Print Portfolio
Megan Braley Print PortfolioMegan Braley Print Portfolio
Megan Braley Print Portfolio
 
3 2 pengguna anggaran
3 2 pengguna anggaran3 2 pengguna anggaran
3 2 pengguna anggaran
 
Appendix 2 domestic preferences
Appendix 2   domestic preferencesAppendix 2   domestic preferences
Appendix 2 domestic preferences
 
Contract for consultancy services time based - d appendix
Contract for consultancy services   time based - d appendixContract for consultancy services   time based - d appendix
Contract for consultancy services time based - d appendix
 
Contract for consultancy services time based - preface
Contract for consultancy services   time based - prefaceContract for consultancy services   time based - preface
Contract for consultancy services time based - preface
 
Session1
Session1Session1
Session1
 

Similar to Adb procurement guidelines introduction1

Appendix 3 guidance to bidders
Appendix 3   guidance to biddersAppendix 3   guidance to bidders
Appendix 3 guidance to bidders
Joy Irman
 
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Joy Irman
 
Adb procurement guidelines introduction2
Adb procurement guidelines   introduction2Adb procurement guidelines   introduction2
Adb procurement guidelines introduction2
Joy Irman
 
Wb procurement intro 2
Wb procurement intro 2Wb procurement intro 2
Wb procurement intro 2
Joy Irman
 
Wb procurement other method-2
Wb procurement other method-2Wb procurement other method-2
Wb procurement other method-2
Joy Irman
 
Adb procurement guidelines icb-b1
Adb procurement guidelines   icb-b1Adb procurement guidelines   icb-b1
Adb procurement guidelines icb-b1
Joy Irman
 
Wb consultant 1b
Wb consultant 1bWb consultant 1b
Wb consultant 1b
Joy Irman
 
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Joy Irman
 
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Joy Irman
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Joy Irman
 
20160826-IRR-RA-9184-procurement-reform (1).pdf
20160826-IRR-RA-9184-procurement-reform (1).pdf20160826-IRR-RA-9184-procurement-reform (1).pdf
20160826-IRR-RA-9184-procurement-reform (1).pdf
catherineCerteza
 
Adb procurement guidelines icb-b3
Adb procurement guidelines   icb-b3Adb procurement guidelines   icb-b3
Adb procurement guidelines icb-b3
Joy Irman
 
Wb procurement other method-1
Wb procurement other method-1Wb procurement other method-1
Wb procurement other method-1
Joy Irman
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Joy Irman
 
Frequently-asked-questions-about-ra-9184
Frequently-asked-questions-about-ra-9184Frequently-asked-questions-about-ra-9184
Frequently-asked-questions-about-ra-9184
june alapa
 
Appendix 1 adb review of procurement decisions
Appendix 1   adb review of procurement decisionsAppendix 1   adb review of procurement decisions
Appendix 1 adb review of procurement decisions
Joy Irman
 
THE 2016 REVISED IMPLEMENTING RULES AND REGULATIONS OF.pptx
THE 2016 REVISED IMPLEMENTING RULES   AND REGULATIONS OF.pptxTHE 2016 REVISED IMPLEMENTING RULES   AND REGULATIONS OF.pptx
THE 2016 REVISED IMPLEMENTING RULES AND REGULATIONS OF.pptx
EMELYNDEVILLA
 
Revised irr.ra9184 2009
Revised irr.ra9184 2009Revised irr.ra9184 2009
Revised irr.ra9184 2009
maridjo_legal
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03
ypinada
 
Cir 39 2016 TT NHNN.pdf
Cir 39 2016 TT NHNN.pdfCir 39 2016 TT NHNN.pdf
Cir 39 2016 TT NHNN.pdf
ThoPhng1470
 

Similar to Adb procurement guidelines introduction1 (20)

Appendix 3 guidance to bidders
Appendix 3   guidance to biddersAppendix 3   guidance to bidders
Appendix 3 guidance to bidders
 
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
 
Adb procurement guidelines introduction2
Adb procurement guidelines   introduction2Adb procurement guidelines   introduction2
Adb procurement guidelines introduction2
 
Wb procurement intro 2
Wb procurement intro 2Wb procurement intro 2
Wb procurement intro 2
 
Wb procurement other method-2
Wb procurement other method-2Wb procurement other method-2
Wb procurement other method-2
 
Adb procurement guidelines icb-b1
Adb procurement guidelines   icb-b1Adb procurement guidelines   icb-b1
Adb procurement guidelines icb-b1
 
Wb consultant 1b
Wb consultant 1bWb consultant 1b
Wb consultant 1b
 
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
 
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
Introduction to Guidelines on The Use of Consultants by Asian Development Ban...
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
20160826-IRR-RA-9184-procurement-reform (1).pdf
20160826-IRR-RA-9184-procurement-reform (1).pdf20160826-IRR-RA-9184-procurement-reform (1).pdf
20160826-IRR-RA-9184-procurement-reform (1).pdf
 
Adb procurement guidelines icb-b3
Adb procurement guidelines   icb-b3Adb procurement guidelines   icb-b3
Adb procurement guidelines icb-b3
 
Wb procurement other method-1
Wb procurement other method-1Wb procurement other method-1
Wb procurement other method-1
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
Frequently-asked-questions-about-ra-9184
Frequently-asked-questions-about-ra-9184Frequently-asked-questions-about-ra-9184
Frequently-asked-questions-about-ra-9184
 
Appendix 1 adb review of procurement decisions
Appendix 1   adb review of procurement decisionsAppendix 1   adb review of procurement decisions
Appendix 1 adb review of procurement decisions
 
THE 2016 REVISED IMPLEMENTING RULES AND REGULATIONS OF.pptx
THE 2016 REVISED IMPLEMENTING RULES   AND REGULATIONS OF.pptxTHE 2016 REVISED IMPLEMENTING RULES   AND REGULATIONS OF.pptx
THE 2016 REVISED IMPLEMENTING RULES AND REGULATIONS OF.pptx
 
Revised irr.ra9184 2009
Revised irr.ra9184 2009Revised irr.ra9184 2009
Revised irr.ra9184 2009
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03
 
Cir 39 2016 TT NHNN.pdf
Cir 39 2016 TT NHNN.pdfCir 39 2016 TT NHNN.pdf
Cir 39 2016 TT NHNN.pdf
 

More from Joy Irman

Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Joy Irman
 
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Joy Irman
 
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv b   jasa konsultansi - peroranganLampiran iv b   jasa konsultansi - perorangan
Lampiran iv b jasa konsultansi - peroranganJoy Irman
 
Lampiran iv a jasa konsultansi - badan usaha
Lampiran iv a   jasa konsultansi - badan usahaLampiran iv a   jasa konsultansi - badan usaha
Lampiran iv a jasa konsultansi - badan usahaJoy Irman
 
Consulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development BankConsulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development Bank
Joy Irman
 
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingGuidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Joy Irman
 
Guidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA LoansGuidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA Loans
Joy Irman
 
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Joy Irman
 
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
Joy Irman
 
12 konsep ramah lingkungan
12 konsep ramah lingkungan12 konsep ramah lingkungan
12 konsep ramah lingkungan
Joy Irman
 
13 pengadaan secara elektronik
13 pengadaan secara elektronik13 pengadaan secara elektronik
13 pengadaan secara elektronik
Joy Irman
 
6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan
Joy Irman
 
3 1 organisasi pengadaan
3 1 organisasi pengadaan3 1 organisasi pengadaan
3 1 organisasi pengadaan
Joy Irman
 
4 rencana umum pengadaan barang
4 rencana umum pengadaan barang4 rencana umum pengadaan barang
4 rencana umum pengadaan barang
Joy Irman
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola
Joy Irman
 
5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola
Joy Irman
 
3 7 penyedia barang jasa
3 7 penyedia barang jasa3 7 penyedia barang jasa
3 7 penyedia barang jasa
Joy Irman
 
3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan
Joy Irman
 
3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan
Joy Irman
 
3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen
Joy Irman
 

More from Joy Irman (20)

Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
 
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
 
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv b   jasa konsultansi - peroranganLampiran iv b   jasa konsultansi - perorangan
Lampiran iv b jasa konsultansi - perorangan
 
Lampiran iv a jasa konsultansi - badan usaha
Lampiran iv a   jasa konsultansi - badan usahaLampiran iv a   jasa konsultansi - badan usaha
Lampiran iv a jasa konsultansi - badan usaha
 
Consulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development BankConsulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development Bank
 
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingGuidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank Financing
 
Guidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA LoansGuidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA Loans
 
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
 
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
 
12 konsep ramah lingkungan
12 konsep ramah lingkungan12 konsep ramah lingkungan
12 konsep ramah lingkungan
 
13 pengadaan secara elektronik
13 pengadaan secara elektronik13 pengadaan secara elektronik
13 pengadaan secara elektronik
 
6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan
 
3 1 organisasi pengadaan
3 1 organisasi pengadaan3 1 organisasi pengadaan
3 1 organisasi pengadaan
 
4 rencana umum pengadaan barang
4 rencana umum pengadaan barang4 rencana umum pengadaan barang
4 rencana umum pengadaan barang
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola
 
5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola
 
3 7 penyedia barang jasa
3 7 penyedia barang jasa3 7 penyedia barang jasa
3 7 penyedia barang jasa
 
3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan
 
3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan
 
3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen
 

Adb procurement guidelines introduction1

  • 1. Introduction Asian Development Bank Procurement Guidelines
  • 2. Table of Contents Purpose General Conditions Applicability of Guidelines Eligibility Advance Contracting and Retroactive Financing
  • 3. Purpose Asian Development Bank Procurement Guidelines
  • 4. Purpose Para 1.1 The purpose of these Guidelines is to inform those carrying out a project that is financed in whole or in part by a loan from the Asian Development Bank (ADB), ADB-financed grant, or ADB-administered funds,of the policies that govern the procurement of goods, works, and services (other than consultant services)required for the project.
  • 5. Purpose Para 1.1 The financing agreement governs the legal relationships between the borrowerand ADB, and the Guidelines are made applicable to procurement of goods and works for the project, as provided in the agreement. The rights and obligations of the borrower and the providers of goods and works for the project are governed by the bidding documents, and by the contracts signed by the borrower with the providers of goods and works, and not by these Guidelines or the financing agreements. No party other than the parties to the financing agreement shall derive any rights therefrom or have any claim to the proceeds of the financing.
  • 6. General Considerations Asian Development Bank Procurement Guidelines
  • 7. General Considerations Para 1.2 The responsibility for the implementation of the project, and therefore for the award and administration of contracts under the project, rests with the borrower. ADB, for its part, has the obligation to ensure that the proceeds of its financing are used with due attention to considerations of economy and efficiency.
  • 8. General Considerations Para 1.2 While in practice the specific procurement rules and procedures to be followed in the implementation of a project depend on the circumstances of the particular case, five basic principles generally guide ADB requirements: subject to the qualification stated in paragraph 2.11 with regard to procurement under loans or grants from Special Funds resources, the proceeds of ADB financing can be used only for procurement of goods and works supplied from, and produced in, member countries of ADB, except in any case in which the Board of Directors determines otherwise under Article 14 (ix) of the Articles of Agreement of ADB; the need for economy and efficiency in the implementation of the project, including the procurement of the goods and works involved;
  • 9. General Considerations Para 1.2 ADB’s interest in giving all eligible bidders from developed and developing countries4 the same information and equal opportunity to compete in providing goods and works financed by ADB; ADB’s interest in encouraging the development of domestic contracting and manufacturing industries in the country of the borrower; and the importance of transparency in the procurement process.
  • 10. General Considerations Para 1.3 Open competition is the basis for efficient public procurement. Borrowers shall select the most appropriate method for the specific procurement. In most cases, international competitive bidding (ICB), properly administered, and with the allowance for preferences for domestically manufactured goods and, where appropriate, for domestic contractors5 for works under prescribed conditions is the most appropriate method. In most cases, therefore, ADB requires its borrowers to obtain goods, works and services through ICB open to eligible suppliers and contractors.6 Section II of these Guidelines describes the procedures for ICB.
  • 11. General Considerations Para 1.4 Where ICB is not the most appropriate method of procurement, other methods of procurement may be used. Section III describes these other methods of procurement and the circumstances under which their application would be more appropriate. The particular methods that may be followed for procurement under a given project are provided for in the financing agreement. The specific contracts to be financed under the project, and their method of procurement, consistent with the financing agreement, are specified in the procurement plan as indicated in paragraph 1.16 of these Guidelines.
  • 12. Applicability of Guidelines Asian Development Bank Procurement Guidelines
  • 13. Applicability of Guidelines Para 1.5 The procedures outlined in these Guidelines apply to all contracts for goods and works financed in whole or in part by ADB.7 For the procurement of those contracts for goods and works not financed by ADB, the borrower may adopt other procedures.
  • 14. Applicability of Guidelines Para 1.5 In such cases ADB shall be satisfied that the procedures to be used will fulfill the borrower’s obligations to cause the project to be carried out diligently and efficiently, and that the goods and works to be procured: are of satisfactory quality and are compatible with the balance of the project; will be delivered or completed in timely fashion; and are priced so as not to affect adversely the economic and financial viability of the project.
  • 15. Eligibility Asian Development Bank Procurement Guidelines
  • 16. Eligibility Para 1.6 To foster competition ADB permits bidders from all eligible member countries to offer goods, works, and services for ADB-financed projects. Any conditions for participation shall be limited to those that are essential to ensure the bidder’s capability to fulfill the contract in question.
  • 17. Eligibility Para 1.7 In connection with any contract to be financed in whole or in part by ADB, ADB does not permit a borrower to deny the participation of a bidder for reasons unrelated to its capability and resources to successfully perform the contract; nor does it permit a borrower to disqualify any bidder for such reasons. Consequently, borrowers should carry out due diligence on the technical and financial qualifications of bidders to be assured of their capabilities in relation to the specific contract.
  • 18. Eligibility Para 1.8 As exceptions to the foregoing: Firms of a country or goods manufactured in a country may be excluded if, by an act of compliance with a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations, the borrower’s country prohibits any import of goods from, or payments to, a particular country, person, or entity. Where the borrower’s country prohibits payments to a particular firm or for particular goods by such an act of compliance, that firm may be excluded.
  • 19. Eligibility Para 1.8 As exceptions to the foregoing: A firm which has been engaged by the borrower to provide consulting services for the preparation or implementation of a project, and any of its affiliates, shall be disqualified from subsequently providing goods, works, or services resulting from or directly related to the firm’s consulting services for such preparation or implementation. This provision does not apply to the various firms (consultants, contractors, or suppliers) which together are performing the contractor’s obligations under a turnkey or design and build contract.
  • 20. Eligibility Para 1.8 As exceptions to the foregoing: Government-owned enterprises in the borrower’s country may participate as a bidder only if they can establish that they are legally and financially autonomous, operate under commercial law, and are not dependent agencies of the borrower or sub-borrower.
  • 21. Eligibility Para 1.8 As exceptions to the foregoing: A firm or individual sanctioned by ADB in accordance with subparagraph (d) of paragraph 1.14 of these Guidelines or ADB’s Anticorruption Policy and Integrity Principles and Guidelines (both as amended from time to time), shall be ineligible to be awarded an ADB-financed or ADB-administered contract or to benefit from an ADB-financed or ADB-administered contract, financially or otherwise, during the period of time determined by ADB.
  • 22. Advance Contracting and Retroactive Financing Asian Development Bank Procurement Guidelines
  • 23. Advance Contracting and Retroactive Financing Para 1.9 ADB encourages borrowers to proceed with the initial steps of procurement before signing the related financing agreement. In such cases, the procurement procedures, including advertising, shall be in accordance with the Guidelines in order for the eventual contracts to be eligible for ADB financing, and ADB shall review the process used by the borrower
  • 24. Advance Contracting and Retroactive Financing Para 1.9 A borrower undertakes such advance contracting at its own risk, and any concurrence by ADB with the procedures, documentation, or proposal for award does not commit ADB to finance the project in question. If the contract is signed, reimbursement by ADB of any payments made by the borrower under the contract prior to signing the financing agreement is referred to as retroactive financing and is only permitted within the limits specified in the financing agreement.