The International Journal Of Engineering And Science (IJES)
||Volume||2 ||Issue|| 11||Pages|| 01-04||2013||
ISSN(e): 2319 – 1813 ISSN(p): 2319 – 1805

Implication of Poor Energy Supply on the Productivity of
Nigerian Manufacturing Industry
By
UZORH AUSTIN C.
Mechanical Engineering Department
Federal University of Technoloy Owerri PMB 1526 Owerri, Imo State, Nigeria.

-----------------------------------------------ABSTRACT----------------------------------------------------------A comprehensive evaluation of the effectiveness and delay contribution due to power outages and fluctuations is
presented. The purpose of this study is to reveal the implications of poor energy supply on the effective
utilization of the input resources in a typical Nigerian Manufacturing Industry. Delta steel company .Delata
state Nigeria was used as a casestudy. Data on power outages were collected from the energy distribution unit,
steel melting shop and the rolling mill. Additionally, the total delays, standard or planned production and actual
production were determined from the records, from which the power delay contributions and effectiveness were
evaluated. Results from this study revealed that power delay contributed more than 6% and the monthly
effectiveness was more than unity throughout year 2010. Analysis of data collected for 2010 production period
showed that the energy distribution unit experienced 54 outages with a total duration of 11472 mins, while a
total of 44947 mins was lost in the steel melting shops due to power outages and under-voltage. More so, 25
billets worth 44tonnes were scrapped and 20811 mins were lost as a result of power failure and fluctuations.
The implications clearly showed that poor power supply lowers the productivity of the company.

KEYWORDS: Energy, Manufacturing, Productivity.
--------------------------------------------------------------------------------------------------------------------------------------Date of Submission: 11, March, 2013
Date of Acceptance: 10, November, 2013
---------------------------------------------------------------------------------------------------------------------------------------

I.

MANUFACTURING SECTOR AND ENERGY SECTOR

Every manufacturing industry requires energy to power their machines, computers, lighting and
establishment for various purposes. However, in Nigeria, power requirement of the manufacturing sector far
outweighs the available power being generated, transmitted and distributed by power holding company of
Nigeria (PHCN) to both manufacturing and non manufacturing sectors. This energy deficiency has resulted in
the emigration of some companies to other companies as exemplified by Mitchelin, which relocated their
production capacity to ghana , some industries lying moribund as experienced by most textile industries in
Nothern Nigeria and some industries resorting to diesel engines as prime movers of industrial alternators, which
supplied inadequate power and cannot run continously for many days. Also, the running cost of these diesel
engines are on the high sides , thereby increasing the cost of production and in many cases, lowers productivity.
FUNDAMENTAL CONCEPTS
Pertinent to this study is the understanding of the keywords: “Manufacturing” and “Productivity”.
MEANING OF MANUFACTURING
The word manufacturing is derived from the latin word manus and factus meaning hand and made
respectively. That is the literal meaning is “made by hand”. However, in the modern sense, manufacturing
means making of goods or articles from raw materials by hand and/or machinery by following a well defined
plan for each activity required.
DEFINITION OF PRODUCTIVITY
Productivity has become an everyday watch word that is crucial to the welfare of the industries as well
as the economic progress of the country. Productivity is the measure of how well the resources are brought
together in an organization and utilized for accomplishing a set of objectives (Telsang 2008).

www.theijes.com

The IJES

Page 1
Implication Of Poor Energy…
Productivity is the ratio of outputs of goods or services from the conversion process to input consumed
in the generation of these outputs (Arthur, 1978). Productivity is a summary measure of the quantity and quality
of work performance with resource utilization considered (Schermerhorn, 1986) Productivity can be defined as
the optimum utilization of all the resoures of organization: Men, material, money and machinery, energy, space,
technology, etc (Sharma, 2006).

II.

MEASUREMENT OF PRODUCTIVITY

Productivity is the arithmetic ratio of amount produced (output) to the amount of resources(input).
Mathematically: Productivity= Output/Input Productivity refers to the efficiency of the production. (Telsang,
2008). The basic component of productivity measurement is a means of comprising output forecasts with actual
output at selected intervals. In general system theory, effectiveness is defined as the degree to which the actual
output of the system corresponds to its desired or planned outputs. Productivity is a function of effectiveness
and efficiency (www.authorsden.com).
Effectiveness= Actual Outputs/Desired Outputs
Productivity = Actual Production/ Standard Production

III.

DELTA STEEL COMPANY AS AN INTEGRATED STEEL PLANT

Delta Steel Company(DSC) is an integrated steel plant with iron making, steel making and rolling mill facilities.
These three important plant consume a lot of power during production and adversely lower the productivity of
the company when there is power fluctuations or failure. However, the steel melting shop and rolling mill were
functional during the period under study.

IV.

DATA COLLECTED AND PRESENTED PROCEDURE

Power outages in DSC were collected for one year (January-December 2010) from the energy
distribution unit. The record which show the specific date , timeout, timein, duration and feeders has been
summarized as shown in table 1. The delay due to power outages, insufficient power to run the furnaces and
preheat ladies, power fluctuation and power failure that resulted in the abortion of heats were determined from
one year record and percentage contribution of the power failure to total delay was determined and compared to
the productivity of the steel melting shop. See table 4.2. Moreso, delay due to power outages, cobbles due to
power outages, percentages contribution of power failure compared to the total delay was determined and
compared to the productivity of rolling mill (see table 4.3)

V.

POWER UTILIZATION IN THE STEEL MELTING SHOP

Melting in the plant is achieved with Electric Arc Furnaces (EAF), which cannot do without electric
Arc Furnaces (EAF), which cannot do without electricity. The melting point of steel is about 1539c, its
superheat temperature before tapping into the preheated ladle is 1700c and the casting temperature in the
continuous casting platform is 1600c. when there is power failure and the temperatture of the liquid steel is
below 1600c, the usual option is to abort the heat by quickly tapping into the ladies and pouring the liquid steel
on the ground floor before it solidifies. More so, when the Power failure is experienced at a temperature of about
1200c, the metal is left in the furnace, while heating and melting continue when the power is re-instated.

VI.

POWER UTILIZATION IN THE STEEL ROLLING MILL

Both power fluctuation and failures are very dangerous and highly undesirable in the rolling mill. This
is as a result of the formation of cobble which can occur when a billet undergoing deformation derails due to the
stoppage or malfunctioning of the mall stands, shears, approach or roller table and loppers along the mill train.
Power fluctuation or failure causes cobble formation in this mill, thereby grounding the rolling operation. Also,
the temperature 1200c of the heated billets drops when there is power failure. When cobble forms, the mill is
shut down, and cobble removal crew cut and remove the cobble, while the maintenance/production crew reinstates the plant before production continues.

VII.

RESULTS AND IMPLICATIONS

The results from the data collected are summarized in tables 4.1, 4.2 and 4.3, while the implications of
poor power supply are revealed in the tables 4.2 and 4. 3 and presented as shown below:

www.theijes.com

The IJES

Page 2
Implication Of Poor Energy…
VIII.

IMPLICATIONS OF POOR POWER SUPPLY IN THE STEEL MELTING SHOP

The implication of poor fluctuation and failure are listed as follows:
[1]
Loss of consumables and ferroalloys are used in the treatment of aborted heat.
[2]
Loss of money accruable from 110 tons (furnace capacity) of steel had it been successfully casted.
[3]
Devaluation of already treated steel to scrap.
[4]
Increased expenditure on the cutting of the aborted steel to sizeable form for easy loading into the EAF.
[5]
Consumption of more energy in re-melting or continued melting because of temperature drop.
[6]
Loss of money paid to PHCN for power expended on return or aborted heat.
[7]
Increased idle times of workers because the entire plant get heated up and polluted when there is heat
abortion.
[8]
Loss of man hours especially when heat is aborted.
[9]
Inability to make the planned or standard production
[10]
Productivity ratio or effectiveness is always less than one with respect to the production quantity.
IMPLICATIONS OF POOR POWER SUPPLY IN THE STEEL ROLLING MILL
The Implications of power fluctuations and outages in the steel mill includes:
[1]
Devaluation of the billet to scrap
[2]
Loss of a would be income if the billet was successfully rolled
[3]
Extra expense on the oxygen and acetylene used in cutting the cobbles
[4]
Maintenance and repair of damage damage parts due to cobble
[5]
Expenditure on the treatment of injured perssonnel or compensation on the family when a worker is
entangled by cobble (death situation)
[6]
Increased downtime
[7]
Increased idle time of some workers
[8]
Increased energy consumption when the furnace temperature drops
[9]
Loss of man-hour and expenditure on power when cobble forms
[10]
Productivity is always less than unity because actual production was always less than the planned
production.
[11]
Loss of machine hours as some machines take up to thirty minutes before assuming normal operating
condition.
COMMENT ON THE RESULT
Table 4.1: The cause of the outages includes system collapse, system disturbance, high frequency, under
voltage, over-voltage and poor generation. The number of power failure times was found to be 54 and the
outage duration totaling 11472mins in 2010.
GIW – Ughelli Supply, S4W – Sapele Supply
Table 4.2: A total of 44937min delay due to power outages and inadequacy was recorded in 2010 and the steel
melting shop which contributed 7. 37% to the total delay and resulted in the abortion or return of heat worth
1107tonnes of liquid steel. No monthly target was achieved throughout 2010, as revealed by the effectiveness.
EAF II and EAF IV delays due to power are presented in second column.
Table 4. 3: when the effectiveness is 0.82, the power delay contribution is 2.90% , while the effectiveness of
0.50 resulted when the power delay contribution is 17. 32%. These clearly show that power delay affect the
productivity adversely. Also, the total number of billets devalued throughout 2010 was 25. Total delay due to
power failure was calculated to be 20811mins with a contribution of 6.27% to the total delay. The effectiveness
from January to December, 2010, was found to be less than unity.

IX.

CONCLUSION

Obviously, poor energy supply lowers the productivity of manufacturing industries in Nigeria as shown
by the two functional plants in Delta Steel Company. This is due to its associated unwanted events such as
increased idle time, delivery time delay, Increased cycle time, reduced machine output, increased expenditure on
material recovery and recycle, increased maintenance and repair expences , semi finished product devaluation,
compensation to injured personnel or family of dead personnel, downtime, loss of consumables, alloys and
extra expenses on raw materials or semi-finished product protection. All these implications arise due to power
fluctuation and outages and in some cases the use of diesel engines as an alternative source of power supply.

www.theijes.com

The IJES

Page 3
Implication Of Poor Energy…
Table 4.1: Power Outages for 2010. Source: Energy Distriburtion Unit
August

GIW

2201

325

Month

Feeders

Distribuion

February
March
April
May
June
July

GIW, S4W
GIW, S4W
GIW
GIW
GIW
GIW

790
1319
68
520
238
642

Number
failures
4
5
4
6
3
10

www.theijes.com

The IJES

of

power

Page 4

More Related Content

Viewers also liked

The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
theijes
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
theijes
 
F03405046048
F03405046048F03405046048
F03405046048
theijes
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
theijes
 
The International Journal of Engineering and Science (The IJES)
 The International Journal of Engineering and Science (The IJES) The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
theijes
 
The International Journal of Engineering and Science (The IJES)
 The International Journal of Engineering and Science (The IJES) The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
theijes
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
theijes
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
theijes
 
K034050900107
K034050900107K034050900107
K034050900107
theijes
 

Viewers also liked (9)

The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
F03405046048
F03405046048F03405046048
F03405046048
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
The International Journal of Engineering and Science (The IJES)
 The International Journal of Engineering and Science (The IJES) The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
The International Journal of Engineering and Science (The IJES)
 The International Journal of Engineering and Science (The IJES) The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
K034050900107
K034050900107K034050900107
K034050900107
 

Similar to The International Journal of Engineering and Science (The IJES)

IRJET- Productivity and Quality Improvement Through Setting Parameters in...
IRJET-  	  Productivity and Quality Improvement Through Setting Parameters in...IRJET-  	  Productivity and Quality Improvement Through Setting Parameters in...
IRJET- Productivity and Quality Improvement Through Setting Parameters in...
IRJET Journal
 
Energy audit in Industry.pptx
Energy audit in Industry.pptxEnergy audit in Industry.pptx
Energy audit in Industry.pptx
Ayush51240
 
IRJET- Design of Fixture for Wind Mill Door Segment
IRJET- Design of Fixture for Wind Mill Door SegmentIRJET- Design of Fixture for Wind Mill Door Segment
IRJET- Design of Fixture for Wind Mill Door Segment
IRJET Journal
 
2009 2013 deep research report on china wind power equipment industry chain
2009 2013 deep research report on china wind power equipment industry chain2009 2013 deep research report on china wind power equipment industry chain
2009 2013 deep research report on china wind power equipment industry chain
qyresearch
 
Cycling is bane for power utilities-pkr
Cycling is bane for power utilities-pkrCycling is bane for power utilities-pkr
Cycling is bane for power utilities-pkr
Dr. Koteswara Rao Pothala MBA, PMP,FIE
 
Development And Testing Of Parabolic Through Collectors For Domestic Applicat...
Development And Testing Of Parabolic Through Collectors For Domestic Applicat...Development And Testing Of Parabolic Through Collectors For Domestic Applicat...
Development And Testing Of Parabolic Through Collectors For Domestic Applicat...
IRJET Journal
 
IRJET-abrication of Multipurpose Dryer
IRJET-abrication of Multipurpose DryerIRJET-abrication of Multipurpose Dryer
IRJET-abrication of Multipurpose Dryer
IRJET Journal
 
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET Journal
 
Portable Small-Scale Vertical Axis Wind Turbine with Pitch Angle Control Syst...
Portable Small-Scale Vertical Axis Wind Turbine with Pitch Angle Control Syst...Portable Small-Scale Vertical Axis Wind Turbine with Pitch Angle Control Syst...
Portable Small-Scale Vertical Axis Wind Turbine with Pitch Angle Control Syst...
IRJET Journal
 
Comparing the thermal power plant performance at variou 2
Comparing the thermal power plant performance at variou 2Comparing the thermal power plant performance at variou 2
Comparing the thermal power plant performance at variou 2
IAEME Publication
 
Comparing the thermal power plant performance at variou 2
Comparing the thermal power plant performance at variou 2Comparing the thermal power plant performance at variou 2
Comparing the thermal power plant performance at variou 2
IAEME Publication
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
theijes
 
Design, Development and Operation of 3.5HP Power Tiller
Design, Development and Operation of 3.5HP Power TillerDesign, Development and Operation of 3.5HP Power Tiller
Design, Development and Operation of 3.5HP Power Tiller
paperpublications3
 
TBEA ENERGY (INDIA) PVT LTD
TBEA ENERGY (INDIA) PVT LTDTBEA ENERGY (INDIA) PVT LTD
TBEA ENERGY (INDIA) PVT LTD
Raviraj solanki
 
Harbel 2 - N Oliveira
Harbel 2 - N OliveiraHarbel 2 - N Oliveira
Harbel 2 - N Oliveira
Neylor Oliveira, PMP
 
Design Optimization for Vibration Level of Root Blower With No Load Condition
Design Optimization for Vibration Level of Root Blower With No Load ConditionDesign Optimization for Vibration Level of Root Blower With No Load Condition
Design Optimization for Vibration Level of Root Blower With No Load Condition
theijes
 
2010 deep research report on china wind turbine blade industry
2010 deep research report on china wind turbine blade industry2010 deep research report on china wind turbine blade industry
2010 deep research report on china wind turbine blade industry
qyresearch
 
2010 deep research report on china wind turbine blade industry
2010 deep research report on china wind turbine blade industry2010 deep research report on china wind turbine blade industry
2010 deep research report on china wind turbine blade industry
qyresearch
 
Ijeet 06 08_003
Ijeet 06 08_003Ijeet 06 08_003
Ijeet 06 08_003
IAEME Publication
 
Design and Stress Analysis of High Pressure Accumulator
Design and Stress Analysis of High Pressure AccumulatorDesign and Stress Analysis of High Pressure Accumulator
Design and Stress Analysis of High Pressure Accumulator
IRJET Journal
 

Similar to The International Journal of Engineering and Science (The IJES) (20)

IRJET- Productivity and Quality Improvement Through Setting Parameters in...
IRJET-  	  Productivity and Quality Improvement Through Setting Parameters in...IRJET-  	  Productivity and Quality Improvement Through Setting Parameters in...
IRJET- Productivity and Quality Improvement Through Setting Parameters in...
 
Energy audit in Industry.pptx
Energy audit in Industry.pptxEnergy audit in Industry.pptx
Energy audit in Industry.pptx
 
IRJET- Design of Fixture for Wind Mill Door Segment
IRJET- Design of Fixture for Wind Mill Door SegmentIRJET- Design of Fixture for Wind Mill Door Segment
IRJET- Design of Fixture for Wind Mill Door Segment
 
2009 2013 deep research report on china wind power equipment industry chain
2009 2013 deep research report on china wind power equipment industry chain2009 2013 deep research report on china wind power equipment industry chain
2009 2013 deep research report on china wind power equipment industry chain
 
Cycling is bane for power utilities-pkr
Cycling is bane for power utilities-pkrCycling is bane for power utilities-pkr
Cycling is bane for power utilities-pkr
 
Development And Testing Of Parabolic Through Collectors For Domestic Applicat...
Development And Testing Of Parabolic Through Collectors For Domestic Applicat...Development And Testing Of Parabolic Through Collectors For Domestic Applicat...
Development And Testing Of Parabolic Through Collectors For Domestic Applicat...
 
IRJET-abrication of Multipurpose Dryer
IRJET-abrication of Multipurpose DryerIRJET-abrication of Multipurpose Dryer
IRJET-abrication of Multipurpose Dryer
 
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
IRJET- Comparative Performance Study of Mine Trucks by Overall Equipment Effe...
 
Portable Small-Scale Vertical Axis Wind Turbine with Pitch Angle Control Syst...
Portable Small-Scale Vertical Axis Wind Turbine with Pitch Angle Control Syst...Portable Small-Scale Vertical Axis Wind Turbine with Pitch Angle Control Syst...
Portable Small-Scale Vertical Axis Wind Turbine with Pitch Angle Control Syst...
 
Comparing the thermal power plant performance at variou 2
Comparing the thermal power plant performance at variou 2Comparing the thermal power plant performance at variou 2
Comparing the thermal power plant performance at variou 2
 
Comparing the thermal power plant performance at variou 2
Comparing the thermal power plant performance at variou 2Comparing the thermal power plant performance at variou 2
Comparing the thermal power plant performance at variou 2
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
Design, Development and Operation of 3.5HP Power Tiller
Design, Development and Operation of 3.5HP Power TillerDesign, Development and Operation of 3.5HP Power Tiller
Design, Development and Operation of 3.5HP Power Tiller
 
TBEA ENERGY (INDIA) PVT LTD
TBEA ENERGY (INDIA) PVT LTDTBEA ENERGY (INDIA) PVT LTD
TBEA ENERGY (INDIA) PVT LTD
 
Harbel 2 - N Oliveira
Harbel 2 - N OliveiraHarbel 2 - N Oliveira
Harbel 2 - N Oliveira
 
Design Optimization for Vibration Level of Root Blower With No Load Condition
Design Optimization for Vibration Level of Root Blower With No Load ConditionDesign Optimization for Vibration Level of Root Blower With No Load Condition
Design Optimization for Vibration Level of Root Blower With No Load Condition
 
2010 deep research report on china wind turbine blade industry
2010 deep research report on china wind turbine blade industry2010 deep research report on china wind turbine blade industry
2010 deep research report on china wind turbine blade industry
 
2010 deep research report on china wind turbine blade industry
2010 deep research report on china wind turbine blade industry2010 deep research report on china wind turbine blade industry
2010 deep research report on china wind turbine blade industry
 
Ijeet 06 08_003
Ijeet 06 08_003Ijeet 06 08_003
Ijeet 06 08_003
 
Design and Stress Analysis of High Pressure Accumulator
Design and Stress Analysis of High Pressure AccumulatorDesign and Stress Analysis of High Pressure Accumulator
Design and Stress Analysis of High Pressure Accumulator
 

Recently uploaded

Operating System Used by Users in day-to-day life.pptx
Operating System Used by Users in day-to-day life.pptxOperating System Used by Users in day-to-day life.pptx
Operating System Used by Users in day-to-day life.pptx
Pravash Chandra Das
 
System Design Case Study: Building a Scalable E-Commerce Platform - Hiike
System Design Case Study: Building a Scalable E-Commerce Platform - HiikeSystem Design Case Study: Building a Scalable E-Commerce Platform - Hiike
System Design Case Study: Building a Scalable E-Commerce Platform - Hiike
Hiike
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
panagenda
 
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptxOcean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
SitimaJohn
 
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
alexjohnson7307
 
Nordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptxNordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptx
MichaelKnudsen27
 
Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)
Jakub Marek
 
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
saastr
 
A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024
Intelisync
 
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Jeffrey Haguewood
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
shyamraj55
 
GraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracyGraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracy
Tomaz Bratanic
 
Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!
GDSC PJATK
 
Recommendation System using RAG Architecture
Recommendation System using RAG ArchitectureRecommendation System using RAG Architecture
Recommendation System using RAG Architecture
fredae14
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
Pixlogix Infotech
 
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Tatiana Kojar
 
WeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation TechniquesWeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation Techniques
Postman
 
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
akankshawande
 
GenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizationsGenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizations
kumardaparthi1024
 

Recently uploaded (20)

Operating System Used by Users in day-to-day life.pptx
Operating System Used by Users in day-to-day life.pptxOperating System Used by Users in day-to-day life.pptx
Operating System Used by Users in day-to-day life.pptx
 
System Design Case Study: Building a Scalable E-Commerce Platform - Hiike
System Design Case Study: Building a Scalable E-Commerce Platform - HiikeSystem Design Case Study: Building a Scalable E-Commerce Platform - Hiike
System Design Case Study: Building a Scalable E-Commerce Platform - Hiike
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
 
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptxOcean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
 
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
leewayhertz.com-AI in predictive maintenance Use cases technologies benefits ...
 
Nordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptxNordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptx
 
Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)Main news related to the CCS TSI 2023 (2023/1695)
Main news related to the CCS TSI 2023 (2023/1695)
 
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
 
A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024
 
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
 
GraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracyGraphRAG for Life Science to increase LLM accuracy
GraphRAG for Life Science to increase LLM accuracy
 
Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!Finale of the Year: Apply for Next One!
Finale of the Year: Apply for Next One!
 
Recommendation System using RAG Architecture
Recommendation System using RAG ArchitectureRecommendation System using RAG Architecture
Recommendation System using RAG Architecture
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
 
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
 
WeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation TechniquesWeTestAthens: Postman's AI & Automation Techniques
WeTestAthens: Postman's AI & Automation Techniques
 
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
 
GenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizationsGenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizations
 

The International Journal of Engineering and Science (The IJES)

  • 1. The International Journal Of Engineering And Science (IJES) ||Volume||2 ||Issue|| 11||Pages|| 01-04||2013|| ISSN(e): 2319 – 1813 ISSN(p): 2319 – 1805 Implication of Poor Energy Supply on the Productivity of Nigerian Manufacturing Industry By UZORH AUSTIN C. Mechanical Engineering Department Federal University of Technoloy Owerri PMB 1526 Owerri, Imo State, Nigeria. -----------------------------------------------ABSTRACT----------------------------------------------------------A comprehensive evaluation of the effectiveness and delay contribution due to power outages and fluctuations is presented. The purpose of this study is to reveal the implications of poor energy supply on the effective utilization of the input resources in a typical Nigerian Manufacturing Industry. Delta steel company .Delata state Nigeria was used as a casestudy. Data on power outages were collected from the energy distribution unit, steel melting shop and the rolling mill. Additionally, the total delays, standard or planned production and actual production were determined from the records, from which the power delay contributions and effectiveness were evaluated. Results from this study revealed that power delay contributed more than 6% and the monthly effectiveness was more than unity throughout year 2010. Analysis of data collected for 2010 production period showed that the energy distribution unit experienced 54 outages with a total duration of 11472 mins, while a total of 44947 mins was lost in the steel melting shops due to power outages and under-voltage. More so, 25 billets worth 44tonnes were scrapped and 20811 mins were lost as a result of power failure and fluctuations. The implications clearly showed that poor power supply lowers the productivity of the company. KEYWORDS: Energy, Manufacturing, Productivity. --------------------------------------------------------------------------------------------------------------------------------------Date of Submission: 11, March, 2013 Date of Acceptance: 10, November, 2013 --------------------------------------------------------------------------------------------------------------------------------------- I. MANUFACTURING SECTOR AND ENERGY SECTOR Every manufacturing industry requires energy to power their machines, computers, lighting and establishment for various purposes. However, in Nigeria, power requirement of the manufacturing sector far outweighs the available power being generated, transmitted and distributed by power holding company of Nigeria (PHCN) to both manufacturing and non manufacturing sectors. This energy deficiency has resulted in the emigration of some companies to other companies as exemplified by Mitchelin, which relocated their production capacity to ghana , some industries lying moribund as experienced by most textile industries in Nothern Nigeria and some industries resorting to diesel engines as prime movers of industrial alternators, which supplied inadequate power and cannot run continously for many days. Also, the running cost of these diesel engines are on the high sides , thereby increasing the cost of production and in many cases, lowers productivity. FUNDAMENTAL CONCEPTS Pertinent to this study is the understanding of the keywords: “Manufacturing” and “Productivity”. MEANING OF MANUFACTURING The word manufacturing is derived from the latin word manus and factus meaning hand and made respectively. That is the literal meaning is “made by hand”. However, in the modern sense, manufacturing means making of goods or articles from raw materials by hand and/or machinery by following a well defined plan for each activity required. DEFINITION OF PRODUCTIVITY Productivity has become an everyday watch word that is crucial to the welfare of the industries as well as the economic progress of the country. Productivity is the measure of how well the resources are brought together in an organization and utilized for accomplishing a set of objectives (Telsang 2008). www.theijes.com The IJES Page 1
  • 2. Implication Of Poor Energy… Productivity is the ratio of outputs of goods or services from the conversion process to input consumed in the generation of these outputs (Arthur, 1978). Productivity is a summary measure of the quantity and quality of work performance with resource utilization considered (Schermerhorn, 1986) Productivity can be defined as the optimum utilization of all the resoures of organization: Men, material, money and machinery, energy, space, technology, etc (Sharma, 2006). II. MEASUREMENT OF PRODUCTIVITY Productivity is the arithmetic ratio of amount produced (output) to the amount of resources(input). Mathematically: Productivity= Output/Input Productivity refers to the efficiency of the production. (Telsang, 2008). The basic component of productivity measurement is a means of comprising output forecasts with actual output at selected intervals. In general system theory, effectiveness is defined as the degree to which the actual output of the system corresponds to its desired or planned outputs. Productivity is a function of effectiveness and efficiency (www.authorsden.com). Effectiveness= Actual Outputs/Desired Outputs Productivity = Actual Production/ Standard Production III. DELTA STEEL COMPANY AS AN INTEGRATED STEEL PLANT Delta Steel Company(DSC) is an integrated steel plant with iron making, steel making and rolling mill facilities. These three important plant consume a lot of power during production and adversely lower the productivity of the company when there is power fluctuations or failure. However, the steel melting shop and rolling mill were functional during the period under study. IV. DATA COLLECTED AND PRESENTED PROCEDURE Power outages in DSC were collected for one year (January-December 2010) from the energy distribution unit. The record which show the specific date , timeout, timein, duration and feeders has been summarized as shown in table 1. The delay due to power outages, insufficient power to run the furnaces and preheat ladies, power fluctuation and power failure that resulted in the abortion of heats were determined from one year record and percentage contribution of the power failure to total delay was determined and compared to the productivity of the steel melting shop. See table 4.2. Moreso, delay due to power outages, cobbles due to power outages, percentages contribution of power failure compared to the total delay was determined and compared to the productivity of rolling mill (see table 4.3) V. POWER UTILIZATION IN THE STEEL MELTING SHOP Melting in the plant is achieved with Electric Arc Furnaces (EAF), which cannot do without electric Arc Furnaces (EAF), which cannot do without electricity. The melting point of steel is about 1539c, its superheat temperature before tapping into the preheated ladle is 1700c and the casting temperature in the continuous casting platform is 1600c. when there is power failure and the temperatture of the liquid steel is below 1600c, the usual option is to abort the heat by quickly tapping into the ladies and pouring the liquid steel on the ground floor before it solidifies. More so, when the Power failure is experienced at a temperature of about 1200c, the metal is left in the furnace, while heating and melting continue when the power is re-instated. VI. POWER UTILIZATION IN THE STEEL ROLLING MILL Both power fluctuation and failures are very dangerous and highly undesirable in the rolling mill. This is as a result of the formation of cobble which can occur when a billet undergoing deformation derails due to the stoppage or malfunctioning of the mall stands, shears, approach or roller table and loppers along the mill train. Power fluctuation or failure causes cobble formation in this mill, thereby grounding the rolling operation. Also, the temperature 1200c of the heated billets drops when there is power failure. When cobble forms, the mill is shut down, and cobble removal crew cut and remove the cobble, while the maintenance/production crew reinstates the plant before production continues. VII. RESULTS AND IMPLICATIONS The results from the data collected are summarized in tables 4.1, 4.2 and 4.3, while the implications of poor power supply are revealed in the tables 4.2 and 4. 3 and presented as shown below: www.theijes.com The IJES Page 2
  • 3. Implication Of Poor Energy… VIII. IMPLICATIONS OF POOR POWER SUPPLY IN THE STEEL MELTING SHOP The implication of poor fluctuation and failure are listed as follows: [1] Loss of consumables and ferroalloys are used in the treatment of aborted heat. [2] Loss of money accruable from 110 tons (furnace capacity) of steel had it been successfully casted. [3] Devaluation of already treated steel to scrap. [4] Increased expenditure on the cutting of the aborted steel to sizeable form for easy loading into the EAF. [5] Consumption of more energy in re-melting or continued melting because of temperature drop. [6] Loss of money paid to PHCN for power expended on return or aborted heat. [7] Increased idle times of workers because the entire plant get heated up and polluted when there is heat abortion. [8] Loss of man hours especially when heat is aborted. [9] Inability to make the planned or standard production [10] Productivity ratio or effectiveness is always less than one with respect to the production quantity. IMPLICATIONS OF POOR POWER SUPPLY IN THE STEEL ROLLING MILL The Implications of power fluctuations and outages in the steel mill includes: [1] Devaluation of the billet to scrap [2] Loss of a would be income if the billet was successfully rolled [3] Extra expense on the oxygen and acetylene used in cutting the cobbles [4] Maintenance and repair of damage damage parts due to cobble [5] Expenditure on the treatment of injured perssonnel or compensation on the family when a worker is entangled by cobble (death situation) [6] Increased downtime [7] Increased idle time of some workers [8] Increased energy consumption when the furnace temperature drops [9] Loss of man-hour and expenditure on power when cobble forms [10] Productivity is always less than unity because actual production was always less than the planned production. [11] Loss of machine hours as some machines take up to thirty minutes before assuming normal operating condition. COMMENT ON THE RESULT Table 4.1: The cause of the outages includes system collapse, system disturbance, high frequency, under voltage, over-voltage and poor generation. The number of power failure times was found to be 54 and the outage duration totaling 11472mins in 2010. GIW – Ughelli Supply, S4W – Sapele Supply Table 4.2: A total of 44937min delay due to power outages and inadequacy was recorded in 2010 and the steel melting shop which contributed 7. 37% to the total delay and resulted in the abortion or return of heat worth 1107tonnes of liquid steel. No monthly target was achieved throughout 2010, as revealed by the effectiveness. EAF II and EAF IV delays due to power are presented in second column. Table 4. 3: when the effectiveness is 0.82, the power delay contribution is 2.90% , while the effectiveness of 0.50 resulted when the power delay contribution is 17. 32%. These clearly show that power delay affect the productivity adversely. Also, the total number of billets devalued throughout 2010 was 25. Total delay due to power failure was calculated to be 20811mins with a contribution of 6.27% to the total delay. The effectiveness from January to December, 2010, was found to be less than unity. IX. CONCLUSION Obviously, poor energy supply lowers the productivity of manufacturing industries in Nigeria as shown by the two functional plants in Delta Steel Company. This is due to its associated unwanted events such as increased idle time, delivery time delay, Increased cycle time, reduced machine output, increased expenditure on material recovery and recycle, increased maintenance and repair expences , semi finished product devaluation, compensation to injured personnel or family of dead personnel, downtime, loss of consumables, alloys and extra expenses on raw materials or semi-finished product protection. All these implications arise due to power fluctuation and outages and in some cases the use of diesel engines as an alternative source of power supply. www.theijes.com The IJES Page 3
  • 4. Implication Of Poor Energy… Table 4.1: Power Outages for 2010. Source: Energy Distriburtion Unit August GIW 2201 325 Month Feeders Distribuion February March April May June July GIW, S4W GIW, S4W GIW GIW GIW GIW 790 1319 68 520 238 642 Number failures 4 5 4 6 3 10 www.theijes.com The IJES of power Page 4