The document is a cut/fill summary for a surface area of 396,124.57 square feet. It shows that excavating (cut) would result in 47,594.07 cubic yards of material, while filling (fill) would require 44,665.31 cubic yards. The net amount of excess material from cutting is 2,928.76 cubic yards.