The document summarizes a case between Lee Lay Ting Jane and MSCT Plan No. 3414 regarding Lee's request to upgrade the electricity supply to her shop units. There were disagreements over whether the unused electricity supply constituted common property, whether consent was required for the upgrade, and whether there was sufficient spare capacity. The Board ultimately found that while the unused electricity supply could be a property right, it did not meet the definition of common property under the BMSMA since it is not part of the land and building.
The annual shareholders meeting presentation summarized the company's plans to achieve profitability through increased production volume and global expansion. Key points included ramping North American production to 70MW annually, establishing manufacturing in South Korea through a partnership, and gaining a foothold in European markets. The company projected achieving positive EBITDA at 80MW of annual production volume.
The document provides an overview of the PowerSaver loan program, which enables homeowners to borrow up to $25,000 through an FHA-insured loan or unsecured consumer loan of up to $7,500 to finance home energy improvements. It discusses the goals of establishing partnerships between DOE, HUD, and lenders to promote the PowerSaver loans, and capturing lessons learned from the pilot program. The webinar objectives are to provide an overview of the PowerSaver program, describe how financing can help energy efficiency projects, and discuss how DOE program sponsors can partner with PowerSaver lenders.
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS Harish Sharma
IREDA Loan scheme is for all Solar rooftop power projects having minimum aggregate/Individual installed capacity 1000 kWp. Finance is available upto 75% of project cost with very Low interest rates range from 9.9% to 10.75%.
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...zubeditufail
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji to import 60mw power from fauji foundation, bin qasim coal based power plant
Gems international
Nov 2015
Draft scheme for allocation of solar power projects for land owning farmersHarish Sharma
After inviting EOI from land owning farmers for the set up of solar power projects of the tune from 1MW to 2.5MW, PEDA has now formulated draft scheme for allocation of solar power projects in Punjab.
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabHarish Sharma
As provided in the NRSE Policy-2012 and subsequent amendment, this scheme is introduced for allocation of Solar Power Projects to the land owning farmers of the state of
Punjab. The Government of Punjab endeavors to promote solar energy projects by land owning farmers with a minimum capacity of 1MWp to a maximum capacity of 2.5 MWp (per land owning farmer) in the state for sale of power to Punjab State Power Corporation Ltd (PSPCL)
2011 fapa conference presentation green economic developmentnzconsultants
The document summarizes a presentation given by Rebecca Grohall, Brandon Schaad, and Nilsa Zacarias at the 2011 APA Florida Conference about the city of Sebastian's approach to sustainable economic development with limited resources. The presentation discusses Sebastian's population growth, demographics, economy, and budget. It also provides examples of sustainable economic development from Germany, the UK, and Florida. The presentation concludes with an overview of Sebastian's sustainable long-term economic development strategy, which focuses on areas like land use, transportation, housing, business support, and attracting green jobs.
Solar Parks are becoming increasingly popular & MNRE is leaving no stone unturned to make them a success.
The ppt mentions the nuts & bolts of the Solar Park Scheme of MNRE.
The annual shareholders meeting presentation summarized the company's plans to achieve profitability through increased production volume and global expansion. Key points included ramping North American production to 70MW annually, establishing manufacturing in South Korea through a partnership, and gaining a foothold in European markets. The company projected achieving positive EBITDA at 80MW of annual production volume.
The document provides an overview of the PowerSaver loan program, which enables homeowners to borrow up to $25,000 through an FHA-insured loan or unsecured consumer loan of up to $7,500 to finance home energy improvements. It discusses the goals of establishing partnerships between DOE, HUD, and lenders to promote the PowerSaver loans, and capturing lessons learned from the pilot program. The webinar objectives are to provide an overview of the PowerSaver program, describe how financing can help energy efficiency projects, and discuss how DOE program sponsors can partner with PowerSaver lenders.
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS Harish Sharma
IREDA Loan scheme is for all Solar rooftop power projects having minimum aggregate/Individual installed capacity 1000 kWp. Finance is available upto 75% of project cost with very Low interest rates range from 9.9% to 10.75%.
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...zubeditufail
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji to import 60mw power from fauji foundation, bin qasim coal based power plant
Gems international
Nov 2015
Draft scheme for allocation of solar power projects for land owning farmersHarish Sharma
After inviting EOI from land owning farmers for the set up of solar power projects of the tune from 1MW to 2.5MW, PEDA has now formulated draft scheme for allocation of solar power projects in Punjab.
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabHarish Sharma
As provided in the NRSE Policy-2012 and subsequent amendment, this scheme is introduced for allocation of Solar Power Projects to the land owning farmers of the state of
Punjab. The Government of Punjab endeavors to promote solar energy projects by land owning farmers with a minimum capacity of 1MWp to a maximum capacity of 2.5 MWp (per land owning farmer) in the state for sale of power to Punjab State Power Corporation Ltd (PSPCL)
2011 fapa conference presentation green economic developmentnzconsultants
The document summarizes a presentation given by Rebecca Grohall, Brandon Schaad, and Nilsa Zacarias at the 2011 APA Florida Conference about the city of Sebastian's approach to sustainable economic development with limited resources. The presentation discusses Sebastian's population growth, demographics, economy, and budget. It also provides examples of sustainable economic development from Germany, the UK, and Florida. The presentation concludes with an overview of Sebastian's sustainable long-term economic development strategy, which focuses on areas like land use, transportation, housing, business support, and attracting green jobs.
Solar Parks are becoming increasingly popular & MNRE is leaving no stone unturned to make them a success.
The ppt mentions the nuts & bolts of the Solar Park Scheme of MNRE.
Whitney MCMurdie's Intern Presentation Fall 2013 Legal RenewMO
The document discusses various projects Whitney is working on for Renew Missouri, including researching the ballot initiative process for a solar rebate program in Springfield, compiling case docket files, assisting with legal research and memos, and learning about the utility regulatory appeals process. It also summarizes information from Public Service Commission meetings, research on net metering and community solar options, and templates for arguing common renewable energy standard issues.
The Federal Energy Regulatory Commission (FERC) authorized a proposed merger between Hawaiian Electric Industries, Inc. and NextEra Energy, Inc. whereby NextEra would indirectly acquire 100% of Hawaiian Electric Industries. The merger would result in Hawaiian Electric Industries becoming a wholly-owned subsidiary of NextEra. FERC determined the proposed merger was consistent with the public interest and would not adversely affect competition, rates, regulation, or result in cross-subsidization. The authorization was subject to conditions including retaining regulatory authority and requiring any necessary rate or status change filings.
The Division of Consumer Advocacy recommends that the Public Utilities Commission deny the request from several clean energy groups to defer consideration of a proposed merger between Hawaiian Electric Industries and NextEra Energy. The Division argues that determining issues in other dockets will take significant time and ongoing changes may affect those determinations. Additionally, analyzing the potential benefits of the proposed merger is important to identify customer savings and benefits. However, the Division's recommendation should not be seen as approval of the proposed merger, which it will rigorously review. If the Commission does not dismiss the request, the Division recommends consolidating it with a similar request in another docket.
Procedure for implementation of short term open access (stoa)Jay Ranvir
This document provides guidelines for implementing short term open access (STOA) in Delhi. It outlines the eligibility requirements, connectivity requirements, metering requirements, and the application process.
The key points are:
1) Only consumers with a contract demand of 1MW or above connected at 11kV or above are eligible for STOA. Generators of any capacity are also eligible.
2) Applicants must be connected to the transmission or distribution system and provide documents regarding connectivity.
3) Meters meeting certain specifications must be installed to measure energy drawal and injection for open access transactions.
4) The application process involves submitting an application form along with documents and fees to the State Load Dispatch Centre
Order 163 of 2017-12062018 Petition of Cleanmax Enviro Energy Solutions Pvt. Ltd. seeking clarification regarding
the Net Metering arrangements for Open Access consumers under the MERC (Net
Metering for Roof-Top Solar Photo Voltaic Systems) Regulations, 2015 and issues
pertaining to connection of Roof Top Solar Power Plant
The respondent argues that:
1) The principle of res judicata does not apply because the issues and reliefs sought in the first and second suits were different.
2) The appellant's claim for arrears is time-barred under the Limitation Act as more than 3 years have passed.
3) The respondent cannot be held liable for the previous owner's electricity dues because there was no agreement or terms to that effect.
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
The document describes a case study involving the joint administration of two FIDIC contracts - a Red Book contract for civil works and a Yellow Book contract for electrical and mechanical works - on a hydropower project. The E&M contractor fell behind schedule, impacting the civil works contractor (CIV). To recover the delay, the Engineer had CIV construct some temporary works to help E&M, then sought reimbursement from E&M for CIV's costs following the proper procedures in both contracts. This involved issuing notices, submitting claims and counterclaims, and making determinations, while ensuring all actions complied with the relevant clauses in the Red and Yellow Books.
Download Michael O' Connor, Head of Projects, Energy and Construction at Matheson's slides from this morning's briefing on Emerging Issues in Energy Litigation – A1P1 ECHR.
The presentation examines last month’s decision of the Court of Appeal in the case of The Department of Energy & Climate Change v Bryer Group PLC & Others.
Visit www.matheson.com/legal-services/projects-energy-and-construction-law to find out more.
Industrial training report of thermal power plantRavinder Jangid
This document provides details from a student's industrial training report on boiler, turbine, and generator operation and maintenance at PPGCL power plant in India. It includes:
1. An introduction to the benefits of industrial training.
2. Vision, mission, targets, and challenges of PPGCL including increasing plant efficiency and facing local opposition during construction.
3. Descriptions of the basic Rankine power cycle, components and specifications of the plant's boiler, turbine, and generator systems.
4. Ways to increase plant efficiency such as lowering condenser pressure and increasing steam superheating and boiler pressure.
The approval document from the Federal Energy Regulatory Commission approving an application filed by Dominion in June 2014 to build new compression facilities at existing compressor stations in West Virginia and Ohio, along with other bits and bobs, collectively called the Clarington Project. Anti-fossil fuel organization Allegheny Defense Project filed a protest against the Clarington Project. In FERC's approval, they rip to shreds Allegheny's pathetic arguments against this project.
This document outlines 3 schemes for interconnecting micro scale renewable energy power generating facilities to the low voltage consumer feeders of Sri Lanka's national grid. Scheme 1 allows net metering where exported energy is credited against imported energy. Scheme 2 adds an export tariff for net exported energy. Scheme 3 involves direct export of all generated energy through a dedicated meter, with the producer paid for exports. The document provides details on technical requirements, application processes, metering, safety features, and the rights and obligations of producers and the grid operator.
Global Energy Private Limited (GEPL) is inviting bids for the supply of 250 MW of firm power from conventional energy generators, IPPs, and CPPs with a minimum capacity of 100 MW. The power will be supplied to GEPL's consumers in the Western Region of India between April 2016 and March 2017. The bid submission deadline is January 4, 2016. The bid must include an unconditional acceptance of terms and conditions and authorization, as well as a financial bid. The power will be delivered at the interconnect point of the Maharashtra state transmission system. The tariff must be quoted as a single part tariff up to two decimals inclusive of taxes. The transmission charges and losses will be borne by the generator up to the delivery
Understanding Utility Easements and Rights of WayJeremy Young
Legal overview of the creation, interpretation, location, expansion, obstruction, maintenance, and termination of utility easements, and selected topics relating to eminent domain.
Practice directions rts net metering regulations 2015Jay Ranvir
CONNECTIVITY FOR ‘CHANGE-OVER’ CONSUMERS
PRACTICE DIRECTIONS Meter reading, energy accounting and settlement with the Consumer shall be
undertaken by the Supply Licensee as per the terms of the Regulations. The Supply
Licensee shall pay the Wheeling Charges, as approved by the Commission for a
particular financial year and corresponding to the unadjusted net credited Units of
electricity at the end of that year, to the Wires Licensee. Such payment will be taken
into account by the Commission while determining the respective Aggregate Revenue
Requirements.
This document is a judgment from the Court of Appeal regarding the Secretary of State's proposal to reduce solar PV feed-in tariffs for installations eligible from December 12, 2011 onwards. The Secretary of State proposed reducing the tariff rate for these installations starting April 1, 2012. The respondents challenged this on the grounds that it undermines the purpose of the FIT scheme and exceeds the Secretary's powers. The court considered whether the proposal has a retrospective effect by removing a "vested right" to the original tariff rate. The key issue is how to interpret the Secretary's powers under the Energy Act 2008 to modify tariff rates over time.
The document summarizes actions from the 2015 Connecticut Legislative Session and June Special Session related to energy and utilities. Key actions included technical revisions to energy statutes, revisions to the commercial PACE program, requiring developers to pay costs for public meetings on telecom towers, expanding small community water system oversight, extending anaerobic digestion and shared clean energy facility pilot programs, establishing a solar home renewable energy credit program, increasing electric rate case hearing requirements, allowing new types of energy procurement, restricting variable rate contracts, and addressing utility customer verification, grid-side energy projects, and property tax abatement policies.
This document is a letter from Kenneth G. Hurwitz, counsel for Regional Energy Holdings, Inc., to the Secretary of the Federal Energy Regulatory Commission regarding an application filed under Section 203 of the Federal Power Act. The letter notes that the original application filed on July 20, 2012 contained an incorrect date on page 2, and submits a revised application with the correct date. The letter requests that the Commission contact Mr. Hurwitz if there are any questions regarding the application.
This document outlines Tata Power's procedure for distribution open access in accordance with the Maharashtra Electricity Regulatory Commission's (MERC) Distribution Open Access Regulations of 2016. It details eligibility criteria, time periods, application process, timelines, metering requirements, scheduling, and other terms for consumers seeking open access distribution in Tata Power's service area. Key points include that open access is available for short term (up to 1 month), medium term (3 months to 3 years), and long term (12-25 years); minimum contract demand for eligibility is 1 MW; and applications must include fees and agreements and be submitted within specified timeframes and formats.
Whitney MCMurdie's Intern Presentation Fall 2013 Legal RenewMO
The document discusses various projects Whitney is working on for Renew Missouri, including researching the ballot initiative process for a solar rebate program in Springfield, compiling case docket files, assisting with legal research and memos, and learning about the utility regulatory appeals process. It also summarizes information from Public Service Commission meetings, research on net metering and community solar options, and templates for arguing common renewable energy standard issues.
The Federal Energy Regulatory Commission (FERC) authorized a proposed merger between Hawaiian Electric Industries, Inc. and NextEra Energy, Inc. whereby NextEra would indirectly acquire 100% of Hawaiian Electric Industries. The merger would result in Hawaiian Electric Industries becoming a wholly-owned subsidiary of NextEra. FERC determined the proposed merger was consistent with the public interest and would not adversely affect competition, rates, regulation, or result in cross-subsidization. The authorization was subject to conditions including retaining regulatory authority and requiring any necessary rate or status change filings.
The Division of Consumer Advocacy recommends that the Public Utilities Commission deny the request from several clean energy groups to defer consideration of a proposed merger between Hawaiian Electric Industries and NextEra Energy. The Division argues that determining issues in other dockets will take significant time and ongoing changes may affect those determinations. Additionally, analyzing the potential benefits of the proposed merger is important to identify customer savings and benefits. However, the Division's recommendation should not be seen as approval of the proposed merger, which it will rigorously review. If the Commission does not dismiss the request, the Division recommends consolidating it with a similar request in another docket.
Procedure for implementation of short term open access (stoa)Jay Ranvir
This document provides guidelines for implementing short term open access (STOA) in Delhi. It outlines the eligibility requirements, connectivity requirements, metering requirements, and the application process.
The key points are:
1) Only consumers with a contract demand of 1MW or above connected at 11kV or above are eligible for STOA. Generators of any capacity are also eligible.
2) Applicants must be connected to the transmission or distribution system and provide documents regarding connectivity.
3) Meters meeting certain specifications must be installed to measure energy drawal and injection for open access transactions.
4) The application process involves submitting an application form along with documents and fees to the State Load Dispatch Centre
Order 163 of 2017-12062018 Petition of Cleanmax Enviro Energy Solutions Pvt. Ltd. seeking clarification regarding
the Net Metering arrangements for Open Access consumers under the MERC (Net
Metering for Roof-Top Solar Photo Voltaic Systems) Regulations, 2015 and issues
pertaining to connection of Roof Top Solar Power Plant
The respondent argues that:
1) The principle of res judicata does not apply because the issues and reliefs sought in the first and second suits were different.
2) The appellant's claim for arrears is time-barred under the Limitation Act as more than 3 years have passed.
3) The respondent cannot be held liable for the previous owner's electricity dues because there was no agreement or terms to that effect.
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
The document describes a case study involving the joint administration of two FIDIC contracts - a Red Book contract for civil works and a Yellow Book contract for electrical and mechanical works - on a hydropower project. The E&M contractor fell behind schedule, impacting the civil works contractor (CIV). To recover the delay, the Engineer had CIV construct some temporary works to help E&M, then sought reimbursement from E&M for CIV's costs following the proper procedures in both contracts. This involved issuing notices, submitting claims and counterclaims, and making determinations, while ensuring all actions complied with the relevant clauses in the Red and Yellow Books.
Download Michael O' Connor, Head of Projects, Energy and Construction at Matheson's slides from this morning's briefing on Emerging Issues in Energy Litigation – A1P1 ECHR.
The presentation examines last month’s decision of the Court of Appeal in the case of The Department of Energy & Climate Change v Bryer Group PLC & Others.
Visit www.matheson.com/legal-services/projects-energy-and-construction-law to find out more.
Industrial training report of thermal power plantRavinder Jangid
This document provides details from a student's industrial training report on boiler, turbine, and generator operation and maintenance at PPGCL power plant in India. It includes:
1. An introduction to the benefits of industrial training.
2. Vision, mission, targets, and challenges of PPGCL including increasing plant efficiency and facing local opposition during construction.
3. Descriptions of the basic Rankine power cycle, components and specifications of the plant's boiler, turbine, and generator systems.
4. Ways to increase plant efficiency such as lowering condenser pressure and increasing steam superheating and boiler pressure.
The approval document from the Federal Energy Regulatory Commission approving an application filed by Dominion in June 2014 to build new compression facilities at existing compressor stations in West Virginia and Ohio, along with other bits and bobs, collectively called the Clarington Project. Anti-fossil fuel organization Allegheny Defense Project filed a protest against the Clarington Project. In FERC's approval, they rip to shreds Allegheny's pathetic arguments against this project.
This document outlines 3 schemes for interconnecting micro scale renewable energy power generating facilities to the low voltage consumer feeders of Sri Lanka's national grid. Scheme 1 allows net metering where exported energy is credited against imported energy. Scheme 2 adds an export tariff for net exported energy. Scheme 3 involves direct export of all generated energy through a dedicated meter, with the producer paid for exports. The document provides details on technical requirements, application processes, metering, safety features, and the rights and obligations of producers and the grid operator.
Global Energy Private Limited (GEPL) is inviting bids for the supply of 250 MW of firm power from conventional energy generators, IPPs, and CPPs with a minimum capacity of 100 MW. The power will be supplied to GEPL's consumers in the Western Region of India between April 2016 and March 2017. The bid submission deadline is January 4, 2016. The bid must include an unconditional acceptance of terms and conditions and authorization, as well as a financial bid. The power will be delivered at the interconnect point of the Maharashtra state transmission system. The tariff must be quoted as a single part tariff up to two decimals inclusive of taxes. The transmission charges and losses will be borne by the generator up to the delivery
Understanding Utility Easements and Rights of WayJeremy Young
Legal overview of the creation, interpretation, location, expansion, obstruction, maintenance, and termination of utility easements, and selected topics relating to eminent domain.
Practice directions rts net metering regulations 2015Jay Ranvir
CONNECTIVITY FOR ‘CHANGE-OVER’ CONSUMERS
PRACTICE DIRECTIONS Meter reading, energy accounting and settlement with the Consumer shall be
undertaken by the Supply Licensee as per the terms of the Regulations. The Supply
Licensee shall pay the Wheeling Charges, as approved by the Commission for a
particular financial year and corresponding to the unadjusted net credited Units of
electricity at the end of that year, to the Wires Licensee. Such payment will be taken
into account by the Commission while determining the respective Aggregate Revenue
Requirements.
This document is a judgment from the Court of Appeal regarding the Secretary of State's proposal to reduce solar PV feed-in tariffs for installations eligible from December 12, 2011 onwards. The Secretary of State proposed reducing the tariff rate for these installations starting April 1, 2012. The respondents challenged this on the grounds that it undermines the purpose of the FIT scheme and exceeds the Secretary's powers. The court considered whether the proposal has a retrospective effect by removing a "vested right" to the original tariff rate. The key issue is how to interpret the Secretary's powers under the Energy Act 2008 to modify tariff rates over time.
The document summarizes actions from the 2015 Connecticut Legislative Session and June Special Session related to energy and utilities. Key actions included technical revisions to energy statutes, revisions to the commercial PACE program, requiring developers to pay costs for public meetings on telecom towers, expanding small community water system oversight, extending anaerobic digestion and shared clean energy facility pilot programs, establishing a solar home renewable energy credit program, increasing electric rate case hearing requirements, allowing new types of energy procurement, restricting variable rate contracts, and addressing utility customer verification, grid-side energy projects, and property tax abatement policies.
This document is a letter from Kenneth G. Hurwitz, counsel for Regional Energy Holdings, Inc., to the Secretary of the Federal Energy Regulatory Commission regarding an application filed under Section 203 of the Federal Power Act. The letter notes that the original application filed on July 20, 2012 contained an incorrect date on page 2, and submits a revised application with the correct date. The letter requests that the Commission contact Mr. Hurwitz if there are any questions regarding the application.
This document outlines Tata Power's procedure for distribution open access in accordance with the Maharashtra Electricity Regulatory Commission's (MERC) Distribution Open Access Regulations of 2016. It details eligibility criteria, time periods, application process, timelines, metering requirements, scheduling, and other terms for consumers seeking open access distribution in Tata Power's service area. Key points include that open access is available for short term (up to 1 month), medium term (3 months to 3 years), and long term (12-25 years); minimum contract demand for eligibility is 1 MW; and applications must include fees and agreements and be submitted within specified timeframes and formats.
Procedure for-distribution-open-access, Tata Power
[2015] SGSTB 5
1. Lee Lay Ting Jane v MSCT Plan No
3414
[2015] SGSTB 5
Case Number :
STB No 92 of 2014
Decision Date :
06 July 2015
Tribunal/Court :
Strata Titles Boards
Coram :
Alfonso Ang; Lee Coo; Tang Hang Wu
Counsel Name(s) :
Toh Kok Seng and Daniel Chen (Lee & Lee) for the applicant ; Chia
Tze Yung Justin (Harry Elias Partnership LLP) for the respondent
Parties :
Lee Lay Ting Jane — MSCT Plan No 3414
1. The Applicant, Ms Lee Lay Ting Jane, is the subsidiary proprietor of two shop units at
7 Rodyk Street #01-31 and #01-33 Watermark Robertson Quay, Singapore 238215 (“ the
Units”).
2. The Respondent is MCST Plan No. 3414, the Management Corporation of the
development known as Watermark Robertson Quay (the “Development”), a mixed
development consisting of 206 residential units and 8 shop units.
Background
3. On 21 May 2012, the Applicant approached the then condominium manager, Mr Mark
de Souza (“Mr de Souza”), to request for permission to carry out an upgrade of the
electricity supply to her Units. The Respondent then forwarded the Applicant’s request to
the Development’s Licensed Electrical Worker (LEW), Mr Ng Hai Hock (“Mr Ng”) of NHH
Consultants, who requested for additional documents.
4. Mr Ng also signed off on two CS/3 Forms on 7 June 2012, stating that he had
‘checked the loading of the electrical installation of the [Applicant’s] load requirement’
and confirmed that the Applicant’s request ‘can be catered for from the rising/horizontal
mains system/main switchboard of the building/complex, and the total approved load to
the entire building/complex will not be exceeded’.
5. On 18 June 2012, NHH Consultants issued a letter to the Respondent stating that
they had ‘no objection’ to the Applicant upgrading the Units’ electricity supply from 63
Ampere Single Phase to 100 Ampere Three Phase.
2. 6. Subsequently, by an email dated 27 June 2012, the Respondent informed the
Applicant that they were unable to accede to her request to an upgrade of the electricity
supply to her Units, as doing so would result in there not being ‘any more spare for future
use by the management for common area upgrading’.
7. On 27 June 2012, NHH Consultants issued another report confirming that they had
no objections to the Applicant’s request for the upgrading of the Units’ electricity supply to
80 Ampere Three Phase. The report also stated that there would be another ‘about 60A
three phase still available for future upgrading’ but the approval shall be subject to the
Management Council’s approval.
8. On 2 July 2012, NHH Consultants issued a third report, but this time, they stated that
they had no objections to the Applicant’s request to upgrade unit #01-31 to 63 Ampere
Three Phase and unit #01-33 to 80 Ampere Three Phase. The report again stated that
there would be another ‘about 60A three phase still available for future upgrading’ but the
approval shall be subject to the Management Council’s approval.
9. However, the Respondent later informed the Applicant by a letter dated 6 July 2012
that the Management Council had rejected her application after consideration of the
‘limited spare electrical capacity for the development’, as the Management Corporation
had to ‘reserve the spare power supply for future common areas upgrading /
improvement works’.
10. The Applicant’s solicitors wrote to the Respondent’s solicitors re-stating the
Applicant’s request, but these were rejected both times.
11. Consequently, the Applicant applied to the Board seeking an order that the
Respondent allow the Applicant’s request to carry out upgrading of the electricity supply
to the Units to 100 Ampere Three Phase.
12. The Applicant submits that there four main issues for the Board’s consideration:
a. Whether electricity supply is part of the common property;
b. Whether consent is required for the Applicant’s requested upgrade;
c. Whether this is a matter which requires a decision to be made at a general
meeting of the Management Corporation; and
d. Whether the Respondent’s refusal to consent to the Applicant’s requested
upgrade is unreasonable.
13. The Respondent submits that the application should be dismissed for the
following reasons:
a. There is insufficient electricity supply in the Development to meet the
Applicant’s requested upgrade;
b. The unutilized electricity supply forms part of common property;
3. c. The Respondent is not in a position to approve the Applicant’s request as such
approval would be tantamount to granting the Applicant exclusive use and
enjoyment or special privileges in respect of the common property;
d. The Board has no jurisdiction to make an order under Section 101(1)(c)
Building Maintenance and Strata Management Act (‘BMSMA’) by virtue of Section
101(6) BMSMA; and
e. The Respondent’s refusal was not unreasonable pursuant to Section 111
BMSMA.
Considerations
14. In considering whether the Respondent had improperly refused the Applicant’s
request, the following are relevant:
a. Whether the electricity supply constitutes common property;
b. Whether the Respondent’s consent is required for the Applicant’s request
and/or whether this is a matter which requires a decision to be made at a general
meeting of the Management Corporation ; and
c. Whether there is sufficient spare electrical capacity for the Applicant to carry out
the upgrading of the Units’ electricity supply.
Applicant’s Case
Whether the electricity supply constitutes ‘common property’
15. The Applicant submitted that the electricity supply did not constitute ‘common
property’ of the Development. In support of this, it was submitted that the electricity is paid
for by the respective subsidiary proprietors to the electricity provider. Nevertheless, the
Applicant conceded that the electricity would have to pass through switchboards, meters,
cables and pipes, all of which are part of the common property.
16. The Respondent argued that the unutilized electricity supply clearly fell within the
definition of ‘common property’ in Section 2(1) of the BMSMA, as it was not comprised in
any lot or proposed lot and was used or capable of being used or enjoyed by occupiers
of two or more lots or proposed lots.
Whether the Respondent can approve the Applicant’s request and/or whether this is
a matter which requires a decision to be made at a general meeting of the
Management Corporation
17. The Respondent contends that the Respondent would not be in a position to
approve the Applicant’s request if the unutilized electricity supply is deemed to be
common property, as such approval would be tantamount to granting the Applicant
exclusive use and enjoyment or special privileges in respect of the common property.
18. It followed that the Applicant would have to satisfy Section 33 BMSMA, namely that a
requisite resolution has to be achieved at a general meeting of the Development.
4. 19. The Respondent further contended that even if the Respondent could approve the
Applicant’s request, the Applicant required a special resolution to procure an upgrade of
the capacity of DB-Shop-1 / DB-Shop-2.
20. The Respondent contends that as the unutilized electricity supply is common
property, the Board does not have jurisdiction to make an order under Section 101(1)(c)
BMSMA by virtue of Section 101(6) BMSMA.
21. The Applicant on the other hand acknowledged that given the fact that the electrical
supply has to pass through the switchboards, cables and conduits which form part of
common property, the Applicant required the Respondent’s consent to upgrade her
electricity supply. The Applicant argued that pursuant to Section 29(1) BMSMA, the
Respondent had a duty to ‘control, manage and administer the common property for the
benefit of all the subsidiary proprietors…’. It was further contended that Section 101(1)
BMSMA provided that the Board may make an order for the settlement of a dispute with
respect to the exercise or performance of, or the failure to discharge its duty under
Section 29(1) BMSMA.
Whether there is sufficient spare capacity for the Applicant’s requested upgrade
22. The Applicant contends that there is sufficient spare electrical capacity for an
upgrade of the electricity supply to the Units to 100 Ampere Three Phase. The
Respondent disputes this, and is of the view that there is simply no spare electrical
capacity in the Development.
23. Both parties called witnesses to give evidence in this regard. We consider the
evidence below.
Board’s Views And Decision
Whether the electricity supply constituted part of the ‘common property’ of the
Development
24. The Board has been invited by the Respondent to make the holding that electricity
supply to the Development constitutes ‘common property’ as defined by the BMSMA.
Certain legal consequences will flow if the unused electricity supply is regarded as
‘common property’. In order for the Respondent to succeed in this respect, the
Respondent has to cross two legal hurdles. First, the Respondent must establish that
the unused electricity supply to the Development is, as a matter of law, a property right.
Second, even if unused electricity supply is a property right, this right must be fall within
the definition of ‘common property’ as defined by the BMSMA.
25. The first issue whether unused electricity supply to the Development is a property
right is an extremely tricky question. As Gray and Gray in Elements of Land Law , (OUP,
2009), para 1.5.1 observed ‘[f]ew concepts are quite so fragile, so elusive and so
frequently misused as the notion of property.’
26. The starting point for the definition of property is the case of National Provincial
Bank v Ainsworth [1965] AC 1175 , 1247 – 1248 where Lord Wilberforce said (cited with
approval by the Court of Appeal in Toh Eng Lan v Foong Fook Yue and another appeal
[1998] 3 SLR(R) 833):
5. “Before a right or an interest can be admitted into the category of property, or of a right
affecting property, it must be definable, identifiable by third parties, capable in its nature
of assumption by third parties and have some degree of permanence or stability.”
27. However, it must be noted that Ainsworth has come under trenchant judicial and
academic criticism (see for example Gray, ‘Property in Thin Air ’ (1991) 50 Cambridge LJ
252 at p 292–293 (this article has been cited by Chan Seng Onn J in Lee Kien Meng v
Cintamani Frank [2015] SGHC 109)). An illustration of such criticism may be found in the
following passage by Susan Gray and Professor Kevin Gray in Elements of Land Law,
(OUP, 2009), para 1.5.29:
“The difficulty with this orthodox understanding of proprietary quality is, of course, that it is
riddled with circularity: the definition of proprietary character becomes entirely self-
fulfilling. If naively we ask which entitlements are ‘proprietary’, we are told that they are
those rights which are assignable and enforceable against third parties. When we then
ask which rights these may be, we are told that they comprise, of course, the
entitlements which are traditionally defined as ‘proprietary’. It is radical and obscurantist
nonsense to formulate a test of proprietary quality in this way.”
28. The Board is more impressed with the definition of the irreducible features of
property offered by Susan Gray and Professor Kevin Gray in Elements of Land Law, (OUP,
2009), para 1.5.32. According to Gray and Gray the following are three key features which
lie irreducibly at the core of the definition of property ownership:
(i) immunity from summary cancellation or extinguishment
(ii) presumptive entitlement to exclude others
(iii) entitlement to prioritise resource values.
29. Based on the three key features, the Board is of the view that the unused electricity
supply to the Development may be regarded as a property right. First, the right to
electricity supply is immune from summary cancellation or extinguishment. As long as
the Respondent met its contractual obligations with the provider of the electricity supply,
SP Services Ltd, SP Services Ltd does not have the right to summarily cancel the power
supply. Second, the Respondent has a presumptive entitlement to exclude third parties
of the Development from this electricity supply. Finally, the Respondent is entitled to
prioritise the resource value of this electricity supply.
30. However, even if the unused electricity supply may be characterized as proprietary
in nature, this right must still come within the definition of ‘common property’. ‘Common
property’ is defined by section 2 of the Building Maintenance Strata Management Act
(‘BMSMA’) as follows:
(a) in relation to any land and building comprised or to be comprised in a strata title
plan, such part of the land and building —
(i) not comprised in any lot or proposed lot in that strata title plan; and
(ii) used or capable of being used or enjoyed by occupiers of 2 or more lots or proposed
lots; or
(b) in relation to any other land and building, such part of the land and building —
(i) not comprised in any non-strata lot; and
(ii) used or capable of being used or enjoyed by occupiers of 2 or more non-strata lots
within that land or building; (emphasis added)
6. 31. Thus, section 2 of the BMSMA provides that before something may be regarded as
‘common property’ the thing concerned must be regarded as forming such part of the
land and building. There are two further pre-requisites to the definition of ‘common
property’. First, it must not be comprised in any lot in the strata plan. Second, it must be
used or capable of being used or enjoyed by occupiers of two or more lots. Intangible
property rights may in the proper circumstances be regarded as part of ‘common
property’. It has been held by Judith Prakash J in Frontfield Investment Holding (Pte) Ltd v
MCST Plan No. 938 [2001] 2 SLR(R) 410 that an easement over land of a third party was
also considered to be part of the common property. Prakash J in Choo Kok Lin and
another v MCST Plan No 2405 [2005] 4 SLR (R) 175 at [44] rationalised her previous
holding in Frontfield as follows:
“ That holding was based on the definition of “land” in the Act which made it clear that
“proprietorship of land includes natural rights to air, light, water and support and the right
of access to any highway on which the land abuts. An easement is not tangible and yet it
has long been recognised by the common law as being part of a parcel of rights which a
purchaser acquires when he purchases a parcel of land which enjoys an easement over
an adjacent parcel”.
32. Prakash J’s decision in Choo Kok Lin v Management Corporation Strata Title Plan
No 2405 [2005] 4 SLR (R) 175 considered the tricky question whether unconsumed
Gross Floor Area allocated to a particular development could be considered ‘common
property’. It is worth quoting in extenso from this decision at [45 - 47]:
“45 Despite my recognition that land, and therefore, common property, can include
intangible rights, I do not think that unconsumed GFA is capable of constituting land. First
of all, the common law does not recognise the concept of GFA. It is not something that
has grown out naturally from the ownership and use of land. GFA is a concept that has
been invented by the planning authorities in order to control and administer the usage of
land in accordance with the currently prevailing policy applied by such authorities.
Secondly, to an extent, the GFA of a development is determined by the amount of
development charge that a developer is prepared to pay, although of course, there may
be guidelines as to the maximum permissible GFA in any particular case. All I am
pointing out is that there is no pre-designated GFA for any particular plot by which I mean
a GFA which has to be assigned to that plot regardless of the size of the GFA applied for
by the developer and the amount that the developer is willing to pay. As a tool of planning
policy, the GFA does not have an inherent connection with any particular plot. It is a
creature of a completely different nature from an easement which the Act itself describes
as a "natural right". Thirdly, the Act itself has not statutorily included GFA in the definition
of "land" for the purposes of the Act.
46 As unconsumed GFA cannot be "land", a fortiori it cannot be common property…
47…With respect, I agree that GFA does not belong to anyone and is not a right of such a
nature that it is capable of being owned by anyone. As the appellants submitted, GFA is
simply an administrative tool. As such, it was solely up to the URA to increase or
decrease the GFA for any particular parcel of land and to decide what it would do if
construction on the land resulted in it being built up beyond the GFA”.
33. Based on the wording of section 2 of the BMSMA and Choo Kok Lin , the Board is of
the view that the unused electricity supply is not properly regarded as ‘common property’
for the following reasons. First, section 2 of BMSMA presupposes that in most cases
‘common property’ is a tangible proprietary right. The section refers to ‘common property’
as being “such part of the land and building”. It is very difficult to stretch the words of the
7. statute i.e. “part of the land and building” to include unused electricity supply. Second,
Prakash J’s decision in Frontfield that an easement enjoyed by the residents of a strata
lot over a third party’s land should be regarded as ‘common property’ may be
distinguished from the present case. As the learned judge perceptively pointed out,
section 4 of the Land Titles Act (which is applicable in the context of the BMSMA) defines
land as “ natural rights to air, light, water and support and the right of access to any
highway on which the land abuts”. An easement being an ancient right which has been
always been regarded as proprietary in nature ‘fits’ comfortably within the definition of
section 4 of the Land Titles Act. In contrast, unused electricity supply to the Development
is not included within the definition of land in section 4 of the Land Titles Act.
34. Even though the Board is of the view that the unused electricity supply is not
regarded as ‘common property’ within the definition of section 2 of the BMSMA, this does
not mean that the Respondent’s right to allocate the electricity supply is completely
unfettered. The Respondent must manage the right to allocate the electricity supply as a
responsible management corporation with reference to their legal duties to the
subsidiary proprietors. The standard of conduct expected of Management Corporation
will be articulated below.
35. Despite the fact that the unused electricity supply is not regarded as common
property, the Board is of the view that given that the electricity supply is supplied by
switchboards in the Development, which form part of the common property, the Applicant
would require the Respondent’s consent in carrying out her request. There is no real
dispute with regard to this legal proposition as the Applicant accepts that the
Respondent’s consent is required.
Whether the Board has jurisdiction to make an order in the present case and/ or
whether this is a matter which requires a decision to be made at a general meeting of
the Management Corporation
36. The Board accepts the Applicant’s counsel’s submission that under Section 29(1)
of the BMSMA, it is the duty of a Management Corporation to control, manage and
administer the common property for the benefit of all the subsidiary proprietors, and that
the Respondent’s refusal to grant the Applicant’s request in the present case would fall
under Section 101(1)(c) , which provides that the Board may make an order for the
settlement of a dispute with respect to the exercise of a duty conferred or imposed by the
BMSMA. The Applicant’s submission is not inconsistent with the Board’s holding that the
unused electricity supply is not regarded as ‘common property’. In order for the Applicant
to upgrade the electricity supply to her Units, she must make necessary adjustments and
connections to the relevant electrical switchboards and cables. These electrical
switchboards and cables are undoubtedly ‘common property’ and within the purview of
the Respondent. Thus, the Respondent must exercise its discretion judiciously in
relation to the Applicant’s access to the relevant electrical switchboards and cables in
order to upgrade the electricity supply to the Applicant’s Units. In other words, the
Respondent’s discretion must be exercised consistently with the Respondent’s legal
duty to control, manage and administer common property for the benefit of all the
subsidiary proprietors. It must be noted that the Applicant’s request to access and make
the relevant adjustments to the relevant electrical switchboards and cables in order to
upgrade the electricity supply to her Units does not amount to exclusive use of common
property because other subsidiary proprietors are not deprived of the use of these
electrical switchboards and cables.
8. 37. The Board does not agree with the Respondent’s counsel’s submission that the
Applicant’s request would be tantamount to granting ‘special privileges to increase her
usage of the unutilized electricity supply over the other subsidiary proprietors’. As the
upgrade of the Applicant’s electrical supply is to come from the Development’s spare
electrical supply, the other subsidiary proprietors will not be deprived of their existing
electricity supply. The Board also found that the Applicant’s request did not amount to a
request for ‘exclusive use’ of common property. As demonstrated above, the unused
electricity supply to the Development cannot be regarded as ‘common property’. Thus,
the Board found that Section 33 and 101(6) of the BMSMA did not apply in the present
case, and the matter is not one to be decided which requires a decision at a general
meeting.
38. In any case, the Board has jurisdiction under Section 111 of the BMSMA to make an
order that the Respondent consent to the Applicant’s request if it so finds that the
Respondent has unreasonably refused the request.
Whether there was sufficient spare electrical capacity in the Development
39. The Board found the Respondent’s arguments for refusing the Applicant’s request
to be inconsistent. For example, the position taken by the Respondent at various times,
i.e. in 2012, 2014 and 2015 was inconsistent. Initially, the Respondent had taken the
view that there was insufficient spare electrical capacity within the Development to
upgrade the Applicant’s Units’ electricity supply in 2012. In 2015, the Respondent’s
position was that there simply was no spare capacity available at all.
40. The Board noted that the evidence relating to the sufficiency of spare electrical
capacity of the Development given by Mr Ng, Mr Tay Oon Tiong, the current Building LEW
of the Development since 2013 (“Mr Tay”) and Mr Lim Sui Yong, the Applicant’s LEW (“Mr
Lim”), was unanimous. All three witnesses, when asked if there was sufficient spare
electricity capacity to effect the Applicant’s request, agreed that in their professional
capacity as engineers, there was indeed enough spare electrical capacity to do so.
41. As explained by Mr Lim, electrical engineers must consider the ‘diversity factor’ i.e.
not all the appliances will be switched on at full capacity at the same time. Mr. Lim
elaborated in para 7 of his Affidavit of Evidence in Chief dated 5 June 2015 as follows:
‘Diversity is in existence in any operating system simply because not all the loads
connected to the supply system are operating simultaneously and not all are
simultaneously operating at their maximum ratings. With the concept of “diversity factor”
one will understand why the main intake breaker ampere rating at a distribution board
(“DB”) does not equal to the sum of all the branch breakers amperes due to this time
interdependence, i.e. diverseness in real time application.’
42. Mr Lim cited examples of developments in which he had approved electrical
upgrades which exceeded the building’s existing design capacity. He noted that these
were possible given the operation of the ‘diversity factor’ and recognised engineering
practice.
43. Mr Lim added that if he was to ‘mathematically’ calculate the sum of the individual
maximum electrical demands, that ‘no upgrading on earth can be done’. His views were
consistent what those of Mr Tay and Mr Ng, who both took the view that there was in fact
sufficient spare electrical capacity to effect the Applicant’s request.
9. Whether the Respondent’s decision to reject the Applicant’s request may be
challenged
44. Both the Applicant and Respondent have submitted that the Board would have the
jurisdiction to interfere if the Respondent’s refusal to allow the Applicant’s request was
unreasonable. It must be noted that the Applicant and Respondent differ in their
submissions as to what constitutes unreasonable behavior. Notwithstanding this
apparent agreement of the law between the Applicant and Respondent, the Board is not
bound by a concession of law which may be regarded as erroneous. As Richard
Malanjum CJ said in NV Multi Corp Bhd & Ors v Suruhanjaya Syarikat Malaysia
[2010] 5 MLJ 573 at [16]:
“It has been said that no court is bound to decide a controversy upon an erroneous
concession of law made by one of disputants before it, more so when a question of
statutory interpretation is involved. The most odd of results would follow if a contrary rule
is to be applied”
45. NV Multi Corp Bhd has been applied by the Singapore Court of Appeal in Paragon
Finance in Yong Kheng Leong v Panweld Trading Pte Ltd [2013] 1 SLR 173.
46. What then is the standard which a Management Corporation’s decision is subject
to review by the Board? In order to discern the standard of review, it is important to revert
to first principles. Since a Management Corporation cannot hold property for itself
absolutely, it must follow that the Management Corporation holds property on trust for the
subsidiary proprietors collectively. This is consistent with the general principle articulated
in the decision of the New South Wales Court of Appeal in Owners Strata Plan 50276 v
Thoo [2013] NSWCA 270. In Thoo, the court said that a Management Corporation held
the common property on a statutory trust for the owners as a whole and owed general
duties and statutory duties to the owners. It could be said that the right to allocate the
unused electricity supply is a right held by the Respondent on trust for the subsidiary
proprietors collectively. Therefore, the Respondent’s duty in this respect is akin to a
trustee making a decision with regard to trust property.
47. Chao Hick Tin JA in Foo Jee Seng v Foo Jhee Tuang [2012] 4 SLR 339 succinctly
sets out the following principles governing the exercise of a trustee’s discretion in
relation to trust property:
(i) “the discretion exercised by the trustees should, as a rule be respected” [51];
(ii) “where the discretion is vested in a trustee, that duty has to be exercised properly.
The court cannot intervene unless the discretion is either improperly exercised, or not
exercised at all” [53];
(iii) the “beneficiaries cannot dictate the way a trustee should exercise his discretion”
[54]; and
(iv) while there is no obligation to follow the beneficiaries’ wishes, the trustee cannot
completely disregard the beneficiaries’ wishes and their objective needs and interests
[54].
48. Chao JA in Foo v Foo accepted the authority of Re Beloved Wilkes’ Charity (1851) 3
Mac & G 440; 42 ER 330 that the court’s supervision will be confined to the “honesty,
integrity, and fairness with which the deliberation has been conducted, and will not be
extended to the accuracy of the conclusion arrived at”. It must be noted that Chao JA did
not state a final view as to whether reasonableness of the trustees’ exercise of discretion
10. is a criteria for interference beyond noting Dundee General Hospital Board of
Management v Walker [1952] 1 All ER 896, 901 where Lord Normand doubted that
reasonableness was an appropriate benchmark for interference.
49. The trustee is also under a duty to take into account relevant considerations and
ignore irrelevant considerations in making decisions. As Chao JA observed in Foo v
Foo:
“In our judgment, we think that the 1 Respondent [the trustee] has failed to take into
account in arriving at his decision not to effect the sale of the Property at this time,
considerations which he should have taken into account and/or he has taken into
account considerations which he should not have taken into account (eg, it was the
Testator’s intention to retain the Property as an ancestral home…)” at [67]
50. The Board is of the view that the observations of the Court of Appeal in Foo v Foo is
also apposite in the context of a Management Corporation making decisions in relation
to unused electricity supply. Therefore, we agree with the Respondent’s submission that
the test of review of a Management Corporation’s decision pursuant to sections 101(c) of
the BMSMA cannot be “a simple test of reasonableness”. The Board cannot be the final
arbiter of every decision which a subsidiary proprietor regards as unreasonable. To hold
otherwise could potentially paralyze the decision making process of the Management
Corporation and inundate the Board with multiple challenges by disgruntled subsidiary
proprietors.
51. Nevertheless , we are of the view that the Respondent is incorrect to say that the
Board may only intervene if the Respondent’s decision was tainted with prejudice, malice
or indifference. As seen in Foo v Foo , a court may also intervene in the decision of a
trustee if the trustee had taken into account an irrelevant consideration and/or ignored a
relevant consideration.
52. In determining whether the Respondent’s decision is proper, the Board has to take
into account the interests of both the Applicant and the other subsidiary proprietors. The
Board has considered carefully the evidence put forward by both parties. There was a
clear consensus amongst the experts at trial that there was sufficient spare electrical
capacity within the Development to cater to the Applicant’s request.
53. The Respondent had erred in adding the individual supply components together in
a linear fashion in reaching the conclusion that there would be insufficient spare
electrical capacity. Due consideration has to be given to the diversity factor, which is the
ratio of the sum of the individual maximum loads of various subdivisions to the maximum
demand of a complete system. By virtue of this, buildings can often accommodate
electrical upgrades which surpass their original design capacity. In this regard, the
Respondent has failed to take into account a relevant consideration i.e. the diversity
factor in arriving at the decision to reject the Applicant’s request to upgrade the electrical
supply to her Units. It must be noted that there was no real dispute between the experts
about whether there was sufficient electricity supply to meet the Applicant’s request. Even
the Respondent’s expert thought as a professional engineer there was sufficient capacity
to meet the Applicant’s request. By ignoring the Respondent’s own LEW’s opinion, the
Respondent has failed to take into account a relevant consideration.
st
11. 54. At trial, Mr de Souza gave evidence for the Respondent. When asked about the
Council’s reasons for rej ecting the Applicant’s request in his examination-in-chief, he
admitted that the Council was concerned that if such a request was granted, the shop
units would operate 24-hour businesses, like a pizza delivery. This, he said, would
adversely affect the residential units which are situated directly above the shop units.
Security would also be a cause for concern as delivery people would be loitering around
at all times of the day.
55. The Board noted that the considerations raised by Mr de Souza at trial were never
communicated to the Applicant. While there is generally no duty to give reasons to the
Applicant, the Board thinks that it is good practice to do so (see Chia Sok Kheng
Kathleen v MCST Plan No 669 [2004] 4 SLR(R) 27 at [38]). However, a Management
Corporation is not entitled to take into account an irrelevant consideration when coming
to a decision. In any case, the Board is of the view that such concerns can be managed
by the passing of relevant by-laws to prevent disruption to the residential units which are
situated above the Applicant’s Units. The Respondent failed to raise any other reasons
for rejecting the Applicant’s request. As such, the Respondent had taken into account an
irrelevant consideration in refusing the Applicant’s request.
56. Given the circumstances, the Board found that the Respondent’s refusal of the
Applicant’s request was improper because the Respondent had failed to take into
account a relevant consideration (that there was spare capacity and the LEW’s opinion)
and taken on board irrelevant considerations (the fear that the Applicant would tenant her
Units to a pizza delivery).
57. Even if the Board is wrong with regard to the standard of review of the
Respondent’s conduct, the Board is of the view that Respondent’s refusal of the
Applicant’s request is regarded as unreasonable in that the Respondent’s conduct is
tainted by prejudice, malice and indifference (see Chia Sok Kheng Kathleen v MCST
Plan No 669 [2004] 4 SLR(R) 27 at [37]). This line of argument is based on section 111
of the BMSMA which provides that the Board has the jurisdiction to intervene if the
Management Corporation had unreasonably refused to consent to a proposal by that
subsidiary proprietor to effect alterations to the common property. As Kan Ting Chiu J
said in Chia Sok Kheng Kathleen v MCST Plan No 669 [2004] 4 SLR(R) 27 at [34]:
“When a management corporation receives an application affecting the common
property, it should exercise its discretion for the benefit of all the subsidiary proprietors.
That means that the interests of the applicant subsidiary proprietor as well as the
interests of the other subsidiary proprietors are to be taken into account. The discretion
should be exercised responsibly. Applications should be dealt with consistently without
favouritism or bias, but flexibility should be retained to take into account changing
circumstances. Policies adopted should not be regarded as edicts set in stone”.
58. Since the Applicant’s request to upgrade would affect some electrical switchboards
and cables which are common property, the proposal would fall within the ambit of
section 111 of the BMSMA. While the Board does not think that the Respondent acted
with prejudice and malice, the Respondent’s conduct may be characterized as being
indifferent. Since there is clear evidence that there was sufficient electricity supply, the
Respondent’s refusal to allow the Applicant to upgrade her electricity supply is regarded
as being indifferent in the face of objective evidence. Furthermore, a Management
Corporation’s decision is not regarded as properly exercised if it was actuated by
extraneous considerations (see Chia Sok Kheng Kathleen v MCST Plan No 669
12. BACK TO TOP
[2004] 4 SLR(R) 27 at [55]). In this regard, the Respondent’s refusal to allow the
Applicant to upgrade the electricity supply was partly motivated by extraneous
considerations i.e. the fear that she would tenant her Units to a pizza delivery business.
Conclusion
59. The Board recognises that all buildings are built to a specified design capacity.
However, some flexibility has to be afforded to take into account individual subsidiary
proprietor’s needs. The Board is mindful that these considerations have to be balanced
against the other subsidiary proprietors’ interests and the Board’s discretion has to be
exercised sensibly. Where the Management Corporation has concerns about the impact
that an applicant’s request might have on the other subsidiary proprietors, the
Management Corporation should also consider whether the passing of appropriate by-
laws might be an appropriate solution.
60. The Board should only interfere where the decision of a Management Corporation
is clearly improper and/or unreasonable. In the present case, the Board found that the
Respondent’s refusal of the Applicant’s request was improper and/or unreasonable. The
Applicant had purchased her Units with the intention of letting them out to tenants. Given
the consensus amongst the witnesses for both parties that there was in fact sufficient
spare electrical capacity to cater to the Applicant’s request, the Respondent had failed to
take this on board as a relevant consideration. Instead, the Respondent had taken into
account extraneous factors which are irrelevant in refusing her request.
61. In view of all of the above, the Board orders that:-
a. The Respondent permits the Applicant to upgrade the electricity supply of her
units to ‘3 phase 100 ampere’ ; and
b. The Board after hearing parties on costs orders the Respondent to pay the
Applicant cost fixed at $18,000.00 and disbursement to be agreed by parties.