The final facility design has been modified based on community feedback, with revised elevations and signage added. Three interpretive signs will provide information about the rain garden, CSO facility components and process, and how individuals can help reduce CSO events. The design will be submitted to the Department of Ecology by December 31st, and interpretive sign development will continue into next year. Construction is scheduled to begin in 2013, with the storage tank installation, facility building work, and utilities to be completed between 2013-2016.