Designing IA for AI - Information Architecture Conference 2024
Incorporating Energy Storage into PV System Design
1. EPRI/Sandia PV Systems Symposium, May 2016
Kevin Christy
Incorporating Energy Storage into
PV System Design
2. P. 2 | SunEdison Confidential
Overview
New & evolving segment
Interconnection issues
Retrofitting complications
Financing issues for storage
Operational issues for storage
3. P. 3 | SunEdison Confidential
Interconnection issues-new systems
If batteries are charged with DC
energy from the PV system,
then the BESS is “an
enhancement of the renewable
generator” and can export
If batteries are charged with AC
energy from the grid, then the
BESS is considered a non-NEM
device and cannot export
Specific interconnection
application guidelines must be
followed
SCE external memorandum
dated 7/22/13 Re: Battery-
Backed Storage System and
Net Metering Eligibility
4. P. 4 | SunEdison Confidential
Can only address one retrofit system with which I’m familiar:
• Existing NEM PV system in SCE territory
• Addition of non-export BESS after the fact
Required shared interconnect facility and approval &
cooperation of PV system owner and installer
Utility will need to be satisfied of non-export controls on BESS
Interconnection issues-retrofit
6. P. 6 | SunEdison Confidential
Foundational Issue: Joint Financeability
Will need to find financier willing to finance both solar and
storage at acceptable cost of capital
May need Joint Facilities Agreement where
equipment/agreements are shared (e.g., interconnection) to
allow solar to go to one financier and storage to go to another
A number of experienced solar financiers are expressing
interest in financing storage, but it is very early days for non-
recourse storage finance
7. P. 7 | SunEdison Confidential
Supplier Bankability
Battery & BMS provider
Bidirectional inverter provider
Integrator
Warranty provider
DCR/Fleet management software providers
Operator & Operations schemes
Line up your IE reports
8. P. 8 | SunEdison Confidential
Degradation of Li-ion Batteries
Note DC/AC conversion losses in battery kWh nameplate rating
Long-term financing question: how long will these last?
Predictable rate of degradation?
Can performance-based agreements be written to reflect
degradation?
Source: NREL, Predictive Models of Li-ion Battery Lifetime, Sept 2014
9. P. 9 | SunEdison Confidential
Methods of Managing Degradation Impacts
1. Oversize
• Chevy Volt depth of discharge “buffer” experience: 1st gen vs. 2nd
gen
• Expect stationary manufacturers to adopt this approach as costs
decrease & energy density increases
2. Capacity Maintenance
• Pay up front/over time for beefed up warranty
3. Underwrite to Expected Degradation
• PV experience:
̶ Straightline to 80% warranty, increased to 90%
̶ Observed degradation, tighter banding
• Would require suppliers to back linear warranties
• Over time, underwrite to experience vs. warranty
10. P. 10 | SunEdison Confidential
Independent Performance Estimates?
BESS systems have no industry-standard PVsyst equivalent—
this is a major hamstring to modeling & financing efficiency
11. P. 11 | SunEdison Confidential
Storage Modeling Efforts in Flight
NREL System Advisor Model
(SAM) PV + storage module
Flow battery module in
development
EPRI Energy Storage
Valuation Tool
StorageVET successor tool in
development for 2nd half 2016
release
Developed under guidance of
the Energy Storage
Integration Council (ESIC)
12. P. 12 | SunEdison Confidential
Key Parameters for Storage Performance Modeling
Ratio of DC/AC capacity (kWh-equivalent)
Round trip conversion efficiencies
Parasitic losses (HVAC, tare)
Depth-of-discharge limits
Operating temperature profiles
Cycle/year profile of application
Availability
For flow:
• Additional pump parasitic losses
• Electrolyte consumption
13. P. 13 | SunEdison Confidential
Contracted vs. Uncontracted Revenue
Only contracted revenue from creditworthy counterparties can
get the lowest cost of capital
Source: RMI
14. P. 14 | SunEdison Confidential
ITC Eligibility for BESS + PV
BESS eligible for ITC as long as the batteries are charged by
the solar energy (does not require direct DC coupling)
Proportional loss of ITC if up to 25% of the energy used to
charge the batteries comes from the grid
Cliff at 25%--anything more and you lose the ITC
Expect financiers to want solid guarantees that grid energy will
not be used to charge batteries
Note: Conclusions based on private letter rulings, final rules not formed and released.
15. P. 15 | SunEdison Confidential
O&M Issues for Solar + Storage
BESS maintenance is more time-sensitive:
• Brittle nature of demand charge management
• LDs associated with capacity/RA contracts
• Consider spares
• Consider response time commitments
Operations will be more hands on:
• Closer monitoring of battery status
• Faster resolution of comm outages
• Need to be able to respond to fleet dispatch orders under
capacity/RA or frequency regulation
May need backup providers:
• Software for DCR, fleet management
• Operations provider