SlideShare a Scribd company logo
1 of 28
Download to read offline
N YSE Am ex : UR G           TSX : UR E


                          Ur-Energy is an Advanced Pre-Production
                                   Junior Mining Company
                             Focused on development of low-cost
                             uranium production properties in the
                                        United States.

                                           Corporate Objectives:
                                           • Resource Growth
                                           • Strategic Opportunities




Corporate P resentation
PDAC M arch 2012
Disclaimer
This presentation contains “forward-looking statements,” within the meaning of applicable securities laws, regarding events or conditions that
may occur in the future. Such statements include without limitation the long term effects on the uranium market of events in Japan in 2011
including supply and demand projection; the Company’s timeframe for events leading to and culminating in the commencement of production at
Lost Creek; the technical and economic viability of the Lost Creek Project (including the projections contained in the preliminary economic
analysis of the Lost Creek Property); receipt of (and related timing of) Record of Decision from the U.S. Bureau of Land Management related to
the Lost Creek Property; the Lost Creek Project will advance to production and the production timeline; production rates, timetables at the Lost
Creek Project; the Company’s procurement and construction plans at the Lost Creek Project; the ability to complete additional favorable
uranium sales agreements; the potential of exploration targets on the LC North and LC South and on the Lost Creek Project area outside the
current Lost Creek resource area; and the further exploration, development and permitting of exploration projects including Lost Soldier, the
exploration properties in Nebraska and at Screech Lake. These statements are based on current expectations that, while considered reasonable
by management at this time, inherently involve a number of significant business, economic and competitive risks, uncertainties and
contingencies. Numerous factors could cause actual events to differ materially from those in the forward-looking statements. Factors that could
cause such differences, without limiting the generality of the following, include: risks inherent in exploration activities; volatility and sensitivity to
market prices for uranium; volatility and sensitivity to capital market fluctuations; the impact of exploration competition; the ability to raise funds
through private or public equity financings; imprecision in resource and reserve estimates; environmental and safety risks including increased
regulatory burdens; unexpected geological or hydrological conditions; a possible deterioration in political support for nuclear energy; changes in
government regulations and policies, including trade laws and policies; demand for nuclear power; weather and other natural phenomena; delays
in obtaining or failures to obtain required governmental, environmental or other project approvals; and other exploration, development, operating,
financial market and regulatory risks. Although Ur-Energy Inc. believes that the assumptions inherent in the forward-looking statements are
reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this presentation. Ur-Energy Inc.
disclaims any intention or obligation to update or revise any forward-looking statement, whether as a result of new information, future events or
otherwise.

Cautionary Note Regarding Projections: Similarly, this presentation also may contain projections relating to an extended future period and,
accordingly, the estimates and assumptions underlying the projections are inherently highly uncertain, based on events that have not taken
place, and are subject to significant economic, financial, regulatory, competitive and other uncertainties and contingencies beyond the control of
Ur-Energy Inc. Further, given the nature of the Company's business and industry that is subject to a number of significant risk factors, there can
be no assurance that the projections can be or will be realized. It is probable that the actual results and outcomes will differ, possibly materially,
from those projected.

The attention of investors is drawn to the Risk Factors set out in the Company's Annual Information Form and Annual Report on Form 40-F,
dated March 17, 2011, which are filed, respectively, with the regulatory authorities in Canada on SEDAR and with the U.S. Securities and
Exchange Commission on EDGAR. (www.sedar.com and http://www.sec.gov/edgar.shtml)

Cautionary Note to U.S. Investors Concerning Estimates of Measured, Indicated or Inferred Resources: the information presented uses
the terms "measured", "indicated" and "inferred" mineral resources. United States investors are advised that while such terms are recognized
and required by Canadian regulations, the United States Securities and Exchange Commission does not recognize these terms. United States
investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral
reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically
or legally minable.

John Cooper, SME Registered Member, a Professional Geologist, and Qualified Person as defined by National Instrument 43-101,
reviewed the technical information contained in this presentation.



                                                                          2                  N YSE Am ex : UR G                          TSX : UR E
Ur-Energy At A Glance

   Advanced Pre-Production Project at Lost Creek, Wyoming
          One approval remaining
          Construction anticipated to commence this summer

   Low-Cost Uranium Production Center that will be Cash-Flow
   Positive in Current Market

   Expanding Resources through Acquisition and Exploration

   Low Technical, Political and Regulatory Risk Strategy



See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                         3   N YSE Am ex : UR G   TSX : UR E
Ur-Energy’s Market Position
Share Capital & Cash Position
                                                                              NYSE Amex: URG
As of 10/24/11
Shares Outstanding                                    103.7M
Stock Options & RSUs                                    6.5M
Fully Diluted                                         110.2M
Market Cap (03/01/12)                             C$121.3M
Cash (09/30/11)                                     C$28.8M
Financing (2/23/12)                                 C$17.25M
Debt                                                  $0

Cash per share (09/30/11)   ~C$0.30
Share price (03/01/12)        C$1.17
52 Week Range           C$.79 - $2.65                                         TSX: URE
Avg. Daily Volume           ~624,000
(3-mo URG & URE 03/01/12)
Member of Russell 3000 & 2000 and S&P/TSX SmallCap Indexes


Geographical Distribution                          as of 6/30/11

United States                   ~48%
Canada                          ~38%
Other                           ~14%
 See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                                                          4         N YSE Am ex : UR G   TSX : UR E
Analyst Coverage

United States
GVC Capital                             Mike Shonstrom (Denver, CO)                       1 303-321-2392
Rodman & Renshaw                        Wayne Atwell (New York, NY)                       1 212-356-0513

Canada
Dundee Securities                       David A. Talbot (Toronto, ON)                     1   416-350-3082
Haywood Securities                      Geordie Mark (Vancouver, BC)                      1   604-697-6112
Raymond James                                                                             1   604-659-8282
RBC Capital                             Adam Schatzker (Toronto, ON)                      1   416-842-7850

Australia
Resource Capital Research               Trent Allen (Sydney, NSW)                         61 2-9252-9405




Ur-Energy Inc. is followed by the analysts listed above. This list, including the firms and individual analysts at these firms,
is subject to change at any time without notice. Please note that any opinions, estimates, forecasts, conclusions or
recommendations regarding Ur-Energy Inc.'s performance made by these analysts are theirs alone and do not represent
opinions, estimates, forecasts, conclusions, recommendations or predictions of Ur-Energy Inc or its management. Ur-
Energy Inc. does not by its reference above or in any other manner imply its endorsement of or concurrence with such
information, conclusions or recommendations.




                                                         5                N YSE Am ex : UR G                     TSX : UR E
The US Uranium Market
     The US produces ~ 4M lbs of uranium/yr1
     The US consumes 55M lbs of uranium/yr1 contributing 20% of US electricity
     October 2011 Nuclear Energy Institute survey shows two-thirds of Americans
     support nuclear energy
     Ur-Energy is well positioned to capitalize on this opportunity




                                                        Chart from U.S . Energy Information Administration
1 – U.S. Energy Information Administration

See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                           6                   N YSE Am ex : UR G   TSX : UR E
Post-Fukushima Nuclear Remains Positive*

        U.S. NRC issued two Construction and Operation Licenses in Feb 2012
           First nuclear power plant licenses in 30+ years

        HEU Agreement to expire next year
          Provides 13% of world and 45% of US annual supply

        96 new reactors are expected to go online worldwide by 2021
           Even half of this growth represents a large growth potential

        Russia, China and India represent 50% of new builds and have
        reaffirmed support for nuclear power
           Last week, India announced plans for 20 new reactors by 2032

        Saudi Arabia & the United Kingdom have announced plans to build 24
        new reactors combined


  *According to World Nuclear Association

  See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                                                           7   N YSE Am ex : UR G   TSX : UR E
Growth of Nuclear Will Continue
                     Historically, growth of nuclear power continued despite major accidents
                     Growth expected to continue beyond Fukushima at 10 reactors per year
                                                                                                                  10 years, 10.2
                                                                                                                  reactors per
                                                                                                                  year
Number of Reactors




                                                                              22 years, 4
                                                                              reactors per
                                                                              year



                                                  8 years, 21.9
                                                  reactors per
                                                  year

                                                                                             Fukushima
                              13 years,
                              11.3reactors                         Chernobyl
                              per year
                                                          Three Mile Island




                     Source: W orld Nuclear Association                        See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                                                       8              N YSE Am ex : UR G                           TSX : UR E
Global Supply/Demand Imbalance
  How will supply be able to expand to the extent necessary to meet growing demand
  levels in the post-Fukushima environment of uncertainty and low prices?

          More damage done to uranium supply than uranium demand
          Deliveries from the HEU Agreement end next year




Source: UxC Uranium M arket Outlook                See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                            9             N YSE Am ex : UR G                           TSX : UR E
Experienced Management Team
                                     Board of Directors

                                        Ex ecutive Directors
      Wayne W. Heili, President & Chief Executive Officer (Metallurgical Engineer)
      Jeffrey T. Klenda*, Board Chairman, Executive Director (Mining Finance)

                                    Non-Ex ecutive Directors
      W. William Boberg*, Former President & CEO (Professional Geologist)
      James M. Franklin*, Chair-Technical Committee (Professional Geologist)
      Paul Macdonell*, Chair-Compensation and Corp. Governance & Nominating Committees
                       (Senior Federal Mediator)
      Thomas H. Parker, Chair-Audit Committee (Professional Engineer)

                                                Officers
      Roger L. Smith, Chief Financial Officer & Chief Administrative Officer(CPA & MBA)
      Steven M. Hatten, VP Operations (Petroleum Engineer)
      John W. Cash, VP Regulatory Affairs, Exploration & Geology (Geologist & Geophysicist)
      Penne A. Goplerud, Corporate Secretary & General Counsel (JD)

* Founding Directors




                                               10             N YSE Am ex : UR G              TSX : UR E
Industry Leading Team
Highly Experienced Technical and Management
Professionals

98 Years of Direct Uranium Production Experience
  ISR operations experience – Nebraska, Texas & Wyoming




                            11        N YSE Am ex : UR G   TSX : UR E
ISR – Low Impact Mining




     CAMECO Smith Ranch ISR Mine
      Powder River Basin, Wyoming


                 12       N YSE Am ex : UR G   TSX : UR E
In-Situ Recovery (ISR) Uranium Mining




                           Environmentally sound production method
                           Well understood by Wyoming state regulators
                           Cost effective, low capital costs
See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                                                         13   N YSE Am ex : UR G   TSX : UR E
Ur-Energy’s Wyoming Projects




             14   N YSE Am ex : UR G   TSX : UR E
The Lost Creek Property
NI 43-101 Resource from Prelim inary Econom ic
Assessm ent of the Lost Creek Property, Sw eetw ater
County, W yom ing (February 29, 2012) (posted on SEDAR                      These exploration targets are conceptual in nature. There has been
and EDGAR )                                                                 insufficient exploration to define a mineral resource outside the
                                                                            current Lost Creek resource. It is uncertain if further exploration
                                                                            will result in the new target areas outside the Lost Creek resource
Measured – 2.9 Mlbs eU3O8 (in 2.69 Mt @ 0.055%)                             being delineated as a mineral resource.
Indicated – 2.8 Mlbs eU3O8 (in 2.4 Mt @ 0.058% )
Inferred – 2.0 Mlbs eU3O8 (in 2.06 Mt @0.052% )
* Based on grade cutoff of 0.02 percent eU3O8 and a grade x
thickness cutoff of 0.3 GT.

 Exploration targets within the Lost
 Creek Project and adjoining projects
 provide potential of additional
 resources U3O8
 Lost Creek Project – 4,254 acres
 Adjoining Projects – 39,300 acres


                                                                      Many of these exploration targets remain conceptual in nature. There has been
  See Disclaimer re Forward-looking Statements and Projections        insufficient exploration to define mineral resource estimates at all such
                                                                      exploration targets. It is uncertain if further exploration will result in the
  (slide 2)
                                                                      additional target areas being delineated as further mineral resource.


                                                                 15                N YSE Am ex : UR G                             TSX : UR E
Lost Creek

Adjacent to Rio Tinto Sweetwater Mine/Complex
 (NRC Licensed Conventional Uranium Mill on Standby)




                                                                     JK


                                             NYSE Amex: URG   TSX: URE
Preliminary Economic Assessment
       2012 PEA* Upgrades Resources, Confirms Economics
              Mineral Resource Increase from 2011 PA
                       11% Increase in Measured and Indicated Resources
                       159% Increase in Inferred Resources (includes first resource
                        estimate at each of LC North and LC South)

              Estimates Operating Costs less than US$20/ lb
                       Lowest Quartile of all Uranium Producers

              Estimates Total P roduction Cost at US$42.65/ lb
                       Includes capital recovery

              Project Internal Rate of Return (I RR ) at 91%
              Pre-Production Capital Costs of Only US$35M Rem aining
                       Lowest Quartile of all developing uranium production facilities
                       Total project Capital Cost of US$59M
  Cautionary Statement: This PEA is preliminary in nature, and includes inferred mineral resources that are considered too speculative geologically to have the
  economic considerations applied to them that would enable them to be categorized as mineral reserves. The estimated mineral recovery used in this PA is
  based on both site-specific laboratory recovery data as well as URE personnel and industry experience at similar facilities. There can be no assurance that
  recovery at this level will be achieved.
                                                                                   * N I 43-101 P relim inary Econom ic Assessm ent of the Lost Creek
 See Disclaimer re Forward-looking Statements and Projections (slide 2)            P roperty, Sw eetw ater County W yom ing – (February 29, 2012)
                                                                                   (posted on SEDAR and EDGAR )

                                                                              17                    N YSE Am ex : UR G                            TSX : UR E
US$24M in CapEx Completed
 Mine Units 1 & 2 Delineated
     MU #1 Monitor Well Ring Completed

 Plant Engineering Completed

 Drilled and Tested Class I UIC
 Well

 Ordered Key Plant Equipment              Ur-Energy’s Ion Exchange Columns

     Ion Exchange Columns
     Elution Columns
     Filter Presses

 Design/Build of Header House
 Building



                                           Interior of Ur-Energy’s Prototype Header House

                                18       N YSE Am ex : UR G                TSX : UR E
Lost Creek Path to Production
 Site Permitting Started in 2006
 Licenses and Permits Received
    US NRC License
    Wyoming DEQ Permit to Mine – Includes Approval of First Mine Unit
    WDEQ Class I UIC Permit (water disposal well)
    EPA Aquifer Exemption

 One Remaining Regulatory Approval Needed
    US Bureau of Land Management Plan of Operations
    Environmental review process underway
    Record of Decision anticipated early summer 2012

 Construction
    6 – 9 month build-out

 First Production
    Planned for second quarter next year
                                       See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                 19            N YSE Am ex : UR G                           TSX : UR E
February 2012 Property Acquisition

   Expansion of the resource base for
   processing facility at Lost Creek
    Asset Exchange: No Cash Cost.
   Ur-Energy possesses ~1,000 holes of
   historic drill data
   Properties directly adjacent with Lost
   Creek Project boundaries
      Two WY state mineral leases
      175 federal mining claims
      Approx 5,250 acres

   Expect updated PEA incorporating new acquisition

See Disclaimer re Forward-looking Statements and Projections (slide 2)




                                                                         20   N YSE Am ex : UR G   TSX : UR E
Lost Soldier – 12.2M M&I lbs U3O8
     Can be licensed with NRC as
     amendment to Lost Creek
     license
    M & I resource average
    17.2 ft @ 0.065% U3O8
     Average 240 feet deep
     Leach efficiency 49% - 84%

 Over 3700 drill holes define deposit
 17 monitor/pump test wells installed

                                                                                   (From Figure 16-2, Technical Report on the Lost Soldier Project, Wyoming, C.
                                                                                   Stewart Wallis, RPA, July 10, 2006 - posted on SEDAR)

 NI 43-101 Compliant Resource
 Measured & Indicated (M & I) – 12.2 Mlbs U3O8 (in 9.4 Mt @ 0.065% )
 Inferred – 1.8 Mlbs U3O8 (in1.6 Mt @0.055% )
  (Technical Report on the Lost Soldier Project, Wyoming, C. Stewart Wallis, Roscoe Postle Associates Inc., July 10, 2006 - Posted on SEDAR)

  See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                              21                     N YSE Am ex : UR G                             TSX : UR E
Screech Lake, Thelon Basin, NWT
         Completed Audio-Magnetotelluric Geophysical Survey,
         and Soil Gas Hydrocarbon and Enzyme Leach Soil
         Geochemistry Analyses to Better Define Drill Targets

                                                                                 MegaTEM Survey




      Screech
       Lake



 See Disclaimer re Forward-looking Statements and Projections (slide 2)              0            4
                                                                                         Kilometers
                                                                          22   N YSE Am ex : UR G     TSX : UR E
Sound Marketing Strategy
Balancing strategic and
economic benefits of the
spot/term ratio
De-risking by securing future
revenue stream in an uncertain
market
Securing pricing that supports
development plans for the Lost
Creek Project
Targeting contracts with North American utilities
Exclusive representation by NuCore Energy, LLC in off-take
purchase agreement negotiations

                           23      N YSE Am ex : UR G   TSX : UR E
Ur-Energy’s Strong Position
       Advanced Development at Lost Creek
             Permitting Process Nearing Completion

       Low Cost Production Will Equal Strong Cash Flow
             ~US$20/lb direct operating cost
             Uranium Term Market is above $60/lb

       Sound Uranium Marketing Strategy with Multiple Long-
       Term Sales Agreements in Place
       Experienced Technical & Managerial Team
       Strong Balance Sheet
              C$28.8 Million (9/30/12)
             C$17.25 Million Financing Completed in 2012
See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                         24   N YSE Am ex : UR G   TSX : UR E
Future Growth Opportunities
     Resource Expansion through ongoing exploration and
     acquisition efforts
           Increase Minable Resources that will be Accessible to the Lost
           Creek Processing Plant

     Growth in the Production Profile
           Development of Currently Held Properties
           Acquisitions of New Properties
           Strategic Alliances

     Exploration Properties in Western Nebraska

     Monetizing Historic Databases

See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                         25   N YSE Am ex : UR G   TSX : UR E
Re-Rating Potential
                                  Stage                                      EV/Lb

URG Upside vs. Producers          Producers                                    $4.60
    3X (+$3.13/Lb)               Developer
                                   URG                                         $1.47
                                           Source: Dundee (February 29, 2012)




                                      As Ur-Energy
                                    Nears Production,
                                    Re-rating is Likely

                           See Disclaimer re Forward-looking Statements and Projections (slide 2)



                     26                 N YSE Am ex : UR G                           TSX : UR E
Ur-Energy – Right Now!
      Technical, Political and Regulatory Certainty

      Advanced Pre-Production Project at Lost Creek
             Low-Cost Uranium Production Center that will be Cash-Flow
             Positive in Today’s Market
             Plant Construction Planned to Begin Summer 2012
             Ramping up to Production Rate of 1M lbs/year

      Signed Multiple Long Term Uranium Sales Agreements
             De-Risking Company Exposure to Volatile Marketplace

      Re-Rating Likely as Ur-Energy Nears Production


See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                         27   N YSE Am ex : UR G   TSX : UR E
Ur-Energy - The Right People. The Right Projects. Right Now.
     For more information, please contact:
       Wayne Heili, President, Chief Executive Officer & Director
       Jeff Klenda, Board Chairman & Director
       Rich Boberg, Director of Public Relations


     By Mail:            Ur-Energy Corporate Office
                          10758 W. Centennial Rd., Ste. 200
                          Littleton, CO 80127 USA

     By Phone:           Office (720) 981-4588
                          Toll-Free (866) 981-4588
                          Fax (720) 981-5643

     By E-mail:          wayne.heili@ur-energyusa.com
                          jeff.klenda@ur-energyusa.com
                          rich.boberg@ur-energyusa.com




                                       28         NYSE Amex:: URG
                                                  N YSE Am ex UR G   TSX::URE
                                                                     TSX UR E

More Related Content

What's hot

Ure corporate presentation final (final) 20140301
Ure corporate presentation final (final) 20140301Ure corporate presentation final (final) 20140301
Ure corporate presentation final (final) 20140301Urenergy
 
Goldmoney Investor Relations Presentation February 2020
Goldmoney Investor Relations Presentation February 2020Goldmoney Investor Relations Presentation February 2020
Goldmoney Investor Relations Presentation February 2020Goldmoney Inc.
 
TCM Investor Presentation Nov 2013
TCM Investor Presentation Nov 2013TCM Investor Presentation Nov 2013
TCM Investor Presentation Nov 2013Adnet Communications
 
Lion One Presenation April 2016
Lion One Presenation April 2016Lion One Presenation April 2016
Lion One Presenation April 2016Lion One Metals
 
Lion One Metals Presentation Oct 2018
Lion One Metals Presentation Oct 2018Lion One Metals Presentation Oct 2018
Lion One Metals Presentation Oct 2018Joe Gray
 

What's hot (20)

20120808 ure corporate presentation (august 2012 final)
20120808 ure corporate presentation  (august 2012 final)20120808 ure corporate presentation  (august 2012 final)
20120808 ure corporate presentation (august 2012 final)
 
July 2012 Corporate Presentation
July 2012 Corporate PresentationJuly 2012 Corporate Presentation
July 2012 Corporate Presentation
 
Ur-Energy January 2013 Corporate Presentation
Ur-Energy January 2013 Corporate PresentationUr-Energy January 2013 Corporate Presentation
Ur-Energy January 2013 Corporate Presentation
 
Ur-Energy January 2013 Corporate Presentation
Ur-Energy January 2013 Corporate PresentationUr-Energy January 2013 Corporate Presentation
Ur-Energy January 2013 Corporate Presentation
 
Ur-Energy February 2013 Corporate Presentation
Ur-Energy February 2013 Corporate PresentationUr-Energy February 2013 Corporate Presentation
Ur-Energy February 2013 Corporate Presentation
 
Ur-Energy March 2013 Corporate Presentation
Ur-Energy March 2013 Corporate PresentationUr-Energy March 2013 Corporate Presentation
Ur-Energy March 2013 Corporate Presentation
 
November 2012 Ur-Energy Corporate Presentation
November 2012 Ur-Energy Corporate PresentationNovember 2012 Ur-Energy Corporate Presentation
November 2012 Ur-Energy Corporate Presentation
 
20110207 ure corporate presentation (february 2011)
20110207 ure corporate presentation (february 2011)20110207 ure corporate presentation (february 2011)
20110207 ure corporate presentation (february 2011)
 
20110225 ure corporate presentation (february 2011)
20110225 ure corporate presentation (february 2011)20110225 ure corporate presentation (february 2011)
20110225 ure corporate presentation (february 2011)
 
Ur-Energy December 2012 Presentation
Ur-Energy December 2012 PresentationUr-Energy December 2012 Presentation
Ur-Energy December 2012 Presentation
 
Ur-Energy March 2013 Corporate Presentation
Ur-Energy March 2013 Corporate PresentationUr-Energy March 2013 Corporate Presentation
Ur-Energy March 2013 Corporate Presentation
 
20121005 ure corporate presentation (october 2012 final)
20121005 ure corporate presentation  (october 2012 final)20121005 ure corporate presentation  (october 2012 final)
20121005 ure corporate presentation (october 2012 final)
 
20110310 ure corporate presentation (march 2011)
20110310 ure corporate presentation (march 2011)20110310 ure corporate presentation (march 2011)
20110310 ure corporate presentation (march 2011)
 
20110207 ure corporate presentation (february 2011)
20110207 ure corporate presentation (february 2011)20110207 ure corporate presentation (february 2011)
20110207 ure corporate presentation (february 2011)
 
20110203 ure corporate presentation (february 2011)
20110203 ure corporate presentation (february 2011)20110203 ure corporate presentation (february 2011)
20110203 ure corporate presentation (february 2011)
 
Ure corporate presentation final (final) 20140301
Ure corporate presentation final (final) 20140301Ure corporate presentation final (final) 20140301
Ure corporate presentation final (final) 20140301
 
Goldmoney Investor Relations Presentation February 2020
Goldmoney Investor Relations Presentation February 2020Goldmoney Investor Relations Presentation February 2020
Goldmoney Investor Relations Presentation February 2020
 
TCM Investor Presentation Nov 2013
TCM Investor Presentation Nov 2013TCM Investor Presentation Nov 2013
TCM Investor Presentation Nov 2013
 
Lion One Presenation April 2016
Lion One Presenation April 2016Lion One Presenation April 2016
Lion One Presenation April 2016
 
Lion One Metals Presentation Oct 2018
Lion One Metals Presentation Oct 2018Lion One Metals Presentation Oct 2018
Lion One Metals Presentation Oct 2018
 

Viewers also liked

CAS2012 Analytics 1 - SEOmom
CAS2012 Analytics 1 - SEOmomCAS2012 Analytics 1 - SEOmom
CAS2012 Analytics 1 - SEOmomGillian Muessig
 
Boston Library Consortium (BLC) annual meeting keynote 2007-04-12
Boston Library Consortium (BLC) annual meeting keynote 2007-04-12Boston Library Consortium (BLC) annual meeting keynote 2007-04-12
Boston Library Consortium (BLC) annual meeting keynote 2007-04-12Casey Bisson
 
Grafos 8.1 2016
Grafos 8.1 2016Grafos 8.1 2016
Grafos 8.1 2016ead1943
 
Internship fair workshop dfw
Internship fair workshop dfwInternship fair workshop dfw
Internship fair workshop dfwNathan Green
 
58638 01
58638 0158638 01
58638 01icenemo
 
The Here-Now Generation
The Here-Now GenerationThe Here-Now Generation
The Here-Now GenerationEdo van Dijk
 
2012 02 OMS san diego - community development workshop
2012 02 OMS san diego - community development workshop2012 02 OMS san diego - community development workshop
2012 02 OMS san diego - community development workshopGillian Muessig
 
Docker San Diego 2015-03-25
Docker San Diego 2015-03-25Docker San Diego 2015-03-25
Docker San Diego 2015-03-25Casey Bisson
 
The Counter Pop Evolution, English Corregido
The Counter Pop Evolution, English CorregidoThe Counter Pop Evolution, English Corregido
The Counter Pop Evolution, English CorregidoIsis Rodriguez
 
Vinci2011会议演讲PPT
Vinci2011会议演讲PPTVinci2011会议演讲PPT
Vinci2011会议演讲PPTdasiyjun
 
פורום סמנכלי משא מצגת נילי כאוס
פורום סמנכלי משא  מצגת נילי כאוספורום סמנכלי משא  מצגת נילי כאוס
פורום סמנכלי משא מצגת נילי כאוסVPHR
 
Linkedin for Business & Personal Branding
Linkedin for Business & Personal BrandingLinkedin for Business & Personal Branding
Linkedin for Business & Personal BrandingBWEST Interactive
 
2012 01 imj summit ahmedabad what are they thinking?
2012 01 imj summit ahmedabad what are they thinking?2012 01 imj summit ahmedabad what are they thinking?
2012 01 imj summit ahmedabad what are they thinking?Gillian Muessig
 
Nielsen social-media-report
Nielsen social-media-reportNielsen social-media-report
Nielsen social-media-reportIAB México
 
The Rule of 5 in Sales Presenting
The Rule of 5 in Sales PresentingThe Rule of 5 in Sales Presenting
The Rule of 5 in Sales PresentingMartin Dale
 
Getting rid of plastic bags in Singapore
Getting rid of plastic bags in SingaporeGetting rid of plastic bags in Singapore
Getting rid of plastic bags in SingaporeEdo van Dijk
 

Viewers also liked (20)

CAS2012 Analytics 1 - SEOmom
CAS2012 Analytics 1 - SEOmomCAS2012 Analytics 1 - SEOmom
CAS2012 Analytics 1 - SEOmom
 
Boston Library Consortium (BLC) annual meeting keynote 2007-04-12
Boston Library Consortium (BLC) annual meeting keynote 2007-04-12Boston Library Consortium (BLC) annual meeting keynote 2007-04-12
Boston Library Consortium (BLC) annual meeting keynote 2007-04-12
 
August 2012 Ur-Energy Corporate Presentation
August 2012 Ur-Energy Corporate PresentationAugust 2012 Ur-Energy Corporate Presentation
August 2012 Ur-Energy Corporate Presentation
 
Grafos 8.1 2016
Grafos 8.1 2016Grafos 8.1 2016
Grafos 8.1 2016
 
Internship fair workshop dfw
Internship fair workshop dfwInternship fair workshop dfw
Internship fair workshop dfw
 
58638 01
58638 0158638 01
58638 01
 
Ucc Tunnes
Ucc TunnesUcc Tunnes
Ucc Tunnes
 
The Here-Now Generation
The Here-Now GenerationThe Here-Now Generation
The Here-Now Generation
 
Kellett Yellowknife Sept-24
Kellett Yellowknife Sept-24Kellett Yellowknife Sept-24
Kellett Yellowknife Sept-24
 
2012 02 OMS san diego - community development workshop
2012 02 OMS san diego - community development workshop2012 02 OMS san diego - community development workshop
2012 02 OMS san diego - community development workshop
 
Docker San Diego 2015-03-25
Docker San Diego 2015-03-25Docker San Diego 2015-03-25
Docker San Diego 2015-03-25
 
The Counter Pop Evolution, English Corregido
The Counter Pop Evolution, English CorregidoThe Counter Pop Evolution, English Corregido
The Counter Pop Evolution, English Corregido
 
777
777777
777
 
Vinci2011会议演讲PPT
Vinci2011会议演讲PPTVinci2011会议演讲PPT
Vinci2011会议演讲PPT
 
פורום סמנכלי משא מצגת נילי כאוס
פורום סמנכלי משא  מצגת נילי כאוספורום סמנכלי משא  מצגת נילי כאוס
פורום סמנכלי משא מצגת נילי כאוס
 
Linkedin for Business & Personal Branding
Linkedin for Business & Personal BrandingLinkedin for Business & Personal Branding
Linkedin for Business & Personal Branding
 
2012 01 imj summit ahmedabad what are they thinking?
2012 01 imj summit ahmedabad what are they thinking?2012 01 imj summit ahmedabad what are they thinking?
2012 01 imj summit ahmedabad what are they thinking?
 
Nielsen social-media-report
Nielsen social-media-reportNielsen social-media-report
Nielsen social-media-report
 
The Rule of 5 in Sales Presenting
The Rule of 5 in Sales PresentingThe Rule of 5 in Sales Presenting
The Rule of 5 in Sales Presenting
 
Getting rid of plastic bags in Singapore
Getting rid of plastic bags in SingaporeGetting rid of plastic bags in Singapore
Getting rid of plastic bags in Singapore
 

Similar to March 2012 PDAC Corporate Presentation

August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)Rich Boberg, SHRM-SCP, SPHR, PHRca
 
Ure corporate presentation 20140815 (final)
Ure corporate presentation 20140815 (final)Ure corporate presentation 20140815 (final)
Ure corporate presentation 20140815 (final)Urenergy
 

Similar to March 2012 PDAC Corporate Presentation (14)

Ur-Energy April 2012 Corporate Presentation
Ur-Energy April 2012 Corporate PresentationUr-Energy April 2012 Corporate Presentation
Ur-Energy April 2012 Corporate Presentation
 
September 2011 Ur-Energy Corporate Presentation
September 2011 Ur-Energy Corporate PresentationSeptember 2011 Ur-Energy Corporate Presentation
September 2011 Ur-Energy Corporate Presentation
 
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
 
Ur-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate PresentationUr-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate Presentation
 
Ur-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate PresentationUr-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate Presentation
 
Ur-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate PresentationUr-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate Presentation
 
20110322 ure corporate presentation (march 2011 webcast)
20110322 ure corporate presentation (march 2011 webcast)20110322 ure corporate presentation (march 2011 webcast)
20110322 ure corporate presentation (march 2011 webcast)
 
20110506 ure corporate presentation (may 2011)
20110506 ure corporate presentation (may 2011)20110506 ure corporate presentation (may 2011)
20110506 ure corporate presentation (may 2011)
 
20110602 ure corporate presentation (june 2011)
20110602 ure corporate presentation (june 2011)20110602 ure corporate presentation (june 2011)
20110602 ure corporate presentation (june 2011)
 
Ur-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate PresentationUr-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate Presentation
 
20110118 ure corporate presentation (january 18 2011)
20110118 ure corporate presentation (january 18 2011)20110118 ure corporate presentation (january 18 2011)
20110118 ure corporate presentation (january 18 2011)
 
20110406 ure corporate presentation (april 2011)
20110406 ure corporate presentation (april 2011)20110406 ure corporate presentation (april 2011)
20110406 ure corporate presentation (april 2011)
 
Ur-Energy October 12, 2012 Webcast Presentation
Ur-Energy October 12, 2012 Webcast PresentationUr-Energy October 12, 2012 Webcast Presentation
Ur-Energy October 12, 2012 Webcast Presentation
 
Ure corporate presentation 20140815 (final)
Ure corporate presentation 20140815 (final)Ure corporate presentation 20140815 (final)
Ure corporate presentation 20140815 (final)
 

More from Rich Boberg, SHRM-SCP, SPHR, PHRca

More from Rich Boberg, SHRM-SCP, SPHR, PHRca (20)

Ur-Energy March 2016 Corporate Presentation
Ur-Energy March 2016 Corporate PresentationUr-Energy March 2016 Corporate Presentation
Ur-Energy March 2016 Corporate Presentation
 
Ur-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and TeleconferenceUr-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and Teleconference
 
Ur-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and TeleconferenceUr-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and Teleconference
 
Ur-Energy February 2016 Corporate Presentation
Ur-Energy February 2016 Corporate PresentationUr-Energy February 2016 Corporate Presentation
Ur-Energy February 2016 Corporate Presentation
 
Ur-Energy January 2016 Corporate Presentation
Ur-Energy January 2016 Corporate PresentationUr-Energy January 2016 Corporate Presentation
Ur-Energy January 2016 Corporate Presentation
 
Ur-Energy December 2015 Corporate Presentation
Ur-Energy December 2015 Corporate PresentationUr-Energy December 2015 Corporate Presentation
Ur-Energy December 2015 Corporate Presentation
 
Ur-Energy November 2015 Corporate Presentation
Ur-Energy November 2015 Corporate PresentationUr-Energy November 2015 Corporate Presentation
Ur-Energy November 2015 Corporate Presentation
 
Ur-Energy 2015 Third Quarter Webcast and Teleconference
Ur-Energy 2015 Third Quarter Webcast and TeleconferenceUr-Energy 2015 Third Quarter Webcast and Teleconference
Ur-Energy 2015 Third Quarter Webcast and Teleconference
 
Ur-Energy October 2015 Corporate Presentation
Ur-Energy October 2015 Corporate PresentationUr-Energy October 2015 Corporate Presentation
Ur-Energy October 2015 Corporate Presentation
 
Ur-Energy September 2015 Corporate Presentation
Ur-Energy September 2015 Corporate PresentationUr-Energy September 2015 Corporate Presentation
Ur-Energy September 2015 Corporate Presentation
 
Ur-Energy 2015 2Q Webcast and Teleconference Presentation
Ur-Energy 2015 2Q Webcast and Teleconference PresentationUr-Energy 2015 2Q Webcast and Teleconference Presentation
Ur-Energy 2015 2Q Webcast and Teleconference Presentation
 
Ur-Energy August 2015 Corporate Presentation
Ur-Energy August 2015 Corporate PresentationUr-Energy August 2015 Corporate Presentation
Ur-Energy August 2015 Corporate Presentation
 
Ur-Energy August 2015 Corporate Presentation
Ur-Energy August 2015 Corporate PresentationUr-Energy August 2015 Corporate Presentation
Ur-Energy August 2015 Corporate Presentation
 
Ur-Energy Second Quarter 2015 Teleconference and Webcast
Ur-Energy Second Quarter 2015 Teleconference and WebcastUr-Energy Second Quarter 2015 Teleconference and Webcast
Ur-Energy Second Quarter 2015 Teleconference and Webcast
 
June 2015 Corporate Presentation
June 2015 Corporate PresentationJune 2015 Corporate Presentation
June 2015 Corporate Presentation
 
Ur-Energy October 2013 Corporate Presentation
Ur-Energy October 2013 Corporate PresentationUr-Energy October 2013 Corporate Presentation
Ur-Energy October 2013 Corporate Presentation
 
Ur-Energy September 2013 Corporate Presentation
Ur-Energy September 2013 Corporate PresentationUr-Energy September 2013 Corporate Presentation
Ur-Energy September 2013 Corporate Presentation
 
Ur-Energy July 2013 Corporate Presentation
Ur-Energy July 2013 Corporate PresentationUr-Energy July 2013 Corporate Presentation
Ur-Energy July 2013 Corporate Presentation
 
Ur-Energy June 2013 Corporate Presentation
Ur-Energy June 2013 Corporate PresentationUr-Energy June 2013 Corporate Presentation
Ur-Energy June 2013 Corporate Presentation
 
Ur-Energy May 2013 Corporate Presentation
Ur-Energy May 2013 Corporate PresentationUr-Energy May 2013 Corporate Presentation
Ur-Energy May 2013 Corporate Presentation
 

Recently uploaded

Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityWSO2
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistandanishmna97
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...apidays
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...apidays
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusZilliz
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsNanddeep Nachan
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native ApplicationsWSO2
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Victor Rentea
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxRemote DBA Services
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfOrbitshub
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontologyjohnbeverley2021
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MIND CTI
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 

Recently uploaded (20)

Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 

March 2012 PDAC Corporate Presentation

  • 1. N YSE Am ex : UR G TSX : UR E Ur-Energy is an Advanced Pre-Production Junior Mining Company Focused on development of low-cost uranium production properties in the United States. Corporate Objectives: • Resource Growth • Strategic Opportunities Corporate P resentation PDAC M arch 2012
  • 2. Disclaimer This presentation contains “forward-looking statements,” within the meaning of applicable securities laws, regarding events or conditions that may occur in the future. Such statements include without limitation the long term effects on the uranium market of events in Japan in 2011 including supply and demand projection; the Company’s timeframe for events leading to and culminating in the commencement of production at Lost Creek; the technical and economic viability of the Lost Creek Project (including the projections contained in the preliminary economic analysis of the Lost Creek Property); receipt of (and related timing of) Record of Decision from the U.S. Bureau of Land Management related to the Lost Creek Property; the Lost Creek Project will advance to production and the production timeline; production rates, timetables at the Lost Creek Project; the Company’s procurement and construction plans at the Lost Creek Project; the ability to complete additional favorable uranium sales agreements; the potential of exploration targets on the LC North and LC South and on the Lost Creek Project area outside the current Lost Creek resource area; and the further exploration, development and permitting of exploration projects including Lost Soldier, the exploration properties in Nebraska and at Screech Lake. These statements are based on current expectations that, while considered reasonable by management at this time, inherently involve a number of significant business, economic and competitive risks, uncertainties and contingencies. Numerous factors could cause actual events to differ materially from those in the forward-looking statements. Factors that could cause such differences, without limiting the generality of the following, include: risks inherent in exploration activities; volatility and sensitivity to market prices for uranium; volatility and sensitivity to capital market fluctuations; the impact of exploration competition; the ability to raise funds through private or public equity financings; imprecision in resource and reserve estimates; environmental and safety risks including increased regulatory burdens; unexpected geological or hydrological conditions; a possible deterioration in political support for nuclear energy; changes in government regulations and policies, including trade laws and policies; demand for nuclear power; weather and other natural phenomena; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; and other exploration, development, operating, financial market and regulatory risks. Although Ur-Energy Inc. believes that the assumptions inherent in the forward-looking statements are reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this presentation. Ur-Energy Inc. disclaims any intention or obligation to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise. Cautionary Note Regarding Projections: Similarly, this presentation also may contain projections relating to an extended future period and, accordingly, the estimates and assumptions underlying the projections are inherently highly uncertain, based on events that have not taken place, and are subject to significant economic, financial, regulatory, competitive and other uncertainties and contingencies beyond the control of Ur-Energy Inc. Further, given the nature of the Company's business and industry that is subject to a number of significant risk factors, there can be no assurance that the projections can be or will be realized. It is probable that the actual results and outcomes will differ, possibly materially, from those projected. The attention of investors is drawn to the Risk Factors set out in the Company's Annual Information Form and Annual Report on Form 40-F, dated March 17, 2011, which are filed, respectively, with the regulatory authorities in Canada on SEDAR and with the U.S. Securities and Exchange Commission on EDGAR. (www.sedar.com and http://www.sec.gov/edgar.shtml) Cautionary Note to U.S. Investors Concerning Estimates of Measured, Indicated or Inferred Resources: the information presented uses the terms "measured", "indicated" and "inferred" mineral resources. United States investors are advised that while such terms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission does not recognize these terms. United States investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally minable. John Cooper, SME Registered Member, a Professional Geologist, and Qualified Person as defined by National Instrument 43-101, reviewed the technical information contained in this presentation. 2 N YSE Am ex : UR G TSX : UR E
  • 3. Ur-Energy At A Glance Advanced Pre-Production Project at Lost Creek, Wyoming One approval remaining Construction anticipated to commence this summer Low-Cost Uranium Production Center that will be Cash-Flow Positive in Current Market Expanding Resources through Acquisition and Exploration Low Technical, Political and Regulatory Risk Strategy See Disclaimer re Forward-looking Statements and Projections (slide 2) 3 N YSE Am ex : UR G TSX : UR E
  • 4. Ur-Energy’s Market Position Share Capital & Cash Position NYSE Amex: URG As of 10/24/11 Shares Outstanding 103.7M Stock Options & RSUs 6.5M Fully Diluted 110.2M Market Cap (03/01/12) C$121.3M Cash (09/30/11) C$28.8M Financing (2/23/12) C$17.25M Debt $0 Cash per share (09/30/11) ~C$0.30 Share price (03/01/12) C$1.17 52 Week Range C$.79 - $2.65 TSX: URE Avg. Daily Volume ~624,000 (3-mo URG & URE 03/01/12) Member of Russell 3000 & 2000 and S&P/TSX SmallCap Indexes Geographical Distribution as of 6/30/11 United States ~48% Canada ~38% Other ~14% See Disclaimer re Forward-looking Statements and Projections (slide 2) 4 N YSE Am ex : UR G TSX : UR E
  • 5. Analyst Coverage United States GVC Capital Mike Shonstrom (Denver, CO) 1 303-321-2392 Rodman & Renshaw Wayne Atwell (New York, NY) 1 212-356-0513 Canada Dundee Securities David A. Talbot (Toronto, ON) 1 416-350-3082 Haywood Securities Geordie Mark (Vancouver, BC) 1 604-697-6112 Raymond James 1 604-659-8282 RBC Capital Adam Schatzker (Toronto, ON) 1 416-842-7850 Australia Resource Capital Research Trent Allen (Sydney, NSW) 61 2-9252-9405 Ur-Energy Inc. is followed by the analysts listed above. This list, including the firms and individual analysts at these firms, is subject to change at any time without notice. Please note that any opinions, estimates, forecasts, conclusions or recommendations regarding Ur-Energy Inc.'s performance made by these analysts are theirs alone and do not represent opinions, estimates, forecasts, conclusions, recommendations or predictions of Ur-Energy Inc or its management. Ur- Energy Inc. does not by its reference above or in any other manner imply its endorsement of or concurrence with such information, conclusions or recommendations. 5 N YSE Am ex : UR G TSX : UR E
  • 6. The US Uranium Market The US produces ~ 4M lbs of uranium/yr1 The US consumes 55M lbs of uranium/yr1 contributing 20% of US electricity October 2011 Nuclear Energy Institute survey shows two-thirds of Americans support nuclear energy Ur-Energy is well positioned to capitalize on this opportunity Chart from U.S . Energy Information Administration 1 – U.S. Energy Information Administration See Disclaimer re Forward-looking Statements and Projections (slide 2) 6 N YSE Am ex : UR G TSX : UR E
  • 7. Post-Fukushima Nuclear Remains Positive* U.S. NRC issued two Construction and Operation Licenses in Feb 2012 First nuclear power plant licenses in 30+ years HEU Agreement to expire next year Provides 13% of world and 45% of US annual supply 96 new reactors are expected to go online worldwide by 2021 Even half of this growth represents a large growth potential Russia, China and India represent 50% of new builds and have reaffirmed support for nuclear power Last week, India announced plans for 20 new reactors by 2032 Saudi Arabia & the United Kingdom have announced plans to build 24 new reactors combined *According to World Nuclear Association See Disclaimer re Forward-looking Statements and Projections (slide 2) 7 N YSE Am ex : UR G TSX : UR E
  • 8. Growth of Nuclear Will Continue Historically, growth of nuclear power continued despite major accidents Growth expected to continue beyond Fukushima at 10 reactors per year 10 years, 10.2 reactors per year Number of Reactors 22 years, 4 reactors per year 8 years, 21.9 reactors per year Fukushima 13 years, 11.3reactors Chernobyl per year Three Mile Island Source: W orld Nuclear Association See Disclaimer re Forward-looking Statements and Projections (slide 2) 8 N YSE Am ex : UR G TSX : UR E
  • 9. Global Supply/Demand Imbalance How will supply be able to expand to the extent necessary to meet growing demand levels in the post-Fukushima environment of uncertainty and low prices? More damage done to uranium supply than uranium demand Deliveries from the HEU Agreement end next year Source: UxC Uranium M arket Outlook See Disclaimer re Forward-looking Statements and Projections (slide 2) 9 N YSE Am ex : UR G TSX : UR E
  • 10. Experienced Management Team Board of Directors Ex ecutive Directors Wayne W. Heili, President & Chief Executive Officer (Metallurgical Engineer) Jeffrey T. Klenda*, Board Chairman, Executive Director (Mining Finance) Non-Ex ecutive Directors W. William Boberg*, Former President & CEO (Professional Geologist) James M. Franklin*, Chair-Technical Committee (Professional Geologist) Paul Macdonell*, Chair-Compensation and Corp. Governance & Nominating Committees (Senior Federal Mediator) Thomas H. Parker, Chair-Audit Committee (Professional Engineer) Officers Roger L. Smith, Chief Financial Officer & Chief Administrative Officer(CPA & MBA) Steven M. Hatten, VP Operations (Petroleum Engineer) John W. Cash, VP Regulatory Affairs, Exploration & Geology (Geologist & Geophysicist) Penne A. Goplerud, Corporate Secretary & General Counsel (JD) * Founding Directors 10 N YSE Am ex : UR G TSX : UR E
  • 11. Industry Leading Team Highly Experienced Technical and Management Professionals 98 Years of Direct Uranium Production Experience ISR operations experience – Nebraska, Texas & Wyoming 11 N YSE Am ex : UR G TSX : UR E
  • 12. ISR – Low Impact Mining CAMECO Smith Ranch ISR Mine Powder River Basin, Wyoming 12 N YSE Am ex : UR G TSX : UR E
  • 13. In-Situ Recovery (ISR) Uranium Mining Environmentally sound production method Well understood by Wyoming state regulators Cost effective, low capital costs See Disclaimer re Forward-looking Statements and Projections (slide 2) 13 N YSE Am ex : UR G TSX : UR E
  • 14. Ur-Energy’s Wyoming Projects 14 N YSE Am ex : UR G TSX : UR E
  • 15. The Lost Creek Property NI 43-101 Resource from Prelim inary Econom ic Assessm ent of the Lost Creek Property, Sw eetw ater County, W yom ing (February 29, 2012) (posted on SEDAR These exploration targets are conceptual in nature. There has been and EDGAR ) insufficient exploration to define a mineral resource outside the current Lost Creek resource. It is uncertain if further exploration will result in the new target areas outside the Lost Creek resource Measured – 2.9 Mlbs eU3O8 (in 2.69 Mt @ 0.055%) being delineated as a mineral resource. Indicated – 2.8 Mlbs eU3O8 (in 2.4 Mt @ 0.058% ) Inferred – 2.0 Mlbs eU3O8 (in 2.06 Mt @0.052% ) * Based on grade cutoff of 0.02 percent eU3O8 and a grade x thickness cutoff of 0.3 GT. Exploration targets within the Lost Creek Project and adjoining projects provide potential of additional resources U3O8 Lost Creek Project – 4,254 acres Adjoining Projects – 39,300 acres Many of these exploration targets remain conceptual in nature. There has been See Disclaimer re Forward-looking Statements and Projections insufficient exploration to define mineral resource estimates at all such exploration targets. It is uncertain if further exploration will result in the (slide 2) additional target areas being delineated as further mineral resource. 15 N YSE Am ex : UR G TSX : UR E
  • 16. Lost Creek Adjacent to Rio Tinto Sweetwater Mine/Complex (NRC Licensed Conventional Uranium Mill on Standby) JK NYSE Amex: URG TSX: URE
  • 17. Preliminary Economic Assessment 2012 PEA* Upgrades Resources, Confirms Economics Mineral Resource Increase from 2011 PA 11% Increase in Measured and Indicated Resources 159% Increase in Inferred Resources (includes first resource estimate at each of LC North and LC South) Estimates Operating Costs less than US$20/ lb Lowest Quartile of all Uranium Producers Estimates Total P roduction Cost at US$42.65/ lb Includes capital recovery Project Internal Rate of Return (I RR ) at 91% Pre-Production Capital Costs of Only US$35M Rem aining Lowest Quartile of all developing uranium production facilities Total project Capital Cost of US$59M Cautionary Statement: This PEA is preliminary in nature, and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. The estimated mineral recovery used in this PA is based on both site-specific laboratory recovery data as well as URE personnel and industry experience at similar facilities. There can be no assurance that recovery at this level will be achieved. * N I 43-101 P relim inary Econom ic Assessm ent of the Lost Creek See Disclaimer re Forward-looking Statements and Projections (slide 2) P roperty, Sw eetw ater County W yom ing – (February 29, 2012) (posted on SEDAR and EDGAR ) 17 N YSE Am ex : UR G TSX : UR E
  • 18. US$24M in CapEx Completed Mine Units 1 & 2 Delineated MU #1 Monitor Well Ring Completed Plant Engineering Completed Drilled and Tested Class I UIC Well Ordered Key Plant Equipment Ur-Energy’s Ion Exchange Columns Ion Exchange Columns Elution Columns Filter Presses Design/Build of Header House Building Interior of Ur-Energy’s Prototype Header House 18 N YSE Am ex : UR G TSX : UR E
  • 19. Lost Creek Path to Production Site Permitting Started in 2006 Licenses and Permits Received US NRC License Wyoming DEQ Permit to Mine – Includes Approval of First Mine Unit WDEQ Class I UIC Permit (water disposal well) EPA Aquifer Exemption One Remaining Regulatory Approval Needed US Bureau of Land Management Plan of Operations Environmental review process underway Record of Decision anticipated early summer 2012 Construction 6 – 9 month build-out First Production Planned for second quarter next year See Disclaimer re Forward-looking Statements and Projections (slide 2) 19 N YSE Am ex : UR G TSX : UR E
  • 20. February 2012 Property Acquisition Expansion of the resource base for processing facility at Lost Creek Asset Exchange: No Cash Cost. Ur-Energy possesses ~1,000 holes of historic drill data Properties directly adjacent with Lost Creek Project boundaries Two WY state mineral leases 175 federal mining claims Approx 5,250 acres Expect updated PEA incorporating new acquisition See Disclaimer re Forward-looking Statements and Projections (slide 2) 20 N YSE Am ex : UR G TSX : UR E
  • 21. Lost Soldier – 12.2M M&I lbs U3O8 Can be licensed with NRC as amendment to Lost Creek license M & I resource average 17.2 ft @ 0.065% U3O8 Average 240 feet deep Leach efficiency 49% - 84% Over 3700 drill holes define deposit 17 monitor/pump test wells installed (From Figure 16-2, Technical Report on the Lost Soldier Project, Wyoming, C. Stewart Wallis, RPA, July 10, 2006 - posted on SEDAR) NI 43-101 Compliant Resource Measured & Indicated (M & I) – 12.2 Mlbs U3O8 (in 9.4 Mt @ 0.065% ) Inferred – 1.8 Mlbs U3O8 (in1.6 Mt @0.055% ) (Technical Report on the Lost Soldier Project, Wyoming, C. Stewart Wallis, Roscoe Postle Associates Inc., July 10, 2006 - Posted on SEDAR) See Disclaimer re Forward-looking Statements and Projections (slide 2) 21 N YSE Am ex : UR G TSX : UR E
  • 22. Screech Lake, Thelon Basin, NWT Completed Audio-Magnetotelluric Geophysical Survey, and Soil Gas Hydrocarbon and Enzyme Leach Soil Geochemistry Analyses to Better Define Drill Targets MegaTEM Survey Screech Lake See Disclaimer re Forward-looking Statements and Projections (slide 2) 0 4 Kilometers 22 N YSE Am ex : UR G TSX : UR E
  • 23. Sound Marketing Strategy Balancing strategic and economic benefits of the spot/term ratio De-risking by securing future revenue stream in an uncertain market Securing pricing that supports development plans for the Lost Creek Project Targeting contracts with North American utilities Exclusive representation by NuCore Energy, LLC in off-take purchase agreement negotiations 23 N YSE Am ex : UR G TSX : UR E
  • 24. Ur-Energy’s Strong Position Advanced Development at Lost Creek Permitting Process Nearing Completion Low Cost Production Will Equal Strong Cash Flow ~US$20/lb direct operating cost Uranium Term Market is above $60/lb Sound Uranium Marketing Strategy with Multiple Long- Term Sales Agreements in Place Experienced Technical & Managerial Team Strong Balance Sheet C$28.8 Million (9/30/12) C$17.25 Million Financing Completed in 2012 See Disclaimer re Forward-looking Statements and Projections (slide 2) 24 N YSE Am ex : UR G TSX : UR E
  • 25. Future Growth Opportunities Resource Expansion through ongoing exploration and acquisition efforts Increase Minable Resources that will be Accessible to the Lost Creek Processing Plant Growth in the Production Profile Development of Currently Held Properties Acquisitions of New Properties Strategic Alliances Exploration Properties in Western Nebraska Monetizing Historic Databases See Disclaimer re Forward-looking Statements and Projections (slide 2) 25 N YSE Am ex : UR G TSX : UR E
  • 26. Re-Rating Potential Stage EV/Lb URG Upside vs. Producers Producers $4.60  3X (+$3.13/Lb) Developer URG $1.47 Source: Dundee (February 29, 2012) As Ur-Energy Nears Production, Re-rating is Likely See Disclaimer re Forward-looking Statements and Projections (slide 2) 26 N YSE Am ex : UR G TSX : UR E
  • 27. Ur-Energy – Right Now! Technical, Political and Regulatory Certainty Advanced Pre-Production Project at Lost Creek Low-Cost Uranium Production Center that will be Cash-Flow Positive in Today’s Market Plant Construction Planned to Begin Summer 2012 Ramping up to Production Rate of 1M lbs/year Signed Multiple Long Term Uranium Sales Agreements De-Risking Company Exposure to Volatile Marketplace Re-Rating Likely as Ur-Energy Nears Production See Disclaimer re Forward-looking Statements and Projections (slide 2) 27 N YSE Am ex : UR G TSX : UR E
  • 28. Ur-Energy - The Right People. The Right Projects. Right Now.  For more information, please contact: Wayne Heili, President, Chief Executive Officer & Director Jeff Klenda, Board Chairman & Director Rich Boberg, Director of Public Relations  By Mail: Ur-Energy Corporate Office 10758 W. Centennial Rd., Ste. 200 Littleton, CO 80127 USA  By Phone: Office (720) 981-4588 Toll-Free (866) 981-4588 Fax (720) 981-5643  By E-mail: wayne.heili@ur-energyusa.com jeff.klenda@ur-energyusa.com rich.boberg@ur-energyusa.com 28 NYSE Amex:: URG N YSE Am ex UR G TSX::URE TSX UR E