SlideShare a Scribd company logo
1 of 73
THE STATE OF VICTORIA'S NEW WORKPLACE
MANSLAUGHTER LEGISLATION AS OF 01-JULY-2020
(UPDATE 28-JAN-2023)
The impact of new legislation on Planning and Scheduling, costs
and potential time delay to project delivery
by
Raphael M Düa – DBA,FAICD,GPCF,FAPE,MACS(Snr),CP, IP3, GDISC
CEO Micro Planning International Pty Ltd
12/02/2023
© Raphael M. Dua
1
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
2
Objectives of presentation
• The changes to OHS&E law in State of Victoria
• The Fatalities and LTI’s in Australia
• The Fatalities and LTI’s in USA
• The Fatalities and LTI’s in UK
• Legislation Overseas
• What Contractors will have to do with the new legislation
• Changes to Planning that will be required
• Summary
• Recommendations
• References
12/02/2023
© Raphael M. Dua
3
What were the facts when the legislation was first introduced?
We know no Construction schedules allowed sufficient time to allow
safety tasks to be carried out immediately before the unsafe task
had to be carried out. Schedulers did not consider the time required to
erect safety needs
CM’s wanted to minimize the project duration at all costs, without
thinking about the danger to the worker even at the cost of a life
12/02/2023
© Raphael M. Dua
4
Causation of Delays in Schedules and project delivery
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 There is a need for the scheduler to understand the impact of failing to
fully implement safety as per OHS&E requirements and how it may
cause delays to schedules
 Because early in the 21st century, the construction fatality and incident
rates are noticeably higher than the average of all industries
worldwide ¹
 This led many jurisdictions to implement OHS&E legislation
12/02/2023
© Raphael M. Dua
5
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 In 2004, the Victorian Government passed
The Occupational Health and Safety Act 2004 and
related regulations aimed to keep Victorian workplaces
safe. The Occupational Health and Safety Act 2004
(OHS Act) is the main workplace health and safety law in
Victoria. It sets out key principles, duties and rights
about OHS
12/02/2023
© Raphael M. Dua
6
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
However, over the intervening years whilst fatalities
were dropping slowly, deaths continued
Falls from heights fatalities: a total of 48
construction workers were killed by falls from
heights in the five years from 2008-9 to 2012-13. The
most at-risk construction occupations for falls from
heights fatalities were: Painting and decorating;
Roofing; Plumbing; Housing construction
12/02/2023
© Raphael M. Dua
7
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 "In 2018, due to pressure from the workplace concerned about the
continuing number of fatalities not being addressed by the 2004
legislation the Andrews government promised if re-elected they
would introduce tougher laws"
 Suggestion: "On re-election the state government, this toughening
of the existing legislation was passed through parliament in 2019
and was promulgated by 01-July -2020"
12/02/2023
© Raphael M. Dua
8
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
Why has the legislation been changed?
Because even though many countries had Occupation, Health
and Safety legislation laws, when a fatality occurred it often
did not result in prosecution as the law was focussed on the
organisation and not the person who may have caused the
fatality as a result of their actions or negligence
12/02/2023
© Raphael M. Dua
9
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
10
• The changes to OHS&E law in State of Victoria
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
Firstly, we need to understand the reasons for why
this change to legislation has occurred and
secondly the likelihood of this change becoming
the norm in many other jurisdictions.
The changes are:-
12/02/2023
© Raphael M. Dua
11
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
A new criminal offence of workplace manslaughter has been
introduced by the government of the State of Victoria into
occupational health and safety laws
The offence applies to negligent conduct by an employer or other
duty holders as outlined below, or an officer of an organisation,
which breaches certain duties under the Occupational Health and
Safety Act 2004 (OHS Act) and causes the death of another person
who was owed the duty
The law provides for a custodial sentence of up to 20 years and a
company fine of $16.5 million
12/02/2023
© Raphael M. Dua
12
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 In 2019, 62% of worker fatalities occurred in the following
industries:
• Transport, postal and warehousing (58 fatalities)
• Agriculture, forestry and fishing (30 fatalities)
• Construction (26 fatalities)
 The most common causes of worker fatalities in 2019 were:
• Vehicle collisions (43%)
• Falls from a height (11%)
• Hit by falling objects (11%)
12/02/2023
© Raphael M. Dua
13
12/02/2023
© Raphael M. Dua
14
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
The statistics
 Work-related fatalities
When it comes to work-related fatalities, the most recent statistics
from the Construction Industry Profile show that between 2003–13,
401 workers died on construction sites in Australia. The majority of
those (28% or 112 workers) involved falls from a height:
• 40 involved ladders, mobile ramps, stairways and scaffolding
• 32 involved a fall from a roof
• 17 involved buildings under construction or demolition.
12/02/2023
© Raphael M. Dua
15
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 Other fatalities during this period were made up of:
• vehicle collisions 16% (65)
• electrocution 15% (61)
• being hit by a moving object 12% (48)
• being hit by a falling object 11% (46)
• being trapped between or in equipment 8% (31)
• other causes 9% (38)
 Also Lost Time Injuries have increased which has implications to
the schedule as does fatalities
12/02/2023
© Raphael M. Dua
16
THE IMPACT OF NEW
LEGISLATION ON
PLANNING AND
SCHEDULING, COSTS
AND POTENTIAL DELAY
TO PROJECT DELIVERY
© Raphael M. Dua 2/12/2023
17
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
18
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
19
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
20
12/02/2023
© Raphael M. Dua
21
So what has been the results of the new legislation?
12/02/2023
© Raphael M. Dua
22
12/02/2023
© Raphael M. Dua
23
12/02/2023
© Raphael M. Dua
24
In spite of new legislation the number of construction deaths
has increased from 144 in 2019 to 169 in 2021
12/02/2023
© Raphael M. Dua
25
Why has there been a worsening of the numbers?
From the limited research I have carried out it would appear that planners and schedulers are being
pushed (told by the PM or CM) to sharpen the timeline as the results of Covid having increased costs so
we need to complete as quickly as possible.
Inevitability this has led to an absence of safety tasks being part of the schedule and taking time as was
proposed and indeed worse – shortcuts being undertaken to reduce time and costs
12/02/2023
© Raphael M. Dua
26
An auto-rule in RDCPM or checklist in Acumen Fuse
should REQUIRE or a FLAG for a safety activity being
predecessor (maybe not immediate - and THAT
requires some special coding) of an activity creating
risk of injury.
Perhaps a solution to this lack of visible safety tasks in the schedule
could be as follows
Source: Dr. Fred Plotnick – Construction CPM 2023
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
27
In the United States the fatality rate is considerably higher than Australia
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 In the USA, the Occupational Safety and Health Administration
is responsible for all aspects of work safety and health
 Work-related fatalities for cases inspected by Federal or State OSHA
 Provides data on work-related fatalities that occurred under Federal
OSHA and State Plan jurisdiction for cases that have been closed or
citations issued on or after January 1, 2017
 Employers must report worker fatalities to OSHA within eight hours.
OSHA investigates all work-related fatalities in all covered workplaces.
The agency has up to six months to complete an investigation and
determine whether citations will be issued
12/02/2023
© Raphael M. Dua
28
12/02/2023
© Raphael M. Dua
29
12/02/2023
© Raphael M. Dua
30
12/02/2023
© Raphael M. Dua
31
12/02/2023
© Raphael M. Dua
32
12/02/2023
© Raphael M. Dua
33
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
OSHA provides
Reports of fatalities for CY17-20.
(“The information is not comprehensive. We
continue to update it as data becomes
available”)
Fatality summaries are listed in descending
order from newest to oldest in the following
table:
12/02/2023
© Raphael M. Dua
34
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
35
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
36
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
UNITED KINGDOM WORKING DAYS LOST
12/02/2023
© Raphael M. Dua
37
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
38
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
It is interesting to note whilst researching the internet for this
paper that in the multitude of learned material, and literature,
government inquiries, etc. there is very little if any reference
to schedule delays caused by Fatalities and LTI’s and other
safety issues
It is obvious, when researching this topic through Google,
that little research into safety and the impact on a Schedules
exists
12/02/2023
© Raphael M. Dua
39
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 Research
 Recent studies indicate that investing in health and safety can yield financial
advantages. Some highlights for example:
• Accident prevention can be improved without higher costs and slower schedules
• Workplace injuries account for 6-9% of project costs whereas an effective
health and safety program accounts for only 2.5% of those costs.
• The higher the safety investment in a project, the lower the injury rates and the
higher the profit
• Increased training, more frequent inspections, and more health and safety
meetings with field supervisors result in fewer lost-time injuries, lower costs, and a
larger profit margin
• CSAO found that construction workers with back injuries who participate in a back
care program are less likely to be re-injured than those who don't participate
12/02/2023
© Raphael M. Dua
40
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
41
If, in the unfortunate event of a fatality on the task, it is the
subject of a criminal offence in Australia, a Culpable Homicide in
the US and in the UK, it will shut the project site down until the
WorkSafe /OSHA inspectors determine that the site is safe after
remedial work has taken place
• In the UK, a Company Director and project manager were
sentenced after a construction worker sustained fatal crush
injuries, as well as a fine
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
In Australia, when a fatality occurs on a construction site it is
immediately closed down by the local WorkSafe organisation
12/02/2023
© Raphael M. Dua
42
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
So what is the impact on the project
plan, the schedule and cost from this
stoppage?
12/02/2023
© Raphael M. Dua
43
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 All jurisdictions around the world have similar safety laws, but it is
rare to find the average Planner and/or Scheduler who has any
reasonable knowledge of the compulsory nature of all the
requirements. This knowledge is imperative so that they can make
informed decisions as to estimate of the impact of particular
regulations on the duration of a specific task
 The Planner must take into account all of the dependent work and
safety requirements before determining the task duration. But so
often there is no visibility in the schedule to indicate that safety risks
have been mitigated
12/02/2023
© Raphael M. Dua
44
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
It is very rare to see in a construction schedule where the time
required for safety tasks have been included.
It is often said to be included in the JSA or SWMS
Some major contractors do plan and schedule such so that any
safety risks have been mitigated and that the work to ensure
the worker’s safety is visible
However, these contractors are in a minority
12/02/2023
© Raphael M. Dua
45
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
46
According to some Construction PMs the
causes of Schedule Delays in Construction Projects
are:
1.Construction site access
2.Differing site conditions
3.Force majeure
4.Adverse weather
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
A serious shortcoming, in maintaining safety in the daily
workflow, is when a project is running behind schedule and
the project director is pressuring the foreman to get the
work done as the need to complete on time is all important
The workers themselves feel that pressure and will take
shortcuts to get the task completed and inevitably cause an
accident, which may prove fatal
12/02/2023
© Raphael M. Dua
47
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
For more information in this area read “Distinguished
Professor Helen Lingard” of RMIT seminal work
12/02/2023
© Raphael M. Dua
48
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
Fatalities involve both direct costs and indirect costs.
Direct costs consist of:
• medical expenses such as ambulance, hospital, and doctors' fees,
medication
• counselling of site employees and contractors
• compensation payments
• WorkSafe Victoria premium increases
• litigation costs
12/02/2023
© Raphael M. Dua
49
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 Indirect costs include:
 Disrupted work schedules, lost productivity, clean-up and repair,
hiring and training replacement workers, bad publicity, reputational
damage, and time spent on accident investigation, claims
management, and litigation
 Re-engineering
 Design implications
 Constructability / methodology
 Having to replan and reschedule the remaining work on the project,
which may have a serious impact on the project completion date
12/02/2023
© Raphael M. Dua
50
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
Since the Westgate and the Milford Haven box girder bridge
collapses back in the 1970’s, strong OHS laws have been
promulgated to prevent such events
This includes the introduction of Job Safety Analysis (JSA)
and a SafeWork Method Statement (SWMS).
Documentation to mitigate any risks which may be
present in the construction process is now
mandatory
12/02/2023
© Raphael M. Dua
51
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
However, in many schedules it is not obvious how much time has
been allowed by the planner in the task durations for the
implementation of the defined safety requirements
The safety and work methodology is generally discussed at a
“Toolbox meeting” first thing at the start of day or shift
Also missing are other identified risks as defined in the JSA or
SWMS
12/02/2023
© Raphael M. Dua
52
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
53
What are the risks?
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
Notice that OHS&E is not considered a risk, which says it all
This would indicate that the schedule will fail to deliver if a
serious safety event occurs, especially a fatality
12/02/2023
© Raphael M. Dua
54
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 According to J.J. Smallwood, Associate Professor, Department of
Construction Management, University of Port Elizabeth, Port
Elizabeth, South Africa in his paper on:
 THE ROLE OF HEALTH AND SAFETY IN PROJECT MANAGEMENT
 “Inadequate or the lack of occupational health and safety not only
negatively affects the traditional construction project parameters of cost,
quality and schedule, but the sustainability of the environment.
Occupational fatalities, injuries and disease constitute defects as they are
not project requirements. They also contribute to the cost of construction
and development as workers’ compensation insurance is included as a
labour overhead and the cost of accidents is integrated into the cost
structure of contractors.”
12/02/2023
© Raphael M. Dua
55
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 Plan Ahead
 Ensure all prework activities, such as approvals, are completed
before work begins.
 A thoughtful planning process can help the workday start on a
more efficient and safer standing.
 Implement zoning to block off areas where certain tasks will
take place,
 install nets and catch platforms and apply any other necessary
safety measures. Keep the work areas free from building refuse
12/02/2023
© Raphael M. Dua
56
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
 Because
 • …major programs are not just magnified versions of smaller projects, they are a
completely different breed in terms of their level of aspiration, lead times, complexity,
and stakeholder involvement.² •
 …9 out of 10 major programs incur cost overruns.³
 • …cost overruns of 50-100% are not uncommon for major programs.³•
 …end-user demand and overall benefits of major programs are typically
overestimated by 20-70% compared with actual developments ³ •
 Construction disputes are increasing due to complex programs; multi-geography
delivery, faster paced schedules and external economic factors⁴
12/02/2023
© Raphael M. Dua
57
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
58
According to Saleh Al-Wadei in his
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
59
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
60
In Saleh’s dissertation, there is no mention of OHS&E and / or safety
issues as being a cause of project schedule failures, His research is based
on a wide range of projects in several countries but does not consider
how the failure to ensure safety has quite an impact on schedule delay
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
61
What changes require to be made to Planning and Scheduling?
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
62
Changes required to mitigate the delays due to LTI’s & Fatalities?
• The Planner when developing the plan for the schedule should identify all those areas of the
project and the site which have safety implications and identify those tasks which are to be
implemented in those areas
• These tasks should be coded such that the different types of safety risks have been identified so
that they can be selected in reports used when preparing the JSA’s or SWMS, as this will provide
the lead trade with the schedule information and duration planned for the task. This may of
course indicate that once the sub tasks are specified in the JSA that the planned duration is
either too short or most unlikely, too long
• These reports should be produced at least two weeks before the planned start of the tasks
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
63
The scheduler must show within the schedule visibility of the pre-work required for a
complex task which may have to comply with safety requirements as defined by the
site OHS&E superintendent. Also ensure that the duration allows time to perform
safe work
If, in the unfortunate event of a fatality on the task, it is the subject of a criminal
offence in Australia, a Culpable Homicide in the US and in the UK, it will shut the
project site down until the WorkSafe /OSHA inspectors determine that the site is safe
after remedial work has taken place
• In the UK, a Company Director and project manager were sentenced after a
construction worker sustained fatal crush injuries, as well as a fine
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
64
What do other professional Planners and Schedulers say
about accounting for safety in a Schedule?
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
65
Mike Testro, a well known, international Planner , Scheduler & Forensic Analyst says the following:-
“Most construction contracts that I have read a breach of safety is not a relevant event for an extension of time which
means that the contractor bears the whole risk, it is important therefore that the planner allows for contingency in the
programme.
Whenever I put together a construction programme I always ensure that site safety is at the forefront of my planning and
sequencing, but I admit that I do not highlight the fact that I've done so.
Things like isolation zones for hot working would be in place but I do not mention it anywhere in the text.
Situations such as having a safe overhead barrier when working underneath, I always ensure that there are three
structural zones above the working zone and that all props and frames are clear .It would be very simple when tasks
involved in safety aspects have a different colour code so that they are easily identified.
Here in the UK site safety has a high importance in the management structure and actual fatalities are rare but when they
do happen then the site is shut down for a full investigation and I've not yet seen construction programme where such a
contingency is built in advance. Nobody anticipates such a thing happening in any case.”
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
66
•Chris Carson FRICS, FAACE, FGPC, PSP, DRMP, CEP, CCM, PMP, who is the
Enterprise Director of Program & Project Controls & Associate Vice President at Arcadis says’
“One of the six fundamental H&S principles that Arcadians have to adhere to is “Undertake H&S Planning”, and
we do look at the H&S plan that is developed for a project to see if there are any time implications to the plan.
Our engineering designers work under an Arcadis safety design that prioritizes safe design; Elimination (design
it out), Substitution (use something else), Engineering Controls (isolation and guarding), Administrative
Controls (training and work scheduling), and Personal Protective Equipment (last resort). And they
particularly look at safety during construction activities. During design, they also have a checklist that includes
things like: providing permanent safe access to roofs, plant rooms, and windows for maintenance and repair,
eliminating need for install temporary barriers by integrated guardrail systems along roof edges, lifting lugs
installed in to prefab equipment/structure, ergonomic principles to avoid designing construction activities that
require repetitive or prolonged movements. When developing a schedule, we do look at their design safety
issues”
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
67
Recommendations
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
68
Perform Constructability Reviews
Performing a constructability review requires an intimate knowledge of the project. The
unfortunate reality is that when a mere few days is set aside for this important step the
reviewer barely has enough time to attain an overview of the project, much less review and
understand its intricacies.
There are five important steps in performing the review, as shown below
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
69
1.Build the Project; Don't focus solely on the problems. Ensure the
Planners and Schedulers are present at the meetings. Only by taking the
time to walk through the construction process step by tedious step will
the problems be discovered. Look for all the potential construction risks
and complex and perhaps dangerous work needs. Ensure sufficient time
has been allowed to execute the tasks safely
2. Review the Interface of Various Systems. Whether it be interior,
exterior, structural or MEP, problems are not discovered nearly as
frequently within the body of a system as they are at the perimeter of a
system where it interfaces with the various adjacent systems and trades,
and the need to ensure safety
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
70
3.Keep the Review of Preliminary Documents Constructive. When
performing a constructability review on 50%, 75%, or even 90% documents,
be cognizant that the design documents are not complete. Check for any
safety implications at the various interfaces
4.Stay Focused on the Important Items. Before making a comment to the
design team, ask two questions. First, "Will this impact the cost, time,
quality of the project?” or secondly “Will the design compromise safety of
the project?"
5. Take the Time to Complete a Thorough Review. A thorough
constructability review will take weeks, even months, but for every hour
spent planning a project the hours saved down the road are exponential. It
may well save a life or prevent any LTI’s
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
71
Summary
There must be sufficient time in the Schedule to carry out the
execution of every task to ensure that no shortcuts are taken.
There must be no dangerous work practices or avoidance of
legislated OHS&E requirements. All must be fully met and be
visible to all the construction workers
Management has a very important role to play to ensure that
everybody goes home every night, and that failure to do so
attracts severe Criminal penalties
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
72
References
¹ (Lingard & Rowlinson, 2004;Sunindijo & Zou, 2011).
2 Bent Flyvberg: What You Should Know About Megaprojects and Why: An Overview (2014)
3 Bent Flyvberg: Over Budget, Over Time, Over and Over Again: Managing Major Projects (2011)
4 Arcadis: Construction Disputes Report (2015)
THE IMPACT OF NEW LEGISLATION ON PLANNING AND
SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY
12/02/2023
© Raphael M. Dua
73
I would appreciate receiving any material you may have to help me with my
research work in this most important area of scheduling.
I would like examples of P6, MSP, OPP, ASTA and Micro Planner schedules showing
the fact that the scheduler did include the prework and provided a sensible
duration to ensure safety of the workers performing the work
Please forward to me:
Raphael M. Düa
raf@microplanning.io
Cell +61 418 53 1111

More Related Content

Similar to State of Victoria's new workplace manslaughter legislation and Overseas Updated in Jan 2023.pptx

ACCIDENT TREND ANALYSIS CONSTRUCTION.pdf
ACCIDENT TREND ANALYSIS CONSTRUCTION.pdfACCIDENT TREND ANALYSIS CONSTRUCTION.pdf
ACCIDENT TREND ANALYSIS CONSTRUCTION.pdf
sriram123456
 
Data Insights Report Planning JUN2022.pdf
Data Insights Report Planning JUN2022.pdfData Insights Report Planning JUN2022.pdf
Data Insights Report Planning JUN2022.pdf
ElissavetPerperidou
 
Whitepaper - Healthy economy carries hidden risks for developers
Whitepaper - Healthy economy carries hidden risks for developersWhitepaper - Healthy economy carries hidden risks for developers
Whitepaper - Healthy economy carries hidden risks for developers
Kit Carroll
 
Canadian wind forecast outlook executive summary
Canadian wind forecast outlook   executive summaryCanadian wind forecast outlook   executive summary
Canadian wind forecast outlook executive summary
Jon Winberg
 

Similar to State of Victoria's new workplace manslaughter legislation and Overseas Updated in Jan 2023.pptx (20)

North America Industrial Construction Cost Guide 2023
North America Industrial Construction Cost Guide 2023North America Industrial Construction Cost Guide 2023
North America Industrial Construction Cost Guide 2023
 
ACCIDENT TREND ANALYSIS CONSTRUCTION.pdf
ACCIDENT TREND ANALYSIS CONSTRUCTION.pdfACCIDENT TREND ANALYSIS CONSTRUCTION.pdf
ACCIDENT TREND ANALYSIS CONSTRUCTION.pdf
 
Data Insights Report Planning JUN2022.pdf
Data Insights Report Planning JUN2022.pdfData Insights Report Planning JUN2022.pdf
Data Insights Report Planning JUN2022.pdf
 
UK CONSTRUCTION INDUSTRY PRIMER (for investors and entrepreneurs)
UK CONSTRUCTION INDUSTRY PRIMER (for investors and entrepreneurs)UK CONSTRUCTION INDUSTRY PRIMER (for investors and entrepreneurs)
UK CONSTRUCTION INDUSTRY PRIMER (for investors and entrepreneurs)
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
 
2023 -power-utilities-outlook.pdf
2023 -power-utilities-outlook.pdf2023 -power-utilities-outlook.pdf
2023 -power-utilities-outlook.pdf
 
Whitepaper - Healthy economy carries hidden risks for developers
Whitepaper - Healthy economy carries hidden risks for developersWhitepaper - Healthy economy carries hidden risks for developers
Whitepaper - Healthy economy carries hidden risks for developers
 
Eia 2006 vs. eia 2020
Eia 2006 vs. eia 2020Eia 2006 vs. eia 2020
Eia 2006 vs. eia 2020
 
Canadian wind forecast outlook executive summary
Canadian wind forecast outlook   executive summaryCanadian wind forecast outlook   executive summary
Canadian wind forecast outlook executive summary
 
Dissertation Final
Dissertation FinalDissertation Final
Dissertation Final
 
PREP - Workforce Related Project Risks
PREP - Workforce Related Project RisksPREP - Workforce Related Project Risks
PREP - Workforce Related Project Risks
 
DTC Evaluation
DTC EvaluationDTC Evaluation
DTC Evaluation
 
Ur-Energy's March 2020 Corporate Presentation
Ur-Energy's March 2020 Corporate PresentationUr-Energy's March 2020 Corporate Presentation
Ur-Energy's March 2020 Corporate Presentation
 
EIA (enviroment impact assessment) 2020
EIA (enviroment impact assessment) 2020EIA (enviroment impact assessment) 2020
EIA (enviroment impact assessment) 2020
 
Critical review and analysis of Gujrera act [2016] and its implication and sa...
Critical review and analysis of Gujrera act [2016] and its implication and sa...Critical review and analysis of Gujrera act [2016] and its implication and sa...
Critical review and analysis of Gujrera act [2016] and its implication and sa...
 
The management of health and safety of construction sites in accra
The management of health and safety of construction sites in accraThe management of health and safety of construction sites in accra
The management of health and safety of construction sites in accra
 
Qbe casualty-risk-management-construction-newsletter-february-2010
Qbe casualty-risk-management-construction-newsletter-february-2010Qbe casualty-risk-management-construction-newsletter-february-2010
Qbe casualty-risk-management-construction-newsletter-february-2010
 
Final project
Final projectFinal project
Final project
 
Feature-SUM-route 3
Feature-SUM-route 3Feature-SUM-route 3
Feature-SUM-route 3
 
Feature-SUM-route 2
Feature-SUM-route 2Feature-SUM-route 2
Feature-SUM-route 2
 

Recently uploaded

Recently uploaded (12)

Group work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and ImportanceGroup work -meaning and definitions- Characteristics and Importance
Group work -meaning and definitions- Characteristics and Importance
 
Nurturing Tomorrow’s Leaders_ The Emerging Leaders Institute.pdf
Nurturing Tomorrow’s Leaders_ The Emerging Leaders Institute.pdfNurturing Tomorrow’s Leaders_ The Emerging Leaders Institute.pdf
Nurturing Tomorrow’s Leaders_ The Emerging Leaders Institute.pdf
 
Spring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical ReviewSpring-2024-Priesthoods of Augustus Yale Historical Review
Spring-2024-Priesthoods of Augustus Yale Historical Review
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
W.H.Bender Quote 63 You Must Plan T.O.P Take-Out Packaging
W.H.Bender Quote 63 You Must Plan T.O.P Take-Out PackagingW.H.Bender Quote 63 You Must Plan T.O.P Take-Out Packaging
W.H.Bender Quote 63 You Must Plan T.O.P Take-Out Packaging
 
Internal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika GargInternal Reconstruction Corporate accounting by bhumika Garg
Internal Reconstruction Corporate accounting by bhumika Garg
 
thesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholarsthesis-and-viva-voce preparation for research scholars
thesis-and-viva-voce preparation for research scholars
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docx
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 

State of Victoria's new workplace manslaughter legislation and Overseas Updated in Jan 2023.pptx

  • 1. THE STATE OF VICTORIA'S NEW WORKPLACE MANSLAUGHTER LEGISLATION AS OF 01-JULY-2020 (UPDATE 28-JAN-2023) The impact of new legislation on Planning and Scheduling, costs and potential time delay to project delivery by Raphael M Düa – DBA,FAICD,GPCF,FAPE,MACS(Snr),CP, IP3, GDISC CEO Micro Planning International Pty Ltd 12/02/2023 © Raphael M. Dua 1
  • 2. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 2 Objectives of presentation • The changes to OHS&E law in State of Victoria • The Fatalities and LTI’s in Australia • The Fatalities and LTI’s in USA • The Fatalities and LTI’s in UK • Legislation Overseas • What Contractors will have to do with the new legislation • Changes to Planning that will be required • Summary • Recommendations • References
  • 3. 12/02/2023 © Raphael M. Dua 3 What were the facts when the legislation was first introduced? We know no Construction schedules allowed sufficient time to allow safety tasks to be carried out immediately before the unsafe task had to be carried out. Schedulers did not consider the time required to erect safety needs CM’s wanted to minimize the project duration at all costs, without thinking about the danger to the worker even at the cost of a life
  • 4. 12/02/2023 © Raphael M. Dua 4 Causation of Delays in Schedules and project delivery
  • 5. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  There is a need for the scheduler to understand the impact of failing to fully implement safety as per OHS&E requirements and how it may cause delays to schedules  Because early in the 21st century, the construction fatality and incident rates are noticeably higher than the average of all industries worldwide ¹  This led many jurisdictions to implement OHS&E legislation 12/02/2023 © Raphael M. Dua 5
  • 6. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  In 2004, the Victorian Government passed The Occupational Health and Safety Act 2004 and related regulations aimed to keep Victorian workplaces safe. The Occupational Health and Safety Act 2004 (OHS Act) is the main workplace health and safety law in Victoria. It sets out key principles, duties and rights about OHS 12/02/2023 © Raphael M. Dua 6
  • 7. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY However, over the intervening years whilst fatalities were dropping slowly, deaths continued Falls from heights fatalities: a total of 48 construction workers were killed by falls from heights in the five years from 2008-9 to 2012-13. The most at-risk construction occupations for falls from heights fatalities were: Painting and decorating; Roofing; Plumbing; Housing construction 12/02/2023 © Raphael M. Dua 7
  • 8. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  "In 2018, due to pressure from the workplace concerned about the continuing number of fatalities not being addressed by the 2004 legislation the Andrews government promised if re-elected they would introduce tougher laws"  Suggestion: "On re-election the state government, this toughening of the existing legislation was passed through parliament in 2019 and was promulgated by 01-July -2020" 12/02/2023 © Raphael M. Dua 8
  • 9. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY Why has the legislation been changed? Because even though many countries had Occupation, Health and Safety legislation laws, when a fatality occurred it often did not result in prosecution as the law was focussed on the organisation and not the person who may have caused the fatality as a result of their actions or negligence 12/02/2023 © Raphael M. Dua 9
  • 10. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 10 • The changes to OHS&E law in State of Victoria
  • 11. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY Firstly, we need to understand the reasons for why this change to legislation has occurred and secondly the likelihood of this change becoming the norm in many other jurisdictions. The changes are:- 12/02/2023 © Raphael M. Dua 11
  • 12. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY A new criminal offence of workplace manslaughter has been introduced by the government of the State of Victoria into occupational health and safety laws The offence applies to negligent conduct by an employer or other duty holders as outlined below, or an officer of an organisation, which breaches certain duties under the Occupational Health and Safety Act 2004 (OHS Act) and causes the death of another person who was owed the duty The law provides for a custodial sentence of up to 20 years and a company fine of $16.5 million 12/02/2023 © Raphael M. Dua 12
  • 13. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  In 2019, 62% of worker fatalities occurred in the following industries: • Transport, postal and warehousing (58 fatalities) • Agriculture, forestry and fishing (30 fatalities) • Construction (26 fatalities)  The most common causes of worker fatalities in 2019 were: • Vehicle collisions (43%) • Falls from a height (11%) • Hit by falling objects (11%) 12/02/2023 © Raphael M. Dua 13
  • 15. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY The statistics  Work-related fatalities When it comes to work-related fatalities, the most recent statistics from the Construction Industry Profile show that between 2003–13, 401 workers died on construction sites in Australia. The majority of those (28% or 112 workers) involved falls from a height: • 40 involved ladders, mobile ramps, stairways and scaffolding • 32 involved a fall from a roof • 17 involved buildings under construction or demolition. 12/02/2023 © Raphael M. Dua 15
  • 16. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  Other fatalities during this period were made up of: • vehicle collisions 16% (65) • electrocution 15% (61) • being hit by a moving object 12% (48) • being hit by a falling object 11% (46) • being trapped between or in equipment 8% (31) • other causes 9% (38)  Also Lost Time Injuries have increased which has implications to the schedule as does fatalities 12/02/2023 © Raphael M. Dua 16
  • 17. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY © Raphael M. Dua 2/12/2023 17
  • 18. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 18
  • 19. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 19
  • 20. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 20
  • 21. 12/02/2023 © Raphael M. Dua 21 So what has been the results of the new legislation?
  • 24. 12/02/2023 © Raphael M. Dua 24 In spite of new legislation the number of construction deaths has increased from 144 in 2019 to 169 in 2021
  • 25. 12/02/2023 © Raphael M. Dua 25 Why has there been a worsening of the numbers? From the limited research I have carried out it would appear that planners and schedulers are being pushed (told by the PM or CM) to sharpen the timeline as the results of Covid having increased costs so we need to complete as quickly as possible. Inevitability this has led to an absence of safety tasks being part of the schedule and taking time as was proposed and indeed worse – shortcuts being undertaken to reduce time and costs
  • 26. 12/02/2023 © Raphael M. Dua 26 An auto-rule in RDCPM or checklist in Acumen Fuse should REQUIRE or a FLAG for a safety activity being predecessor (maybe not immediate - and THAT requires some special coding) of an activity creating risk of injury. Perhaps a solution to this lack of visible safety tasks in the schedule could be as follows Source: Dr. Fred Plotnick – Construction CPM 2023
  • 27. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 27 In the United States the fatality rate is considerably higher than Australia
  • 28. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  In the USA, the Occupational Safety and Health Administration is responsible for all aspects of work safety and health  Work-related fatalities for cases inspected by Federal or State OSHA  Provides data on work-related fatalities that occurred under Federal OSHA and State Plan jurisdiction for cases that have been closed or citations issued on or after January 1, 2017  Employers must report worker fatalities to OSHA within eight hours. OSHA investigates all work-related fatalities in all covered workplaces. The agency has up to six months to complete an investigation and determine whether citations will be issued 12/02/2023 © Raphael M. Dua 28
  • 34. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY OSHA provides Reports of fatalities for CY17-20. (“The information is not comprehensive. We continue to update it as data becomes available”) Fatality summaries are listed in descending order from newest to oldest in the following table: 12/02/2023 © Raphael M. Dua 34
  • 35. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 35
  • 36. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 36
  • 37. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY UNITED KINGDOM WORKING DAYS LOST 12/02/2023 © Raphael M. Dua 37
  • 38. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 38
  • 39. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY It is interesting to note whilst researching the internet for this paper that in the multitude of learned material, and literature, government inquiries, etc. there is very little if any reference to schedule delays caused by Fatalities and LTI’s and other safety issues It is obvious, when researching this topic through Google, that little research into safety and the impact on a Schedules exists 12/02/2023 © Raphael M. Dua 39
  • 40. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  Research  Recent studies indicate that investing in health and safety can yield financial advantages. Some highlights for example: • Accident prevention can be improved without higher costs and slower schedules • Workplace injuries account for 6-9% of project costs whereas an effective health and safety program accounts for only 2.5% of those costs. • The higher the safety investment in a project, the lower the injury rates and the higher the profit • Increased training, more frequent inspections, and more health and safety meetings with field supervisors result in fewer lost-time injuries, lower costs, and a larger profit margin • CSAO found that construction workers with back injuries who participate in a back care program are less likely to be re-injured than those who don't participate 12/02/2023 © Raphael M. Dua 40
  • 41. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 41 If, in the unfortunate event of a fatality on the task, it is the subject of a criminal offence in Australia, a Culpable Homicide in the US and in the UK, it will shut the project site down until the WorkSafe /OSHA inspectors determine that the site is safe after remedial work has taken place • In the UK, a Company Director and project manager were sentenced after a construction worker sustained fatal crush injuries, as well as a fine
  • 42. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY In Australia, when a fatality occurs on a construction site it is immediately closed down by the local WorkSafe organisation 12/02/2023 © Raphael M. Dua 42
  • 43. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY So what is the impact on the project plan, the schedule and cost from this stoppage? 12/02/2023 © Raphael M. Dua 43
  • 44. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  All jurisdictions around the world have similar safety laws, but it is rare to find the average Planner and/or Scheduler who has any reasonable knowledge of the compulsory nature of all the requirements. This knowledge is imperative so that they can make informed decisions as to estimate of the impact of particular regulations on the duration of a specific task  The Planner must take into account all of the dependent work and safety requirements before determining the task duration. But so often there is no visibility in the schedule to indicate that safety risks have been mitigated 12/02/2023 © Raphael M. Dua 44
  • 45. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY It is very rare to see in a construction schedule where the time required for safety tasks have been included. It is often said to be included in the JSA or SWMS Some major contractors do plan and schedule such so that any safety risks have been mitigated and that the work to ensure the worker’s safety is visible However, these contractors are in a minority 12/02/2023 © Raphael M. Dua 45
  • 46. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 46 According to some Construction PMs the causes of Schedule Delays in Construction Projects are: 1.Construction site access 2.Differing site conditions 3.Force majeure 4.Adverse weather
  • 47. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY A serious shortcoming, in maintaining safety in the daily workflow, is when a project is running behind schedule and the project director is pressuring the foreman to get the work done as the need to complete on time is all important The workers themselves feel that pressure and will take shortcuts to get the task completed and inevitably cause an accident, which may prove fatal 12/02/2023 © Raphael M. Dua 47
  • 48. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY For more information in this area read “Distinguished Professor Helen Lingard” of RMIT seminal work 12/02/2023 © Raphael M. Dua 48
  • 49. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY Fatalities involve both direct costs and indirect costs. Direct costs consist of: • medical expenses such as ambulance, hospital, and doctors' fees, medication • counselling of site employees and contractors • compensation payments • WorkSafe Victoria premium increases • litigation costs 12/02/2023 © Raphael M. Dua 49
  • 50. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  Indirect costs include:  Disrupted work schedules, lost productivity, clean-up and repair, hiring and training replacement workers, bad publicity, reputational damage, and time spent on accident investigation, claims management, and litigation  Re-engineering  Design implications  Constructability / methodology  Having to replan and reschedule the remaining work on the project, which may have a serious impact on the project completion date 12/02/2023 © Raphael M. Dua 50
  • 51. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY Since the Westgate and the Milford Haven box girder bridge collapses back in the 1970’s, strong OHS laws have been promulgated to prevent such events This includes the introduction of Job Safety Analysis (JSA) and a SafeWork Method Statement (SWMS). Documentation to mitigate any risks which may be present in the construction process is now mandatory 12/02/2023 © Raphael M. Dua 51
  • 52. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY However, in many schedules it is not obvious how much time has been allowed by the planner in the task durations for the implementation of the defined safety requirements The safety and work methodology is generally discussed at a “Toolbox meeting” first thing at the start of day or shift Also missing are other identified risks as defined in the JSA or SWMS 12/02/2023 © Raphael M. Dua 52
  • 53. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 53 What are the risks?
  • 54. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY Notice that OHS&E is not considered a risk, which says it all This would indicate that the schedule will fail to deliver if a serious safety event occurs, especially a fatality 12/02/2023 © Raphael M. Dua 54
  • 55. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  According to J.J. Smallwood, Associate Professor, Department of Construction Management, University of Port Elizabeth, Port Elizabeth, South Africa in his paper on:  THE ROLE OF HEALTH AND SAFETY IN PROJECT MANAGEMENT  “Inadequate or the lack of occupational health and safety not only negatively affects the traditional construction project parameters of cost, quality and schedule, but the sustainability of the environment. Occupational fatalities, injuries and disease constitute defects as they are not project requirements. They also contribute to the cost of construction and development as workers’ compensation insurance is included as a labour overhead and the cost of accidents is integrated into the cost structure of contractors.” 12/02/2023 © Raphael M. Dua 55
  • 56. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  Plan Ahead  Ensure all prework activities, such as approvals, are completed before work begins.  A thoughtful planning process can help the workday start on a more efficient and safer standing.  Implement zoning to block off areas where certain tasks will take place,  install nets and catch platforms and apply any other necessary safety measures. Keep the work areas free from building refuse 12/02/2023 © Raphael M. Dua 56
  • 57. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY  Because  • …major programs are not just magnified versions of smaller projects, they are a completely different breed in terms of their level of aspiration, lead times, complexity, and stakeholder involvement.² •  …9 out of 10 major programs incur cost overruns.³  • …cost overruns of 50-100% are not uncommon for major programs.³•  …end-user demand and overall benefits of major programs are typically overestimated by 20-70% compared with actual developments ³ •  Construction disputes are increasing due to complex programs; multi-geography delivery, faster paced schedules and external economic factors⁴ 12/02/2023 © Raphael M. Dua 57
  • 58. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 58 According to Saleh Al-Wadei in his
  • 59. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 59
  • 60. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 60 In Saleh’s dissertation, there is no mention of OHS&E and / or safety issues as being a cause of project schedule failures, His research is based on a wide range of projects in several countries but does not consider how the failure to ensure safety has quite an impact on schedule delay
  • 61. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 61 What changes require to be made to Planning and Scheduling?
  • 62. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 62 Changes required to mitigate the delays due to LTI’s & Fatalities? • The Planner when developing the plan for the schedule should identify all those areas of the project and the site which have safety implications and identify those tasks which are to be implemented in those areas • These tasks should be coded such that the different types of safety risks have been identified so that they can be selected in reports used when preparing the JSA’s or SWMS, as this will provide the lead trade with the schedule information and duration planned for the task. This may of course indicate that once the sub tasks are specified in the JSA that the planned duration is either too short or most unlikely, too long • These reports should be produced at least two weeks before the planned start of the tasks
  • 63. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 63 The scheduler must show within the schedule visibility of the pre-work required for a complex task which may have to comply with safety requirements as defined by the site OHS&E superintendent. Also ensure that the duration allows time to perform safe work If, in the unfortunate event of a fatality on the task, it is the subject of a criminal offence in Australia, a Culpable Homicide in the US and in the UK, it will shut the project site down until the WorkSafe /OSHA inspectors determine that the site is safe after remedial work has taken place • In the UK, a Company Director and project manager were sentenced after a construction worker sustained fatal crush injuries, as well as a fine
  • 64. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 64 What do other professional Planners and Schedulers say about accounting for safety in a Schedule?
  • 65. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 65 Mike Testro, a well known, international Planner , Scheduler & Forensic Analyst says the following:- “Most construction contracts that I have read a breach of safety is not a relevant event for an extension of time which means that the contractor bears the whole risk, it is important therefore that the planner allows for contingency in the programme. Whenever I put together a construction programme I always ensure that site safety is at the forefront of my planning and sequencing, but I admit that I do not highlight the fact that I've done so. Things like isolation zones for hot working would be in place but I do not mention it anywhere in the text. Situations such as having a safe overhead barrier when working underneath, I always ensure that there are three structural zones above the working zone and that all props and frames are clear .It would be very simple when tasks involved in safety aspects have a different colour code so that they are easily identified. Here in the UK site safety has a high importance in the management structure and actual fatalities are rare but when they do happen then the site is shut down for a full investigation and I've not yet seen construction programme where such a contingency is built in advance. Nobody anticipates such a thing happening in any case.”
  • 66. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 66 •Chris Carson FRICS, FAACE, FGPC, PSP, DRMP, CEP, CCM, PMP, who is the Enterprise Director of Program & Project Controls & Associate Vice President at Arcadis says’ “One of the six fundamental H&S principles that Arcadians have to adhere to is “Undertake H&S Planning”, and we do look at the H&S plan that is developed for a project to see if there are any time implications to the plan. Our engineering designers work under an Arcadis safety design that prioritizes safe design; Elimination (design it out), Substitution (use something else), Engineering Controls (isolation and guarding), Administrative Controls (training and work scheduling), and Personal Protective Equipment (last resort). And they particularly look at safety during construction activities. During design, they also have a checklist that includes things like: providing permanent safe access to roofs, plant rooms, and windows for maintenance and repair, eliminating need for install temporary barriers by integrated guardrail systems along roof edges, lifting lugs installed in to prefab equipment/structure, ergonomic principles to avoid designing construction activities that require repetitive or prolonged movements. When developing a schedule, we do look at their design safety issues”
  • 67. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 67 Recommendations
  • 68. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 68 Perform Constructability Reviews Performing a constructability review requires an intimate knowledge of the project. The unfortunate reality is that when a mere few days is set aside for this important step the reviewer barely has enough time to attain an overview of the project, much less review and understand its intricacies. There are five important steps in performing the review, as shown below
  • 69. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 69 1.Build the Project; Don't focus solely on the problems. Ensure the Planners and Schedulers are present at the meetings. Only by taking the time to walk through the construction process step by tedious step will the problems be discovered. Look for all the potential construction risks and complex and perhaps dangerous work needs. Ensure sufficient time has been allowed to execute the tasks safely 2. Review the Interface of Various Systems. Whether it be interior, exterior, structural or MEP, problems are not discovered nearly as frequently within the body of a system as they are at the perimeter of a system where it interfaces with the various adjacent systems and trades, and the need to ensure safety
  • 70. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 70 3.Keep the Review of Preliminary Documents Constructive. When performing a constructability review on 50%, 75%, or even 90% documents, be cognizant that the design documents are not complete. Check for any safety implications at the various interfaces 4.Stay Focused on the Important Items. Before making a comment to the design team, ask two questions. First, "Will this impact the cost, time, quality of the project?” or secondly “Will the design compromise safety of the project?" 5. Take the Time to Complete a Thorough Review. A thorough constructability review will take weeks, even months, but for every hour spent planning a project the hours saved down the road are exponential. It may well save a life or prevent any LTI’s
  • 71. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 71 Summary There must be sufficient time in the Schedule to carry out the execution of every task to ensure that no shortcuts are taken. There must be no dangerous work practices or avoidance of legislated OHS&E requirements. All must be fully met and be visible to all the construction workers Management has a very important role to play to ensure that everybody goes home every night, and that failure to do so attracts severe Criminal penalties
  • 72. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 72 References ¹ (Lingard & Rowlinson, 2004;Sunindijo & Zou, 2011). 2 Bent Flyvberg: What You Should Know About Megaprojects and Why: An Overview (2014) 3 Bent Flyvberg: Over Budget, Over Time, Over and Over Again: Managing Major Projects (2011) 4 Arcadis: Construction Disputes Report (2015)
  • 73. THE IMPACT OF NEW LEGISLATION ON PLANNING AND SCHEDULING, COSTS AND POTENTIAL DELAY TO PROJECT DELIVERY 12/02/2023 © Raphael M. Dua 73 I would appreciate receiving any material you may have to help me with my research work in this most important area of scheduling. I would like examples of P6, MSP, OPP, ASTA and Micro Planner schedules showing the fact that the scheduler did include the prework and provided a sensible duration to ensure safety of the workers performing the work Please forward to me: Raphael M. Düa raf@microplanning.io Cell +61 418 53 1111