SlideShare a Scribd company logo
1 of 3
Download to read offline
COLLABORATE 12 Page 1
Copyright ©2012 by Peter T. VanSickler
Data flow between P6 & CM (Save Time and Effort Utilizing the Primavera
PCM - P6 System Integration)
Peter T. VanSickler
Alutiiq, LLC – An ANC (8a) Alaskan Native Corporation, located in Anchorage Alaska. The
company has 8 divisions with the Construction Division utilizing the Oracle Primavera Contract
Management and P6 Systems.
Introduction  — With the current corporate environment of ―Doing More with Less‖ mind-set, a company can
save time and effort utilizing the Oracle-Primavera provided integration package for both Oracle Primavera Contract
Management and P6. I will be discussing the integration and one way of taking advantage of the integration
solution, provided as part of the software systems, to update a Project Schedule through data entry in the Daily
Report and then from the updated Project Schedule, creating a Payment Requisition for a Client or Subcontractor
based on schedule activity’s percent complete to determine the billable amount for the particular Schedule of Value
in the Payment Requisition.
Ease of integrating P6 and Contract Management with very
little effort — By configuring the two system to point at each other,
utilizing the system’s Primavera Administrator; the key piece is completed.
Once a Project is created in the PCM System and the P6 System, the two
projects need to be linked and data items to flow between the systems need to
be selected. After the linking of the two projects and selecting the data items,
the systems are integrated and ready for use.
The P6 system PULLS the data from PCM system and the PCM system
PULLS the data from the P6 system.
Reference: Master Note for Integrating Contract Management with P6
[ID 914068.1]
Demonstration of the CM Daily Report data to update an P6 Activity Status  — When an
employee is creating a Daily Report Document within the project, there is the ―Schedule‖ tab in which provides the
employee the opportunity to ―Get Activities‖ from the P6 Project Schedule that will Start, Finish or are In-Progress
on the day of the Daily Report date. Once the Schedule activities are pulled into the document, the activity’s status
can be updated. In addition, Schedule items that were started early can be added to the daily report using the ―Add‖
selection and a P6 Activity item can be added and then statused. With the schedule activities updated, the
information is ready to be imported (pulled) into the P6 schedule.
COLLABORATE 12 Page 2
Copyright ©2012 by Peter T. VanSickler
When the scheduling person that is updating the project schedule is
ready, the updated information can be imported into the schedule.
Prior to the actual data being updated in the system, an import log is
created documenting which schedule activities have updates, which
can be saved and reviewed. This step provides a log of the update.
The updates can be cancelled or committed to the schedule and
modified, if needed.
Using the PCM Daily Report Activities and P6 Schedule integration,
effort is saved by the person creating the Daily Report because they
are not required to enter the activities worked, just update the
activities for that document period and pull in the other activities
that were started early. The Schedule is updated by using the data
entered as part of the Daily Report, thus saving effort by the Project
Scheduler of going through activity by activity and updating each,
just reviewing the updated status provided and modifying if needed.
Demonstration of the P6 Schedule Percent Complete data to update a Payment Requisition
Schedule of Value Item — When an employee is creating the Payment Requisition for the client or a
subcontractor in the project, the schedule of value can be linked to that actual Project schedule activity in the P6
system. This way, the billing is based on the actual percent complete from the project schedule.
The initial Payment Requisition requires the Schedule of Values to
be linked and all subsequent requisitions will have the link
automatically associated with the SOVs. When the P6 schedule
activities have been updated and has been approved for use in the
Payment Requisition, activity percent complete is then pulled into
the payment requisition for review and modification, if needed.
This pull of the Schedule Percent Complete can be done when the
subsequent requisition is generated or during the requisition process
by utilizing the ―Get Percent Complete‖ function within the Payment
Requisition Document in the ―Schedule of Values‖ section under the
COLLABORATE 12 Page 3
Copyright ©2012 by Peter T. VanSickler
―More Commands‖. Each of the Schedule of Values is then updated
with the percent complete and the billable amount is calculated to
complete the Payment Requisition.
Using the P6 Schedule Activity percent complete and the PCM
Payment Requisition Schedule of Values integration, effort is saved by
the person creating the Payment Requisition because they are not
required to enter the individual billing amount for each Schedule of
Value, just pull in the Schedule of Value activity percent complete, the
system calculates each value, totals it and it is ready for review and
modifications as needed. Since the schedule data is utilized for the
calculation of the billing values, effort is saved by the Project
Administrator or Manager of going through Schedule of Value line
item by line updating each, just reviewing the calculated values provided and modifying if needed
Conclusion — To save time, effort and data errors, it would be beneficial to a company to utilize the Oracle
Primavera Contract Management – P6 integration system provided with each system. It requires a few simple steps
to create links between the systems and projects and provides huge benefits. Time and effort is saved in just
utilizing the project daily report activities updates to update the project schedule along with the updated schedule to
update and calculate the payment requisition schedules of values. There are many other benefits provided with the
PCM – P6 integration not covered here which are documented on the Oracle ―My Support‖ website in the
knowledge base.

More Related Content

What's hot

P6 analytics product roadmap and overview - Oracle Primavera P6 Collaborate 14
P6 analytics product roadmap and overview - Oracle Primavera P6 Collaborate 14P6 analytics product roadmap and overview - Oracle Primavera P6 Collaborate 14
P6 analytics product roadmap and overview - Oracle Primavera P6 Collaborate 14p6academy
 
Online primavera p6 advanced topics training
Online primavera p6 advanced topics trainingOnline primavera p6 advanced topics training
Online primavera p6 advanced topics trainingTen Six Consulting
 
Primavera software
Primavera softwarePrimavera software
Primavera softwareMohit Goyal
 
Using Change Management in Primavera Contract Management
Using Change Management in Primavera Contract ManagementUsing Change Management in Primavera Contract Management
Using Change Management in Primavera Contract Managementp6academy
 
Primavera EPPM in Asset-Intensive Organizations
Primavera EPPM in Asset-Intensive OrganizationsPrimavera EPPM in Asset-Intensive Organizations
Primavera EPPM in Asset-Intensive Organizationsp6academy
 
Oracle primavera eppm presentation
Oracle primavera eppm presentationOracle primavera eppm presentation
Oracle primavera eppm presentationThanh Hoang Lam
 
hyperion-project-financial-planning
hyperion-project-financial-planninghyperion-project-financial-planning
hyperion-project-financial-planningAdam Sheehan
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...p6academy
 
Oracle primavera p6 and ebs projects where do they meet ppt
Oracle primavera p6 and ebs projects   where do they meet pptOracle primavera p6 and ebs projects   where do they meet ppt
Oracle primavera p6 and ebs projects where do they meet pptp6academy
 
Resume of Dale Halterman
Resume of Dale HaltermanResume of Dale Halterman
Resume of Dale Haltermandalehalterman
 
PMO View Dashboard Brochure_2 Page.compressed
PMO View Dashboard Brochure_2 Page.compressedPMO View Dashboard Brochure_2 Page.compressed
PMO View Dashboard Brochure_2 Page.compressedRuss King
 
Primavera vision & roadmap collaborate13 april 2013
Primavera vision & roadmap collaborate13 april 2013Primavera vision & roadmap collaborate13 april 2013
Primavera vision & roadmap collaborate13 april 2013p6academy
 
Oracle primavera and bpm the power of integration ppt
Oracle primavera and bpm   the power of integration pptOracle primavera and bpm   the power of integration ppt
Oracle primavera and bpm the power of integration pptp6academy
 
Case Study for Project Management System Using Sharepoint
Case Study for Project Management System Using SharepointCase Study for Project Management System Using Sharepoint
Case Study for Project Management System Using SharepointMike Taylor
 

What's hot (20)

P6 analytics product roadmap and overview - Oracle Primavera P6 Collaborate 14
P6 analytics product roadmap and overview - Oracle Primavera P6 Collaborate 14P6 analytics product roadmap and overview - Oracle Primavera P6 Collaborate 14
P6 analytics product roadmap and overview - Oracle Primavera P6 Collaborate 14
 
Online primavera p6 advanced topics training
Online primavera p6 advanced topics trainingOnline primavera p6 advanced topics training
Online primavera p6 advanced topics training
 
Primavera software
Primavera softwarePrimavera software
Primavera software
 
SAP PPM 6.0 powered by HANA
SAP PPM 6.0 powered by HANASAP PPM 6.0 powered by HANA
SAP PPM 6.0 powered by HANA
 
Primavera software
Primavera softwarePrimavera software
Primavera software
 
Using Change Management in Primavera Contract Management
Using Change Management in Primavera Contract ManagementUsing Change Management in Primavera Contract Management
Using Change Management in Primavera Contract Management
 
Primavera EPPM in Asset-Intensive Organizations
Primavera EPPM in Asset-Intensive OrganizationsPrimavera EPPM in Asset-Intensive Organizations
Primavera EPPM in Asset-Intensive Organizations
 
Oracle primavera eppm presentation
Oracle primavera eppm presentationOracle primavera eppm presentation
Oracle primavera eppm presentation
 
hyperion-project-financial-planning
hyperion-project-financial-planninghyperion-project-financial-planning
hyperion-project-financial-planning
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...
 
Oracle primavera p6 and ebs projects where do they meet ppt
Oracle primavera p6 and ebs projects   where do they meet pptOracle primavera p6 and ebs projects   where do they meet ppt
Oracle primavera p6 and ebs projects where do they meet ppt
 
SAP sample
SAP sampleSAP sample
SAP sample
 
Resume of Dale Halterman
Resume of Dale HaltermanResume of Dale Halterman
Resume of Dale Halterman
 
Pmi lexicon
Pmi lexiconPmi lexicon
Pmi lexicon
 
PMO View Dashboard Brochure_2 Page.compressed
PMO View Dashboard Brochure_2 Page.compressedPMO View Dashboard Brochure_2 Page.compressed
PMO View Dashboard Brochure_2 Page.compressed
 
Primavera vision & roadmap collaborate13 april 2013
Primavera vision & roadmap collaborate13 april 2013Primavera vision & roadmap collaborate13 april 2013
Primavera vision & roadmap collaborate13 april 2013
 
Oracle primavera and bpm the power of integration ppt
Oracle primavera and bpm   the power of integration pptOracle primavera and bpm   the power of integration ppt
Oracle primavera and bpm the power of integration ppt
 
Case Study for Project Management System Using Sharepoint
Case Study for Project Management System Using SharepointCase Study for Project Management System Using Sharepoint
Case Study for Project Management System Using Sharepoint
 
Avinash_ Resume_
Avinash_ Resume_Avinash_ Resume_
Avinash_ Resume_
 
Kjf16d1 chron
Kjf16d1 chronKjf16d1 chron
Kjf16d1 chron
 

Viewers also liked

Enhanced Unifier Reporting with BI Publisher: On Prem and Cloud
Enhanced Unifier Reporting with BI Publisher: On Prem and CloudEnhanced Unifier Reporting with BI Publisher: On Prem and Cloud
Enhanced Unifier Reporting with BI Publisher: On Prem and Cloudp6academy
 
4D Scheduling: The Reality and The Hype
4D Scheduling: The Reality and The Hype4D Scheduling: The Reality and The Hype
4D Scheduling: The Reality and The Hypep6academy
 
Trouver des ressources documentaires en open access
Trouver des ressources documentaires en open accessTrouver des ressources documentaires en open access
Trouver des ressources documentaires en open accessULB - Bibliothèques
 
Upk for p6 testing system documentation training and job alerts ppt (1)
Upk for p6 testing system documentation training and job alerts ppt (1)Upk for p6 testing system documentation training and job alerts ppt (1)
Upk for p6 testing system documentation training and job alerts ppt (1)p6academy
 
Digitheque des Archives & Bibliotheque ULB
Digitheque des Archives & Bibliotheque ULBDigitheque des Archives & Bibliotheque ULB
Digitheque des Archives & Bibliotheque ULBULB - Bibliothèques
 
Sales to Delivery Automation at Powell Industries - A Case Study
Sales to Delivery Automation at Powell Industries - A Case StudySales to Delivery Automation at Powell Industries - A Case Study
Sales to Delivery Automation at Powell Industries - A Case Studyp6academy
 
Migrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer Story
Migrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer StoryMigrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer Story
Migrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer Storyp6academy
 
Whats new in Primavera Prime 15.2?
Whats new in Primavera Prime 15.2?Whats new in Primavera Prime 15.2?
Whats new in Primavera Prime 15.2?p6academy
 
206460 primavera mobile
206460 primavera mobile206460 primavera mobile
206460 primavera mobilep6academy
 
Implementation demystification 10 keys to a successful p6 implementation wh...
Implementation demystification   10 keys to a successful p6 implementation wh...Implementation demystification   10 keys to a successful p6 implementation wh...
Implementation demystification 10 keys to a successful p6 implementation wh...p6academy
 
Increase your resource capacity without hiring ppt
Increase your resource capacity without hiring pptIncrease your resource capacity without hiring ppt
Increase your resource capacity without hiring pptp6academy
 
FNRS Règlement relatif au libre accès
FNRS Règlement relatif au libre accès FNRS Règlement relatif au libre accès
FNRS Règlement relatif au libre accès ULB - Bibliothèques
 
Primavera Integrations with special emphasis on the Cloud
Primavera Integrations with special emphasis on the CloudPrimavera Integrations with special emphasis on the Cloud
Primavera Integrations with special emphasis on the Cloudp6academy
 
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...p6academy
 
Primavera Unifier Roadmap 2015
Primavera Unifier Roadmap 2015Primavera Unifier Roadmap 2015
Primavera Unifier Roadmap 2015p6academy
 
La grande histoire de la distribution bio et du commerce éthique
La grande histoire de la distribution bio et du commerce éthiqueLa grande histoire de la distribution bio et du commerce éthique
La grande histoire de la distribution bio et du commerce éthiqueSauveur Fernandez
 

Viewers also liked (20)

Enhanced Unifier Reporting with BI Publisher: On Prem and Cloud
Enhanced Unifier Reporting with BI Publisher: On Prem and CloudEnhanced Unifier Reporting with BI Publisher: On Prem and Cloud
Enhanced Unifier Reporting with BI Publisher: On Prem and Cloud
 
4D Scheduling: The Reality and The Hype
4D Scheduling: The Reality and The Hype4D Scheduling: The Reality and The Hype
4D Scheduling: The Reality and The Hype
 
Trouver des ressources documentaires en open access
Trouver des ressources documentaires en open accessTrouver des ressources documentaires en open access
Trouver des ressources documentaires en open access
 
Upk for p6 testing system documentation training and job alerts ppt (1)
Upk for p6 testing system documentation training and job alerts ppt (1)Upk for p6 testing system documentation training and job alerts ppt (1)
Upk for p6 testing system documentation training and job alerts ppt (1)
 
Ebooks - perspectives
Ebooks - perspectivesEbooks - perspectives
Ebooks - perspectives
 
Ressources electroniques
Ressources electroniques Ressources electroniques
Ressources electroniques
 
Digitheque des Archives & Bibliotheque ULB
Digitheque des Archives & Bibliotheque ULBDigitheque des Archives & Bibliotheque ULB
Digitheque des Archives & Bibliotheque ULB
 
Sales to Delivery Automation at Powell Industries - A Case Study
Sales to Delivery Automation at Powell Industries - A Case StudySales to Delivery Automation at Powell Industries - A Case Study
Sales to Delivery Automation at Powell Industries - A Case Study
 
Migrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer Story
Migrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer StoryMigrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer Story
Migrating from Instantis 8.0 to EnterpriseTrack 8.7 - A Customer Story
 
Whats new in Primavera Prime 15.2?
Whats new in Primavera Prime 15.2?Whats new in Primavera Prime 15.2?
Whats new in Primavera Prime 15.2?
 
206460 primavera mobile
206460 primavera mobile206460 primavera mobile
206460 primavera mobile
 
Implementation demystification 10 keys to a successful p6 implementation wh...
Implementation demystification   10 keys to a successful p6 implementation wh...Implementation demystification   10 keys to a successful p6 implementation wh...
Implementation demystification 10 keys to a successful p6 implementation wh...
 
Di fusion scholar
Di fusion scholarDi fusion scholar
Di fusion scholar
 
E book, etude de cas (ULB)
E book, etude de cas (ULB)E book, etude de cas (ULB)
E book, etude de cas (ULB)
 
Increase your resource capacity without hiring ppt
Increase your resource capacity without hiring pptIncrease your resource capacity without hiring ppt
Increase your resource capacity without hiring ppt
 
FNRS Règlement relatif au libre accès
FNRS Règlement relatif au libre accès FNRS Règlement relatif au libre accès
FNRS Règlement relatif au libre accès
 
Primavera Integrations with special emphasis on the Cloud
Primavera Integrations with special emphasis on the CloudPrimavera Integrations with special emphasis on the Cloud
Primavera Integrations with special emphasis on the Cloud
 
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
 
Primavera Unifier Roadmap 2015
Primavera Unifier Roadmap 2015Primavera Unifier Roadmap 2015
Primavera Unifier Roadmap 2015
 
La grande histoire de la distribution bio et du commerce éthique
La grande histoire de la distribution bio et du commerce éthiqueLa grande histoire de la distribution bio et du commerce éthique
La grande histoire de la distribution bio et du commerce éthique
 

Similar to Data flow between p6 and cm white paper

Time based progress analysis in project system (revenue recognition) sap blogs
Time based progress analysis in project system (revenue recognition)   sap blogsTime based progress analysis in project system (revenue recognition)   sap blogs
Time based progress analysis in project system (revenue recognition) sap blogsVenu Vemula
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
 
Data flow between p6 and cm ppt
Data flow between p6 and cm pptData flow between p6 and cm ppt
Data flow between p6 and cm pptp6academy
 
Real Estate Business Review
Real Estate Business Review Real Estate Business Review
Real Estate Business Review lunaalice
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntPMA Consultants
 
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdfintegrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdfAngusMacleod20
 
Promaxpmc Presentation 1
Promaxpmc Presentation 1Promaxpmc Presentation 1
Promaxpmc Presentation 1sbalagem
 
Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...p6academy
 
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)Rego University: Integrating MSP with CA PPM (CA Clarity PPM)
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)Rego Consulting
 
Digité Enterprise v6.4
Digité Enterprise v6.4Digité Enterprise v6.4
Digité Enterprise v6.4Digite, Inc.
 
Time & labor toolbox the tools you need for a successful implementation to p...
Time & labor toolbox  the tools you need for a successful implementation to p...Time & labor toolbox  the tools you need for a successful implementation to p...
Time & labor toolbox the tools you need for a successful implementation to p...Hazelknight Media & Entertainment Pvt Ltd
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxcarolinef5
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxdonaldp2
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysGlen Alleman
 
A Planning Process
A Planning ProcessA Planning Process
A Planning Processpipmonck
 
Heavy Civil Contractors: ERP Solution
Heavy Civil Contractors:  ERP SolutionHeavy Civil Contractors:  ERP Solution
Heavy Civil Contractors: ERP SolutionVisibility by Design
 
Capex opex
Capex opexCapex opex
Capex opexRaju_p1
 

Similar to Data flow between p6 and cm white paper (20)

Time based progress analysis in project system (revenue recognition) sap blogs
Time based progress analysis in project system (revenue recognition)   sap blogsTime based progress analysis in project system (revenue recognition)   sap blogs
Time based progress analysis in project system (revenue recognition) sap blogs
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Data flow between p6 and cm ppt
Data flow between p6 and cm pptData flow between p6 and cm ppt
Data flow between p6 and cm ppt
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
Real Estate Business Review
Real Estate Business Review Real Estate Business Review
Real Estate Business Review
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons Learnt
 
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdfintegrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
integrationtcm-framework-etoxquidamian-aaceperu21-211101193750.pdf
 
Promaxpmc Presentation 1
Promaxpmc Presentation 1Promaxpmc Presentation 1
Promaxpmc Presentation 1
 
Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...
 
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)Rego University: Integrating MSP with CA PPM (CA Clarity PPM)
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)
 
SAP PS overview
SAP PS overviewSAP PS overview
SAP PS overview
 
Digité Enterprise v6.4
Digité Enterprise v6.4Digité Enterprise v6.4
Digité Enterprise v6.4
 
Time & labor toolbox the tools you need for a successful implementation to p...
Time & labor toolbox  the tools you need for a successful implementation to p...Time & labor toolbox  the tools you need for a successful implementation to p...
Time & labor toolbox the tools you need for a successful implementation to p...
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 
A Planning Process
A Planning ProcessA Planning Process
A Planning Process
 
Heavy Civil Contractors: ERP Solution
Heavy Civil Contractors:  ERP SolutionHeavy Civil Contractors:  ERP Solution
Heavy Civil Contractors: ERP Solution
 
Capex opex
Capex opexCapex opex
Capex opex
 

More from p6academy

Oracle OpenWorld 2015
Oracle OpenWorld 2015Oracle OpenWorld 2015
Oracle OpenWorld 2015p6academy
 
Plan and Execute the Right Projects— Easily and Affordably
Plan and Execute the Right Projects—  Easily and AffordablyPlan and Execute the Right Projects—  Easily and Affordably
Plan and Execute the Right Projects— Easily and Affordablyp6academy
 
What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1p6academy
 
Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2p6academy
 
Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2p6academy
 
What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1p6academy
 
What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1p6academy
 
What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1p6academy
 
What's New in Unifier 16.1
What's New in Unifier 16.1What's New in Unifier 16.1
What's New in Unifier 16.1p6academy
 
20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktopp6academy
 
Oracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 AnnouncedOracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 Announcedp6academy
 
Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1p6academy
 
P6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations OverviewP6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations Overviewp6academy
 
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM  (Web) Release 8 and laterAdministering Users, Access and Views in P6 EPPM  (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and laterp6academy
 
P6 Release 8 Installation Orientation
P6 Release 8 Installation OrientationP6 Release 8 Installation Orientation
P6 Release 8 Installation Orientationp6academy
 
Oracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value PropositionOracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value Propositionp6academy
 
Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)p6academy
 
Oracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study GuideOracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study Guidep6academy
 
Oracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study GuideOracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study Guidep6academy
 
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) ...
Primavera P6 Enterprise Project Portfolio Management 8  Essentials (1Z0-567) ...Primavera P6 Enterprise Project Portfolio Management 8  Essentials (1Z0-567) ...
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) ...p6academy
 

More from p6academy (20)

Oracle OpenWorld 2015
Oracle OpenWorld 2015Oracle OpenWorld 2015
Oracle OpenWorld 2015
 
Plan and Execute the Right Projects— Easily and Affordably
Plan and Execute the Right Projects—  Easily and AffordablyPlan and Execute the Right Projects—  Easily and Affordably
Plan and Execute the Right Projects— Easily and Affordably
 
What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1
 
Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2
 
Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2
 
What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1
 
What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1
 
What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1
 
What's New in Unifier 16.1
What's New in Unifier 16.1What's New in Unifier 16.1
What's New in Unifier 16.1
 
20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop
 
Oracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 AnnouncedOracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 Announced
 
Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1
 
P6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations OverviewP6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations Overview
 
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM  (Web) Release 8 and laterAdministering Users, Access and Views in P6 EPPM  (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
 
P6 Release 8 Installation Orientation
P6 Release 8 Installation OrientationP6 Release 8 Installation Orientation
P6 Release 8 Installation Orientation
 
Oracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value PropositionOracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value Proposition
 
Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)
 
Oracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study GuideOracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study Guide
 
Oracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study GuideOracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study Guide
 
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) ...
Primavera P6 Enterprise Project Portfolio Management 8  Essentials (1Z0-567) ...Primavera P6 Enterprise Project Portfolio Management 8  Essentials (1Z0-567) ...
Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) ...
 

Data flow between p6 and cm white paper

  • 1. COLLABORATE 12 Page 1 Copyright ©2012 by Peter T. VanSickler Data flow between P6 & CM (Save Time and Effort Utilizing the Primavera PCM - P6 System Integration) Peter T. VanSickler Alutiiq, LLC – An ANC (8a) Alaskan Native Corporation, located in Anchorage Alaska. The company has 8 divisions with the Construction Division utilizing the Oracle Primavera Contract Management and P6 Systems. Introduction  — With the current corporate environment of ―Doing More with Less‖ mind-set, a company can save time and effort utilizing the Oracle-Primavera provided integration package for both Oracle Primavera Contract Management and P6. I will be discussing the integration and one way of taking advantage of the integration solution, provided as part of the software systems, to update a Project Schedule through data entry in the Daily Report and then from the updated Project Schedule, creating a Payment Requisition for a Client or Subcontractor based on schedule activity’s percent complete to determine the billable amount for the particular Schedule of Value in the Payment Requisition. Ease of integrating P6 and Contract Management with very little effort — By configuring the two system to point at each other, utilizing the system’s Primavera Administrator; the key piece is completed. Once a Project is created in the PCM System and the P6 System, the two projects need to be linked and data items to flow between the systems need to be selected. After the linking of the two projects and selecting the data items, the systems are integrated and ready for use. The P6 system PULLS the data from PCM system and the PCM system PULLS the data from the P6 system. Reference: Master Note for Integrating Contract Management with P6 [ID 914068.1] Demonstration of the CM Daily Report data to update an P6 Activity Status  — When an employee is creating a Daily Report Document within the project, there is the ―Schedule‖ tab in which provides the employee the opportunity to ―Get Activities‖ from the P6 Project Schedule that will Start, Finish or are In-Progress on the day of the Daily Report date. Once the Schedule activities are pulled into the document, the activity’s status can be updated. In addition, Schedule items that were started early can be added to the daily report using the ―Add‖ selection and a P6 Activity item can be added and then statused. With the schedule activities updated, the information is ready to be imported (pulled) into the P6 schedule.
  • 2. COLLABORATE 12 Page 2 Copyright ©2012 by Peter T. VanSickler When the scheduling person that is updating the project schedule is ready, the updated information can be imported into the schedule. Prior to the actual data being updated in the system, an import log is created documenting which schedule activities have updates, which can be saved and reviewed. This step provides a log of the update. The updates can be cancelled or committed to the schedule and modified, if needed. Using the PCM Daily Report Activities and P6 Schedule integration, effort is saved by the person creating the Daily Report because they are not required to enter the activities worked, just update the activities for that document period and pull in the other activities that were started early. The Schedule is updated by using the data entered as part of the Daily Report, thus saving effort by the Project Scheduler of going through activity by activity and updating each, just reviewing the updated status provided and modifying if needed. Demonstration of the P6 Schedule Percent Complete data to update a Payment Requisition Schedule of Value Item — When an employee is creating the Payment Requisition for the client or a subcontractor in the project, the schedule of value can be linked to that actual Project schedule activity in the P6 system. This way, the billing is based on the actual percent complete from the project schedule. The initial Payment Requisition requires the Schedule of Values to be linked and all subsequent requisitions will have the link automatically associated with the SOVs. When the P6 schedule activities have been updated and has been approved for use in the Payment Requisition, activity percent complete is then pulled into the payment requisition for review and modification, if needed. This pull of the Schedule Percent Complete can be done when the subsequent requisition is generated or during the requisition process by utilizing the ―Get Percent Complete‖ function within the Payment Requisition Document in the ―Schedule of Values‖ section under the
  • 3. COLLABORATE 12 Page 3 Copyright ©2012 by Peter T. VanSickler ―More Commands‖. Each of the Schedule of Values is then updated with the percent complete and the billable amount is calculated to complete the Payment Requisition. Using the P6 Schedule Activity percent complete and the PCM Payment Requisition Schedule of Values integration, effort is saved by the person creating the Payment Requisition because they are not required to enter the individual billing amount for each Schedule of Value, just pull in the Schedule of Value activity percent complete, the system calculates each value, totals it and it is ready for review and modifications as needed. Since the schedule data is utilized for the calculation of the billing values, effort is saved by the Project Administrator or Manager of going through Schedule of Value line item by line updating each, just reviewing the calculated values provided and modifying if needed Conclusion — To save time, effort and data errors, it would be beneficial to a company to utilize the Oracle Primavera Contract Management – P6 integration system provided with each system. It requires a few simple steps to create links between the systems and projects and provides huge benefits. Time and effort is saved in just utilizing the project daily report activities updates to update the project schedule along with the updated schedule to update and calculate the payment requisition schedules of values. There are many other benefits provided with the PCM – P6 integration not covered here which are documented on the Oracle ―My Support‖ website in the knowledge base.