Praptono Nugroho
NIM : 03120062
Implementation of Design and Build on Development
Bali Maritime Tourism Hub (BMTH) in Port of Benoa
Ronny Durrotun Nasihien, ST.,MT
NIDN : 0720127002
“Research steps to analyze technically about choosing the right type
contract of work according to the perception of the owner of the job
using Analytical Hierarchy Process (AHP) method”
Why this is
important…?
This project is one of the efforts to support government programs related to
economic equality, reducing development gaps and inequality in Indonesia,
and increasing trade in Eastern Indonesia
1
2 Choosing the right type of contract is one of the most important managerial
decisions because it has a direct impact on the success of project as it affects
performance indicators such as cost, quality, times and job safety
To find out what the main factors to choose the type of contract
3
Over View
ZONA
PERIKANAN
ZONA YACHT
TERMINAL
ZONA
PARIWISAT
A
ZONA CURAH
CAIR DAN
PETIKEMAS
DUMPING I PELABUHAN
BENOA EKSISTING
BALI
TENTEN
MELASTI
TAMAN DANU
KERTHI
https://www.youtube.com/watch?v=aVNMBbe-xZ0&t=7s
What the best type of contract for
deliver oof developed Bali
Maritime Touris Hub (BMTH)
project according to the
perception of the owner?
Research Variable
Variabel bebas (Independent
Variable)
1. Compleks of project
2. Urgent of project
3. The major criteria
influencing
Time
Cost
Quality
Desain Bid
Build
Desain And
Build
Desain And
Managemnet
Variabel terikat ( Dependent
Variable)
Choosing the right type of
contract is one of the most
important managerial decisions
because it has a direct impact on the
success of project as it affects
performance indicators such as cost,
quality, times and job safety
Methodology
Contract type selection
Problems
Determination of Criteria
Presentation of calculation
results and discussion
Begin
Study of literature
Criteria Assessment AHP Method
Expert
Finished
Data collection:
1. Primary Data : 2. Secondary Data :
- Interview result - Port master plan data
- Questionnaire result - Development plan data
Selecting Criteria
Resume criteria for selecting the type of contract
according to the reference : Grouping the results of previous research :
“These criteria will be used as a
questionnaire to experts”
Cost
uncertainty
Technical
uncertainty
Scope
uncertainty
Process
Uncertainty
Budget
availability
Backup
Availability
Resource
Long
Term
Goals
Critical
schedule
Performance
Claim
Contractor
Difficulty
Technology
Risk
Allocation
Political
factor
Hosseini et al., (2016) X X X X X X X
Kardila & Ranggadara,
(2020)
X X X X
Antoniou et al., (2012) X X X X X X X X X
Antoniou et al., (2013) X X X X X X X X X
Moon et al., (2011) X X X X X
Mahdi & Alreshaid, (2005) X X X X X X X X X X X
Barati et al., (2015) X X X X X X X X X X X
Setiawan, (2005) X X X X X X
Abed, (2015) X X X X X X X X X X X X X X
Ahmed & El-Sayegh,
(2021)
X X X X X X X X X
Bhakti et al., (2013) X X X X
Fauziyah et al., (2016) X X X X X X
Suryadinata Hartono,
(2016)
X X X X X X
DBIA, (2015) X X X X X X X X
Group Scope
Technical
Aspects
Technical uncertainty, Scope uncertainty,
Process Uncertainty, Performance,
Technology.
Financial
Aspects
Cost uncertainty , Budget availability ,
Backup Availability Resource
Legal
Aspects
Political factor
Project
Schedule
Long Term Goals , Critical schedule ,
Contractor Difficulty
Risk Claim, Risk Allocation
Criteria
Reference
AHP Processes
1
Make hierarchy
tree
Pairwise Comparison
2 3
Eigen vector (Ev)
4
Consistency
1. Maksimun Eigen
Value (MEV)
2. Consistency Index
(CI)
3. Consistency Ratio
(CR)
5
Global
Priority
CR < 0,1
Yes
No CR > 0,1
Expert profile (25 expert)
Experiences
Expert
Contract type selection
Technical
Aspect
23.34 %
Financial
Aspect
15.79 %
Legal
Aspect
26.90 %
Project
schedule
13.83 %
Desain – Bid – Build
Contract
26.42 %
Desain and Build Contract
50.12 %
Risk
Aspect
20.14 %
Desain and Management
Contract
23.45 %
Result
The results are then compared with the data
from interviews where most of the expert
explained that the biggest issues that often
occur at project sites are social, political,
legal and technical Issues. From this it can
be concluded that the assessment or
research carried out can describe the
owner’s perception regarding the
implementation of work at that location
Consistensi Ratio (CR)
CR =
CI , RI =1.12 (of Satty table)
RI
CR = 0.091
CR < 0,1
Yes
Thank You

More Related Content

Similar to AHS BMTH Journal Presentation.pptx

Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Controlcivej
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Controlcivejjour
 
Innovative project management practices for large power sector projects.
Innovative project management  practices for large power sector projects.Innovative project management  practices for large power sector projects.
Innovative project management practices for large power sector projects.sanjeeev bahadur, m.tech,mba
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewIRJET Journal
 
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSAN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSFredy Kurniawan
 
An Integrated Project Evaluation Tool for PFI Seaport Project
An Integrated Project Evaluation Tool for PFI Seaport ProjectAn Integrated Project Evaluation Tool for PFI Seaport Project
An Integrated Project Evaluation Tool for PFI Seaport ProjectFredy Kurniawan
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET Journal
 
The people factor in contracts and procurement, Barry Trebes, 16th June 2016
The people factor in contracts and procurement, Barry Trebes, 16th June 2016The people factor in contracts and procurement, Barry Trebes, 16th June 2016
The people factor in contracts and procurement, Barry Trebes, 16th June 2016Association for Project Management
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...IRJET Journal
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassanOyeniyi Samuel
 
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...IRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
Projrkzni menadžment - istraživanje
Projrkzni menadžment - istraživanjeProjrkzni menadžment - istraživanje
Projrkzni menadžment - istraživanjemsisko
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsIRJET Journal
 

Similar to AHS BMTH Journal Presentation.pptx (20)

Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
Innovative project management practices for large power sector projects.
Innovative project management  practices for large power sector projects.Innovative project management  practices for large power sector projects.
Innovative project management practices for large power sector projects.
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSAN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
 
An Integrated Project Evaluation Tool for PFI Seaport Project
An Integrated Project Evaluation Tool for PFI Seaport ProjectAn Integrated Project Evaluation Tool for PFI Seaport Project
An Integrated Project Evaluation Tool for PFI Seaport Project
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction Project
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
The people factor in contracts and procurement, Barry Trebes, 16th June 2016
The people factor in contracts and procurement, Barry Trebes, 16th June 2016The people factor in contracts and procurement, Barry Trebes, 16th June 2016
The people factor in contracts and procurement, Barry Trebes, 16th June 2016
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
Proposal .pdf
Proposal .pdfProposal .pdf
Proposal .pdf
 
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
 
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
Projrkzni menadžment - istraživanje
Projrkzni menadžment - istraživanjeProjrkzni menadžment - istraživanje
Projrkzni menadžment - istraživanje
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 

Recently uploaded

Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsKarakKing
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxPooja Bhuva
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the ClassroomPooky Knightsmith
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jisc
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxCeline George
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - Englishneillewis46
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 

Recently uploaded (20)

Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 

AHS BMTH Journal Presentation.pptx

  • 1. Praptono Nugroho NIM : 03120062 Implementation of Design and Build on Development Bali Maritime Tourism Hub (BMTH) in Port of Benoa Ronny Durrotun Nasihien, ST.,MT NIDN : 0720127002
  • 2. “Research steps to analyze technically about choosing the right type contract of work according to the perception of the owner of the job using Analytical Hierarchy Process (AHP) method” Why this is important…? This project is one of the efforts to support government programs related to economic equality, reducing development gaps and inequality in Indonesia, and increasing trade in Eastern Indonesia 1 2 Choosing the right type of contract is one of the most important managerial decisions because it has a direct impact on the success of project as it affects performance indicators such as cost, quality, times and job safety To find out what the main factors to choose the type of contract 3
  • 3. Over View ZONA PERIKANAN ZONA YACHT TERMINAL ZONA PARIWISAT A ZONA CURAH CAIR DAN PETIKEMAS DUMPING I PELABUHAN BENOA EKSISTING BALI TENTEN MELASTI TAMAN DANU KERTHI https://www.youtube.com/watch?v=aVNMBbe-xZ0&t=7s
  • 4. What the best type of contract for deliver oof developed Bali Maritime Touris Hub (BMTH) project according to the perception of the owner? Research Variable Variabel bebas (Independent Variable) 1. Compleks of project 2. Urgent of project 3. The major criteria influencing Time Cost Quality Desain Bid Build Desain And Build Desain And Managemnet Variabel terikat ( Dependent Variable) Choosing the right type of contract is one of the most important managerial decisions because it has a direct impact on the success of project as it affects performance indicators such as cost, quality, times and job safety
  • 5. Methodology Contract type selection Problems Determination of Criteria Presentation of calculation results and discussion Begin Study of literature Criteria Assessment AHP Method Expert Finished Data collection: 1. Primary Data : 2. Secondary Data : - Interview result - Port master plan data - Questionnaire result - Development plan data
  • 6. Selecting Criteria Resume criteria for selecting the type of contract according to the reference : Grouping the results of previous research : “These criteria will be used as a questionnaire to experts” Cost uncertainty Technical uncertainty Scope uncertainty Process Uncertainty Budget availability Backup Availability Resource Long Term Goals Critical schedule Performance Claim Contractor Difficulty Technology Risk Allocation Political factor Hosseini et al., (2016) X X X X X X X Kardila & Ranggadara, (2020) X X X X Antoniou et al., (2012) X X X X X X X X X Antoniou et al., (2013) X X X X X X X X X Moon et al., (2011) X X X X X Mahdi & Alreshaid, (2005) X X X X X X X X X X X Barati et al., (2015) X X X X X X X X X X X Setiawan, (2005) X X X X X X Abed, (2015) X X X X X X X X X X X X X X Ahmed & El-Sayegh, (2021) X X X X X X X X X Bhakti et al., (2013) X X X X Fauziyah et al., (2016) X X X X X X Suryadinata Hartono, (2016) X X X X X X DBIA, (2015) X X X X X X X X Group Scope Technical Aspects Technical uncertainty, Scope uncertainty, Process Uncertainty, Performance, Technology. Financial Aspects Cost uncertainty , Budget availability , Backup Availability Resource Legal Aspects Political factor Project Schedule Long Term Goals , Critical schedule , Contractor Difficulty Risk Claim, Risk Allocation Criteria Reference
  • 7. AHP Processes 1 Make hierarchy tree Pairwise Comparison 2 3 Eigen vector (Ev) 4 Consistency 1. Maksimun Eigen Value (MEV) 2. Consistency Index (CI) 3. Consistency Ratio (CR) 5 Global Priority CR < 0,1 Yes No CR > 0,1 Expert profile (25 expert) Experiences Expert
  • 8. Contract type selection Technical Aspect 23.34 % Financial Aspect 15.79 % Legal Aspect 26.90 % Project schedule 13.83 % Desain – Bid – Build Contract 26.42 % Desain and Build Contract 50.12 % Risk Aspect 20.14 % Desain and Management Contract 23.45 % Result The results are then compared with the data from interviews where most of the expert explained that the biggest issues that often occur at project sites are social, political, legal and technical Issues. From this it can be concluded that the assessment or research carried out can describe the owner’s perception regarding the implementation of work at that location Consistensi Ratio (CR) CR = CI , RI =1.12 (of Satty table) RI CR = 0.091 CR < 0,1 Yes