1. Salient Features of the Project
Catchment area : 1,915 km2
Reservoir Capacity : 32.2 million m3
Reservoir impounded area : 1.88 km2
Design Discharge : 88.0 m3
/s
Gross Head : 220 m
Plant Factor : 52 %
Installed Capacity : 150 MW
Annual Energy Output : 682 GWh/year
Length of Headrace tunnel : 7803 m
Length of Penstock : 849 m
Peshawar Islamabad
Project Site
Dam Site
Powerstation Site
-vii-
Frontispiece 1 Site Location for Sharmai Hydropower Project