2. Enter the “WBS Detail List” function in your menu in the WBS tab
Choose the project and the contract you want to work on
Define the WBS of this project from level 1 up to level 4 as shown in this example
Numeric
Level1:2 Characters
Level2:4 Characters
Level3:8 Characters
Level4:12 Characters
Example in next slide
4. Than go to the second function “Define WBS vs. BOQ Take off”
Choose any WBS already defined and link correspondent BOQs to it.
You have to add the take off quantity of every BOQ on its WBS
You can see the cumulative quantity of this BOQ
The cumulative quantity should not exceed the contractual quantity or you will receive an error
Allocate qty to this
Specific WBS
System gives you
The total allocated for
All WBS you entered
System shows you
The BOQ qty as per
contract
NB: you can enter take off at any level