A PROJECT REPORT ON CONSTRUCTION OF ROADS IN NIT
WARANGAL CAMPUS
By
NARHARI SAI(128937)
NISHANT SINGH(128938)
P.VALLIAPPAN(128939)
PAGIDIMARRI GEETHA(128940)
PALAKURTHY ANUSHA(128941)
Under the Guidance of
Sri. Syed Habeeb
(Faculty)
SCHOOL OF MANAGEMENT
NATIONAL INSTITUTE OF TECHNOLOGY
WARANGAL (2012-2014)
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 1
CERTIFICATE
This is to certify that the candidates Narahari sai G , Nishant Singh , P.Valliappan ,
Pagidimarri Geetha , Palakurthy Anusha who are the students of NATIONAL INSTITUTE
OF TECHNOLOGY, has completed their project “Construction of Roads in NIT Warangal”
in Warangal, Andhra Pradesh.
This project is the record of the authentic work carried out during the academic year 2012-2014.
They have done this project by themselves as a team
Syed Habeeb
(Faculty)
School Of Management
National Institute Of Technology
Warangal, Andhra Pradesh
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 2
DECLARATION
We declare that this written submission represents ours ideas in our own words and where others’
ideas or words have been included, we have adequately cited and referenced the original sources.
We also declared that we have adhered to all principles of academic honesty and integrity and
have not misrepresented or fabricated or falsified any idea/data/fact/source in my submission. we
understand that any violation of the above will cause for disciplinary action by the institute and
can also evoke penal action from the sources which have not been properly cited or from whom
proper permission has not been taken when needed.
NARHARI SAI(128937)
NISHANT SINGH(128938)
P.VALLIAPPAN(128939)
PAGIDIMARRI GEETHA(128940)
PALAKURTHY ANUSHA(128941)
Date: 07-11-12
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 3
CONTENTS
1.INTRODUCTION……………………………………………………..8
OBJECTIVE
TYPES OF ROADS……………………………………………………………………………………...10
STATUS OF MAIN HIGHWAYS……………………………………………………………………….11
NATIONAL HIGHWAY DEVELOPMENT PROJECT…………………………………………………12
ROAD CONSTRUCTION………………………………………………………………………………..14
CONSTRUCTION MATERIAL………………………………………………………………………….14
ROAD CONSTRUCTION EQUIPMENT………………………………………………………………..14 1.7FLYASH
FOR ROAD EMBANKMENT………………………………………………………………..16
MATERIAL FOR ROAD PAVEMENT…………………………………………………………………18
2.PROJECT LIFE CYCLE………………………………………………21
2.1 PHASES IN ROAD CONSTRUCTION…………………………………………………………………..22
3.TOOLS AND TECHNIQUES…………………………………………24
WORK BREAKDOWN STRUCTURE………………………………………………………………….25
ACTIVITY DIAGRAM………………………………………………………………………………….28
GANTT CHART………………………………………………………………………………………....29
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 4
4.FINDING AND CONCLUSIONS……………………………………..30
KNOWLEDG AREAS
4.1 PROJECT SCOPE MANAGEMENT………………………………………………………………………31
4.2PROJECT COST MANAGEMENT………………………………………………………………………...31 4.3
PROJECT INTEGRATION MANAGEMENT…………………………………………………………….31
4.4PROJECT HUMAN RESOURCE MANAGEMENT……………………………………………………….32
PROJECT PROCUREMENT MANAGEMENT……………………………………………………………32
PROJECT TIME MANAGEMENT…………………………………………………………………………32 4.FINDINGS
AND CONCLUSTIONS………………………………………………………………………….33
5. BIBLIOGRAPHY………………………………………………………34
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 5
EXECUTIVE SUMMARY
Construction planning and execution is a fundamental and challenging activity in the
management of construction projects. It involves the choice of technology, the definition of work
tasks, the estimation of the required resources and durations for individual tasks, and the
identification of any interactions among the different work tasks. A good construction plan is the
basis for developing the budget and the schedule for work. Developing the construction plan is a
critical task in the management of construction, even if the plan is not written or otherwise
formally recorded. In addition to these technical aspects of construction planning, it may also be
necessary to make organizational decisions about the relationships between project participants
and even which organizations to include in a project. For example, the extent to which sub-
contractors will be used on a project is often determined during construction planning.
Construction time performance (CTP) and flexibility in approaches to project time planning have
been shown to be significantly associated. This raises interesting questions about how effective
planning and control to facilitate flexibility in overcoming unexpected problems may be
achieved. Various tools and techniques such as Gantt chart, activity diagram and Work
Breakdown Structure (WBS) have aided the road construction projects in an effective manner.
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 6
Site view of Roads in NIT Warangal Campus
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 7
CHAPTER 1
INTRODUCTION
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 8
OBJECTIVE :
Complete the project in the specified time horizon and allocated cost.
Deliver value to the customers by providing excellent customer support.
Roads are an integral part of the transport system. A country’s road network should be efficient in
order to maximize economic and social benefits. They play a significant role in achieving
national development and contributing to the overall performance and social functioning of the
community. It is acknowledged that roads enhance mobility, taking people out of isolation and
therefore poverty. In China for instance, the government has popularized this belief by
emphasizing that for any economy to develop, transport must start off first which will later
stimulate other sectors to develop in an orderly fashion
The most important factors which are needed in the developing country are economics, political
and military. Each of them play great role in the respective part but they cannot perform an
excellence job without proper communication and transportation. There are three main kinds of
transportation, they are by air, land and water .There are two main transportations on land, they
are trains and cars but roads are necessary for both of them. Cars can be driven without roads but
it is difficult and very dangerous. Trains cannot travel with railroads. It is very hard to travel in
tropical country such as Myanmar in raining season without a road. There are muds everywhere
and they always cause trouble for cars and trains. Thus our government is building roads and
railroads around the country for the safety of the citizens. The basic of economic is trading and
when people trade, the transportation will be needed. The country economic will develop when
people travel to different the places and do businesses. When the politic ants travel around the
country to meet the public, they will also need a road. When the military officers receive an order
to check an area for the safety of the citizens, they will need roads to get there as soon as
possible. By that way people can stay at their houses safe and sound. So people will love the
their leader and obey the laws of our country.
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 9
1.Types Of Roads:
1.1. Generally private roads:
Driveway
1.2. Lower capacity highways
AlleyArterial roadAvenuBackroadBoulevardTerrace
BywayCollector roadCourtCul -de- sacDirt road
Frontage roadHighwayLaneRoadRouteSingle carriageway
StreetWinter road
1.3. Higher capacity highways, sometimes with medians
Parkway
Expressway
Turnpike
2+1 road
2+2 road
Farm to Market Road
1.4. Limited access HYPERLINK "http://en.wikipedia.org/wiki/Grade-
separated" grade-separated highways
Autobahn
Auto-estrada
Autopista
Autostrada
Autostrasse
Controlled-access highway
Expressway, a term used inconsistently in different locations; see Controlled-access highway and
Limited-access highway
Freeway
High-quality dual carriageway (HQDC)
Interstate Highway
Limited-access highway
Motorway
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 10
“…IT IS NOT WEALTH THAT BUILT THE ROADS BUT, ROADS
THAT BUILT OUR WEALTH”
-John F. Kennedy
1. INDIAN ROAD NETWORK-CURRENT STATUS
National Highway (NH)
58,112
State Highways (SH)
1,37,119
Major District Roads (MDR)
4,70,000
Village and Other Roads (ODR &
26,50,000
VR)
Total Road Length
33,15,231
NHs are less than 2% of network but carry 40% of total traffic
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 11
2. STATUS OF MAIN HIGHWAYS
Carriageway
National Highways
State Highways
Length KM
Percent
Length KM
Percent
Four-lane
1800
4
1200
1
Two-lane
23700
66
238800
19
One-lane
15000
30
100500
80
Total
49500
100
125500
100
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 12
3. NATIONAL HIGHWAY DEVELOPMENT PROJECT
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 13
4. ROAD CONSTRUCTION
Road construction in India is about rs.150 billion. The contracting industry consist of large scale
contractors (Rs.500 million and above) about 20 large contractors accounting 40% of
construction activities, medium scale contractors (Rs.100-500 million) is involved about 20% of
construction activities and small scale contractors (Rs.5-100 million) is involved in remaining
40%.
5. CONSTRUCTION MATERIAL
Embankment
Subgrade
Pavement structure base course
Surface course
Special materials for drainage
Maintenance
6. ROAD CONSTRUCTION EQUIPMENT
Earlier labour-based method In 1960s Mechanisationintroduced.
Govt. Bodies are the main buyers of the road construction equipment, market is limited
During 1980s, transformation took place. Project became much larger size –external agency
funding –mandatory to use appropriate equipment
Pre-qualification criteria: based on ownership of equipment for selection of contractors. In large
projects 10 % advance were given, as a result contractors began purchasing their own equipment.
Half of Indian manufactures producing equipment in India have tie-up with foreign partners to
improve their products.
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 14
FLYASH FOR ROAD EMBANKMENT
Ideally suited as back fill material
Higher shear strength leads to greater stability
Design by conventional method
Intermediate soil layers to provide confinement Guidelines approved by IRC
USE OF GEOTEXTILES FOR CONSTRUCTION OF EMBANKMENT
WITH STEEP SLOPE
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 15
LAYING OF GEOTEXTILE OVER SOIL SUBGRADE (AS SEPARATOR)
MATERIALS FOR ROAD PAVEMENTS
Sub gradeup gradation (stabilisation)
Improvement in CBR and reduction in pavement thickness by stabilisation (use of foamed
bitumen-cement, enzymes, resins etc.)
2.Sub-base/base courses
Use of waste materials like fly ash, Blast furnace slag, Aircooled slags, municipal wastes, etc
3.Wearing courses
Modified bitumens, multigradebitumens and improved emulsions
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 16
Lime stabilisation of (Orissa)
View of finished road surface
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 17
USE OF PROCESSED MUNICIPAL WASTES
1.Construction of stabilised base/sub-base courses(PMW-lime-fly ash, PMW-
soil-cement)
2.Construction of test track using municipal wastes
CRITERIA FOR SELECTION OF MODIFIERS and Raw Materials
Traffic
Climate
Cost-effectiveness
Performance reports
Constructabilit
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 18
MATERIALS FOR RIGID PAVEMENTS
Roller compacted concrete (RCCP)
Faster and economical
Can be used for base course and for wearing course
Saving of cement by using fly ash and GBFS
Construction of roller compacted concrete
Use of waste materials like Marble slurry dust, Slag, Fly ash, etc
-Use of waste materials to replace aggregates (DLC)
-Use of pozzolanic waste materials to replace part of cement (CC and RCC pavements)
Magnesium oxychloride cement
-As a substitute to OPC in CC pavements
-Used for stabilisation of sand
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 19
FUNDAMENTALS OF ROAD CONSTRUCTION CONSISTS OF FIVE
TOPICS:
Topic 1: Construction Management Overview
Topic 2: Preliminary Investigations
Topic 3: Setting Out
Topic 4: Earthworks
Topic 5: Roadsides BRIEF:
Construction Management Overview – the critical issues in construction management including
scheduling techniques, plant and equipment, human resources, materials, project management,
works program, safety and traffic management, quality systems and environmental management.
Preliminary Investigations – the phases of road investigation including land acquisition, environmental
issues, relocation of services and cultural and indigenous heritage management.
Setting Out – covers vertical and horizontal alignments, preparation for earthworks and trimming
sub grades.
Earthworks – includes specifications, definition of earthworks terms, hold points, witness points and
milestones, earthworks planning, plant and equipment, earthmoving operations and compliance
testing and measurement.
Drainage – urban drainage, geo-textiles, surface erosion protection, moisture, permeability, road
drainage systems, construction methods and selection of materials.
Roadsides – items at the roadside including furniture/signs, batter slopes, landscaping, guardrails,
crash barriers and noise fences/barriers
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 20
CHAPTER 2
PROJECT LIFE CYCLE
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 21
2.1Phases in road construction
2.1.1Feasibility phase
Generation and development of ideas
Feasibility studies
Studies of infrastructure needs
Layout studies
Assessment of design data
Cost estimation
Construction and procurement scheduling
Environmental impact assessment
Social impact assessment
2.1.2Design phase
Establishment of design basis
Design data studies
Geotechnical assessments
Durability design
Civil and structural design
Mechanical and electrical installations
Operational risk assessment
2.1.3Tender phase
Development of tender design
Management of tender procedures
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 22
Value engineering
Preparation of contract for construction
2.1.4Construction phase
Construction management
Quality, environmental and safety management
Construction risk management
Interface coordination
Program and budget control
Site supervision
Contract and claims management
2.1.5Operation and maintenance (O&M)
O&M management system
Inspection of structures and installations
Ranking of maintenance and reinvestment needs
Repair and strengthening design
Institutional development and training
Quality management
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 23
CHAPTER 3
TOOLS AND TECHNIQUES
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 24
3.1 Work Breakdown Structure (WBS):
A work breakdown structure (WBS), in project management and systems engineering, is a
deliverable oriented decomposition of a project into smaller components. A work breakdown
structure element may be a product, data, service, or any combination thereof. A WBS also
provides the necessary framework for detailed cost estimating and control along with providing
guidance for schedule development and control.
WBS is a hierarchical and incremental decomposition of the project into phases, deliverables and
work packages. It is a tree structure, which shows a subdivision of effort required to achieve an
objective; for example a program, project, and contract. In a project or contract, the WBS is
developed by starting with the end objective and successively subdividing it into manageable
components in terms of size, duration, and responsibility (e.g., systems, subsystems,
components, tasks, subtasks, and work packages) which include all steps necessary to achieve
the objective.
A work breakdown structure permits summing of subordinate costs for tasks, materials, etc., into
their successively higher level “parent” tasks, materials, etc. For each element of the work
breakdown structure, a description of the task to be performed is generated. This technique
(sometimes called a system breakdown structure is used to define and organize the total scope of
a project.
The WBS is organized around the primary products of the project (or planned outcomes) instead
of the work needed to produce the products (planned actions). Since the planned outcomes are
the desired ends of the project, they form a relatively stable set of categories in which the costs
of the
planned actions needed to achieve them can be collected. A well-designed WBS makes it easy to
assign each project activity to one and only one terminal element of the WBS. In addition to its
function in cost accounting, the WBS also helps map requirements from one level of system
specification to another, for example a requirements cross reference matrix mapping functional
requirements to high level or low level design documents.
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 25
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 26
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 27
3.2 Activity Diagram:
Activity diagrams are graphical representations of workflows of stepwise activities and actions
with support for choice, iteration and concurrency. In the Unified Modeling Language, activity
diagrams are intended to model both computational and organisational processes (i.e.
workflows). Activity diagrams show the overall flow of control.
Activity diagrams are constructed from a limited number of shapes, connected with arrows.The
most important shape types:
rounded rectangles represent actions;
diamonds represent decisions;
bars represent the start (split) or end (join) of concurrent activities;
a black circle represents the start (initial state) of the workflow;
an encircled black circle represents the end (final state).
Arrows run from the start towards the end and represent the order in which activities happen.
Hence they can be regarded as a form of flowchart. Typical flowchart techniques lack constructs
for expressing concurrency
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 28
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 29
CHAPTER 4
FINDINGS AND CONCLUSTIONS
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 30
KNOWLEDGE AREA
4.1 PROJECT SCOPE MANAGEMENT
The project is first conceptualized for a specific segment of customers. The market is understood
and the needs of the segment are analyzed. The location and the environmental factors of the
project are decided based on the previous analysis. In this project, the upper middle class and
higher class of people are selected and the need of status is identified. The project will be located
in a residential area which is well connected to the centrally to the city. The design of the project,
selection of contractors and architects, approval of local municipal laws etc. are decided and
made available. The role of each stakeholder is decided and the cost requirement (Budget) for
completion of the project is determined. This can be done quickly based on the previous
experience of the other similar projects. The risks are identified and the steps are taken to subdue
the risks in order to avoid scope creep.
4.2 PROJECT COST MANAGEMENT
The contracting industry consist of large scale contractors (Rs.500 million and above) about
20 large contractors accounting 40% of construction activities, medium scale contractors
(Rs.100-500 million) is involved about 20% of construction activities and small scale contractors
(Rs.5-100 million) is involved in remaining 40%. This project basically deal with the small scale
contractors.
4.3 PROJECT INTEGRATION MANAGEMNT
This is the stage where the actual work on the plan starts. It is not an easy task for anyone to
convert the plan on paper into reality. This requires expertise in the specific area such as
electrical, plumbing, civil, structural etc. Each task is assigned team to complete the job. These
tasks are sometimes dependent and sometimes overlapping (independent). A proper coordination
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 31
between teams is required to avoid any communication gap which can lead to cost overruns and
scope creep. Any team will consist of a project manager who manages and controls the overall
project. Under him the task managers/supervisors are assigned who looks after the progress of
the particular task. Contractors, architects, structural engineers and civil engineers are assigned
for each task and works closely with the task manager/supervisor.
The implementation/construction can be divided into phases depending on the bookings by
customers and the availability of materials and labor. The problem comes with the material
quality and delivery, labor issues, Safety issues, Compliance, Coordination etc. which ultimately
results in the scope creep, cost overruns and hinders customer delivery and satisfaction. Thus in
order to achieve the target, a project manager has to closely monitor the progress and avid
bottlenecks.
4.4PROJECT HUMAN RESOURCE MANAGEMENT
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 32
4.5 PROJECT PROCUREMENT MANAGEMENT
In this stage the procurement of the necessary materials are done. This is done
through tendering where various contractors are invited from the qualified
contractors. At first the BOQ and tender specifications are decided by the tenderer.
These details are then used for the compilation of the tender. These tenders are
then sent to the selected number of contractors for different tasks and the filled
tenders are received in the time specified by the tenderer. These tenders are then
verified and the selection of the contractor is done. Negotiation takes place and
finally the tender is awarded to the successful contractor.
This stage is one of the most crucial stages of a project. The root cause of any
project not completing in time is majorly due to defaults in this stage. A tenderer
has to be very careful about wrong information filing, faulty tender specifications
and BOQ. This causes increase the ordering cost, change in contractors, increase in
project completion time, complexities etc. which actually increases the scope of the
project.
4.6 PROJECT TIME MANAGEMENT
Scheduling of the project is done in order to micro manage the project and monitor
the progress of the project. This helps in understanding the variations from the
actual plan and a manager can decide how fast the work has to be done and
whether there will be a scope creep. This can be done by preparing Gantt chart
where the start, completion and progress of a project are mentioned.
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 33
CHAPTER 5
BIBLIOGRAPHY
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 34
WEBSITES
POZAN.COM http://www.ikb.poznan.pl/fcee/2005.06/full/fcee_2005-06_203-
216_logistics_of_construction.pdf (03-Nov 04:45 pm)
TANDFONLINE
http://www.tandfonline.com/doi/abs/10.1080/01446190110089691#.Unqcx XAy1Vo
(05-Nov 11:30 pm)
ILLINOIS DEPARTMENT OF TRANSPORT
http://www.dot.state.il.us/const/constbrochure/constbrochure.html (05- Nov
11:45 pm)
EUROPE TRANSPORT
http://ec.europa.eu/transport/road_safety/projects/doc/nr2c_final_report.pdf
(06-Nov 10:30 pm)
MINISTRY OF ROAD TRANSPORT http://morth.nic.in/ (06-Nov 11:45 pm)
BOOKS:
PMBOK Guide – Fourth Edition
NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 35

More Related Content

Similar to pdfcoffee.com_road-construction-7-pdf-free.pdf

PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONGLA University
 
CASE STUDY POLICY OF NITI AYOG SALIENT FEATURES,RECOMMENDATION HIGHWAY PROJECT
CASE STUDY POLICY OF NITI AYOG SALIENT FEATURES,RECOMMENDATION HIGHWAY PROJECTCASE STUDY POLICY OF NITI AYOG SALIENT FEATURES,RECOMMENDATION HIGHWAY PROJECT
CASE STUDY POLICY OF NITI AYOG SALIENT FEATURES,RECOMMENDATION HIGHWAY PROJECTSmit Patel
 
Concrete Road Pavement
Concrete Road Pavement Concrete Road Pavement
Concrete Road Pavement Awinash Tiwari
 
Internship Report
Internship ReportInternship Report
Internship Reportprathagarg
 
Transportation Planning as Effective Mean to Rejuvenate a Pilgrimage Town
Transportation  Planning as Effective Mean to Rejuvenate a Pilgrimage TownTransportation  Planning as Effective Mean to Rejuvenate a Pilgrimage Town
Transportation Planning as Effective Mean to Rejuvenate a Pilgrimage TownIRJET Journal
 
Project Report Modified222
Project Report Modified222Project Report Modified222
Project Report Modified222Ratan Patil
 
Study of causes of failures and remedies on road
Study of causes of failures and remedies on roadStudy of causes of failures and remedies on road
Study of causes of failures and remedies on roadShantanu Patil
 
Training report on JMRC
Training report on JMRCTraining report on JMRC
Training report on JMRCtushar garg
 
Training report of road construction
Training report of road constructionTraining report of road construction
Training report of road constructionManavSinghal8
 
Road sector in India
Road sector in IndiaRoad sector in India
Road sector in Indiasharifishere
 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)Ratnesh Kushwaha
 
Rural road development_of_india_based_on PMGSY.
Rural road development_of_india_based_on PMGSY.Rural road development_of_india_based_on PMGSY.
Rural road development_of_india_based_on PMGSY.CHAND PASHA KHAN
 
Feasibility Study of Samruddhi Expressway
Feasibility Study of Samruddhi ExpresswayFeasibility Study of Samruddhi Expressway
Feasibility Study of Samruddhi Expresswayvivatechijri
 
project final year civil
project final year civilproject final year civil
project final year civilAlankar jaiswal
 
IRJET- Study of Parking Space in Surat Railway Station Road and Resolving the...
IRJET- Study of Parking Space in Surat Railway Station Road and Resolving the...IRJET- Study of Parking Space in Surat Railway Station Road and Resolving the...
IRJET- Study of Parking Space in Surat Railway Station Road and Resolving the...IRJET Journal
 
SOLVING CONGESTION AT 4 LEGGED FATAL INTERSECTION BASED ON PROPORTIONATE TRA...
 SOLVING CONGESTION AT 4 LEGGED FATAL INTERSECTION BASED ON PROPORTIONATE TRA... SOLVING CONGESTION AT 4 LEGGED FATAL INTERSECTION BASED ON PROPORTIONATE TRA...
SOLVING CONGESTION AT 4 LEGGED FATAL INTERSECTION BASED ON PROPORTIONATE TRA...IAEME Publication
 
Summar tranning report of pwd
Summar tranning report of pwdSummar tranning report of pwd
Summar tranning report of pwdAlankar jaiswal
 
CSG__UNIT-3.pptx
CSG__UNIT-3.pptxCSG__UNIT-3.pptx
CSG__UNIT-3.pptxVenkat Ramana
 

Similar to pdfcoffee.com_road-construction-7-pdf-free.pdf (20)

PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
CASE STUDY POLICY OF NITI AYOG SALIENT FEATURES,RECOMMENDATION HIGHWAY PROJECT
CASE STUDY POLICY OF NITI AYOG SALIENT FEATURES,RECOMMENDATION HIGHWAY PROJECTCASE STUDY POLICY OF NITI AYOG SALIENT FEATURES,RECOMMENDATION HIGHWAY PROJECT
CASE STUDY POLICY OF NITI AYOG SALIENT FEATURES,RECOMMENDATION HIGHWAY PROJECT
 
Concrete Road Pavement
Concrete Road Pavement Concrete Road Pavement
Concrete Road Pavement
 
Internship Report
Internship ReportInternship Report
Internship Report
 
Transportation Planning as Effective Mean to Rejuvenate a Pilgrimage Town
Transportation  Planning as Effective Mean to Rejuvenate a Pilgrimage TownTransportation  Planning as Effective Mean to Rejuvenate a Pilgrimage Town
Transportation Planning as Effective Mean to Rejuvenate a Pilgrimage Town
 
Project Report Modified222
Project Report Modified222Project Report Modified222
Project Report Modified222
 
Study of causes of failures and remedies on road
Study of causes of failures and remedies on roadStudy of causes of failures and remedies on road
Study of causes of failures and remedies on road
 
Training report on JMRC
Training report on JMRCTraining report on JMRC
Training report on JMRC
 
Training report of road construction
Training report of road constructionTraining report of road construction
Training report of road construction
 
Road sector in India
Road sector in IndiaRoad sector in India
Road sector in India
 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
 
Road Safety Management audit course report
Road Safety Management audit course reportRoad Safety Management audit course report
Road Safety Management audit course report
 
Rural road development_of_india_based_on PMGSY.
Rural road development_of_india_based_on PMGSY.Rural road development_of_india_based_on PMGSY.
Rural road development_of_india_based_on PMGSY.
 
Feasibility Study of Samruddhi Expressway
Feasibility Study of Samruddhi ExpresswayFeasibility Study of Samruddhi Expressway
Feasibility Study of Samruddhi Expressway
 
project final year civil
project final year civilproject final year civil
project final year civil
 
Unit 1
Unit 1Unit 1
Unit 1
 
IRJET- Study of Parking Space in Surat Railway Station Road and Resolving the...
IRJET- Study of Parking Space in Surat Railway Station Road and Resolving the...IRJET- Study of Parking Space in Surat Railway Station Road and Resolving the...
IRJET- Study of Parking Space in Surat Railway Station Road and Resolving the...
 
SOLVING CONGESTION AT 4 LEGGED FATAL INTERSECTION BASED ON PROPORTIONATE TRA...
 SOLVING CONGESTION AT 4 LEGGED FATAL INTERSECTION BASED ON PROPORTIONATE TRA... SOLVING CONGESTION AT 4 LEGGED FATAL INTERSECTION BASED ON PROPORTIONATE TRA...
SOLVING CONGESTION AT 4 LEGGED FATAL INTERSECTION BASED ON PROPORTIONATE TRA...
 
Summar tranning report of pwd
Summar tranning report of pwdSummar tranning report of pwd
Summar tranning report of pwd
 
CSG__UNIT-3.pptx
CSG__UNIT-3.pptxCSG__UNIT-3.pptx
CSG__UNIT-3.pptx
 

Recently uploaded

NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...
NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...
NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...Amil baba
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfAmirYakdi
 
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Delhi Call girls
 
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵anilsa9823
 
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️soniya singh
 
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`dajasot375
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Sitegalleryaagency
 
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...babafaisel
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpmainac1
 
Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...Narsimha murthy
 
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...Suhani Kapoor
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...home
 
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceCALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceanilsa9823
 
MASONRY -Building Technology and Construction
MASONRY -Building Technology and ConstructionMASONRY -Building Technology and Construction
MASONRY -Building Technology and Constructionmbermudez3
 
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...Yantram Animation Studio Corporation
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricksabhishekparmar618
 

Recently uploaded (20)

NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...
NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...
NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
 
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
 
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
 
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
 
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
VIP Call Girls Service Mehdipatnam Hyderabad Call +91-8250192130
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
 
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
 
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
Abu Dhabi Call Girls O58993O4O2 Call Girls in Abu Dhabi`
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Site
 
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUp
 
Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...Revit Understanding Reference Planes and Reference lines in Revit for Family ...
Revit Understanding Reference Planes and Reference lines in Revit for Family ...
 
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
 
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...
VIP Russian Call Girls in Gorakhpur Deepika 8250192130 Independent Escort Ser...
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
 
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceCALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
 
MASONRY -Building Technology and Construction
MASONRY -Building Technology and ConstructionMASONRY -Building Technology and Construction
MASONRY -Building Technology and Construction
 
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricks
 

pdfcoffee.com_road-construction-7-pdf-free.pdf

  • 1. A PROJECT REPORT ON CONSTRUCTION OF ROADS IN NIT WARANGAL CAMPUS By NARHARI SAI(128937) NISHANT SINGH(128938) P.VALLIAPPAN(128939) PAGIDIMARRI GEETHA(128940) PALAKURTHY ANUSHA(128941) Under the Guidance of Sri. Syed Habeeb (Faculty) SCHOOL OF MANAGEMENT NATIONAL INSTITUTE OF TECHNOLOGY WARANGAL (2012-2014)
  • 2. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 1
  • 3. CERTIFICATE This is to certify that the candidates Narahari sai G , Nishant Singh , P.Valliappan , Pagidimarri Geetha , Palakurthy Anusha who are the students of NATIONAL INSTITUTE OF TECHNOLOGY, has completed their project “Construction of Roads in NIT Warangal” in Warangal, Andhra Pradesh. This project is the record of the authentic work carried out during the academic year 2012-2014. They have done this project by themselves as a team Syed Habeeb (Faculty) School Of Management National Institute Of Technology Warangal, Andhra Pradesh
  • 4. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 2
  • 5. DECLARATION We declare that this written submission represents ours ideas in our own words and where others’ ideas or words have been included, we have adequately cited and referenced the original sources. We also declared that we have adhered to all principles of academic honesty and integrity and have not misrepresented or fabricated or falsified any idea/data/fact/source in my submission. we understand that any violation of the above will cause for disciplinary action by the institute and can also evoke penal action from the sources which have not been properly cited or from whom proper permission has not been taken when needed. NARHARI SAI(128937) NISHANT SINGH(128938) P.VALLIAPPAN(128939) PAGIDIMARRI GEETHA(128940) PALAKURTHY ANUSHA(128941) Date: 07-11-12
  • 6. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 3
  • 7. CONTENTS 1.INTRODUCTION……………………………………………………..8 OBJECTIVE TYPES OF ROADS……………………………………………………………………………………...10 STATUS OF MAIN HIGHWAYS……………………………………………………………………….11 NATIONAL HIGHWAY DEVELOPMENT PROJECT…………………………………………………12 ROAD CONSTRUCTION………………………………………………………………………………..14 CONSTRUCTION MATERIAL………………………………………………………………………….14 ROAD CONSTRUCTION EQUIPMENT………………………………………………………………..14 1.7FLYASH FOR ROAD EMBANKMENT………………………………………………………………..16 MATERIAL FOR ROAD PAVEMENT…………………………………………………………………18 2.PROJECT LIFE CYCLE………………………………………………21 2.1 PHASES IN ROAD CONSTRUCTION…………………………………………………………………..22 3.TOOLS AND TECHNIQUES…………………………………………24 WORK BREAKDOWN STRUCTURE………………………………………………………………….25 ACTIVITY DIAGRAM………………………………………………………………………………….28 GANTT CHART………………………………………………………………………………………....29
  • 8. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 4
  • 9. 4.FINDING AND CONCLUSIONS……………………………………..30 KNOWLEDG AREAS 4.1 PROJECT SCOPE MANAGEMENT………………………………………………………………………31 4.2PROJECT COST MANAGEMENT………………………………………………………………………...31 4.3 PROJECT INTEGRATION MANAGEMENT…………………………………………………………….31 4.4PROJECT HUMAN RESOURCE MANAGEMENT……………………………………………………….32 PROJECT PROCUREMENT MANAGEMENT……………………………………………………………32 PROJECT TIME MANAGEMENT…………………………………………………………………………32 4.FINDINGS AND CONCLUSTIONS………………………………………………………………………….33 5. BIBLIOGRAPHY………………………………………………………34
  • 10. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 5
  • 11. EXECUTIVE SUMMARY Construction planning and execution is a fundamental and challenging activity in the management of construction projects. It involves the choice of technology, the definition of work tasks, the estimation of the required resources and durations for individual tasks, and the identification of any interactions among the different work tasks. A good construction plan is the basis for developing the budget and the schedule for work. Developing the construction plan is a critical task in the management of construction, even if the plan is not written or otherwise formally recorded. In addition to these technical aspects of construction planning, it may also be necessary to make organizational decisions about the relationships between project participants and even which organizations to include in a project. For example, the extent to which sub- contractors will be used on a project is often determined during construction planning. Construction time performance (CTP) and flexibility in approaches to project time planning have been shown to be significantly associated. This raises interesting questions about how effective planning and control to facilitate flexibility in overcoming unexpected problems may be achieved. Various tools and techniques such as Gantt chart, activity diagram and Work Breakdown Structure (WBS) have aided the road construction projects in an effective manner. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 6
  • 12.
  • 13. Site view of Roads in NIT Warangal Campus
  • 14. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 7
  • 16. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 8
  • 17. OBJECTIVE : Complete the project in the specified time horizon and allocated cost. Deliver value to the customers by providing excellent customer support. Roads are an integral part of the transport system. A country’s road network should be efficient in order to maximize economic and social benefits. They play a significant role in achieving national development and contributing to the overall performance and social functioning of the community. It is acknowledged that roads enhance mobility, taking people out of isolation and therefore poverty. In China for instance, the government has popularized this belief by emphasizing that for any economy to develop, transport must start off first which will later stimulate other sectors to develop in an orderly fashion The most important factors which are needed in the developing country are economics, political and military. Each of them play great role in the respective part but they cannot perform an excellence job without proper communication and transportation. There are three main kinds of transportation, they are by air, land and water .There are two main transportations on land, they are trains and cars but roads are necessary for both of them. Cars can be driven without roads but it is difficult and very dangerous. Trains cannot travel with railroads. It is very hard to travel in tropical country such as Myanmar in raining season without a road. There are muds everywhere and they always cause trouble for cars and trains. Thus our government is building roads and railroads around the country for the safety of the citizens. The basic of economic is trading and when people trade, the transportation will be needed. The country economic will develop when people travel to different the places and do businesses. When the politic ants travel around the country to meet the public, they will also need a road. When the military officers receive an order to check an area for the safety of the citizens, they will need roads to get there as soon as possible. By that way people can stay at their houses safe and sound. So people will love the their leader and obey the laws of our country. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 9
  • 18. 1.Types Of Roads: 1.1. Generally private roads: Driveway 1.2. Lower capacity highways AlleyArterial roadAvenuBackroadBoulevardTerrace BywayCollector roadCourtCul -de- sacDirt road Frontage roadHighwayLaneRoadRouteSingle carriageway StreetWinter road 1.3. Higher capacity highways, sometimes with medians Parkway Expressway Turnpike 2+1 road 2+2 road Farm to Market Road 1.4. Limited access HYPERLINK "http://en.wikipedia.org/wiki/Grade- separated" grade-separated highways Autobahn Auto-estrada Autopista Autostrada Autostrasse Controlled-access highway Expressway, a term used inconsistently in different locations; see Controlled-access highway and Limited-access highway
  • 19. Freeway High-quality dual carriageway (HQDC) Interstate Highway Limited-access highway Motorway NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 10
  • 20. “…IT IS NOT WEALTH THAT BUILT THE ROADS BUT, ROADS THAT BUILT OUR WEALTH” -John F. Kennedy 1. INDIAN ROAD NETWORK-CURRENT STATUS National Highway (NH) 58,112 State Highways (SH) 1,37,119 Major District Roads (MDR) 4,70,000 Village and Other Roads (ODR & 26,50,000 VR) Total Road Length 33,15,231 NHs are less than 2% of network but carry 40% of total traffic
  • 21. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 11
  • 22. 2. STATUS OF MAIN HIGHWAYS Carriageway National Highways State Highways Length KM Percent Length KM Percent Four-lane 1800 4 1200 1 Two-lane 23700 66 238800 19 One-lane 15000 30 100500 80
  • 24. 3. NATIONAL HIGHWAY DEVELOPMENT PROJECT
  • 25. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 13
  • 26. 4. ROAD CONSTRUCTION Road construction in India is about rs.150 billion. The contracting industry consist of large scale contractors (Rs.500 million and above) about 20 large contractors accounting 40% of construction activities, medium scale contractors (Rs.100-500 million) is involved about 20% of construction activities and small scale contractors (Rs.5-100 million) is involved in remaining 40%. 5. CONSTRUCTION MATERIAL Embankment Subgrade Pavement structure base course Surface course Special materials for drainage Maintenance 6. ROAD CONSTRUCTION EQUIPMENT Earlier labour-based method In 1960s Mechanisationintroduced. Govt. Bodies are the main buyers of the road construction equipment, market is limited During 1980s, transformation took place. Project became much larger size –external agency funding –mandatory to use appropriate equipment Pre-qualification criteria: based on ownership of equipment for selection of contractors. In large projects 10 % advance were given, as a result contractors began purchasing their own equipment. Half of Indian manufactures producing equipment in India have tie-up with foreign partners to improve their products. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 14
  • 27. FLYASH FOR ROAD EMBANKMENT Ideally suited as back fill material Higher shear strength leads to greater stability Design by conventional method Intermediate soil layers to provide confinement Guidelines approved by IRC USE OF GEOTEXTILES FOR CONSTRUCTION OF EMBANKMENT WITH STEEP SLOPE
  • 28. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 15
  • 29. LAYING OF GEOTEXTILE OVER SOIL SUBGRADE (AS SEPARATOR) MATERIALS FOR ROAD PAVEMENTS Sub gradeup gradation (stabilisation) Improvement in CBR and reduction in pavement thickness by stabilisation (use of foamed bitumen-cement, enzymes, resins etc.) 2.Sub-base/base courses Use of waste materials like fly ash, Blast furnace slag, Aircooled slags, municipal wastes, etc 3.Wearing courses
  • 30. Modified bitumens, multigradebitumens and improved emulsions NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 16
  • 31. Lime stabilisation of (Orissa) View of finished road surface
  • 32. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 17
  • 33. USE OF PROCESSED MUNICIPAL WASTES 1.Construction of stabilised base/sub-base courses(PMW-lime-fly ash, PMW- soil-cement) 2.Construction of test track using municipal wastes CRITERIA FOR SELECTION OF MODIFIERS and Raw Materials Traffic Climate
  • 35. MATERIALS FOR RIGID PAVEMENTS Roller compacted concrete (RCCP) Faster and economical Can be used for base course and for wearing course Saving of cement by using fly ash and GBFS Construction of roller compacted concrete Use of waste materials like Marble slurry dust, Slag, Fly ash, etc -Use of waste materials to replace aggregates (DLC) -Use of pozzolanic waste materials to replace part of cement (CC and RCC pavements) Magnesium oxychloride cement
  • 36. -As a substitute to OPC in CC pavements -Used for stabilisation of sand NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 19
  • 37. FUNDAMENTALS OF ROAD CONSTRUCTION CONSISTS OF FIVE TOPICS: Topic 1: Construction Management Overview Topic 2: Preliminary Investigations Topic 3: Setting Out Topic 4: Earthworks Topic 5: Roadsides BRIEF: Construction Management Overview – the critical issues in construction management including scheduling techniques, plant and equipment, human resources, materials, project management, works program, safety and traffic management, quality systems and environmental management. Preliminary Investigations – the phases of road investigation including land acquisition, environmental issues, relocation of services and cultural and indigenous heritage management. Setting Out – covers vertical and horizontal alignments, preparation for earthworks and trimming sub grades. Earthworks – includes specifications, definition of earthworks terms, hold points, witness points and milestones, earthworks planning, plant and equipment, earthmoving operations and compliance testing and measurement. Drainage – urban drainage, geo-textiles, surface erosion protection, moisture, permeability, road drainage systems, construction methods and selection of materials. Roadsides – items at the roadside including furniture/signs, batter slopes, landscaping, guardrails, crash barriers and noise fences/barriers
  • 38. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 20
  • 40. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 21
  • 41. 2.1Phases in road construction 2.1.1Feasibility phase Generation and development of ideas Feasibility studies Studies of infrastructure needs Layout studies Assessment of design data Cost estimation Construction and procurement scheduling Environmental impact assessment Social impact assessment 2.1.2Design phase Establishment of design basis Design data studies Geotechnical assessments Durability design Civil and structural design Mechanical and electrical installations Operational risk assessment 2.1.3Tender phase Development of tender design
  • 42. Management of tender procedures NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 22
  • 43. Value engineering Preparation of contract for construction 2.1.4Construction phase Construction management Quality, environmental and safety management Construction risk management Interface coordination Program and budget control Site supervision Contract and claims management 2.1.5Operation and maintenance (O&M) O&M management system Inspection of structures and installations Ranking of maintenance and reinvestment needs Repair and strengthening design Institutional development and training Quality management
  • 44. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 23
  • 45. CHAPTER 3 TOOLS AND TECHNIQUES
  • 46. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 24
  • 47. 3.1 Work Breakdown Structure (WBS): A work breakdown structure (WBS), in project management and systems engineering, is a deliverable oriented decomposition of a project into smaller components. A work breakdown structure element may be a product, data, service, or any combination thereof. A WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. WBS is a hierarchical and incremental decomposition of the project into phases, deliverables and work packages. It is a tree structure, which shows a subdivision of effort required to achieve an objective; for example a program, project, and contract. In a project or contract, the WBS is developed by starting with the end objective and successively subdividing it into manageable components in terms of size, duration, and responsibility (e.g., systems, subsystems, components, tasks, subtasks, and work packages) which include all steps necessary to achieve the objective. A work breakdown structure permits summing of subordinate costs for tasks, materials, etc., into their successively higher level “parent” tasks, materials, etc. For each element of the work breakdown structure, a description of the task to be performed is generated. This technique (sometimes called a system breakdown structure is used to define and organize the total scope of a project. The WBS is organized around the primary products of the project (or planned outcomes) instead of the work needed to produce the products (planned actions). Since the planned outcomes are the desired ends of the project, they form a relatively stable set of categories in which the costs of the planned actions needed to achieve them can be collected. A well-designed WBS makes it easy to assign each project activity to one and only one terminal element of the WBS. In addition to its function in cost accounting, the WBS also helps map requirements from one level of system specification to another, for example a requirements cross reference matrix mapping functional requirements to high level or low level design documents. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 25
  • 48.
  • 49. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 26
  • 50.
  • 51. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 27
  • 52. 3.2 Activity Diagram: Activity diagrams are graphical representations of workflows of stepwise activities and actions with support for choice, iteration and concurrency. In the Unified Modeling Language, activity diagrams are intended to model both computational and organisational processes (i.e. workflows). Activity diagrams show the overall flow of control. Activity diagrams are constructed from a limited number of shapes, connected with arrows.The most important shape types: rounded rectangles represent actions; diamonds represent decisions; bars represent the start (split) or end (join) of concurrent activities; a black circle represents the start (initial state) of the workflow; an encircled black circle represents the end (final state). Arrows run from the start towards the end and represent the order in which activities happen. Hence they can be regarded as a form of flowchart. Typical flowchart techniques lack constructs for expressing concurrency
  • 53. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 28
  • 54.
  • 55. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 29
  • 56. CHAPTER 4 FINDINGS AND CONCLUSTIONS
  • 57. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 30
  • 58. KNOWLEDGE AREA 4.1 PROJECT SCOPE MANAGEMENT The project is first conceptualized for a specific segment of customers. The market is understood and the needs of the segment are analyzed. The location and the environmental factors of the project are decided based on the previous analysis. In this project, the upper middle class and higher class of people are selected and the need of status is identified. The project will be located in a residential area which is well connected to the centrally to the city. The design of the project, selection of contractors and architects, approval of local municipal laws etc. are decided and made available. The role of each stakeholder is decided and the cost requirement (Budget) for completion of the project is determined. This can be done quickly based on the previous experience of the other similar projects. The risks are identified and the steps are taken to subdue the risks in order to avoid scope creep. 4.2 PROJECT COST MANAGEMENT The contracting industry consist of large scale contractors (Rs.500 million and above) about 20 large contractors accounting 40% of construction activities, medium scale contractors (Rs.100-500 million) is involved about 20% of construction activities and small scale contractors (Rs.5-100 million) is involved in remaining 40%. This project basically deal with the small scale contractors. 4.3 PROJECT INTEGRATION MANAGEMNT This is the stage where the actual work on the plan starts. It is not an easy task for anyone to
  • 59. convert the plan on paper into reality. This requires expertise in the specific area such as electrical, plumbing, civil, structural etc. Each task is assigned team to complete the job. These tasks are sometimes dependent and sometimes overlapping (independent). A proper coordination NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 31
  • 60. between teams is required to avoid any communication gap which can lead to cost overruns and scope creep. Any team will consist of a project manager who manages and controls the overall project. Under him the task managers/supervisors are assigned who looks after the progress of the particular task. Contractors, architects, structural engineers and civil engineers are assigned for each task and works closely with the task manager/supervisor. The implementation/construction can be divided into phases depending on the bookings by customers and the availability of materials and labor. The problem comes with the material quality and delivery, labor issues, Safety issues, Compliance, Coordination etc. which ultimately results in the scope creep, cost overruns and hinders customer delivery and satisfaction. Thus in order to achieve the target, a project manager has to closely monitor the progress and avid bottlenecks. 4.4PROJECT HUMAN RESOURCE MANAGEMENT
  • 61. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 32
  • 62. 4.5 PROJECT PROCUREMENT MANAGEMENT In this stage the procurement of the necessary materials are done. This is done through tendering where various contractors are invited from the qualified contractors. At first the BOQ and tender specifications are decided by the tenderer. These details are then used for the compilation of the tender. These tenders are then sent to the selected number of contractors for different tasks and the filled tenders are received in the time specified by the tenderer. These tenders are then verified and the selection of the contractor is done. Negotiation takes place and finally the tender is awarded to the successful contractor. This stage is one of the most crucial stages of a project. The root cause of any project not completing in time is majorly due to defaults in this stage. A tenderer has to be very careful about wrong information filing, faulty tender specifications and BOQ. This causes increase the ordering cost, change in contractors, increase in project completion time, complexities etc. which actually increases the scope of the project. 4.6 PROJECT TIME MANAGEMENT Scheduling of the project is done in order to micro manage the project and monitor the progress of the project. This helps in understanding the variations from the actual plan and a manager can decide how fast the work has to be done and whether there will be a scope creep. This can be done by preparing Gantt chart where the start, completion and progress of a project are mentioned.
  • 63. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 33
  • 65. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 34
  • 66. WEBSITES POZAN.COM http://www.ikb.poznan.pl/fcee/2005.06/full/fcee_2005-06_203- 216_logistics_of_construction.pdf (03-Nov 04:45 pm) TANDFONLINE http://www.tandfonline.com/doi/abs/10.1080/01446190110089691#.Unqcx XAy1Vo (05-Nov 11:30 pm) ILLINOIS DEPARTMENT OF TRANSPORT http://www.dot.state.il.us/const/constbrochure/constbrochure.html (05- Nov 11:45 pm) EUROPE TRANSPORT http://ec.europa.eu/transport/road_safety/projects/doc/nr2c_final_report.pdf (06-Nov 10:30 pm) MINISTRY OF ROAD TRANSPORT http://morth.nic.in/ (06-Nov 11:45 pm) BOOKS: PMBOK Guide – Fourth Edition
  • 67. NATIONAL INSTITUTE OF TECHNOLOGY,WARANGAL Page 35