SlideShare a Scribd company logo
1 of 96
Download to read offline
 Estimation is the scientific way of working out
the approximate cost of an engineering project
before execution of the work.
 In estimation and costing we will estimate all the
quantities like concrete, shuttering, brickwork,
plastering, reinforcement, etc.
 Then cost is applied.
 Estimation and costing is also known as quantity
survey.
 Quantity survey can be done manually or with
help of Microsoft excel.
2Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
 Types of footings.
 Types of columns.
 Types of beams.
 Types of Slabs.
 Types ofWalls.
 Length calculation.
 Area calculation.
 Volume calculation.
3Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
Module-i~ Sub-structure calculation
<below ground level>.
Module-ii~ Super-structure calculation
<above ground level>.
Module-iii~ Reinforcement calculation
for RCC & Steel structure.
Module-iv~ Computer application < MS
excel sheet>.
Module-v~ Project work.
4Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
 PCC under footings.
 Footings.
 Neck columns.
 Tie beams.
 PCC under tie beams.
 Plinth beams.
 PCC under plinth beams.
 Grade slabs.
 Septic tank.
 Etc.
5Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
o Volume of concrete in m3
o Area of shuttering in m2
o Area of bitumen paint in m2
o Area of termite control in m2
o Area of polythene sheet in m2
o Reinforcement in Kgs. Or tons.
6Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
 Floor columns.
 Floor beams.
 Floor slabs.
 Stair case.
 Brick work.
 Door.
 Windows
 Over head water tank
 Flooring calculations
7Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
8Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
This is the process of digging earth on site where the foundation is to be laid
9Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
After excavation, compaction is done on the earth’s surface and then it is treated
with termite control (Anti fungus spray).
10Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
Polythene sheet is laid on the surface of ground afterTermite
Control Spray is spread. Generally they are 2mm to 6mm thick.
11Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
This is also called as blinding. It is just a mixture of cement, sand and
aggregate without reinforcement. Generally the Grade of concrete
for PCC is used as M7.5 with ratio or proportion of concrete as 1:4:8.
12Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
This is a Concrete with cement, sand and aggregate with
reinforcement. Generally the Grade of concrete is used as M15 with
ratio 1:2:4,
13Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
The part of Column which comes between the top of footing to
bottom of Ground beam is called as Neck column.
14Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
It’s a black colour paint, painted to the structure which is under ground before
back filling of Soil.The purpose of using the Bitumen paint is to
(i) Increase the life of the structure
(ii) Give strength to it
(iii)To acts as water-proofing agent
(iv)And to safe the structure from Corrosion.
(iv) Liquid or sheet form.
15Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
Formwork
Masonry (Stone Masonry and Brick Masonry)
Flooring
Plastering
Pointing
Doors and Windows
Whitewashing, Colour washing and Distempering
Painting
Lump sum Item
Electrification
Nomenclature if Item
Rates
16Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
17Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
18Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
19Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
20Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
21Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
22Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
23Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
24Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
25Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
26Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
27Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
28Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
29Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
30Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 31
 PCC CONCRETE = 7.5565m3
 GRADE OF CONCRETE USED FOR PCC M7.5
 RATIO = 1:4:8
 SAND: FOR 1m3 OF CONCRETE = 0.46m3
 FOR 7.5565m3 = 7.5565 X 0.46 =3.47599m3
 AGGRIGATE OF SIZE 40mm
 For 1 m3 of concrete = 0.92 m3
 For 7.5565 m3 = 7.5565 x 0.92 =6.95198 m3
 CEMENT FOR 1m3 OF CONCRETE = 165.60KGS
 FOR 7.5565 m3
 7.5565 X 165.60 =1251.3564KGS
 RCC CONCRETE = 101 m3
 GRADE OF CONCRETE USED FOR PCC M15
 RATIO = 1:2:4
 SAND: FOR 1m3 OF CONCRETE = 0.46m3
 FOR ,101m3 = 101 X 0.46 =46.46m3
 AGGRIGATE OF SIZE 20mm
 For 1 m3 of concrete = 0.92 m3
 For 101 m3 = 101 x 0.92 =92.92 m3
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 32
 CEMENT FOR 1m3 OF CONCRETE = 331.20KGS
 FOR 101 m3
 101 X 331.20 =33451.2KGS
 TOTAL SAND = 3.47599 + 46.46 = 49.95 m3
 AGGRIGATE 40mm = 6.95198 m3
 AGGRIGATE 20mm = 92.92 m3
 TOTALCEMENT = 1251.3564 + 33451.2 =34702.5564KGS
 = 695 BAGS
 TOTALQUANTITYOF SAND = 49.95 m3
 VOLUMEOF SAND EACHTRUCK ORTIPPER = AREA X DEPTH
 = 4.29 X 2.5 X 1.4 = 15.01 m3
 NOOF SAND IN EACHTRUCK = 15.01 m3
 NOOF SANDTRUCK REQUIRED =VOL OF SAND /VOL OFTRUCK
 = 49.95 / 15.01 = 3.765TRUCKSAPPROX 4
TRUCKS
 TOTALVOLUMEOF AGGRIGATE 40mm & 20mm = 100 m3
 NOOF AGGRIGATE EACHTRUCK = 9 m3
 NOOF AGGRIGATETRUCK REQUIRED =VOL OF AGGRIGATE /VOL OF
TRUCK
= 100 / 15.01 = 6.668TRUCKSAPPROX 7TRUCKS
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 33
34Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
35Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
36Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
37Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
38Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
39Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
40Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
41Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
42Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
43Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
44Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
 BRICK SIZE: 0.2m x 0.1m x 0.1m
 WALLTHICKNESS: 0.2m
 ROLLER SHUTTER: 2.43m x 2.43m
 WALLTHICKNESS: 0.23m
 BRICKWORK CALCULATION:
 BRICKWORK AREA:
 1.WALL: length=21.73m, depth=4m.
 Area=21.73 x 4= 86.92m2
 2.WALL: length=21.73m, depth=4m.
 Area=21.73 x 4= 86.92m2
 3.WALL: length=13m, depth=4m.
 Area=13 x 4=52m2
 4.WALL: length=13m, depth=4m.
 Area=13 x 4=52m2
 WALL 4 Length same
 52 +52 +52 + 52 + 52 + 52 =312m2
 5.WALL: length=21m, depth=4m.
 Area=21 x 4=84m2
 WALL 5 Length same
 84 + 84 +84 =252m2
45Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
 BRICKWORK AREA =86.92+86.92+52+312+252 = 789.84M2
 DEDUCTIONS:
 1. ROLLER SHUTTER: length=2.43m, depth=2.43m.
 Area=2.43 x 2.43= 5.91m2
 ROLLER SHUTTERTOTAL = 18
 PER ROLLER SHUTTER AREA = 5.91 X 18 = 107m2
 2. MAIN GATE AREA: length=3m, depth=4m.
 Area=3 x 4= 12m2
 MAIN GATE AREATOTAL = 6
 PER MAIN GATE AREA: 12 X 6 =72m2
 3. STAIR CASE AREA: length=3.35m, depth=4m.
 Area=3.35 x 4= 13.4m2
 STAIR CASE AREATOTAL = 3
 PER STAIR CASE AREA: 13.4 X 3 = 40.2m2
 TOTAL DEDUCTION AREA = 107 + 72 + 40.2 = 219.2m2
 TOTAL BRICKWORK AREA = BRICKWORK AREA – DEDUCTION AREA
 = 789.84 – 219.2
 = 570.64M2
 VOLUME OF BRICK WORK =TOTAL BRICKWORK AREA XWALLTHICKNESS
 = 570.64 X 0.23
 = 131.2472M2
 VOLUME OF SINGLE BRICK = LENGTH X BREADTH X DEPTH
 = 0.2 X 0.1 X 0.1
 = 0.002m3
 NUMBEROF BRICKS =VOLUME OF BRICKWORK /VOLUME OF SINGLE BRICK
 = 131.2472/0.002m3
 =65623.6 BRICKS
 = 65624 BRICKS 46Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
47Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
48Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
 ROLLER SHUTTER: 2.43m x 2.43m
 PLASTERINGTHICKNESS: 0.02m
 PLASTERINGCALCULATION:
 PLASTERINGAREA: INTERNALAREA 1
 INTERNAL DIMENSION 1: LENGTH = 3.83m, BREADTH = 3.83m,
DEPTH = 4m.
 INTERNALAREA 1= (LENGTH + BREADTH) X 2 X DEPTH m2
 = (3.83 + 3.83) x 2 x4
 = 61.28m2
 TOTAL INTERNALAREA 1: =61.28 * 15
 = 919.2m2
 INTERNAL DEDUCTIONS 1:
 SHUTTER: LENGTH = 2.43m, DEPTH = 2.43m.
 SHUTTERAREA = 2.43 x 2.43=5.9049m2
 TOTAL DEDUCTIONAREA: 5.9049 X 18 =106.2882m2
 INTERNAL DIMENSIONS 2:
 STAIR CASE : LENGTH = 3.83, DEPTH = 4m.
 INTERNALAREA 2= (LENGTH + BREADTH + LENGTH) X DEPTH m2
 = (3.83 + 3.83 = 3.83) X 4
 = 11.49 X 4 = 45.96m2
 TOTAL DIMENSION = 45.96 X 2 =91.92m2 49Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
 TOTAL INTERNAL AREA = INTERNAL AREA – DEDUCTION AREA
 = (91.92 + 919.2)–106.1882
 = 904.9318m2
 EXTERNAL AREA 1: LENGTH = 4.05, BREADTH = 4.05, DEPTH = 4M
 = (L + B +L)X 4
 = (4.05+4.05+4.05)X 4=48.6m2
 TOTAL EXTERNAL AREA 1: 48.6X3=145.8m2
 EXTERNAL AREA 2: LENGTH = 4.05, BREADTH = 4.05, DEPTH = 4M
 = (L + B)X 4
 = (4.05+4.05)X4 =32.4m2
 TOTAL EXTERNAL AREA 2: 32.4X7=226.8m2
 EXTERNAL AREA 3: LENGTH = 4.05, BREADTH = 4.05, DEPTH = 4M
 = (L)X 4
 = (4.05)X4 =16.2m2
 TOTAL EXTERNAL AREA 3: 16.2X8=132.0m2
 TOTAL EXTERNAL AREA: 145.8 + 226.8 +132.0m2
 = 504.6m2
 EXTERNAL DEDUCTIONS 1:
 SHUTTER: LENGTH = 2.43m, DEPTH = 2.43m.
 SHUTTERAREA = 2.43 x 2.43=5.9049m2
 TOTAL EXTERNAL DEDUCTION AREA: 5.9049 X 18 = 106.2882
 TOTAL EXTERNAL AREA = EXTERNAL AREA – DEDUCTION AREA
 = 504.6–106.1882
 = 398.3118m2
 TOTAL PLASTERING AREA: INTERNAL + EXTERNAL PLASTERING AREA
 = 904.9318m2 + 398.3118m2
 = 1303.2436m2
50Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
51Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
52Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
53Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
54Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
55Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
56Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
57Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
58Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
59Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 60
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 61
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 62
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 63
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 64
 1. DIAMETERS:
 6mm,8mm,10mm,12mm,16mm,20mm,25mm,28mm
 2. STANDARD LENGTH OF BAR = 12m.
 3.WEIGHT PER METER = D2/162 kg/m. D=DIAMETER
 FOR EXAMPLE SAY 8mm BAR.
 WEIGHT PER METER = 82/162 = 0.39 kg/m.
 4.WEIGHT PER BAR = (D2/162)*12 KGS/BAR.
 FOR EXAMPLE SAY 8mm BAR.
 WEIGHT PER METER = (82/162)*12 = 4.74 KGS/BAR
 5. HOOK :
 LENGTH OF HOOK =9d, d = diameter.
 LENGTH OF BAR = L + 9d +9d m
 6. BEND :
 LENGTH OF BEND =10d – 16d, d = diameter.
 LENGTH OF BAR = L + 12d +12d m. (BEND = 12d).
 NECK COLUMNTO FOOTING OVERLAPPING = 40d – 50d, or 16D
 COLUMNTO COLUMN = 50d,
 GENERALOVERLAPPINGWHEN 12m BAR FINISHES = 50d.
D=DIAMETER
 8. CRANK BAR :
 CRANK = 0.42d,
 LENGTHOFTHE CRANK BAR = L + 0.42d + 0.42d,
 D= SLAB OR BEAMTHICKNESS –TOP N BOTTOM COVER.
 LENGTHOF EXTRA BAR = L/4.
 9. COVER: SPACE BETWEEN REINFORCEMENTAND SHUTTERING.
COVERING BLOCKSARE USED FOR PROVIDINGCOVER.
 FOOTING = 75mm
 COLUMN = 25mm - 50mm
 BEAM = 25mm - 50mm
 SLAB = 25mm
 10. SPACING: DISTANCE BETWEENTWO REINFORCEMENT BARS.
 11. NUMBER OF BARS = (OPPOSITE LENGTH /SPACING) + 1.
 12. NUMBER OF STIRRUPS = (ACTUAL LENGTH OF COLUMN OR
BEAM /SPACING) + 1.
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 65
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 66
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 67
 FOOTING REINFORCEMENT CALCULATIONS:
 SHORTWAY BARS:
 1. LENGTH OF S/W BAR = L - 0.1 – 0.1 + D + D M
 LENGTH OF S/W BAR = 1.4 – 0. 1 – 0.1 +0.3 + 0.3 M
 LENGTH OF S/W BAR = 1.80 M

 2. NUMBER OF SHORTWAY BAR = (OPPOSITE LENGTH / SPACING) + 1
 NUMBER OF SHORTWAY BAR = {(1.8 – 0.1 – 0.1)/0.1} + 1
 NUMBER OF SHORTWAY BAR = {1.6/0.1} + 1
 NUMBER OF SHORTWAY BAR = 17 BARS
 3.TOTAL LENGTH OF SHORT WAY BARS = LENGTH OF BAR * NUMBER OF BARS M
 TOTAL LENGTH OF SHORTWAY BARS = 1.80 *17 M
 TOTAL LENGTH OF SHORTWAY BARS = 30.60 M
 4. DIAMETER OF SHORT WAY BAR = 10 MM (GIVEN IN DRAWING)
 5.WEIGHT PER METER OF SHORTWAY BAR K= D2/162 GS/M
 WEIGHT PER METER OF SHORT WAY BAR = 10*10/162 KGS/M
 WEIGHT PER METER OF SHORT WAY BAR = 0.62 KGS/M
 6.TOTAL WEIGHT OF SHORTWAY BARS =TOTAL LENGTH * WEIGHT PER METER * NO OF
MEMBER KGS
 TOTALWEIGHT OF SHORT WAY BARS = 30.60 * 0.62 * 7 KGS
 TOTALWEIGHT OF SHORT WAY BARS = 132.804 KGS
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 68
 LONGWAY BARS:
 1. LENGTH OF L/W BAR = L - 0.1 – 0.1 + D + D M
 LENGTH OF L/W BAR = 1.8 – 0. 1 – 0.1 +0.3 + 0.3 M
 LENGTH OF L/W BAR = 2.20 M

 2. NUMBER OF LONGWAY BAR = (OPPOSITE LENGTH / SPACING) + 1
 NUMBER OF LONGWAY BAR = {(1.4 – 0.1 – 0.1)/0.1} + 1
 NUMBER OF LONGWAY BAR = {1.2/0.1} + 1
 NUMBER OF LONGWAY BAR = 13 BARS

 3.TOTAL LENGTH OF LONGWAY BARS = LENGTH OF BAR * NUMBER OF BARS M
 TOTAL LENGTH OF LONGWAY BARS = 2.2 *13 M
 TOTAL LENGTH OF LONGWAY BARS = 28.60 M

 4. DIAMETER OF LONGWAY BAR = 10 MM (GIVEN IN DRAWING).

 5.WEIGHT PER METER OF LONGWAY BAR = D2/162 KGS/M
 WEIGHT PER METER OF LONGWAY BAR = 10*10/162 KGS/M
 WEIGHT PER METER OF LONGWAY BAR = 0.62 KGS/M

 6.TOTAL WEIGHT OF LONGWAY BARS =TOTAL LENGTH * WEIGHT PER METER * NO OF
MEMBER KGS
 TOTAL WEIGHT OF LONGWAY BARS = 28.60 * 0.62 * 7 KGS
 TOTAL WEIGHT OF LONGWAY BARS = 124.124 KGS
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 69
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 70
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 71
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 72
 NECK COLUMN (MAIN BAR)
 L = NECK COLUMN + FOOTING BOTTOM MESH
 L = 1.2 + 0.3
 L = 1.5 DIA = 12MM
 LENGTHOF EACH MAIN BAR = L + 50D + 16D
 = 1.5 + 66D
 = 1.5 + 66 (0.012)
 = 2.30 M
 NO OF MAIN BAR = 8
 TOTAL LENGTH OF MAIN BAR = LENGTH OF EACH BAR X NO OF MAIN
BAR
 = 2.30 X 8
 = 18.4 M
 WEIGHT OF STEEL BAR IN KGS / M = D2/162 KGS/M
 = 12*12/162
 = 0.88 KGS/ M
 REQUIREDWEIGHT OF STEEL FOR MAIN BAR = WEIGHT/M XTOTAL
LENGTHOF MAIN BAR X NO OF MEMBER
 = 0.88 X 18.4 X 7
 = 113.344 KGS
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 73
 NECK COLUMN (STIRRUPS)
 25 MM (0.025 M) CONCRETE COVER HASTO BE DEDUCTED FROM EACH
SIDE OF COLUMN
 L = LENGTH OF EACH STIRRUPS
 L = (0.40 + 0.18) X 2
 L = 1.16 M
 LENGTH OF EACH STIRRUPSWITH HOOK = L +18D
 = 1.16 + 18(0.008)
 = 1.304 M
 NO OF STIRRUPS = (HEIGHT OF NECK COLUMN / SPACING) + 1
 = (1.5 / 0.1) + 1
 = 16 STIRRUPS
 TOTAL LENGTH OF STIRRUPS = LENGTH OF EACH STIRRUPS X NO OF
STIRRUPS
 = 1.304 X 16
 = 20.864 M
 WEIGHT OF STEEL BAR IN KGS / M = D2/162 KGS/M
 = 8*8 / 162
 = 0.39 KGS / M
 REQUIREDWEIGHT OF BAR FOR STIRRUPS = WEIGHT OF STEEL BAR IN
KGS/M XTOTAL LENGTH X NO OF ITEM
 = 0.39 X 20.864 X 7 = 56.959 KGS
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 74
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 75
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 76
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 77
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 78
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 79
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 80
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 81
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 82
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 83
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 84
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 85
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 86
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 87
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 88
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 89
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 90
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 91
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 92
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 93
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 94
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 95
Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 96

More Related Content

Similar to QUANTITY SURVEY For Residential Building By MD USOOF ALAM

Pavement Design Methods 2 (Flexible and Rigid).pdf
Pavement Design Methods 2 (Flexible and Rigid).pdfPavement Design Methods 2 (Flexible and Rigid).pdf
Pavement Design Methods 2 (Flexible and Rigid).pdfMohammadKabirHossain4
 
project ppt 2 pdf.pdf
project ppt 2 pdf.pdfproject ppt 2 pdf.pdf
project ppt 2 pdf.pdfKarthikMasky
 
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODECOMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODEIRJET Journal
 
SUMMER INTERNSHIP REPORT
SUMMER INTERNSHIP REPORTSUMMER INTERNSHIP REPORT
SUMMER INTERNSHIP REPORTSusom Dutta
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowAnchit Agrawal
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank designHarish Mahavar
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line methodmalang1214
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Design and fabriction of an interlocking tiles crusher
Design and fabriction of an interlocking tiles crusherDesign and fabriction of an interlocking tiles crusher
Design and fabriction of an interlocking tiles crusherAlexander Decker
 
post tensioning slabs
post tensioning slabspost tensioning slabs
post tensioning slabsgopichand's
 
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...Nafisa Nazneen Choudhury
 

Similar to QUANTITY SURVEY For Residential Building By MD USOOF ALAM (20)

Pavement Design Methods 2 (Flexible and Rigid).pdf
Pavement Design Methods 2 (Flexible and Rigid).pdfPavement Design Methods 2 (Flexible and Rigid).pdf
Pavement Design Methods 2 (Flexible and Rigid).pdf
 
Wells & Pumps Project Report
Wells & Pumps Project ReportWells & Pumps Project Report
Wells & Pumps Project Report
 
project ppt 2 pdf.pdf
project ppt 2 pdf.pdfproject ppt 2 pdf.pdf
project ppt 2 pdf.pdf
 
Connecting Bridge
Connecting BridgeConnecting Bridge
Connecting Bridge
 
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODECOMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
COMPARISON BETWEEN VARIOUS STEEL SECTION BY USING IS CODE AND EURO CODE
 
SUMMER INTERNSHIP REPORT
SUMMER INTERNSHIP REPORTSUMMER INTERNSHIP REPORT
SUMMER INTERNSHIP REPORT
 
BATCH 4 PPT.pptx
BATCH 4 PPT.pptxBATCH 4 PPT.pptx
BATCH 4 PPT.pptx
 
Vivek Kuliyal
Vivek KuliyalVivek Kuliyal
Vivek Kuliyal
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknow
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Design and fabriction of an interlocking tiles crusher
Design and fabriction of an interlocking tiles crusherDesign and fabriction of an interlocking tiles crusher
Design and fabriction of an interlocking tiles crusher
 
post tensioning slabs
post tensioning slabspost tensioning slabs
post tensioning slabs
 
M.i tank
M.i  tankM.i  tank
M.i tank
 
Sheet pile presentation
Sheet pile presentationSheet pile presentation
Sheet pile presentation
 
Thin cylinder ppt
Thin cylinder pptThin cylinder ppt
Thin cylinder ppt
 
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
 
Basic E&Mcalculations for a coal mining project
Basic E&Mcalculations for a coal mining projectBasic E&Mcalculations for a coal mining project
Basic E&Mcalculations for a coal mining project
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Recently uploaded (20)

Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

QUANTITY SURVEY For Residential Building By MD USOOF ALAM

  • 1.
  • 2.  Estimation is the scientific way of working out the approximate cost of an engineering project before execution of the work.  In estimation and costing we will estimate all the quantities like concrete, shuttering, brickwork, plastering, reinforcement, etc.  Then cost is applied.  Estimation and costing is also known as quantity survey.  Quantity survey can be done manually or with help of Microsoft excel. 2Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 3.  Types of footings.  Types of columns.  Types of beams.  Types of Slabs.  Types ofWalls.  Length calculation.  Area calculation.  Volume calculation. 3Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 4. Module-i~ Sub-structure calculation <below ground level>. Module-ii~ Super-structure calculation <above ground level>. Module-iii~ Reinforcement calculation for RCC & Steel structure. Module-iv~ Computer application < MS excel sheet>. Module-v~ Project work. 4Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 5.  PCC under footings.  Footings.  Neck columns.  Tie beams.  PCC under tie beams.  Plinth beams.  PCC under plinth beams.  Grade slabs.  Septic tank.  Etc. 5Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 6. o Volume of concrete in m3 o Area of shuttering in m2 o Area of bitumen paint in m2 o Area of termite control in m2 o Area of polythene sheet in m2 o Reinforcement in Kgs. Or tons. 6Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 7.  Floor columns.  Floor beams.  Floor slabs.  Stair case.  Brick work.  Door.  Windows  Over head water tank  Flooring calculations 7Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 8. 8Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 9. This is the process of digging earth on site where the foundation is to be laid 9Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 10. After excavation, compaction is done on the earth’s surface and then it is treated with termite control (Anti fungus spray). 10Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 11. Polythene sheet is laid on the surface of ground afterTermite Control Spray is spread. Generally they are 2mm to 6mm thick. 11Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 12. This is also called as blinding. It is just a mixture of cement, sand and aggregate without reinforcement. Generally the Grade of concrete for PCC is used as M7.5 with ratio or proportion of concrete as 1:4:8. 12Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 13. This is a Concrete with cement, sand and aggregate with reinforcement. Generally the Grade of concrete is used as M15 with ratio 1:2:4, 13Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 14. The part of Column which comes between the top of footing to bottom of Ground beam is called as Neck column. 14Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 15. It’s a black colour paint, painted to the structure which is under ground before back filling of Soil.The purpose of using the Bitumen paint is to (i) Increase the life of the structure (ii) Give strength to it (iii)To acts as water-proofing agent (iv)And to safe the structure from Corrosion. (iv) Liquid or sheet form. 15Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 16. Formwork Masonry (Stone Masonry and Brick Masonry) Flooring Plastering Pointing Doors and Windows Whitewashing, Colour washing and Distempering Painting Lump sum Item Electrification Nomenclature if Item Rates 16Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 17. 17Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 18. 18Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 19. 19Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 20. 20Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 21. 21Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 22. 22Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 23. 23Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 24. 24Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 25. 25Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 26. 26Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 27. 27Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 28. 28Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 29. 29Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 30. 30Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 31. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 31
  • 32.  PCC CONCRETE = 7.5565m3  GRADE OF CONCRETE USED FOR PCC M7.5  RATIO = 1:4:8  SAND: FOR 1m3 OF CONCRETE = 0.46m3  FOR 7.5565m3 = 7.5565 X 0.46 =3.47599m3  AGGRIGATE OF SIZE 40mm  For 1 m3 of concrete = 0.92 m3  For 7.5565 m3 = 7.5565 x 0.92 =6.95198 m3  CEMENT FOR 1m3 OF CONCRETE = 165.60KGS  FOR 7.5565 m3  7.5565 X 165.60 =1251.3564KGS  RCC CONCRETE = 101 m3  GRADE OF CONCRETE USED FOR PCC M15  RATIO = 1:2:4  SAND: FOR 1m3 OF CONCRETE = 0.46m3  FOR ,101m3 = 101 X 0.46 =46.46m3  AGGRIGATE OF SIZE 20mm  For 1 m3 of concrete = 0.92 m3  For 101 m3 = 101 x 0.92 =92.92 m3 Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 32
  • 33.  CEMENT FOR 1m3 OF CONCRETE = 331.20KGS  FOR 101 m3  101 X 331.20 =33451.2KGS  TOTAL SAND = 3.47599 + 46.46 = 49.95 m3  AGGRIGATE 40mm = 6.95198 m3  AGGRIGATE 20mm = 92.92 m3  TOTALCEMENT = 1251.3564 + 33451.2 =34702.5564KGS  = 695 BAGS  TOTALQUANTITYOF SAND = 49.95 m3  VOLUMEOF SAND EACHTRUCK ORTIPPER = AREA X DEPTH  = 4.29 X 2.5 X 1.4 = 15.01 m3  NOOF SAND IN EACHTRUCK = 15.01 m3  NOOF SANDTRUCK REQUIRED =VOL OF SAND /VOL OFTRUCK  = 49.95 / 15.01 = 3.765TRUCKSAPPROX 4 TRUCKS  TOTALVOLUMEOF AGGRIGATE 40mm & 20mm = 100 m3  NOOF AGGRIGATE EACHTRUCK = 9 m3  NOOF AGGRIGATETRUCK REQUIRED =VOL OF AGGRIGATE /VOL OF TRUCK = 100 / 15.01 = 6.668TRUCKSAPPROX 7TRUCKS Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 33
  • 34. 34Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 35. 35Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 36. 36Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 37. 37Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 38. 38Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 39. 39Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 40. 40Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 41. 41Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 42. 42Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 43. 43Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 44. 44Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 45.  BRICK SIZE: 0.2m x 0.1m x 0.1m  WALLTHICKNESS: 0.2m  ROLLER SHUTTER: 2.43m x 2.43m  WALLTHICKNESS: 0.23m  BRICKWORK CALCULATION:  BRICKWORK AREA:  1.WALL: length=21.73m, depth=4m.  Area=21.73 x 4= 86.92m2  2.WALL: length=21.73m, depth=4m.  Area=21.73 x 4= 86.92m2  3.WALL: length=13m, depth=4m.  Area=13 x 4=52m2  4.WALL: length=13m, depth=4m.  Area=13 x 4=52m2  WALL 4 Length same  52 +52 +52 + 52 + 52 + 52 =312m2  5.WALL: length=21m, depth=4m.  Area=21 x 4=84m2  WALL 5 Length same  84 + 84 +84 =252m2 45Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 46.  BRICKWORK AREA =86.92+86.92+52+312+252 = 789.84M2  DEDUCTIONS:  1. ROLLER SHUTTER: length=2.43m, depth=2.43m.  Area=2.43 x 2.43= 5.91m2  ROLLER SHUTTERTOTAL = 18  PER ROLLER SHUTTER AREA = 5.91 X 18 = 107m2  2. MAIN GATE AREA: length=3m, depth=4m.  Area=3 x 4= 12m2  MAIN GATE AREATOTAL = 6  PER MAIN GATE AREA: 12 X 6 =72m2  3. STAIR CASE AREA: length=3.35m, depth=4m.  Area=3.35 x 4= 13.4m2  STAIR CASE AREATOTAL = 3  PER STAIR CASE AREA: 13.4 X 3 = 40.2m2  TOTAL DEDUCTION AREA = 107 + 72 + 40.2 = 219.2m2  TOTAL BRICKWORK AREA = BRICKWORK AREA – DEDUCTION AREA  = 789.84 – 219.2  = 570.64M2  VOLUME OF BRICK WORK =TOTAL BRICKWORK AREA XWALLTHICKNESS  = 570.64 X 0.23  = 131.2472M2  VOLUME OF SINGLE BRICK = LENGTH X BREADTH X DEPTH  = 0.2 X 0.1 X 0.1  = 0.002m3  NUMBEROF BRICKS =VOLUME OF BRICKWORK /VOLUME OF SINGLE BRICK  = 131.2472/0.002m3  =65623.6 BRICKS  = 65624 BRICKS 46Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 47. 47Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 48. 48Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 49.  ROLLER SHUTTER: 2.43m x 2.43m  PLASTERINGTHICKNESS: 0.02m  PLASTERINGCALCULATION:  PLASTERINGAREA: INTERNALAREA 1  INTERNAL DIMENSION 1: LENGTH = 3.83m, BREADTH = 3.83m, DEPTH = 4m.  INTERNALAREA 1= (LENGTH + BREADTH) X 2 X DEPTH m2  = (3.83 + 3.83) x 2 x4  = 61.28m2  TOTAL INTERNALAREA 1: =61.28 * 15  = 919.2m2  INTERNAL DEDUCTIONS 1:  SHUTTER: LENGTH = 2.43m, DEPTH = 2.43m.  SHUTTERAREA = 2.43 x 2.43=5.9049m2  TOTAL DEDUCTIONAREA: 5.9049 X 18 =106.2882m2  INTERNAL DIMENSIONS 2:  STAIR CASE : LENGTH = 3.83, DEPTH = 4m.  INTERNALAREA 2= (LENGTH + BREADTH + LENGTH) X DEPTH m2  = (3.83 + 3.83 = 3.83) X 4  = 11.49 X 4 = 45.96m2  TOTAL DIMENSION = 45.96 X 2 =91.92m2 49Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 50.  TOTAL INTERNAL AREA = INTERNAL AREA – DEDUCTION AREA  = (91.92 + 919.2)–106.1882  = 904.9318m2  EXTERNAL AREA 1: LENGTH = 4.05, BREADTH = 4.05, DEPTH = 4M  = (L + B +L)X 4  = (4.05+4.05+4.05)X 4=48.6m2  TOTAL EXTERNAL AREA 1: 48.6X3=145.8m2  EXTERNAL AREA 2: LENGTH = 4.05, BREADTH = 4.05, DEPTH = 4M  = (L + B)X 4  = (4.05+4.05)X4 =32.4m2  TOTAL EXTERNAL AREA 2: 32.4X7=226.8m2  EXTERNAL AREA 3: LENGTH = 4.05, BREADTH = 4.05, DEPTH = 4M  = (L)X 4  = (4.05)X4 =16.2m2  TOTAL EXTERNAL AREA 3: 16.2X8=132.0m2  TOTAL EXTERNAL AREA: 145.8 + 226.8 +132.0m2  = 504.6m2  EXTERNAL DEDUCTIONS 1:  SHUTTER: LENGTH = 2.43m, DEPTH = 2.43m.  SHUTTERAREA = 2.43 x 2.43=5.9049m2  TOTAL EXTERNAL DEDUCTION AREA: 5.9049 X 18 = 106.2882  TOTAL EXTERNAL AREA = EXTERNAL AREA – DEDUCTION AREA  = 504.6–106.1882  = 398.3118m2  TOTAL PLASTERING AREA: INTERNAL + EXTERNAL PLASTERING AREA  = 904.9318m2 + 398.3118m2  = 1303.2436m2 50Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 51. 51Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 52. 52Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 53. 53Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 54. 54Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 55. 55Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 56. 56Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 57. 57Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 58. 58Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 59. 59Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S.
  • 60. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 60
  • 61. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 61
  • 62. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 62
  • 63. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 63
  • 64. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 64  1. DIAMETERS:  6mm,8mm,10mm,12mm,16mm,20mm,25mm,28mm  2. STANDARD LENGTH OF BAR = 12m.  3.WEIGHT PER METER = D2/162 kg/m. D=DIAMETER  FOR EXAMPLE SAY 8mm BAR.  WEIGHT PER METER = 82/162 = 0.39 kg/m.  4.WEIGHT PER BAR = (D2/162)*12 KGS/BAR.  FOR EXAMPLE SAY 8mm BAR.  WEIGHT PER METER = (82/162)*12 = 4.74 KGS/BAR  5. HOOK :  LENGTH OF HOOK =9d, d = diameter.  LENGTH OF BAR = L + 9d +9d m  6. BEND :  LENGTH OF BEND =10d – 16d, d = diameter.  LENGTH OF BAR = L + 12d +12d m. (BEND = 12d).
  • 65.  NECK COLUMNTO FOOTING OVERLAPPING = 40d – 50d, or 16D  COLUMNTO COLUMN = 50d,  GENERALOVERLAPPINGWHEN 12m BAR FINISHES = 50d. D=DIAMETER  8. CRANK BAR :  CRANK = 0.42d,  LENGTHOFTHE CRANK BAR = L + 0.42d + 0.42d,  D= SLAB OR BEAMTHICKNESS –TOP N BOTTOM COVER.  LENGTHOF EXTRA BAR = L/4.  9. COVER: SPACE BETWEEN REINFORCEMENTAND SHUTTERING. COVERING BLOCKSARE USED FOR PROVIDINGCOVER.  FOOTING = 75mm  COLUMN = 25mm - 50mm  BEAM = 25mm - 50mm  SLAB = 25mm  10. SPACING: DISTANCE BETWEENTWO REINFORCEMENT BARS.  11. NUMBER OF BARS = (OPPOSITE LENGTH /SPACING) + 1.  12. NUMBER OF STIRRUPS = (ACTUAL LENGTH OF COLUMN OR BEAM /SPACING) + 1. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 65
  • 66. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 66
  • 67. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 67
  • 68.  FOOTING REINFORCEMENT CALCULATIONS:  SHORTWAY BARS:  1. LENGTH OF S/W BAR = L - 0.1 – 0.1 + D + D M  LENGTH OF S/W BAR = 1.4 – 0. 1 – 0.1 +0.3 + 0.3 M  LENGTH OF S/W BAR = 1.80 M   2. NUMBER OF SHORTWAY BAR = (OPPOSITE LENGTH / SPACING) + 1  NUMBER OF SHORTWAY BAR = {(1.8 – 0.1 – 0.1)/0.1} + 1  NUMBER OF SHORTWAY BAR = {1.6/0.1} + 1  NUMBER OF SHORTWAY BAR = 17 BARS  3.TOTAL LENGTH OF SHORT WAY BARS = LENGTH OF BAR * NUMBER OF BARS M  TOTAL LENGTH OF SHORTWAY BARS = 1.80 *17 M  TOTAL LENGTH OF SHORTWAY BARS = 30.60 M  4. DIAMETER OF SHORT WAY BAR = 10 MM (GIVEN IN DRAWING)  5.WEIGHT PER METER OF SHORTWAY BAR K= D2/162 GS/M  WEIGHT PER METER OF SHORT WAY BAR = 10*10/162 KGS/M  WEIGHT PER METER OF SHORT WAY BAR = 0.62 KGS/M  6.TOTAL WEIGHT OF SHORTWAY BARS =TOTAL LENGTH * WEIGHT PER METER * NO OF MEMBER KGS  TOTALWEIGHT OF SHORT WAY BARS = 30.60 * 0.62 * 7 KGS  TOTALWEIGHT OF SHORT WAY BARS = 132.804 KGS Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 68
  • 69.  LONGWAY BARS:  1. LENGTH OF L/W BAR = L - 0.1 – 0.1 + D + D M  LENGTH OF L/W BAR = 1.8 – 0. 1 – 0.1 +0.3 + 0.3 M  LENGTH OF L/W BAR = 2.20 M   2. NUMBER OF LONGWAY BAR = (OPPOSITE LENGTH / SPACING) + 1  NUMBER OF LONGWAY BAR = {(1.4 – 0.1 – 0.1)/0.1} + 1  NUMBER OF LONGWAY BAR = {1.2/0.1} + 1  NUMBER OF LONGWAY BAR = 13 BARS   3.TOTAL LENGTH OF LONGWAY BARS = LENGTH OF BAR * NUMBER OF BARS M  TOTAL LENGTH OF LONGWAY BARS = 2.2 *13 M  TOTAL LENGTH OF LONGWAY BARS = 28.60 M   4. DIAMETER OF LONGWAY BAR = 10 MM (GIVEN IN DRAWING).   5.WEIGHT PER METER OF LONGWAY BAR = D2/162 KGS/M  WEIGHT PER METER OF LONGWAY BAR = 10*10/162 KGS/M  WEIGHT PER METER OF LONGWAY BAR = 0.62 KGS/M   6.TOTAL WEIGHT OF LONGWAY BARS =TOTAL LENGTH * WEIGHT PER METER * NO OF MEMBER KGS  TOTAL WEIGHT OF LONGWAY BARS = 28.60 * 0.62 * 7 KGS  TOTAL WEIGHT OF LONGWAY BARS = 124.124 KGS Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 69
  • 70. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 70
  • 71. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 71
  • 72. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 72
  • 73.  NECK COLUMN (MAIN BAR)  L = NECK COLUMN + FOOTING BOTTOM MESH  L = 1.2 + 0.3  L = 1.5 DIA = 12MM  LENGTHOF EACH MAIN BAR = L + 50D + 16D  = 1.5 + 66D  = 1.5 + 66 (0.012)  = 2.30 M  NO OF MAIN BAR = 8  TOTAL LENGTH OF MAIN BAR = LENGTH OF EACH BAR X NO OF MAIN BAR  = 2.30 X 8  = 18.4 M  WEIGHT OF STEEL BAR IN KGS / M = D2/162 KGS/M  = 12*12/162  = 0.88 KGS/ M  REQUIREDWEIGHT OF STEEL FOR MAIN BAR = WEIGHT/M XTOTAL LENGTHOF MAIN BAR X NO OF MEMBER  = 0.88 X 18.4 X 7  = 113.344 KGS Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 73
  • 74.  NECK COLUMN (STIRRUPS)  25 MM (0.025 M) CONCRETE COVER HASTO BE DEDUCTED FROM EACH SIDE OF COLUMN  L = LENGTH OF EACH STIRRUPS  L = (0.40 + 0.18) X 2  L = 1.16 M  LENGTH OF EACH STIRRUPSWITH HOOK = L +18D  = 1.16 + 18(0.008)  = 1.304 M  NO OF STIRRUPS = (HEIGHT OF NECK COLUMN / SPACING) + 1  = (1.5 / 0.1) + 1  = 16 STIRRUPS  TOTAL LENGTH OF STIRRUPS = LENGTH OF EACH STIRRUPS X NO OF STIRRUPS  = 1.304 X 16  = 20.864 M  WEIGHT OF STEEL BAR IN KGS / M = D2/162 KGS/M  = 8*8 / 162  = 0.39 KGS / M  REQUIREDWEIGHT OF BAR FOR STIRRUPS = WEIGHT OF STEEL BAR IN KGS/M XTOTAL LENGTH X NO OF ITEM  = 0.39 X 20.864 X 7 = 56.959 KGS Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 74
  • 75. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 75
  • 76. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 76
  • 77. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 77
  • 78. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 78
  • 79. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 79
  • 80. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 80
  • 81. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 81
  • 82. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 82
  • 83. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 83
  • 84. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 84
  • 85. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 85
  • 86. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 86
  • 87. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 87
  • 88. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 88
  • 89. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 89
  • 90. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 90
  • 91. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 91
  • 92. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 92
  • 93. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 93
  • 94. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 94
  • 95. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 95
  • 96. Dept of Civil Engg, A.H.C.E.T, Damaragidda,Chevella,T.S. 96