The document is a portfolio of projects completed by Maged Mahmoud Hemeda as a project engineer. It includes projects for Gulf Drilling International offices, Qatar General Electricity & Water Corporation, Qatar Public Works Authority, InterContinental Hotel, and Al Jazeera Finance headquarters. The portfolio outlines Hemeda's role, project costs ranging from $1 million to $15 million, total areas from 80 square meters to 6,400 square meters, and the scope of work involving MEP and fit-out works.
2. GULF DRILLING INTERNATTIONAL (GDI) OFFICES (PALM TOWERS)
POSITION:
PROJECT ENGINER
PROJECT COST:
12 MILLION
PROJECT AREA:
6,400 m2
2 FLOORS
PROJECT SCOPE:
MEP and FIT OUT
WORKS
Maged M. Hemeda - PORTFOLIO Page 1 of 31 *Last Updated March 2016
3. GULF DRILLING INTERNATTIONAL (GDI) OFFICES – PALM TOWERS 9TH & 19TH FLOORS
Maged M. Hemeda - PORTFOLIO Page 2 of 31 *Last Updated March 2016
4. GULF DRILLING INTERNATTIONAL (GDI) OFFICES – PALM TOWERS 9TH & 19TH FLOORS
Maged M. Hemeda - PORTFOLIO Page 3 of 31 *Last Updated March 2016
5. QATAR GENERAL ELECTRICITY & WATER CORPORATION “KAHRAMAA”
POSITION:
PROJECT ENGINEER
PROJECT COST:
3 MILLION
PROJECT AREA:
1,500 m2
1 FLOOR
PROJECT SCOPE:
MEP, FIT OUT WORKS
and Furniture
Maged M. Hemeda - PORTFOLIO Page 4 of 31 *Last Updated March 2016
6. QATAR GENERAL ELECTRICITY & WATER CORPORATION “KAHRAMAA” 12TH FLOOR
ENTRANCE LOBBY
Maged M. Hemeda - PORTFOLIO Page 5 of 31 *Last Updated March 2016
7. QATAR GENERAL ELECTRICITY & WATER CORPORATION “KAHRAMAA” 12TH FLOOR
MAIN MEETING ROOM (BOARD ROOM)
Maged M. Hemeda - PORTFOLIO Page 6 of 31 *Last Updated March 2016
8. QATAR GENERAL ELECTRICITY & WATER CORPORATION “KAHRAMAA” 12TH FLOOR
TRAINING ROOMS
Maged M. Hemeda - PORTFOLIO Page 7 of 31 *Last Updated March 2016
9. QATAR GENERAL ELECTRICITY & WATER CORPORATION “KAHRAMAA” 12TH FLOOR
CAFETRIA AREA
Maged M. Hemeda - PORTFOLIO Page 8 of 31 *Last Updated March 2016
10. QATAR GENERAL ELECTRICITY & WATER CORPORATION “KAHRAMAA” 12TH FLOOR
MAJLIS AREA
Maged M. Hemeda – PORTFOLIO Page 9 of 31 *Last Updated March 2016
11. QATAR GENERAL ELECTRICITY & WATER CORPORATION “KAHRAMAA” 12TH FLOOR
GYM AREA
Maged M. Hemeda - PORTFOLIO Page 10 of 31 *Last Updated March 2016
12. QATAR PUBLIC WORKS AUTHORITY.”ASHGAAL” 16TH FLOOR
PRESIDENT’S VIP MAJLIS
POSITION:
PROJECT ENGINEER
PROJECT COST:
1 MILLION
PROJECT AREA:
80 m2
1 FLOOR
PROJECT SCOPE:
MEP, FIT OUT WORKS
and Furniture
Maged M. Hemeda - PORTFOLIO Page 1 1 of 31 *Last Updated March 2016
13. QATAR PUBLIC WORKS AUTHORITY.”ASHGAAL” 16TH FLOOR
PRESIDENT’S VIP MAJLIS
Maged M. Hemeda - PORTFOLIO Page 12 of 31 *Last Updated March 2016
14. QATAR PUBLIC WORKS AUTHORITY.”ASHGAAL” GROUND FLOOR
CUSTOMER SERVICES CENTRE
POSITION:
PROJECT ENGINEER
PROJECT COST:
1MILLION
PROJECT AREA:
300 m2
1 FLOOR
PROJECT SCOPE:
MEP, FIT OUT WORKS
and Furniture
Maged M. Hemeda - PORTFOLIO Page 13 of 31 *Last Updated March 2016
15. QATAR PUBLIC WORKS AUTHORITY.”ASHGAAL” GROUND FLOOR
CUSTOMER SERVICES CENTRE
Maged M. Hemeda - PORTFOLIO Page 14 of 31 *Last Updated March 2016
16. POSITION:
PROJECT ENGINEER
PROJECT COST:
1.5 MILLION
PROJECT AREA:
100 m2
PROJECT SCOPE:
(MEP, FIT OUT WORKS
and FURNITURE)
INTERCONTINANTAL HOTEL ( MAIN OFFICE )
Maged M. Hemeda - PORTFOLIO Page 15 of 31 *Last Updated March 2016
17. INTERCONTINANTAL HOTEL ( MAIN OFFICE )
Maged M. Hemeda - PORTFOLIO Page 16 of 31 *Last Updated March 2016
18. POSITION:
PROJECT ENGINEER
PROJECT COST:
2 MILLION
PROJECT AREA:
100 M2
2 FLOORS
PROJECT SCOPE :
(MEP, FIT OUT WORKS
and FURNITURE)
INTERCONTINANTAL HOTEL PENTHOUSE (SHEIKH AHMED ELKABISI)
Maged M. Hemeda - PORTFOLIO Page 17 of 31 *Last Updated March 2016
20. Qatar general electricity & Water Corporation Customer Services
Branches (Alhilal – Industrial area – Mushireb). (KAHRAMAA)
POSITION:
PROJECT ENGINEER
PROJECT COST:
10 MILLION
PROJECT AREA:
500 M2
3 BRANCHES
PROJECT SCOPE:
(MEP, FIT OUT WORKS
and FURNITURE)
Maged M. Hemeda - PORTFOLIO Page 19 of 31 *Last Updated March 2016
21. Qatar general electricity & Water Corporation Customer Services
Branches (Alhilal – Industrial area – Mushireb). (KAHRAMAA)
Maged M. Hemeda - PORTFOLIO Page 20 of 31 *Last Updated March 2016
22. Qatar general electricity & Water Corporation Customer Services
Branches (Alhilal – Industrial area – Mushireb). (KAHRAMAA)
Maged M. Hemeda - PORTFOLIO Page 21 of 31 *Last Updated March 2016
23. Al Jazeera Finance Head Quarter Building – Medmac Round About
POSITION:
PROJECT ENGINEER
PROJECT COST:
15 MILLION
PROJECT AREA:
2000 M2
3FLOORS
PROJECT SCOPE:
(MEP, FIT OUT WORKS
and FURNITURE)
CURRENT PROJECT
Maged M. Hemeda - PORTFOLIO Page 22 of 31 *Last Updated March 2016
24. Al Jazeera Finance Head Quarter Building – Midmac Round About
GROUND Floor – CUSTOMER SERVICES SHOWROOM
Maged M. Hemeda - PORTFOLIO Page 23 of 31 *Last Updated March 2016
25. Al Jazeera Finance Head Quarter Building – Midmac Round About
GROUND Floor – RETAIL SHOWROOM
Maged M. Hemeda - PORTFOLIO Page 24 of 31 *Last Updated March 2016
26. Al Jazeera Finance Head Quarter Building – Midmac Round About
First Floor
Maged M. Hemeda - PORTFOLIO Page 25 of 31 *Last Updated March 2016
27. Al Jazeera Finance Head Quarter Building – Midmac Round About
First Floor
Maged M. Hemeda - PORTFOLIO Page 26 of 31 *Last Updated March 2016
28. Al Jazeera Finance Head Quarter Building – Medmac Round About
First Floor
Maged M. Hemeda - PORTFOLIO Page 27 of 31 *Last Updated March 2016
29. Al Jazeera Finance Head Quarter Building – Medmac Round About
SECOND Floor- VIP AREA - RECEPTION AREA
Maged M. Hemeda - PORTFOLIO Page 28 of 31 *Last Updated March 2016
30. Al Jazeera Finance Head Quarter Building – Medmac Round About
SECOND Floor- VIP AREA - CHAIRMAN OFFICE
Maged M. Hemeda - PORTFOLIO Page 29 of 31 *Last Updated March 2016
31. Al Jazeera Finance Head Quarter Building – Medmac Round About
SECOND Floor- VIP AREA – CEO OFFICE
Maged M. Hemeda - PORTFOLIO Page 30 of 31 *Last Updated March 2016
32. Al Jazeera Finance Head Quarter Building – Medmac Round About
SECOND Floor- VIP AREA – MEETING ROOM
Maged M. Hemeda - PORTFOLIO Page 31 of 31 *Last Updated March 2016