PROGRESS PHOTOS JUNE 2014, (2)
- 1. Page 1 of 5
CONSTRUCTION OF 28 ADDITIONAL RESIDENTIAL UNITS AT IMANI/SHELL ESTATE,MAITAMA,ABUJA.JUNE ,2014
Photo 01: Steward Qrts grd.beam 02.06.2014. Photo 02: Block C,level 03 Liftwall fmwk.02.06.2014. Photo 03: Block B,level 02 clay pot 03.06.2014
Photo04: Block C,services/scase casted at lev.02 03.06.2014. Photo05:BlockB,m/s case casted at lev.02.03.06.2014. Photo 06:1st
flr. fmwk at 1 & 2 Terrace house 3.6.2014
. 01.04.2014.
Photo 07:Fmwk toTerrace 1& 2 1st
flr. .04.06.2014. Photo08:Terracehouse1 & 2 col.concrete 04.06.2014 Photo 09:Blk .B lev. 02Concrt.slab 05.06.2014
- 2. Page 2 of 5
CONSTRUCTION OF 28 ADDITIONAL RESIDENTIAL UNITS AT IMANI/SHELL ESTATE,MAITAMA,ABUJA.JUNE,2014
Photo10:Compacting& levellingof stewardqrts 05.06.2014 Photo 11:. Plumbing pipes in progress at B/Q. 05.06.2014. Photo 12:Lev.02-03liftwall at blockc,casted 05.06.2014
05.06.2014.
Photo 13:plumbing pipingworks at B/Q . 06.06.2014. Photo 14: Terrace 1 &2 s/case casted 06.06.2014 . Photo 15:Block B,level 02 m/staircase 06.06.2014
Photo16:Terrace1 & 2Blkwkin progress 06.06.2014. Photo17:Terrace3 & 4 1st
flr. Bm reinft .06.06.2014. Photo18:Terrace 3 & 4 ist flr. Fmwto s/case .09.06.2014
- 3. Page 3 of 5
CONSTRUCTION OF 28 ADDITIONAL RESIDENTIAL UNITS AT IMANI/SHELL ESTATE,MAITAMA,ABUJA.JUNE,2014.
Photo19:Hardcore in BQ in progress . 09.06.2014. Photo20: Terrace house 3 & 4 1st flr. fmwk 10.06.2014 Photo21: BlockB,LEV.02-03 liftwall 10.06.2014.
Photo 22: : Terracehouses 3 &4 Fmwk.10.06.2014 Photo 23: Blk B,Lev.02-03 fmwk tocols. 11.06.2014 Photo 23: Blk c,Lev.03 fmwkto slab& bms 12.06.2014
.
Photo25: HardcoreinB/Qcompleted . 12.06.2014 Photo26: Terracehouse 3& 4 1st flr. reinft.12.06.2014 Photo 27:Terracehouse 1 &2 1st flr.col to roof 13.06.2014
- 4. Page 4 of 5
CONSTRUCTION OF 28 ADDITIONAL RESIDENTIAL UNITS AT IMANI/SHELL ESTATE,MAITAMA,ABUJA.JUNE,2014.
Photo 28: electrical piping in terracehouse1 & 2.13.06.2014 Photo 29:Terracehouse 3& 4 Plumbing pipes 13.06.2014 Photo29:Terracehouse3 & 4ist flr.conc.casting 19.06.2014 .
Photo31:BlockC,LEV.01Blk work in progress . 19.06.2014. Photo 32:Reinft.on the B/Q grd.slab.19.06.2014 Photo 33: Terracehouse 3 & 4 1st
flr.conc.completed. 19.06.2014
Photo34:Terrace house 1 & 2 grd.flr.blkwk 1/2 20.06.2014. Photo35: Terrace house 1 & 2 grd.flr.blkwk 2/2 20.06.2014. Photo36:blockA ,lev.02claypots 20.06.2014
- 5. Page 5 of 5
CONSTRUCTION OF 28 ADDITIONAL RESIDENTIAL UNITS AT IMANI/SHELL ESTATE,MAITAMA,ABUJA.JUNE,2014
Photo37: B/Qgrd flr.reinft . 23.06.2014 Photo38:Terracehouse 1 & 2 blkwork 23.06.2014. Photo 39:BlockA,Claypots at lev.02 23.06.2014
Photo 40:Grd. Flr. concrete slabin B/Q 26.06.2014 Photo41: Terrace1 & 2,blkwk at grd.flr.26.06.2014 Photo 42:Grd. Flr. concrete slabin B/Q 27.04.2014
Photo 43: BlockA,level 02conc.slab 30.06.2014 Photo44: Service S/case to lev.02Blk A . 30.06.2014 Photo45:BlockC, level 01,Blkwk in progress 30.06.2014