SlideShare a Scribd company logo
1 of 255
F-35 JOINT STRIKE
FIGHTER
Assessment Needed
to Address
Affordability
Challenges
Report to Congressional Committees
April 2015
GAO-15-364
United States Government Accountability Office
United States Government Accountability Office
Highlights of GAO-15-364, a report to
congressional committees
April 2015
F-35 JOINT STRIKE FIGHTER
Assessment Needed to Address Affordability
Challenges
Why GAO Did This Study
With estimated acquisition costs of
nearly $400 billion, the F-35 Lightning
II—also known as the Joint Strike
Fighter—is DOD's most costly and
ambitious acquisition program. The
U.S. portion of the program will require
annual acquisition funding of $12.4
billion on average through 2038 to
complete development and procure a
total of 2,457 aircraft. GAO’s prior work
has found that the program has
experienced significant cost, schedule,
and performance problems.
In 2009, Congress mandated that GAO
review the F-35 acquisition program
annually for 6 years. This report,
GAO's sixth, assesses the program's
(1) development and testing progress,
(2) cost and affordability, and (3)
manufacturing and supply chain
performance.
GAO reviewed and analyzed the latest
available manufacturing, cost, testing,
and performance data through
December 2014; program test plans;
and internal DOD analyses; and
interviewed DOD, program, engine and
aircraft contractor officials.
What GAO Recommends
GAO recommends that DOD assess
the affordability of F-35’s current
procurement plan that reflects various
assumptions about technical progress
and future funding.
What GAO Found
The F-35 Joint Strike Fighter program had to make unexpected
changes to its
development and test plans over the last year, largely in
response to a structural
failure on a durability test aircraft, an engine failure, and
software challenges. At
the same time, engine reliability is poor and has a long way to
go to meet
program goals. With nearly 2 years and 40 percent of
developmental testing to
go, more technical problems are likely. Addressing new
problems and improving
engine reliability may require additional design changes and
retrofits. Meanwhile,
the Department of Defense (DOD) has plans to increase annual
aircraft
procurement from 38 to 90 over the next 5 years. As GAO has
previously
reported, increasing production while concurrently developing
and testing creates
risk and could result in additional cost growth and schedule
delays in the future.
Cost and affordability challenges remain. DOD plans to
significantly increase
annual F-35 funding from around $8 billion to nearly $12
billion over the next 5
years (see figure) reaching $14 billion in 2022 and remaining
between $14 and
$15 billion for nearly a decade. Over the last year, DOD
reduced near-term
aircraft procurement by 4 aircraft, largely due to budget
constraints. While these
deferrals may lower annual near-term funding needs, they will
likely increase the
cost of aircraft procured in that time frame and may increase
funding liability in
the future. It is unlikely the program will be able to sustain such
a high level of
annual funding and if required funding levels are not reached,
the program’s
procurement plan may not be affordable. DOD policy requires
affordability
analyses to inform long-term investment decisions. The
consistent changes in F-
35 procurement plans indicate that DOD’s prior analyses did not
adequately
account for future technical and funding uncertainty.
F-35 Joint Strike Fighter Budgeted Costs by Service, 2015-2019
Manufacturing progress continued despite mixed supplier
performance. The
aircraft contractor delivered 36 aircraft as planned in 2014,
despite a fleet
grounding, added inspections, and software delays. In contrast,
the labor hours
needed to manufacture an aircraft and the number of major
design changes have
continued to decline over time. Because supplier performance
has been mixed,
late aircraft and engine part deliveries could pose a risk to the
program's plans to
increase production. The contractors are taking steps to address
these issues.
View GAO-15-364. For more information,
contact Michael J. Sullivan at (202) 512-4841
or [email protected]
http://www.gao.gov/products/GAO-15-364�
http://www.gao.gov/products/GAO-15-364�
Page i GAO-15-364 F-35 Joint Strike Fighter
Letter 1
Background 2
Recent Technical Challenges Will Likely Result in Cost Growth
and Schedule Delays 8
Affordability Challenges Will Likely Continue to Affect
Program
Plans to Increase F-35 Procurement 14
While Manufacturing Progress Remains Steady, Planned
Production Increases Could Be a Challenge 17
Conclusions 23
Recommendations 23
Agency Comments and Our Evaluation 23
Appendix I Prior GAO Reports on F-35 Joint Strike Fighter
(JSF) and Department
of Defense (DOD) Responses and Subsequent Actions 26
Appendix II Scope and Methodology 30
Appendix III DOD Comments 32
Appendix IV GAO Contact and Staff Acknowledgments 34
Related GAO Products 35
Table
Table 1: Changes in Reported F-35 Joint Strike Fighter Program
Cost, Quantity, and Deliveries, 2001-2014 5
Figures
Figure 1: Changes in F-35 Joint Strike Fighter Near-Term
Procurements 4
Figure 2: Subsequent Development of F-35 Joint Strike Fighter
Software Blocks 7
Contents
Page ii GAO-15-364 F-35 Joint Strike Fighter
Figure 3: Measured Mean Flight Hours between Failure-(design
controlled) for the F-35 Joint Strike Fighter Engine Only 12
Figure 4: Budgeted Development and Procurement Costs by
Service, 2015-2038 15
Figure 5: Trend of F-35 Joint Strike Fighter Contractual
Delivery
Dates Compared to Actual Delivery Dates 18
Figure 6: Trend in Labor Hours to Build the F-35 Joint Strike
Fighter Aircraft by Variant 19
Figure 7: Trend in Percent of Labor Hours Spent on Scrap,
Rework, and Repair for the F-35 Joint Strike Fighter 20
Figure 8: Average Number of F-35 Joint Strike Fighter Part
Shortage Occurrences at Prime Contractor Facility 21
This is a work of the U.S. government and is not subject to
copyright protection in the
United States. The published product may be reproduced and
distributed in its entirety
without further permission from GAO. However, because this
work may contain
copyrighted images or other material, permission from the
copyright holder may be
necessary if you wish to reproduce this material separately.
Page 1 GAO-15-364 F-35 Joint Strike Fighter
441 G St. N.W.
Washington, DC 20548
April 14, 2015
Congressional Committees
With estimated acquisition costs of nearly $400 billion, the F-
35 Lightning
II—also known as the Joint Strike Fighter—is the Department
of
Defense’s (DOD) most costly and ambitious acquisition
program. Through
this program, DOD is developing and fielding a family of next
generation
strike fighter aircraft, integrating low observable (stealth)
technologies
with advanced sensors and computer networking capabilities for
the
United States Air Force, Navy, and Marine Corps, as well as
eight
international partners.1 The F-35 family is comprised of the F-
35A
conventional takeoff and landing variant, the F-35B short
takeoff and
vertical landing variant, and the F-35C carrier-suitable variant.
According
to current projections, the U.S. portion of the program will
require
acquisition funding of $12.4 billion a year, on average, through
2038 to
complete development and procure a total of 2,457 aircraft. In
addition,
DOD and program office estimates indicate that the F-35 fleet
could cost
around $1 trillion to operate and support over its lifetime,
which will pose
significant affordability challenges.
We have reported on F-35 issues for many years. Over time, we
have
reported significant cost, schedule, and performance problems
and have
found those problems, in part, can be traced to (1) decisions
made at key
junctures without adequate product knowledge and (2) a highly
concurrent acquisition strategy with significant overlap among
development, testing, and manufacturing activities. We have
made
numerous recommendations for improvement in our previous
reports.
DOD has taken action to address many of our recommendations
to
varying degrees.2
1The international partners are the United Kingdom, Italy, the
Netherlands, Turkey,
Canada, Australia, Denmark, and Norway. These nations
contributed funds for system
development and signed agreements to procure aircraft. In
addition, Israel, Japan, and
South Korea have signed on as foreign military sales customers.
2See app. I for a matrix of prior GAO reports,
recommendations, and DOD actions.
Letter
Page 2 GAO-15-364 F-35 Joint Strike Fighter
The National Defense Authorization Act for Fiscal Year 2010
requires
GAO to review the F-35 acquisition program annually for 6
years.3 This is
the sixth and final report under that mandate, and in this report
we assess
program (1) development and testing progress, (2) cost and
affordability
and (3) manufacturing and supply chain performance.
To conduct our work, we reviewed and analyzed program
briefings,
management reports, test data and results, and internal DOD
program
analyses. We collected data on and discussed key aspects of F-
35
development and test progress with program management and
contractor
officials as well as DOD test officials and program test pilots.
We
collected and analyzed program acquisition cost estimates and
reviewed
total program funding requirements to project annual funding
requirements through 2038. To assess the reliability of the cost
data, we
reviewed the supporting documentation and discussed the
development
of those estimates with DOD officials instrumental in producing
them. We
collected and analyzed production and supply chain
performance data
from DOD, Lockheed Martin, and Pratt & Whitney. We assessed
the
reliability of the data by reviewing supporting documentation
and
interviewing knowledgeable agency officials. We determined
that all of the
data we used were sufficiently reliable for the purposes of this
report. We
also discussed ongoing manufacturing process improvements
with
contracting and Defense Contract Management Agency officials.
Appendix Il contains a more detailed description of our scope
and
methodology.
We conducted this performance audit from July 2014 to April
2015 in
accordance with generally accepted government auditing
standards.
Those standards required that we plan and perform the audit to
obtain
sufficient, appropriate evidence to provide a reasonable basis
for our
findings and conclusions based on our audit objectives. We
believe that
the evidence obtained provides a reasonable basis for our
findings and
conclusions based on our audit objectives.
DOD began the F-35 acquisition program in October 2001
without
adequate knowledge about the aircraft’s critical technologies or
design. In
addition, DOD’s acquisition strategy called for high levels of
concurrency
3Pub. L. No. 111-84, § 244 (2009).
Background
Page 3 GAO-15-364 F-35 Joint Strike Fighter
between development, testing, and production.4 In our prior
work, we
have identified the lack of knowledge and high levels of
concurrency as
major drivers in the significant cost and schedule growth as
well as
performance shortfalls that the program has experienced since
2001. The
program has been restructured three times since it began: first
in
December 2003, again in March 2007, and most recently in
March 2012.
The most recent restructuring was initiated in early 2010 when
the
program’s unit cost estimates exceeded critical thresholds
established by
statute—a condition known as a Nunn-McCurdy breach.5 DOD
subsequently certified to Congress in June 2010 that the
program was
essential to national security and needed to continue. DOD then
began
efforts to significantly restructure the program and establish a
new
acquisition program baseline. These restructuring efforts
continued
through 2011 and into 2012, during which time the department
increased
the program’s cost estimates, extended its testing and delivery
schedules,
and reduced near-term aircraft procurement quantities by
deferring the
procurement of 450 aircraft into the future—total procurement
quantities
did not change. Figure 1 shows how planned quantities in the
near-term
have steadily declined over time.
4Concurrency is broadly defined as the overlap between
technology development and
product development or between product development and
production.
5Section 2433 of title 10 of the United States Code, commonly
referred to as Nunn-
McCurdy, requires DOD to notify Congress whenever a major
defense acquisition
program’s unit cost experiences cost growth that exceeds
certain thresholds. This is
commonly referred to as a Nunn-McCurdy breach. Significant
breaches occur when the
program acquisition unit cost or procurement unit cost increases
by at least 15 percent
over the current baseline estimate or at least 30 percent over the
original estimate. For
critical breaches, when these unit costs increase at least 25
percent over the current
baseline estimate or at least 50 percent over the original, DOD
is required to take
additional steps, including conducting an in-depth review of the
program. Programs with
critical breaches must be terminated unless the Secretary of
Defense certifies to certain
facts related to the program and takes other actions, including
restructuring the program.
10 U.S.C. § 2433a.
Page 4 GAO-15-364 F-35 Joint Strike Fighter
Figure 1: Changes in F-35 Joint Strike Fighter Near-Term
Procurements
The new F-35 acquisition program baseline was finalized in
March 2012,
and since that time costs have remained relatively stable. Table
1 shows
the significant cost, quantity, and schedule changes from the
initial
program baseline and the relative stability since the new
baseline was
established.
Page 5 GAO-15-364 F-35 Joint Strike Fighter
Table 1: Changes in Reported F-35 Joint Strike Fighter Program
Cost, Quantity, and Deliveries, 2001-2014
October 2001
Initial
Baseline
March 2012
Latest
Baseline
December
2014
Estimates
Change from
2001 to 2012
Change from
2012 to 2014
Expected quantities (number of aircraft)
Developmental quantities 14 14 14 0% 0%
Procurement quantities 2,852 2,443 2,443 -14 0
Total quantities 2,866 2,457 2,457 -14 0
Cost estimates (then-year dollars in billions) a
Development $34.4 $55.2 $54.9 60% -0.5%
Procurement 196.6 335.7 331.6 71 -1.2
Military construction 2.0 4.8 4.6 140 -4.2
Total program acquisition 233.0 395.7 391.1 70 -1.2
Unit cost estimates (then-year dollars in millions) a
Program acquisition $81 $161 $159 99% -1.2%
Average procurement 69 137 136 99 -0.7
Estimated delivery and production dates
Initial operational capability 2010-2012 Undetermined 2015-
2018 Undetermined 5-6 years
Full-rate production 2012 2019 2019 7 years 0 years
Source: GAO analysis of DOD data | GAO-15-364
a
Annual projected cost estimates expressed in then-year dollars
reflect inflation assumptions made by
a program
In March 2012, when the new acquisition program baseline was
finalized,
DOD had not yet identified new initial operating capability
dates for the
military services.6 The following year, DOD issued a
memorandum stating
that the Marine Corps and Air Force were planning to field
initial operating
capabilities in 2015 and 2016 respectively, and that the Navy
planned to
field its initial operating capability in 2018, which represented a
delay of 5
to 6 years since the program’s initial baseline.
DOD is currently conducting developmental flight testing to
verify that the
F-35 system’s design works as intended and can reliably
provide the
capabilities needed for the services to field their respective
initial
6Initial operating capability is generally obtained when
organizations or units have
received a specified number of systems and have the ability to
employ and maintain those
systems.
Page 6 GAO-15-364 F-35 Joint Strike Fighter
operational capabilities. The program’s flight testing is
separated into two
key areas referred to as mission systems and flight sciences.
Mission
systems testing is done to verify that the software and systems
that
provide warfighting capabilities function properly and meet
requirements,
while flight science testing is done to verify the aircraft’s basic
flying
capabilities. For the F-35 program, DOD is developing and
fielding
mission systems capabilities in software blocks: (1) Block 1, (2)
Block 2A,
(3) Block 2B, (4) Block 3i, and (5) Block 3F. Each subsequent
block builds
on the capabilities of the preceding blocks. Blocks 1 and 2A are
essentially complete. The program is now focused on
completing Block
2B testing to support Marine Corps initial operating capability,
but some
testing of specific Block 3i and Block 3F capabilities is also
being
conducted. Blocks 2B and 3i will provide initial warfighting
capabilities
while Block 3F is expected to provide the full suite of
warfighting
capabilities. Figure 2 identifies the sequence of software blocks
and
capabilities expected to be delivered in each.
Page 7 GAO-15-364 F-35 Joint Strike Fighter
Figure 2: Subsequent Development of F-35 Joint Strike Fighter
Software Blocks
As developmental flight testing continues, DOD is concurrently
purchasing and fielding aircraft. The F-35 airframe and engine
are
managed as one program, but they are manufactured in separate
facilities by different contractors. The airframe is being
manufactured by
Lockheed Martin, the prime contractor, in Fort Worth, Texas,
while the
engine—which is designated the F135—is manufactured by
Pratt &
Whitney in Middletown, Connecticut. The engines are
purchased by the
government directly from Pratt & Whitney and delivered as
government
furnished equipment to Lockheed Martin for integration into the
airframes
during production. As a result, engine development and testing
activities
are managed by Pratt & Whitney and not Lockheed Martin.
Page 8 GAO-15-364 F-35 Joint Strike Fighter
The F-35 program continued to experience development and
testing
discoveries over the past year, largely due to a structural failure
on the F-
35B durability test aircraft, an engine failure, and more mission
system
test growth than expected. Together, these factors led to
adjustments in
the program’s test schedule. Test resources and some aircraft
capabilities
were reprioritized, and test points were deferred or eliminated.
While
these actions mitigated some of the schedule risk, ultimately the
completion of key developmental test activities had to be
delayed.
Decisions were also made to restructure an early operational
test event
that likely would have reduced operational risk for the Marine
Corps. The
event will now be conducted over time and will not be
completed as
originally scheduled. Instability in the development program is
likely to
continue with more complex and demanding development
testing still to
go. As the program continues to discover problems in
development and
testing, it also faces a significant challenge to improve the
reliability of the
engine. Program data show that the reliability of the engine is
very poor
(less than half of where it should be) and has limited the
program’s
progress toward its overall reliability targets. The engine
contractor, Pratt
& Whitney, has identified a number of design changes that it
believes will
help improve engine reliability, but some of those changes have
not yet
been implemented. With complex and challenging
developmental testing
remaining and engine reliability challenges ahead, DOD still
plans to
increase procurement rates by nearly threefold over the next 5
years.
This same highly concurrent strategy has already proven to have
negatively impacted the program. According to program reports,
$1.7
billion could be incurred in costs associated with retrofits to
already
delivered aircraft. This cost will likely increase, as more
aircraft are
purchased and delivered before development ends.
A significant structural failure on the F-35B durability test
aircraft, an
engine failure, and a higher than expected amount of test point
growth
largely to address software rework, over the past year, delayed
key test
activities and forced unexpected adjustments to the program’s
development schedule and test plans. Each of these three factors
is
discussed in more detail below.
• At around 9,000 hours of durability testing—about half of the
16,000
hours required—a major airframe segment, known as a
bulkhead, on
the F-35B durability test aircraft severed, and one other
bulkhead was
Recent Technical
Challenges Will Likely
Result in Cost Growth
and Schedule Delays
Test Failures and Software
Challenges Forced
Program Changes
Page 9 GAO-15-364 F-35 Joint Strike Fighter
fractured as a result.7 Durability testing on the F-35B was
halted for
more than a year as program officials conducted a root cause
analysis
and Lockheed Martin worked to repair the durability test
aircraft. The
root cause analysis determined that the bulkhead severed
because its
design did not take into account appropriate factors in the
manufacturing processes, resulting in a bulkhead that had less
durability life than expected. According to officials, the fracture
in the
other bulkhead was caused by the added weight it had to bear
after
the first bulkhead severed. Lockheed Martin is currently
redesigning
the bulkheads to strengthen the aluminum and plans to
incorporate
the updated designs into the ninth low-rate initial production
lot. A total
of 50 aircraft will have to be modified using additional
structural
reinforcement techniques. According to program and contractor
officials, because the incident occurred halfway through
durability
testing, retrofits will not be required until the aircraft reach
about half
of their expected service life, or about 10 years. According to
officials,
the total costs of related modifications are yet to be determined
at this
time.
• In June 2014, an F-35A engine caught fire during take-off. As
a result,
the entire F-35 fleet was grounded for nearly one month and
then
placed under flight restrictions for several additional months. A
root
cause analysis conducted by Pratt & Whitney determined that
excessive heat caused by rubbing between engine fan
components
ultimately led to parts of the engine breaking free at a high rate
of
speed, resulting in a fire. The program could not execute any
planned
flight test points while the fleet was grounded. After flying
resumed
there were still hundreds of planned test points that could not be
executed because the fleet was restricted from flying at the
speeds
and conducting the maneuvers necessary to execute those
points.
Despite these obstacles, the program was able to keep its test
aircraft
productive and accomplished some test points that had been
planned
to be done in the future. Follow-up inspections conducted by the
contractor identified 22 engines with evidence of overheating.
Officials
have identified a short-term fix that they believe will allow the
fleet to
return to normal flight test operations. As of January 31, 2015,
18 of
22 engines had received the short-term fix and were cleared to
return
7The F-35B is the only aircraft affected as its bulkhead is made
of aluminum material. The
other F-35 variants have titanium bulkheads that are not as
vulnerable to these cracks.
Page 10 GAO-15-364 F-35 Joint Strike Fighter
to normal flight operations. Pratt & Whitney has identified
several
potential long-term fixes but no final determination has been
made.
• While the program’s test plan for 2014 reflected an allowance
of 45
percent growth in mission system software test points for the
year—
largely to address software rework that might be needed—
officials
from the Office of the Secretary of Defense noted that the
program
experienced around 90 percent growth, or nearly twice the
planned
amount. As of January 2015, 56 percent of the Block 2B
functionality
had been verified by program officials, which was about 10
percent
short of its goal. According to DOD and contractor officials, the
higher
than anticipated amount of rework was largely due to the fact
that
portions of the Block 2B software did not function as expected
during
flight testing. To address these deficiencies, changes were made
to
the software and this extended the Block 2B test schedule by
approximately 3 months. As of January 2015, all of the updated
software was in flight testing.
DOD continued to address other key technical risks that we
have
highlighted in the past including the Helmet Mounted Display,
Arresting
Hook System, and the Autonomic Logistics Information System
(ALIS).8 A
new helmet design was developed and integrated that includes
previously
developed updates and addresses shortfalls in night vision
capability.
Test pilots we spoke with noted that while testing of the new
helmet
design has just begun, some improvements over the previous
design are
evident, but more testing is needed. A redesigned Arresting
Hook System
was also integrated on the aircraft. While sea trial testing of the
redesigned system was slightly delayed, the testing took place
in
November 2014 and the system performed very well with a 100
percent
arrestment rate. Lastly, program officials began testing a more
capable
version of ALIS in September 2014 and expect to begin testing
a
deployable version in February 2015. Although DOD plans to
release the
deployable version in time for Marine Corps initial operational
capability, it
faces tight timeframes. A portion of the system’s capabilities,
Prognostics
Health Management downlink, has been deferred to follow-on
development.
8GAO-14-322
http://www.gao.gov/products/GAO-14-322�
Page 11 GAO-15-364 F-35 Joint Strike Fighter
In response to the challenges faced in 2014, program officials
reprioritized test resources and aircraft capabilities, deferred or
eliminated
test points, and ultimately delayed completion of some
developmental test
activities. Personnel and facilities that had been dedicated to
developing
and testing Block 3i and Block 3F—software blocks required by
the Air
Force and the Navy to field initial operational capabilities in
2016 and
2018 respectively—were reassigned to focus on delivering
Block 2B to
support the Marine Corps’ initial operational capability in 2015.
In
addition, program officials eliminated over 1,500 test points
from the
overall Block 2B developmental test plan, and deferred some
Block 2B
capabilities. According to program officials, they chose to delay
some test
points that had been scheduled to be accomplished in 2014, and
accomplish other test points that they had scheduled to be done
in the
future. In addition, program officials, in conjunction with
officials from the
Director, Operational Test and Evaluation, restructured a Block
2B early
operational test event that had been planned for 2015. The
restructured
event will now be conducted over time as resources allow but
will not be
completed as originally scheduled. While these changes allowed
the
program to accomplish nearly the same number of test points it
had
planned for the year, officials stated that not all of the specific
test
activities scheduled were completed. In the end, the completion
of Block
2B developmental testing is 3 months behind schedule, Block 3i
testing is
about 3 months behind schedule, and Block 3F could be as much
as 6
months behind schedule.
The program has a long way to go to achieve its engine
reliability goals.
Reliability is a function of how well a system design performs
over a
specified period of time without failure, degradation, or need of
repair.
During system acquisition, reliability growth should occur over
time
through a process of testing, analyzing, and fixing deficiencies
through
design changes or manufacturing process improvements. Once
fielded,
there are limited opportunities to improve a system’s reliability
without
additional cost increases and schedule delays. Currently, the F-
35
engine’s reliability is very poor and overall aircraft reliability
growth has
been limited. Improving engine reliability will likely require
additional
design changes and retrofits.
Need to Improve Engine
Reliability Presents
Additional Challenges
Page 12 GAO-15-364 F-35 Joint Strike Fighter
The program uses various measures to track and improve
reliability,
including the mean flying hours between failures (design
controlled).9
Data provided by Pratt & Whitney indicate that the mean flight
hours
between failure for the F-35A engine is about 21 percent of
where the
engine was expected to be at this point in the program. The F-
35B engine
is about 52 percent of where the engine was expected to be at
this point.
This means that the engine is failing at a much greater rate and
requiring
more maintenance than expected. Pratt & Whitney has identified
a
number of design changes that officials believe will improve the
engine’s
reliability and is in the process of incorporating some of those
changes
into the engine design, production, and retrofitted to already
built aircraft;
however, other design changes that Pratt & Whitney officials
believe are
needed, such as changes to engine hoses and sensors, are not
currently
funded. Figure 3 shows the trend in the engine’s mean flight
hours
between failures (design controlled).
Figure 3: Measured Mean Flight Hours between Failure-(design
controlled) for the F-35 Joint Strike Fighter Engine Only
9This specific metric tracks failures that are directly attributed
to design and are
considered fixable with design changes.
Page 13 GAO-15-364 F-35 Joint Strike Fighter
Poor engine reliability has limited the F-35’s overall reliability
progress.
The overall reliability of the aircraft, which includes engine
reliability data,
has been improving over the past year. Contractor officials
attribute the
improvements in reliability to having an increasing number of
aircraft in
flight operations that have received design changes to address
previously
identified problems. For example, design changes in the way
certain
metal plates—known as nut plates—are bonded to the aircraft,
and
changes to fix problems with contamination of the On-board
Oxygen
Generating System have been incorporated into 62 aircraft that
were
delivered and began flying throughout 2013 and 2014. While
overall
reliability has increased, engine reliability over the last year has
remained
well below expected levels. Improving the F-35 engine
reliability to
achieve established goals will likely require more time and
resources than
originally planned.
In addition, in September 2014, we reported problems with the
F-35
software reliability and maintainability. Specifically, we
reported that the
program continues to experience both hardware and software
reliability
issues, but DOD had no processes or metrics that provide
sufficient
insight into the impact of software reliability and
maintainability
contributing to the overall aircraft reliability. We recommended
that DOD
develop a software reliability and maintainability assessment
process with
metrics, and DOD concurred with this recommendation.10
While DOD has taken steps over the past few years to reduce
concurrency, the program’s strategy still contains a noteworthy
overlap
between the completion of flight testing and the increase in
aircraft
procurement rates. With about 2 years and 40 percent of the
developmental test program remaining and significant engine
reliability
growth needed, DOD plans to continue increasing procurement
rates.
Over the next 5 years, procurement will increase from 38
aircraft per year
to 90 aircraft per year, and by the time developmental testing is
finished—
currently expected to occur in 2017—DOD expects to have
purchased a
cumulative total of 340 aircraft. During this time, there are
plans to
conduct testing to prove that the F-35 can provide full
warfighting
capabilities—Block 3F—needed to perform in more demanding
and
10GAO- F-35 Sustainment: Need for Affordable Strategy,
Greater Attention to Risks, and
Improved Cost Estimates, GAO-14-778 (Washington, D.C.:
September 23, 2014).
Unexpected Technical
Issues and Ongoing
Reliability Challenges
Amplify Concurrency Risk
http://www.gao.gov/products/GAO-%20F-35�
http://www.gao.gov/products/GAO-14-778�
Page 14 GAO-15-364 F-35 Joint Strike Fighter
stressing environments. In addition, DOD plans to complete
operational
testing in early 2019 and at that time will have procured 518
aircraft or 21
percent of its total planned procurement quantities. At the same
time,
efforts will be ongoing to improve F-35 engine reliability.
As of June 2014, DOD estimated that at that point about $1.7
billion in
funding was needed to rework and retrofit aircraft with design
changes
needed as a result of test discoveries. This concurrency cost
estimate
does not include any costs related to the most recent failures.
According
to DOD officials, the estimate takes into account some
unexpected costs
and they believe that the estimate will not exceed $1.7 billion.
However,
with more complex and demanding testing ahead and engine
reliability
improvements needed, it is almost certain that the program will
encounter
more discoveries. Depending on the nature and significance of
the
discoveries, the program may need additional time and money,
beyond
the current $1.7 billion estimate, to incorporate design changes
and
retrofit aircraft at the same time that it increases procurement.
As of December 2014, the program office estimated that the
total
acquisition cost of the F-35 will be $391.1 billion, or $7.4
billion less than
DOD reported in December 2013. Our analysis indicates that the
program
will require an average of $12.4 billion per year, which
represents around
one-quarter of DOD’s annual funding for major defense
acquisition
programs over the next 5 years. From fiscal years 2015 to 2019,
DOD
plans to increase annual development and procurement funding
for the F-
35 from around $8 billion to around $12 billion, an investment
of more
than $54 billion over that 5-year period, while competing with
other large
programs for limited acquisition resources. This funding
reflects the U. S.
military services’ plans to significantly increase annual aircraft
procurement buys from 38 in 2015 to 90 in 2019. International
partners
will also increase procurement buys during this time, and the
combined
purchases will peak at 179 aircraft in 2021, with the United
States
purchasing 100 aircraft and the international partners
purchasing an
additional 79 aircraft. DOD projects that the program’s
acquisition funding
needs will increase to around $14 billion in 2022. Funding
needs will
remain between $14 and $15 billion for nearly a decade and
peak at
$15.1 billion in 2029 (see figure 4). Given resource limitations
and the
funding needs of other major acquisition programs such as the
KC-46A
tanker, the DDG-51 Class Destroyer, the Ohio Class submarine
replacement, and a long-range strike bomber, in addition to the
high
estimated costs of sustaining the fleet over the next several
years, we
Affordability
Challenges Will Likely
Continue to Affect
Program Plans to
Increase F-35
Procurement
Page 15 GAO-15-364 F-35 Joint Strike Fighter
believe funding of this magnitude will pose significant
affordability
challenges.
Figure 4: Budgeted Development and Procurement Costs by
Service, 2015-2038
Note: Annual projected cost estimates expressed in then-year
dollars reflect inflation assumptions
made by a program.
Since the 2012 re-baselining, DOD has made changes to its F-35
procurement plans on an annual basis. In 2013, DOD reduced
the
number of aircraft that it planned to purchase between 2015 and
2019 by
37 aircraft and extended the procurement timeline by one year.
In 2014,
DOD deferred the purchase of 4 more aircraft over that same
timeframe.
DOD officials attribute this decision to affordability concerns
due to
budget constraints, among other factors. Although this action
may reduce
near-term funding requirements as well as concurrency risks, it
will likely
increase the average unit cost of the aircraft purchased over that
time and
may increase funding liability in the future. DOD policy
requires
Page 16 GAO-15-364 F-35 Joint Strike Fighter
affordability analyses to inform long-term investment
decisions.11 The
consistent changes in F-35 procurement plans, made during the
annual
DOD budget process, indicate that the analysis done to support
the
program’s 2012 baseline did not accurately account for future
technical
risks or funding realities. Changes in procurement plans are also
impacted by adjustments to military service and DOD priorities.
Program office data indicates that after accounting for quantity
changes,
the program is unlikely to achieve the affordability unit cost
targets set by
the Under Secretary of Defense for Acquisition, Technology,
and
Logistics in 2012.12 The aircraft deferrals will also reduce the
number of F-
35s fielded over the next several years, which could force the
military
services to invest in extending the life of their current aircraft
fighter fleets,
including the Air Force A-10 Thunderbolt II and the Navy F/A-
18 Hornet.
We believe maintaining the level of sustained funding required
to build an
F-35 fleet in addition to incurring costs to extend the life of
current aircraft
will be difficult in a period of austere defense budgets.
Officials from the Office of Secretary of Defense have stated
that the
current sustainment strategy is not affordable. Both the program
office
and the Cost Assessment and Program Evaluation (CAPE)
office, within
the Office of the Secretary of Defense, estimate sustainment
costs will be
about $1 trillion over the life of the F-35 fleet. Since 2012,
CAPE’s
sustainment cost estimate has decreased by nearly $100 billion.
CAPE
attributes the bulk of this decrease to updated cost estimating
ground
rules and assumptions related to the cost of spare parts, labor
rates, and
fuel efficiency. The program office has also issued a separate
sustainment cost estimate of approximately $859 billion, which
is $57.8
billion less than it estimated last year. The CAPE and program
estimates
differ primarily in assumptions about reliability, depot
maintenance,
personnel, and fuel consumption. However, as we reported in
September
2014, the current estimates are still higher than the current
operation and
support costs of the existing aircraft the F-35 is expected to
replace, and
11Department of Defense Instruction 5000.02, Operation of the
Defense Acquisition
System Encl. 8, para. 2 (Jan. 7, 2015).
12These targets are based upon planning assumptions reflected
in the FY 2013
President’s Budget and the 2011 projection for international
partner procurement. If there
are subsequent changes to either the United States or
international partner procurement
quantities, the program will isolate the effect that this has on
the targets as a factor that is
not within its control.
Page 17 GAO-15-364 F-35 Joint Strike Fighter
according to officials from the Office of Secretary of Defense,
remain
unaffordable. In addition, we reported that DOD’s sustainment
cost
estimates may not reflect the most likely costs that the F-35
program will
incur.13
While the F-35 program office and contractors have initiatives
underway
to improve affordability, those initiatives have a specific focus
on reducing
procurement and sustainment costs but do not assess the
affordability of
the program’s overall procurement plan within budget
constraints. These
initiatives include the “War on Cost,” “Cost War Room,” and
“Blueprint for
Affordability” that are intended to identify ways to reduce
procurement
and sustainment costs of the aircraft and engine. The initiatives
are still
ongoing and the total cost savings related to these initiatives is
yet to be
determined.
As Lockheed Martin continues to deliver more aircraft, the
number of
hours needed to build each aircraft has declined and efficiency
rates have
improved despite increases in the time spent on scrap, rework,
and
repairs. Supplier performance has been mixed as late deliveries
have
resulted in increases to part shortages. Supplier quality defects
have also
increased while scrap, rework, and repair attributable to
suppliers have
remained steady. Pratt & Whitney is experiencing problems
with quality
and late deliveries from its suppliers.
The number of aircraft produced in the Lockheed Martin’s final
assembly
facility has remained relatively stable over the last 3 years. The
contractor
has delivered a total of 110 aircraft since 2011—9 in 2011, 30
in 2012, 35
in 2013, and 36 in 2014. None of the aircraft delivered currently
possess
initial warfighting capability and are being used primarily for
training
purposes. As a result, delivered aircraft will have to be
retrofitted with 2B
initial warfighting capabilities prior to becoming operational.
Although
aircraft continued to be delivered later than contracted delivery
dates—
averaging 3.6 months late in 2014—Lockheed Martin officials
believe they
are closing the gap and expect to begin delivering to contract
dates in
2015. Figure 5 shows actual aircraft deliveries compared to
contracted
13For a full discussion of GAO’s previous analysis of the F-35
estimated sustainment costs
and our recommendations, please see GAO- 14-778.
While Manufacturing
Progress Remains
Steady, Planned
Production Increases
Could Be a Challenge
Manufacturing Efficiency
Remains Steady
Page 18 GAO-15-364 F-35 Joint Strike Fighter
delivery dates over the last 2 years. In 2014, Lockheed Martin
achieved
its goal of delivering 36 aircraft despite multiple setbacks
throughout the
year, such as late software deliveries, a fleet grounding, and
increased
engine inspections.
Figure 5: Trend of F-35 Joint Strike Fighter Contractual
Delivery Dates Compared to Actual Delivery Dates
Note: This figure includes deliveries to the United States and all
foreign partners.
As Lockheed Martin produces more aircraft and learns more
about its
manufacturing processes, it continues to reduce the number of
labor
hours needed to manufacture aircraft. The reduction in labor
hours
remained relatively steady over the last year; however, in the
case of the
F-35B, labor hours briefly trended upward. Officials stated that
a gap in
production of the F-35B variant between lots four and six and
part
shortages drove the increased labor hours. The number of labor
hours to
produce the last F-35B delivered in 2014 was lower than
previous aircraft,
and officials believe labor hours will continue to decrease as
production
quantities for the F-35B increase. Figure 6 identifies the trend
in reduction
of labor hours per aircraft since the beginning of low-rate initial
production.
Page 19 GAO-15-364 F-35 Joint Strike Fighter
Figure 6: Trend in Labor Hours to Build the F-35 Joint Strike
Fighter Aircraft by Variant
Note: Labor hour data only represents aircraft built start to
finish at Lockheed Martin’s facility. Data
includes aircraft delivered to foreign partners.
The number of major engineering design changes has also
continued to
decline over time, and is currently tracking to the program’s
plan. The
reduction in labor hours and engineering design changes over
time has
allowed Lockheed Martin to increase manufacturing efficiency
rates as
measured by the hours it takes to complete certain production
tasks
compared to the number of hours established by engineering
standards.
The efficiency rate increased from about 16 to about 20 percent
over the
last year, nearly achieving Lockheed Martin’s goal of about 22
percent.
Labor hours and efficiency rates improved despite increases in
time spent
on scrap, rework, and repair over the last year. The time spent
on scrap,
rework, and repair increased from 13.8 percent in production lot
four to
14.9 percent in production lot five, falling short of Lockheed
Martin’s goal
of 12.8 percent. At 14.9 percent, Lockheed Martin’s scrap,
rework, and
repair rates are nearly equal to percentages experienced in the
third
production lot. According to Lockheed Martin officials, a
majority of the
scrap, rework, and repair hours are associated with fixing
mislocated
brackets and mismatched seams. Figure 7 shows the trend in
percent of
labor hours spent on scrap, rework, and repair along with the
goal for the
Page 20 GAO-15-364 F-35 Joint Strike Fighter
fifth production lot. If these trends continue, Lockheed Martin
could have
difficulty improving its manufacturing efficiency at its expected
rates.
Figure 7: Trend in Percent of Labor Hours Spent on Scrap,
Rework, and Repair for
the F-35 Joint Strike Fighter
Lockheed Martin reports that less than 40 percent of its critical
manufacturing processes are considered in statistical control
which
means that for those processes it can consistently produce parts
within
quality tolerances and standards. Statistical control is a measure
of
manufacturing maturity. The best practice standard is to have
100 percent
of the critical manufacturing processes in control by the start of
low-rate
initial production, which began in 2011 for the F-35 program.
According to
Lockheed Martin officials, only 54 percent of its F-35 critical
manufacturing processes will provide enough data to measure
statistical
control. As a result, they do not expect to achieve 100 percent.
Page 21 GAO-15-364 F-35 Joint Strike Fighter
Suppliers continue to deliver late parts to Lockheed Martin
resulting in
part shortages. Since 2013, the average number of part shortage
occurrences at Lockheed Martin’s facility has increased. The
severity of
part shortages is measured in five categories, category 1 being
the least
severe, and category 4 and above being the most severe with
those
shortages requiring a major workaround or work stoppage.14
Figure 8
identifies changes in the average number of part shortage
occurrences at
Lockheed Martin’s facility over the last year.
Figure 8: Average Number of F-35 Joint Strike Fighter Part
Shortage Occurrences at
Prime Contractor Facility
According to Lockheed Martin officials, suppliers are
delivering late parts
for several reasons. Those reasons include the need for
suppliers to fix
faulty parts and the inability of some suppliers to handle large
amounts of
throughput. In addition, Lockheed Martin officials stated that
some delays
are a result of late request for proposals, late responses to those
proposals, and delayed contract negotiations with the
government that
result in late contract awards. Officials do not expect to begin
making
authorizations with appropriate lead time until the end of low-
rate initial
production in 2019. Part shortages will likely remain
problematic and
could be amplified as production rates increase over the next 5
years.
Supplier quality at Lockheed Martin has been mixed. Lockheed
Martin
uses a reactive approach to managing most of its supplier base
because,
14The severity of part shortages is measured in categories by
Lockheed Martin. Category
1: the part is late to on-dock requirement date. Category 2: the
part is late to the material
kit start date of the kit build. Category 3: the part is late to the
date when production needs
the kit on the manufacturing floor. Category 4: the part is late
to the extent that it has
become sequence critical, meaning other work may be limited
while waiting for the part. A
major workaround is required or production may not proceed to
the next work station.
Category 4 and above: the part is late to the extent that work on
the production floor is
stopped and there is no workaround.
Late Deliveries from
Suppliers Continue, and
Could Challenge Planned
Production Increases
Page 22 GAO-15-364 F-35 Joint Strike Fighter
according to officials, they do not have access to supplier
specific
manufacturing data. The company uses internal metrics to track
supplier
performance such as the number of quality defects—known as
non-
conformances—discovered at the Lockheed Martin facility and
the
amount of scrap, rework, and repair driven by poor supplier
performance.
Over the last year, the number of supplier related non-
conformances has
slightly increased and Lockheed Martin continues to experience
supplier
related non-conformances for things like hole-drilling and
bracket
placement, among others. Lockheed Martin officials identified
22 of their
more than 1,500 suppliers that contributed to 75 percent of the
non-
conformances. In order to address these non-conformances,
Lockheed
Martin developed a management team aimed at improving
quality
management at those suppliers. Lockheed Martin reported a 58
percent
improvement in non-conformances for those suppliers over the
last year,
which it attributes to the work of its team. For example, the key
supplier of
the aircraft weapons bay door experienced quality problems in
2013.
Over the last year, Lockheed Martin sent more personnel to the
supplier’s
facility to work with the supplier’s management team to identify
problems
in their production processes and solutions to those problems.
As a
result, the supplier adjusted its tooling and modified its quality
management techniques, and the number of defects and part
shortages
from that supplier decreased. In addition, the percent of time
spent on
scrap, rework, and repair for supplied parts has remained
steady.
Supplier deliveries requiring scrap, rework, and repair averaged
1.3
percent of the hours spent building an aircraft over the last 2
years.
Pratt & Whitney is also experiencing challenges with part
shortages and
supplier quality. Nearly 45 percent of Pratt & Whitney’s key
suppliers
have delivered late parts over the past year. In order to mitigate
some of
the risk, Pratt & Whitney has pulled or borrowed some parts
meant for
spare engines to use in place of the late parts. According to
Pratt &
Whitney officials, they have taken steps to reduce the number of
parts
that are borrowed; however, the number of borrowed parts
remains high,
which could lead to further part shortages and late engine
deliveries if
production rates increase over the next several years as planned.
In
addition, in 2014, poor supplier quality negatively impacted
engine
performance. For example, improper lubrication of an oil valve
adapter by
the valve supplier resulted in an in-flight emergency in June
2014. As a
result, the oil valves on 136 F-35 aircraft—28 of which were in
production
and 108 of which were delivered—had to be removed and
replaced.
According to Pratt & Whitney officials, the associated retrofit
costs were
borne by the valve supplier. The supplier also made changes to
its
procedures to prevent future incidents.
Page 23 GAO-15-364 F-35 Joint Strike Fighter
The F-35 remains DOD’s most costly and ambitious programs
and one of
its highest priority acquisition programs. The program began
with an
acquisition strategy that called for high levels of concurrency
between
developmental testing and aircraft procurement. Since then,
however, the
program has experienced significant technical problems that
have
resulted in schedule delays and additional unplanned, or latent,
concurrency. With more than 100 production aircraft delivered
as of
December 2014, the program continues to encounter significant
technical
problems like the engine and bulkhead failures that require
design
changes. Programs in developmental testing are expected to
encounter
technical problems that require design changes. However, in a
concurrent
acquisition environment, the destabilizing effects of design
changes are
amplified as more systems are produced and delivered, thus
requiring
costly retrofits, and rework. With around 40 percent of
developmental
testing remaining, additional unanticipated changes are likely as
much of
that testing will be very challenging. At the same time, DOD
plans to
steeply increase its procurement funding requests over the next
5 years
and projects that it will need between $14 and $15 billion
annually for
nearly a decade. It is unlikely that the program will be able to
receive and
sustain such a high and unprecedented level of funding over this
extended period, especially with other significant fiscal
demands weighing
on the nation. This poses significant affordability challenges to
DOD as
other costly, high priority acquisition efforts, including the KC-
46A Tanker
and the DDG 51 Class Destroyer, compete for limited resources
at the
same time. DOD continues to adjust its F-35 procurement plans
on an
annual basis. This reactionary approach indicates that DOD may
not be
accurately accounting for the future technical and funding
uncertainty it
faces, and thus may not fully understand the affordability
implications of
increasing F-35 procurement funding at the planned rates.
As DOD plans to significantly increase F-35 procurement
funding over the
next 5 years, we recommend that the Secretary of Defense
conduct an
affordability analysis of the program’s current procurement plan
that
reflects various assumptions about future technical progress and
funding
availability.
We provided a draft of this report to DOD for comment. In its
written
comments, which are reprinted in appendix III, DOD concurred
with our
recommendation. DOD also provided technical comments which
we
incorporated as appropriate.
Conclusions
Recommendations
Agency Comments
and Our Evaluation
Page 24 GAO-15-364 F-35 Joint Strike Fighter
We are sending copies of this report to appropriate
congressional
committees; the Secretary of Defense; the Secretaries of the Air
Force,
Army, and Navy; the Commandant of the Marine Corps; and the
Director
of the Office of Management and Budget. The report is
available at no
charge on the GAO website at http://www.gao.gov.
If you or your staff have any questions about this report, please
contact
me at (202) 512-4841 or [email protected] Contact points for
our
Offices of Congressional Relations and Public Affairs may be
found on
the last page of this report. Staff members making key
contributions to
this report are listed in Appendix IV.
Michael J. Sullivan
Director
Acquisition and Sourcing Management
http://www.gao.gov/�
mailto:[email protected]�
Page 25 GAO-15-364 F-35 Joint Strike Fighter
List of Committees
The Honorable John McCain
Chairman
The Honorable Jack Reed
Ranking Member
Committee on Armed Services
United States Senate
The Honorable Thad Cochran
Chairman
The Honorable Richard J. Durbin
Ranking Member
Subcommittee on Defense
Committee on Appropriations
United States Senate
The Honorable Mac Thornberry
Chairman
The Honorable Adam Smith
Ranking Member
Committee on Armed Services
House of Representatives
The Honorable Rodney Frelinghuysen
Chairman
The Honorable Pete Visclosky
Ranking Member
Subcommittee on Defense
Committee on Appropriations
House of Representatives
Appendix I: Prior GAO Reports on F-35 Joint
Strike Fighter (JSF) and Department of
Defense (DOD) Responses and Subsequent
Actions
Page 26 GAO-15-364 F-35 Joint Strike Fighter
GAO report
Estimated
Development
Costs
Development
Length
Aircraft unit cost Key program event
Primary GAO
Conclusion/Recommendation DOD response and actions
2001
GAO-02-39
$34.4 Billion
10 years
$69 Million
Start of system
development and
demonstration approved.
Critical technologies needed for
key aircraft performance elements
are not mature. Program should
delay start of system development
until critical technologies are
mature to acceptable levels.
DOD did not delay start of
system development and
demonstration, stating
technologies were at
acceptable maturity levels
and stated it would manage
risks in development.
2005
GAO-05-271
$44.8 Billion
12 years
$82 Million
The program underwent a
re-plan to address higher
than expected design
weight, which added $7
billion and 18 months to
development schedule.
We recommended that the DOD
reduce risks and establish an
executable business case that is
knowledge-based with an
evolutionary acquisition strategy.
DOD partially concurred but
did not adjust strategy,
believing that its approach
was balanced between cost,
schedule, and technical risk.
2006
GAO-06-356
$45.7 Billion
12 years
$86 Million
Program set in motion a
plan to enter production in
2007 shortly after first
flight of the non-
production representative
aircraft.
The program was entering
production with less than 1
percent of testing complete. We
recommended that
DOD delay investing in production
until flight testing shows that JSF
performs as expected.
DOD partially concurred but
did not delay start of
production because it
believed the risk level was
appropriate.
2007
GAO-07-360
$44.5 Billion
12 years
$104 Million
Congress reduced
funding for first two low-
rate production buys
thereby slowing the ramp
up of production.
Progress was being made but
concerns remained about undue
overlap in testing and production.
We recommended limits to annual
production quantities to 24 a year
until flying quantities were
demonstrated.
DOD non-concurred and felt
that the program had an
acceptable level of
concurrency and an
appropriate acquisition
strategy.
2008
GAO-08-388
$44.2 Billion
12 years
$104 Million
DOD implemented a Mid-
Course Risk Reduction
Plan to replenish
management reserves
from about $400 million to
about $1 billion by
reducing test resources.
We found the new plan increased
risks and recommended that DOD
should revise the plan to address
concerns about testing,
management reserves, and
manufacturing. We determined
that the cost estimate was not
reliable and that a new cost
estimate and schedule risk
assessment was needed.
DOD did not revise risk plan
or restore testing resources,
stating that it will monitor the
new plan and adjust it if
necessary. Consistent with
one of our
recommendations, a new
cost estimate was prepared,
but DOD did not conduct a
risk and uncertainty analysis.
GAO report Estimated
Development Costs
Development
Length
Aircraft unit cost
Key program event Primary GAO
Conclusion/Recommendation
DOD response and actions
Appendix I: Prior GAO Reports on F-35 Joint
Strike Fighter (JSF) and Department of
Defense (DOD) Responses and Subsequent
Actions
http://www.gao.gov/products/GAO-02-39�
http://www.gao.gov/products/GAO-05-271�
http://www.gao.gov/products/GAO-06-356�
http://www.gao.gov/products/GAO-07-360�
http://www.gao.gov/products/GAO-08-388�
Appendix I: Prior GAO Reports on F-35 Joint
Strike Fighter (JSF) and Department of
Defense (DOD) Responses and Subsequent
Actions
Page 27 GAO-15-364 F-35 Joint Strike Fighter
GAO report
Estimated
Development
Costs
Development
Length
Aircraft unit cost Key program event
Primary GAO
Conclusion/Recommendation DOD response and actions
2009
GAO-09-303
$44.4 Billion
13 years
$104 Million
The program increased
the cost estimate and
added a year to
development but
accelerated the
production ramp up.
Independent DOD cost
estimate (JET I) projects
even higher costs and
further delays.
Moving forward with an
accelerated procurement plan and
use of cost reimbursement
contracts is very risky. We
recommended the program report
on the risks and mitigation
strategy for this approach.
DOD agreed to report its
contracting strategy and
plans to Congress and
conduct a schedule risk
analysis. The program
reported completing the first
schedule risk assessment
with plans to update semi-
annually. The Department
announced a major program
restructure, reducing
procurement and moving to
fixed-price contracts.
2010
GAO-10-382
$49.3 Billion
15 years
$112 Million
The program was
restructured to reflect
findings of recent
independent cost team
(JET II) and independent
manufacturing review
team. As a result,
development funds
increased, test aircraft
were added, the schedule
was extended, and the
early production rate
decreased.
Costs and schedule delays
inhibited the program’s ability to
meet needs on time. We
recommended the program
complete a full comprehensive
cost estimate and assess
warfighter and initial operating
capability requirements. We
suggested that Congress require
DOD to tie annual procurement
requests to demonstrated
progress.
DOD continued
restructuring, increasing test
resources and lowering the
production rate. Independent
review teams evaluated
aircraft and engine
manufacturing processes.
Cost increases later resulted
in a Nunn-McCurdy breach.
Military services are
currently reviewing capability
requirements as we
recommended.
2011
GAO-11-325
$51.8 Billion
16 years
$133 Million
Restructuring continued
with additional
development cost
increases; schedule
growth; further reduction
in near-term procurement
quantities; and decreased
the rate for future
production. The Secretary
of Defense placed the
Short-takeoff Vertical
Landing (STOVL) variant
on a two-year probation;
decoupled STOVL from
the other variants; and
reduced STOVL
production plans for fiscal
years 2011 to 2013.
The restructuring actions were
positive and if implemented
properly should lead to more
achievable and predictable
outcomes. Concurrency of
development, test, and production
was substantial and provided risk
to the program. We recommended
the DOD maintain funding levels
as budgeted; establish criteria for
STOVL probation; and conduct an
independent review of software
development, integration, and test
processes.
DOD concurred with all three
of the recommendations.
DOD lifted STOVL probation
citing improved performance.
Subsequently, DOD further
reduced procurement
quantities, decreasing
funding requirements
through 2016. The initial
independent software
assessment began and
ongoing reviews were
planned to continue through
2012.
http://www.gao.gov/products/GAO-09-303�
http://www.gao.gov/products/GAO-10-382�
http://www.gao.gov/products/GAO-11-325�
Appendix I: Prior GAO Reports on F-35 Joint
Strike Fighter (JSF) and Department of
Defense (DOD) Responses and Subsequent
Actions
Page 28 GAO-15-364 F-35 Joint Strike Fighter
GAO report
Estimated
Development
Costs
Development
Length
Aircraft unit cost Key program event
Primary GAO
Conclusion/Recommendation DOD response and actions
2012
GAO-12-437
$55.2 Billion
18 years
$137 Million
The program established
a new acquisition program
baseline and approved
the continuation of system
development, increasing
costs for development
and procurements and
extending the period of
planned procurements by
2 years.
Extensive restructuring placed the
program on a more achievable
course. Most of the program’s
instability continued to be
concurrency of development, test,
and production. We recommended
the Cost Assessment Program
Evaluation office conduct an
analysis on the impact of lower
annual funding levels; and the
program office conduct an
assessment of the supply chain
and transportation network.
DOD partially concurred with
conducting an analysis on
the impact of lower annual
funding levels and concurred
with assessing the supply
chain and transportation
network.
2013
GAO-13-309
$55.2 Billion
18 years
$137 Million
The program continued to
move forward following a
new acquisition program
baseline in 2012. In doing
so, the program
incorporated positive and
more realistic
restructuring actions
taken since 2010
including more time and
funding for development
and deferred procurement
of more than 400 aircraft
to future years.
The program was moving in the
right direction but must fully
validate design and operational
performance and at the same time
make the system affordable. We
did not make recommendations to
DOD in this report.
DOD agreed with GAO’s
observations.
2014
GAO-14-322
$55.2 Billion
18 years
$135 Million
The services established
initial operational
capabilities dates in 2013.
The Marine Corps and Air
Force are planning to field
initial operational
capabilities in 2015 and
2016, respectively, and
the Navy plans to field its
initial capability in 2018.
Delays in developmental flight
testing of the F-35’s critical
software may hinder delivery of
the warfighting capabilities the
military services. We
recommended DOD conduct an
assessment of the specific
capabilities that can be delivered
and those that will not likely be
delivered to each of the services
by their established initial
operational capability dates
DOD concurred with our
recommendation and is in
the process of conducting
the assessment.
http://www.gao.gov/products/GAO-12-437�
http://www.gao.gov/products/GAO-13-309�
http://www.gao.gov/products/GAO-14-322�
Appendix I: Prior GAO Reports on F-35 Joint
Strike Fighter (JSF) and Department of
Defense (DOD) Responses and Subsequent
Actions
Page 29 GAO-15-364 F-35 Joint Strike Fighter
GAO report
Estimated
Development
Costs
Development
Length
Aircraft unit cost Key program event
Primary GAO
Conclusion/Recommendation DOD response and actions
2014
GAO-14-778
Not reported The Department of
Defense (DOD) currently
has or is developing
several plans and
analyses that will make up
its overall F-35
sustainment strategy,
which is expected to be
complete in fiscal year
2019.
The annual F-35 operating and
support costs are estimated to be
considerably higher than the
combined annual costs of several
legacy aircraft. DOD had not fully
addressed several issues that
have an effect on affordability and
operational readiness. Operating
and support cost estimates may
not be reliable. We recommended
that DOD develop better informed
affordability constraints; address
three risks that could affect
sustainment, affordability, and
operational readiness; and take
steps to improve the reliability of
its cost estimates.
DOD concurred with all but
one recommendation and
partially concurred with the
recommendation to conduct
uncertainty analysis on one
of its cost estimates, stating
it already conducts a form of
uncertainty analysis. GAO
continues to believe that the
recommended analysis
would provide a more
comprehensive sense of the
uncertainty in the estimates.
Source: GAO
http://www.gao.gov/products/GAO-14-778�
Appendix II: Scope and Methodology
Page 30 GAO-15-364 F-35 Joint Strike Fighter
To assess the program’s ongoing development and testing we
reviewed
the status of software development and integration and
contractor
management improvement initiatives. We also interviewed
officials from
the program office, Lockheed Martin, Pratt & Whitney, and the
Defense
Contract Management Agency (DCMA) to discuss current
development
status and software releases. In addition, we compared
management
objectives to progress made on these objectives during the year.
We
obtained and analyzed data on flights and test points, both
planned and
accomplished during 2014. We compared test progress against
the total
program plans to complete. In addition, we interviewed officials
from the
F-35 program office, Lockheed Martin, Pratt & Whitney, and
Director,
Operational Test and Evaluation office to discuss development
test plans
and achievements. We also collected information from the
program office,
prime contractor, engine contractor, and Department of Defense
test
pilots regarding the program’s technical risks including the
helmet
mounted display, autonomic logistics information system,
carrier arresting
hook, structural durability, and engine. We analyzed reliability
data and
discussed these issues with program and contractor officials.
To assess the program’s cost and affordability, we reviewed
financial
management reports and monthly status reports available as of
December 2014. In addition, we reviewed total program funding
requirements from the December 2014 Selected Acquisition
Report. We
used these data to project annual funding requirements through
the
expected end of the F-35 acquisition in 2038. We also compared
the
December 2014 Selected Acquisition Report data to prior
Selected
Acquisition Reports to identify changes in cost and quantity.
We obtained
life-cycle operating and support cost through the program’s
Selected
Acquisition Report and projections made by the Cost Analysis
and
Program Evaluation (CAPE) office. We discussed future plans
of the
Department of Defense (DOD) and contractors to try and reduce
life-cycle
sustainment costs with officials from the program office,
Lockheed Martin,
and Pratt & Whitney.
To assess manufacturing and supply chain performance we
obtained and
analyzed data related to aircraft delivery rates and work
performance data
through the end of calendar year 2014. This data was compared
to
program objectives identified in these areas and used to identify
trends.
We reviewed data and briefings provided by the program office,
Lockheed
Martin, Pratt & Whitney, and DCMA in order to identify issues
in
manufacturing processes. We discussed reasons for delivery
delays and
plans for improvement with Lockheed Martin and Pratt &
Whitney. We
also toured Pratt and Whitney’s manufacturing facility in
Middletown,
Appendix II: Scope and Methodology
Appendix II: Scope and Methodology
Page 31 GAO-15-364 F-35 Joint Strike Fighter
Connecticut and collected and analyzed data related to aircraft
quality
through December 2014. We collected and analyzed supply
chain
performance data and discussed plans taken to improve quality
and
deliveries with Lockheed Martin and Pratt & Whitney.
We assessed the reliability of DOD and contractor data by
reviewing
existing information about the data, and interviewing agency
officials
knowledgeable about the data. We determined that the data were
sufficiently reliable for the purposes of this report. We
conducted this
performance audit from July 2014 to April 2015 in accordance
with
generally accepted government auditing standards. Those
standards
require that we plan and perform the audit to obtain sufficient,
appropriate
evidence to provide a reasonable basis for our findings and
conclusions
based on our audit objectives. We believe that the evidence
obtained
provides a reasonable basis for our findings and conclusions
based on
our audit objectives.
Appendix III: DOD Comments
Page 32 GAO-15-364 F-35 Joint Strike Fighter
Appendix III: DOD Comments
Appendix III: DOD Comments
Page 33 GAO-15-364 F-35 Joint Strike Fighter
Appendix IV: GAO Contact and Staff
Acknowledgments
Page 34 GAO-15-364 F-35 Joint Strike Fighter
Michael Sullivan (202) 512-4841 [email protected]
In addition the contact name above, the following staff members
made
key contributions to this report: Travis Masters, Assistant
Director; Peter
Anderson; James Bennett; Marvin Bonner; Kristine Hassinger;
Megan
Porter; Marie Suding; and Abby Volk.
Appendix IV: GAO Contact and Staff
Acknowledgments
GAO Contact
Acknowledgments
Related GAO Products
Page 35 GAO-15-364 F-35 Joint Strike Fighter
F-35 Sustainment: Need for Affordable Strategy, Greater
Attention to
Risks, and Improved Cost Estimates. GAO-14-778. Washington,
D.C.:
September 23, 2014.
F-35 Joint Strike Fighter: Slower Than Expected Progress in
Software
Testing May Limit Initial Warfighting Capabilities. GAO-14-
468T
Washington, D.C.: March 26 2014.
F-35 Joint Strike Fighter: Problems Completing Software
Testing May
Hinder Delivery of Expected Warfighting Capabilities. GAO-
14-322.
Washington, D.C.: March 24, 2014.
F-35 Joint Strike Fighter: Restructuring Has Improved the
Program, but
Affordability Challenges and Other Risks Remain. GAO-13-
690T.
Washington, D.C.: June 19, 2013.
F-35 Joint Strike Fighter: Program Has Improved in Some
Areas, but
Affordability Challenges and Other Risks Remain. GAO-13-
500T.
Washington, D.C.: April 17, 2013.
F-35 Joint Strike Fighter: Current Outlook Is Improved, but
Long-Term
Affordability Is a Major Concern. GAO-13-309. Washington,
D.C.: March
11, 2013.
Fighter Aircraft: Better Cost Estimates Needed for Extending
the Service
Life of Selected F-16s and F/A-18s. GAO-13-51. Washington,
D.C.:
November 15, 2012
Joint Strike Fighter: DOD Actions Needed to Further Enhance
Restructuring and Address Affordability Risks. GAO-12-437.
Washington,
D.C.: June 14, 2012.
Defense Acquisitions: Assessments of Selected Weapon
Programs.
GAO-12-400SP. Washington, D.C.: March 29, 2012.
Joint Strike Fighter: Restructuring Added Resources and
Reduced Risk,
but Concurrency Is Still a Major Concern. GAO-12-525T.
Washington,
D.C.: March 20, 2012.
Joint Strike Fighter: Implications of Program Restructuring and
Other
Recent Developments on Key Aspects of DOD’s Prior Alternate
Engine
Analyses. GAO-11-903R. Washington, D.C.: September 14,
2011.
Related GAO Products
http://www.gao.gov/products/GAO-14-778�
http://www.gao.gov/products/GAO-14-468T�
http://www.gao.gov/products/GAO-14-322�
http://www.gao.gov/products/GAO-13-690T�
http://www.gao.gov/products/GAO-13-500T�
http://www.gao.gov/products/GAO-13-309�
http://www.gao.gov/products/GAO-13-51�
http://www.gao.gov/products/GAO-12-437�
http://www.gao.gov/products/GAO-12-400SP�
http://www.gao.gov/products/GAO-12-525T�
http://www.gao.gov/products/GAO-11-903R�
Related GAO Products
Page 36 GAO-15-364 F-35 Joint Strike Fighter
Joint Strike Fighter: Restructuring Places Program on Firmer
Footing, but
Progress Is Still Lagging. GAO-11-677T. Washington, D.C.:
May 19,
2011.
Joint Strike Fighter: Restructuring Places Program on Firmer
Footing, but
Progress Still Lags. GAO-11-325. Washington, D.C.: April 7,
2011.
Joint Strike Fighter: Restructuring Should Improve Outcomes,
but
Progress Is Still Lagging Overall. GAO-11-450T. Washington,
D.C.:
March 15, 2011.
Tactical Aircraft: Air Force Fighter Force Structure Reports
Generally
Addressed Congressional Mandates, but Reflected Dated Plans
and
Guidance, and Limited Analyses. GAO-11-323R. Washington,
D.C.:
February 24, 2011.
Defense Management: DOD Needs to Monitor and Assess
Corrective
Actions Resulting from Its Corrosion Study of the F-35 Joint
Strike
Fighter. GAO-11-171R. Washington D.C.: December 16, 2010.
Joint Strike Fighter: Assessment of DOD’s Funding Projection
for the
F136 Alternate Engine. GAO-10-1020R. Washington, D.C.:
September
15, 2010.
Tactical Aircraft: DOD’s Ability to Meet Future Requirements
is Uncertain,
with Key Analyses Needed to Inform Upcoming Investment
Decisions.
GAO-10-789. Washington, D.C.: July 29, 2010.
Defense Acquisitions: Assessments of Selected Weapon
Programs.
GAO-10-388SP. Washington, D.C.: March 30, 2010.
Joint Strike Fighter: Significant Challenges and Decisions
Ahead.
GAO-10-478T. Washington, D.C.: March 24, 2010.
Joint Strike Fighter: Additional Costs and Delays Risk Not
Meeting
Warfighter Requirements on Time. GAO-10-382. Washington,
D.C.:
March 19, 2010.
Joint Strike Fighter: Significant Challenges Remain as DOD
Restructures
Program. GAO-10-520T. Washington, D.C.: March 11, 2010.
http://www.gao.gov/products/GAO-11-677T�
http://www.gao.gov/products/GAO-11-325�
http://www.gao.gov/products/GAO-11-450T�
http://www.gao.gov/products/GAO-11-323R�
http://www.gao.gov/products/GAO-11-171R�
http://www.gao.gov/products/GAO-10-1020R�
http://www.gao.gov/products/GAO-10-789�
http://www.gao.gov/products/GAO-10-388SP�
http://www.gao.gov/products/GAO-10-478T�
http://www.gao.gov/products/GAO-10-382�
http://www.gao.gov/products/GAO-10-520T�
Related GAO Products
Page 37 GAO-15-364 F-35 Joint Strike Fighter
Joint Strike Fighter: Strong Risk Management Essential as
Program
Enters Most Challenging Phase. GAO-09-711T. Washington,
D.C.: May
20, 2009.
Defense Acquisitions: Assessments of Selected Weapon
Programs.
GAO-09-326SP. Washington, D.C.: March 30, 2009.
Joint Strike Fighter: Accelerating Procurement before
Completing
Development Increases the Government’s Financial Risk. GAO-
09-303.
Washington D.C.: March 12, 2009.
Defense Acquisitions: Better Weapon Program Outcomes
Require
Discipline, Accountability, and Fundamental Changes in the
Acquisition
Environment. GAO-08-782T. Washington, D.C.: June 3, 2008.
Defense Acquisitions: Assessments of Selected Weapon
Programs.
GAO-08-467SP. Washington, D.C.: March 31, 2008.
Joint Strike Fighter: Impact of Recent Decisions on Program
Risks.
GAO-08-569T. Washington, D.C.: March 11, 2008.
Joint Strike Fighter: Recent Decisions by DOD Add to Program
Risks.
GAO-08-388. Washington, D.C.: March 11, 2008.
Tactical Aircraft: DOD Needs a Joint and Integrated Investment
Strategy.
GAO-07-415. Washington, D.C.: April 2, 2007.
Defense Acquisitions: Analysis of Costs for the Joint Strike
Fighter Engine
Program. GAO-07-656T. Washington, D.C.: March 22, 2007.
Joint Strike Fighter: Progress Made and Challenges Remain.
GAO-07-360. Washington, D.C.: March 15, 2007.
Tactical Aircraft: DOD’s Cancellation of the Joint Strike
Fighter Alternate
Engine Program Was Not Based on a Comprehensive Analysis.
GAO-06-717R. Washington, D.C.: May 22, 2006.
Defense Acquisitions: Major Weapon Systems Continue to
Experience
Cost and Schedule Problems under DOD’s Revised Policy.
GAO-06-368.
Washington, D.C.: April 13, 2006.
Defense Acquisitions: Actions Needed to Get Better Results on
Weapons
Systems Investments. GAO-06-585T. Washington, D.C.: April
5, 2006.
http://www.gao.gov/products/GAO-09-711T�
http://www.gao.gov/products/GAO-09-326SP�
http://www.gao.gov/products/GAO-09-303�
http://www.gao.gov/products/GAO-08-782T�
http://www.gao.gov/products/GAO-08-467SP�
http://www.gao.gov/products/GAO-08-569T�
http://www.gao.gov/products/GAO-08-388�
http://www.gao.gov/products/GAO-07-415�
http://www.gao.gov/products/GAO-07-656T�
http://www.gao.gov/products/GAO-07-360�
http://www.gao.gov/products/GAO-06-717R�
http://www.gao.gov/products/GAO-06-368�
http://www.gao.gov/products/GAO-06-585T�
Related GAO Products
Page 38 GAO-15-364 F-35 Joint Strike Fighter
Tactical Aircraft: Recapitalization Goals Are Not Supported by
Knowledge-Based F-22A and JSF Business Cases. GAO-06-
487T.
Washington, D.C.: March 16, 2006.
Joint Strike Fighter: DOD Plans to Enter Production before
Testing
Demonstrates Acceptable Performance. GAO-06-356.
Washington, D.C.:
March 15, 2006.
Joint Strike Fighter: Management of the Technology Transfer
Process.
GAO-06-364. Washington, D.C.: March 14, 2006.
Tactical Aircraft: F/A-22 and JSF Acquisition Plans and
Implications for
Tactical Aircraft Modernization. GAO-05-519T. Washington,
D.C: April 6,
2005.
Tactical Aircraft: Opportunity to Reduce Risks in the Joint
Strike Fighter
Program with Different Acquisition Strategy. GAO-05-271.
Washington,
D.C.: March 15, 2005.
(121234)
http://www.gao.gov/products/GAO-06-487T�
http://www.gao.gov/products/GAO-06-356�
http://www.gao.gov/products/GAO-06-364�
http://www.gao.gov/products/GAO-05-519T�
http://www.gao.gov/products/GAO-05-271�
The Government Accountability Office, the audit, evaluation,
and
investigative arm of Congress, exists to support Congress in
meeting its
constitutional responsibilities and to help improve the
performance and
accountability of the federal government for the American
people. GAO
examines the use of public funds; evaluates federal programs
and
policies; and provides analyses, recommendations, and other
assistance
to help Congress make informed oversight, policy, and funding
decisions.
GAO’s commitment to good government is reflected in its core
values of
accountability, integrity, and reliability.
The fastest and easiest way to obtain copies of GAO documents
at no
cost is through GAO’s website (http://www.gao.gov). Each
weekday
afternoon, GAO posts on its website newly released reports,
testimony,
and correspondence. To have GAO e-mail you a list of newly
posted
products, go to http://www.gao.gov and select “E-mail
Updates.”
The price of each GAO publication reflects GAO’s actual cost
of
production and distribution and depends on the number of pages
in the
publication and whether the publication is printed in color or
black and
white. Pricing and ordering information is posted on GAO’s
website,
http://www.gao.gov/ordering.htm.
Place orders by calling (202) 512-6000, toll free (866) 801-
7077, or
TDD (202) 512-2537.
Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional
information.
Connect with GAO on Facebook, Flickr, Twitter, and YouTube.
Subscribe to our RSS Feeds or E-mail Updates. Listen to our
Podcasts .
Visit GAO on the web at www.gao.gov.
Contact:
Website: http://www.gao.gov/fraudnet/fraudnet.htm
E-mail: [email protected]
Automated answering system: (800) 424-5454 or (202) 512-
7470
Katherine Siggerud, Managing Director, [email protected],
(202) 512-
4400, U.S. Government Accountability Office, 441 G Street
NW, Room
7125, Washington, DC 20548
Chuck Young, Managing Director, [email protected], (202) 512-
4800
U.S. Government Accountability Office, 441 G Street NW,
Room 7149
Washington, DC 20548
GAO’s Mission
Obtaining Copies of
GAO Reports and
Testimony
Order by Phone
Connect with GAO
To Report Fraud,
Waste, and Abuse in
Federal Programs
Congressional
Relations
Public Affairs
Please Print on Recycled Paper.
http://www.gao.gov/�
http://www.gao.gov/�
http://www.gao.gov/ordering.htm�
http://facebook.com/usgao�
http://flickr.com/usgao�
http://twitter.com/usgao�
http://youtube.com/usgao�
http://www.gao.gov/feeds.html�
http://www.gao.gov/subscribe/index.php�
http://www.gao.gov/podcast/watchdog.html�
http://www.gao.gov/�
http://www.gao.gov/fraudnet/fraudnet.htm�
mailto:[email protected]�
mailto:[email protected]�
mailto:[email protected]�F-35 Joint Strike FighterAssessment
Needed to Address Affordability
ChallengesContentsLetterBackgroundRecent Technical
Challenges Will Likely Result in Cost Growth and Schedule
DelaysTest Failures and Software Challenges Forced Program
ChangesNeed to Improve Engine Reliability Presents Additional
ChallengesUnexpected Technical Issues and Ongoing
Reliability Challenges Amplify Concurrency RiskAffordability
Challenges Will Likely Continue to Affect Program Plans to
Increase F-35 ProcurementWhile Manufacturing Progress
Remains Steady, Planned Production Increases Could Be a
ChallengeManufacturing Efficiency Remains SteadyLate
Deliveries from Suppliers Continue, and Could Challenge
Planned Production
IncreasesConclusionsRecommendationsAgency Comments and
Our EvaluationAppendix I: Prior GAO Reports on F-35 Joint
Strike Fighter (JSF) and Department of Defense (DOD)
Responses and Subsequent ActionsAppendix II: Scope and
MethodologyAppendix III: DOD CommentsAppendix IV: GAO
Contact and Staff AcknowledgmentsGAO
ContactAcknowledgmentsRelated GAO
Productsd15364_HIGHLIGHTS.pdfF-35 JOINT STRIKE
FIGHTERAssessment Needed to Address Affordability
ChallengesWhy GAO Did This StudyWhat GAO
RecommendsWhat GAO FoundCost and affordability challenges
remain. DOD plans to significantly increase annual F-35
funding from around $8 billion to nearly $12 billion over the
next 5 years (see figure) reaching $14 billion in 2022 and
remaining between $14 and $15 billion fo...
<<
/ASCII85EncodePages false
/AllowTransparency false
/AutoPositionEPSFiles true
/AutoRotatePages /PageByPage
/Binding /Left
/CalGrayProfile (Dot Gain 20%)
/CalRGBProfile (sRGB IEC61966-2.1)
/CalCMYKProfile (U.S. Sheetfed Uncoated v2)
/sRGBProfile (sRGB IEC61966-2.1)
/CannotEmbedFontPolicy /Warning
/CompatibilityLevel 1.7
/CompressObjects /All
/CompressPages true
/ConvertImagesToIndexed true
/PassThroughJPEGImages true
/CreateJobTicket false
/DefaultRenderingIntent /Default
/DetectBlends true
/DetectCurves 0.1000
/ColorConversionStrategy /LeaveColorUnchanged
/DoThumbnails false
/EmbedAllFonts true
/EmbedOpenType false
/ParseICCProfilesInComments true
/EmbedJobOptions true
/DSCReportingLevel 0
/EmitDSCWarnings false
/EndPage -1
/ImageMemory 1048576
/LockDistillerParams true
/MaxSubsetPct 100
/Optimize true
/OPM 1
/ParseDSCComments true
/ParseDSCCommentsForDocInfo true
/PreserveCopyPage true
/PreserveDICMYKValues true
/PreserveEPSInfo true
/PreserveFlatness true
/PreserveHalftoneInfo false
/PreserveOPIComments false
/PreserveOverprintSettings true
/StartPage 1
/SubsetFonts true
/TransferFunctionInfo /Preserve
/UCRandBGInfo /Preserve
/UsePrologue false
/ColorSettingsFile ()
/AlwaysEmbed [ true
]
/NeverEmbed [ true
]
/AntiAliasColorImages false
/CropColorImages true
/ColorImageMinResolution 150
/ColorImageMinResolutionPolicy /OK
/DownsampleColorImages true
/ColorImageDownsampleType /Bicubic
/ColorImageResolution 300
/ColorImageDepth -1
/ColorImageMinDownsampleDepth 1
/ColorImageDownsampleThreshold 1.50000
/EncodeColorImages true
/ColorImageFilter /DCTEncode
/AutoFilterColorImages true
/ColorImageAutoFilterStrategy /JPEG
/ColorACSImageDict <<
/QFactor 0.15
/HSamples [1 1 1 1] /VSamples [1 1 1 1]
>>
/ColorImageDict <<
/QFactor 0.76
/HSamples [2 1 1 2] /VSamples [2 1 1 2]
>>
/JPEG2000ColorACSImageDict <<
/TileWidth 256
/TileHeight 256
/Quality 15
>>
/JPEG2000ColorImageDict <<
/TileWidth 256
/TileHeight 256
/Quality 15
>>
/AntiAliasGrayImages false
/CropGrayImages true
/GrayImageMinResolution 150
/GrayImageMinResolutionPolicy /OK
/DownsampleGrayImages true
/GrayImageDownsampleType /Bicubic
/GrayImageResolution 300
/GrayImageDepth -1
/GrayImageMinDownsampleDepth 2
/GrayImageDownsampleThreshold 1.50000
/EncodeGrayImages true
/GrayImageFilter /DCTEncode
/AutoFilterGrayImages true
/GrayImageAutoFilterStrategy /JPEG
/GrayACSImageDict <<
/QFactor 0.15
/HSamples [1 1 1 1] /VSamples [1 1 1 1]
>>
/GrayImageDict <<
/QFactor 0.76
/HSamples [2 1 1 2] /VSamples [2 1 1 2]
>>
/JPEG2000GrayACSImageDict <<
/TileWidth 256
/TileHeight 256
/Quality 15
>>
/JPEG2000GrayImageDict <<
/TileWidth 256
/TileHeight 256
/Quality 15
>>
/AntiAliasMonoImages false
/CropMonoImages true
/MonoImageMinResolution 1200
/MonoImageMinResolutionPolicy /OK
/DownsampleMonoImages true
/MonoImageDownsampleType /Bicubic
/MonoImageResolution 1200
/MonoImageDepth -1
/MonoImageDownsampleThreshold 1.50000
/EncodeMonoImages true
/MonoImageFilter /CCITTFaxEncode
/MonoImageDict <<
/K -1
>>
/AllowPSXObjects false
/CheckCompliance [
/None
]
/PDFX1aCheck false
/PDFX3Check false
/PDFXCompliantPDFOnly false
/PDFXNoTrimBoxError true
/PDFXTrimBoxToMediaBoxOffset [
0.00000
0.00000
0.00000
0.00000
]
/PDFXSetBleedBoxToMediaBox true
/PDFXBleedBoxToTrimBoxOffset [
0.00000
0.00000
0.00000
0.00000
]
/PDFXOutputIntentProfile (None)
/PDFXOutputConditionIdentifier ()
/PDFXOutputCondition ()
/PDFXRegistryName ()
/PDFXTrapped /False
/CreateJDFFile false
/Description <<
/ARA
<FEFF0633062A062E062F064500200647063006470020062706
4406250639062F0627062F0627062A0020064406250646063406
27062100200648062B062706260642002000410064006F006200
65002000500044004600200645064606270633062806290020064
4063906310636002006480637062806270639062900200648062
B06270626064200200627064406230639064506270644002E002
00020064A06450643064600200641062A062D00200648062B06
27062606420020005000440046002006270644062A064A002006
2A06450020062506460634062706260647062700200628062706
33062A062E062F062706450020004100630072006F0062006100
7400200648002000410064006F00620065002000520065006100
640065007200200036002E003000200648064506270020062806
39062F0647002E>
/BGR
<FEFF04180437043F043E043B04370432043004390442043500
2004420435043704380020043D0430044104420440043E043904
3A0438002C00200437043000200434043000200441044A043704
3404300432043004420435002000410064006F00620065002000
500044004600200434043E043A0443043C0435043D044204380
02C0020043F043E04340445043E0434044F04490438002004370
4300020043D04300434043504360434043D043E0020044004300
4370433043B0435043604340430043D0435002004380020043F0
4350447043004420430043D04350020043D04300020043104380
437043D0435044100200434043E043A0443043C0435043D0442
0438002E00200421044A04370434043004340435043D04380442
0435002000500044004600200434043E043A0443043C0435043
D044204380020043C043E0433043004420020043404300020044
104350020043E0442043204300440044F0442002004410020004
100630072006F00620061007400200438002000410064006F006
20065002000520065006100640065007200200036002E0030002
004380020043F043E002D043D043E0432043800200432043504
40044104380438002E>
/CHS
<FEFF4f7f75288fd94e9b8bbe5b9a521b5efa76840020004100640
06f006200650020005000440046002065876863900275284e8e55
464e1a65876863768467e5770b548c62535370300260a853ef4ee5
4f7f75280020004100630072006f0062006100740020548c002000
410064006f0062006500200052006500610064006500720020003
6002e003000204ee553ca66f49ad87248672c676562535f00521b5
efa768400200050004400460020658768633002>
/CHT
<FEFF4f7f752890194e9b8a2d7f6e5efa7acb76840020004100640
06f006200650020005000440046002065874ef69069752865bc66
6e901a554652d965874ef6768467e5770b548c52175370300260a
853ef4ee54f7f75280020004100630072006f00620061007400205
48c002000410064006f0062006500200052006500610064006500
7200200036002e003000204ee553ca66f49ad87248672c4f86958b
555f5df25efa7acb76840020005000440046002065874ef63002>
/CZE
<FEFF0054006f0074006f0020006e006100730074006100760065
006e00ed00200070006f0075017e0069006a007400650020006b0
020007600790074007600e101590065006e00ed00200064006f00
6b0075006d0065006e0074016f002000410064006f00620065002
0005000440046002000760068006f0064006e00fd006300680020
006b0065002000730070006f006c00650068006c0069007600e90
06d0075002000700072006f0068006c00ed017e0065006e00ed00
2000610020007400690073006b00750020006f006200630068006
f0064006e00ed0063006800200064006f006b0075006d0065006e
0074016f002e002000200056007900740076006f01590065006e0
0e900200064006f006b0075006d0065006e007400790020005000
4400460020006c007a00650020006f007400650076015900ed007
400200076002000610070006c0069006b0061006300ed00630068
0020004100630072006f006200610074002000610020004100630
072006f0062006100740020005200650061006400650072002000
36002e0030002000610020006e006f0076011b006a016100ed006
30068002e>
/DAN
<FEFF004200720075006700200069006e0064007300740069006
c006c0069006e006700650072006e0065002000740069006c0020
006100740020006f0070007200650074007400650020004100640
06f006200650020005000440046002d0064006f006b0075006d00
65006e007400650072002c0020006400650072002000650067006
e006500720020007300690067002000740069006c002000640065
00740061006c006a006500720065007400200073006b00e600720
06d007600690073006e0069006e00670020006f00670020007500
640073006b007200690076006e0069006e0067002000610066002
00066006f0072007200650074006e0069006e006700730064006f
006b0075006d0065006e007400650072002e00200044006500200
06f00700072006500740074006500640065002000500044004600
2d0064006f006b0075006d0065006e0074006500720020006b006
1006e002000e50062006e00650073002000690020004100630072
006f00620061007400200065006c006c006500720020004100630
072006f0062006100740020005200650061006400650072002000
36002e00300020006f00670020006e0079006500720065002e>
/DEU
<FEFF00560065007200770065006e00640065006e00200053006
90065002000640069006500730065002000450069006e00730074
0065006c006c0075006e00670065006e0020007a0075006d00200
0450072007300740065006c006c0065006e00200076006f006e00
2000410064006f006200650020005000440046002d0044006f006
b0075006d0065006e00740065006e002c00200075006d00200065
0069006e00650020007a0075007600650072006c00e4007300730
0690067006500200041006e007a00650069006700650020007500
6e00640020004100750073006700610062006500200076006f006
e00200047006500730063006800e40066007400730064006f006b
0075006d0065006e00740065006e0020007a00750020006500720
07a00690065006c0065006e002e00200044006900650020005000
440046002d0044006f006b0075006d0065006e007400650020006
b00f6006e006e0065006e0020006d006900740020004100630072
006f00620061007400200075006e0064002000520065006100640
065007200200036002e003000200075006e00640020006800f600
680065007200200067006500f600660066006e006500740020007
70065007200640065006e002e>
/ESP
<FEFF005500740069006c0069006300650020006500730074006
100200063006f006e0066006900670075007200610063006900f3
006e0020007000610072006100200063007200650061007200200
064006f00630075006d0065006e0074006f007300200064006500
2000410064006f006200650020005000440046002000610064006
50063007500610064006f00730020007000610072006100200076
0069007300750061006c0069007a00610063006900f3006e00200
06500200069006d0070007200650073006900f3006e0020006400
6500200063006f006e006600690061006e007a006100200064006
500200064006f00630075006d0065006e0074006f007300200063
006f006d00650072006300690061006c00650073002e002000530
065002000700075006500640065006e0020006100620072006900
7200200064006f00630075006d0065006e0074006f00730020005
000440046002000630072006500610064006f007300200063006f
006e0020004100630072006f006200610074002c0020004100640
06f00620065002000520065006100640065007200200036002e00
3000200079002000760065007200730069006f006e00650073002
00070006f00730074006500720069006f007200650073002e>
/ETI
<FEFF004b00610073007500740061006700650020006e0065006
900640020007300e400740074006500690064002c002000650074
0020006c0075007500610020005000440046002d0064006f006b0
075006d0065006e00740065002c0020006d006900730020007300
6f00620069007600610064002000e4007200690064006f006b007
5006d0065006e00740069006400650020007500730061006c0064
00750073007600e400e4007200730065006b00730020007600610
06100740061006d006900730065006b00730020006a0061002000
7000720069006e00740069006d006900730065006b0073002e002
00020004c006f006f0064007500640020005000440046002d0064
006f006b0075006d0065006e00740065002000730061006100620
02000610076006100640061002000760061006900640020004100
630072006f0062006100740020006a0061002000410064006f006
20065002000520065006100640065007200200036002e00300020
006a00610020007500750065006d0061007400650020007600650
07200730069006f006f006e00690064006500670061002e>
/FRA
<FEFF005500740069006c006900730065007a002000630065007
30020006f007000740069006f006e00730020006100660069006e
00200064006500200063007200e90065007200200064006500730
0200064006f00630075006d0065006e0074007300200041006400
6f006200650020005000440046002000700072006f00660065007
300730069006f006e006e0065006c007300200066006900610062
006c0065007300200070006f007500720020006c0061002000760
069007300750061006c00690073006100740069006f006e002000
6500740020006c00270069006d007000720065007300730069006
f006e002e0020004c0065007300200064006f00630075006d0065
006e00740073002000500044004600200063007200e900e900730
02000700065007500760065006e0074002000ea00740072006500
20006f007500760065007200740073002000640061006e0073002
0004100630072006f006200610074002c002000610069006e0073
0069002000710075002700410064006f006200650020005200650
06100640065007200200036002e00300020006500740020007600
65007200730069006f006e007300200075006c007400e90072006
900650075007200650073002e>
/GRE
<FEFF03A703C103B703C303B903BC03BF03C003BF03B903A
E03C303C403B5002003B103C503C403AD03C2002003C403B9
03C2002003C103C503B803BC03AF03C303B503B903C200200
3B303B903B1002003BD03B1002003B403B703BC03B903BF03
C503C103B303AE03C303B503C403B5002003AD03B303B303
C103B103C603B1002000410064006F006200650020005000440
046002003BA03B103C403AC03BB03BB03B703BB03B100200
3B303B903B1002003B103BE03B903CC03C003B903C303C403
B7002003C003C103BF03B203BF03BB03AE002003BA03B103
B9002003B503BA03C403CD03C003C903C303B7002003B503C
003B103B303B303B503BB03BC03B103C403B903BA03CE03B
D002003B503B303B303C103AC03C603C903BD002E00200020
03A403B1002003AD03B303B303C103B103C603B1002000500
0440046002003C003BF03C5002003B803B1002003B403B703B
C03B903BF03C503C103B303B703B803BF03CD03BD002003B
103BD03BF03AF03B303BF03C503BD002003BC03B50020004
100630072006F006200610074002003BA03B103B90020004100
64006F0062006500200052006500610064006500720020003600
2E0030002003BA03B103B9002003BD03B503CC03C403B503C
103B503C2002003B503BA03B403CC03C303B503B903C2002E
>
/HEB
<FEFF05D405E905EA05DE05E905D5002005D105E705D105D
905E205D505EA002005D005DC05D4002005DB05D305D9002
005DC05D905E605D505E8002005DE05E105DE05DB05D9002
000410064006F006200650020005000440046002005D405DE05
EA05D005D905DE05D905DD002005DC05EA05E605D505D20
5D4002005D505DC05D405D305E405E105D4002005D005DE05
D905E005D505EA002005E905DC002005DE05E105DE05DB05
D905DD002005E205E105E705D905D905DD002E0020002005E
005D905EA05DF002005DC05E405EA05D505D7002005E705D
505D105E605D90020005000440046002005D1002D0020004100
630072006F006200610074002005D505D1002D0020004100640
06F006200650020005200650061006400650072002005DE05D20
5E805E105D400200036002E0030002005D505DE05E205DC05
D4002E>
/HRV
<FEFF004F0076006500200070006F0073007400610076006B00
650020006B006F00720069007300740069007400650020006B00
61006B006F002000620069007300740065002000730074007600
6F00720069006C0069002000410064006F006200650020005000
44004600200064006F006B0075006D0065006E00740065002000
6B006F006A00690020007300750020007000720069006B006C0
0610064006E00690020007A006100200070006F0075007A00640
061006E00200070007200650067006C006500640020006900200
069007300700069007300200070006F0073006C006F0076006E0
069006800200064006F006B0075006D0065006E0061007400610
02E0020005300740076006F00720065006E00690020005000440
04600200064006F006B0075006D0065006E007400690020006D
006F006700750020007300650020006F00740076006F00720069
0074006900200075002000700072006F006700720061006D0069
006D00610020004100630072006F006200610074002000690020
00410064006F0062006500200052006500610064006500720020
0036002E0030002000690020006E006F00760069006A0069006
D0020007600650072007A0069006A0061006D0061002E>
/HUN
<FEFF0045007a0065006b006b0065006c0020006100200062006
500e1006c006c00ed007400e10073006f006b006b0061006c0020
00fc007a006c00650074006900200064006f006b0075006d00650
06e00740075006d006f006b0020006d00650067006200ed007a00
680061007400f30020006d00650067006a0065006c0065006e00e
d007400e9007300e900720065002000e900730020006e0079006f
006d00740061007400e1007300e10072006100200061006c006b0
061006c006d00610073002000410064006f006200650020005000
440046002d0064006f006b0075006d0065006e00740075006d006
f006b006100740020006b00e90073007a00ed0074006800650074
002e002000200041007a002000ed006700790020006c00e900740
07200650068006f007a006f007400740020005000440046002d00
64006f006b0075006d0065006e00740075006d006f006b0020006
1007a0020004100630072006f006200610074002000e900730020
0061007a002000410064006f00620065002000520065006100640
065007200200036002c0030002d0073002000e900730020006b00
e9007301510062006200690020007600650072007a006900f3006
900760061006c0020006e00790069007400680061007400f3006b
0020006d00650067002e>
/ITA (Utilizzare queste impostazioni per creare documenti
Adobe PDF adatti per visualizzare e stampare documenti
aziendali in modo affidabile. I documenti PDF creati possono
essere aperti con Acrobat e Adobe Reader 6.0 e versioni
successive.)
/JPN
<FEFF30d330b830cd30b9658766f8306e8868793a304a30883073
53705237306b90693057305f002000410064006f0062006500200
050004400460020658766f8306e4f5c6210306b4f7f75283057307
e305930023053306e8a2d5b9a30674f5c62103055308c305f00200
05000440046002030d530a130a430eb306f300100410063007200
6f0062006100740020304a30883073002000410064006f0062006
5002000520065006100640065007200200036002e003000204ee5
964d3067958b304f30533068304c3067304d307e3059300230533
06e8a2d5b9a3067306f30d530a930f330c8306e57cb30818fbc307f
3092884c3044307e30593002>
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx
F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx

More Related Content

Similar to F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx

DARPA -Transition of Technologies
DARPA -Transition of TechnologiesDARPA -Transition of Technologies
DARPA -Transition of TechnologiesDr Dev Kambhampati
 
GAO Report US Congress September 2013
 GAO Report US Congress September 2013 GAO Report US Congress September 2013
GAO Report US Congress September 2013Dmitry Tseitlin
 
STRATEGIC SOURCING(MATERIALS MANAGEMENT AND PURCHASING)(OS.docx
STRATEGIC SOURCING(MATERIALS MANAGEMENT AND PURCHASING)(OS.docxSTRATEGIC SOURCING(MATERIALS MANAGEMENT AND PURCHASING)(OS.docx
STRATEGIC SOURCING(MATERIALS MANAGEMENT AND PURCHASING)(OS.docxcpatriciarpatricia
 
Investor presentation february 2018 final
Investor presentation february 2018 finalInvestor presentation february 2018 final
Investor presentation february 2018 finalOshkosh_Investors
 
Aerospace & Defense 2014 Year in Review and 2015 Forecast
Aerospace & Defense 2014 Year in Review and 2015 ForecastAerospace & Defense 2014 Year in Review and 2015 Forecast
Aerospace & Defense 2014 Year in Review and 2015 ForecastSeda Eskiler
 
[Invbots' Insight] Investment Strategy - US Defense Sector
[Invbots' Insight] Investment Strategy - US Defense Sector [Invbots' Insight] Investment Strategy - US Defense Sector
[Invbots' Insight] Investment Strategy - US Defense Sector Invbots Limited
 
Deloitte, global aerospace industry
Deloitte, global aerospace industryDeloitte, global aerospace industry
Deloitte, global aerospace industryStudsPlanet.com
 
Conference Call 4Q13
Conference Call 4Q13Conference Call 4Q13
Conference Call 4Q13Embraer RI
 
Investor presentation march 2018
Investor presentation march 2018Investor presentation march 2018
Investor presentation march 2018Oshkosh_Investors
 
Deloitte Maverick Season III Round 1 Presentation
Deloitte Maverick Season III Round 1 Presentation Deloitte Maverick Season III Round 1 Presentation
Deloitte Maverick Season III Round 1 Presentation Srinivas Amara
 
Teekay Offshore Partners Q4-2019 Earnings Presentation
Teekay Offshore Partners Q4-2019 Earnings PresentationTeekay Offshore Partners Q4-2019 Earnings Presentation
Teekay Offshore Partners Q4-2019 Earnings PresentationAltera Infrastructure
 
Conference Call 3Q13.
Conference Call 3Q13.Conference Call 3Q13.
Conference Call 3Q13.Embraer RI
 
Coming Late to the Party - Getting to Green on the Fly
Coming Late to the Party - Getting to Green on the FlyComing Late to the Party - Getting to Green on the Fly
Coming Late to the Party - Getting to Green on the FlyGlen Alleman
 
Gx mfg 2013_globalad_industryoutlook
Gx mfg 2013_globalad_industryoutlookGx mfg 2013_globalad_industryoutlook
Gx mfg 2013_globalad_industryoutlookJacob Yosha
 
Miami University 2016 Cleveland Research Company Stock Pitch Competition Winner
Miami University 2016 Cleveland Research Company Stock Pitch Competition WinnerMiami University 2016 Cleveland Research Company Stock Pitch Competition Winner
Miami University 2016 Cleveland Research Company Stock Pitch Competition WinnerMichael T. Loffredo
 
COMM430 Final Project
COMM430 Final Project COMM430 Final Project
COMM430 Final Project Lisa Koykar
 
Selling to the Government Best Prospects for Small Entreprene.docx
Selling to the Government   Best Prospects for Small Entreprene.docxSelling to the Government   Best Prospects for Small Entreprene.docx
Selling to the Government Best Prospects for Small Entreprene.docxtcarolyn
 
Aviation industry in india (2)
Aviation industry in india (2)Aviation industry in india (2)
Aviation industry in india (2)P SHRAVAN KUMAR
 

Similar to F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx (20)

DARPA -Transition of Technologies
DARPA -Transition of TechnologiesDARPA -Transition of Technologies
DARPA -Transition of Technologies
 
GAO Report US Congress September 2013
 GAO Report US Congress September 2013 GAO Report US Congress September 2013
GAO Report US Congress September 2013
 
STRATEGIC SOURCING(MATERIALS MANAGEMENT AND PURCHASING)(OS.docx
STRATEGIC SOURCING(MATERIALS MANAGEMENT AND PURCHASING)(OS.docxSTRATEGIC SOURCING(MATERIALS MANAGEMENT AND PURCHASING)(OS.docx
STRATEGIC SOURCING(MATERIALS MANAGEMENT AND PURCHASING)(OS.docx
 
Investor presentation february 2018 final
Investor presentation february 2018 finalInvestor presentation february 2018 final
Investor presentation february 2018 final
 
Aerospace & Defense 2014 Year in Review and 2015 Forecast
Aerospace & Defense 2014 Year in Review and 2015 ForecastAerospace & Defense 2014 Year in Review and 2015 Forecast
Aerospace & Defense 2014 Year in Review and 2015 Forecast
 
[Invbots' Insight] Investment Strategy - US Defense Sector
[Invbots' Insight] Investment Strategy - US Defense Sector [Invbots' Insight] Investment Strategy - US Defense Sector
[Invbots' Insight] Investment Strategy - US Defense Sector
 
Deloitte, global aerospace industry
Deloitte, global aerospace industryDeloitte, global aerospace industry
Deloitte, global aerospace industry
 
Conference Call 4Q13
Conference Call 4Q13Conference Call 4Q13
Conference Call 4Q13
 
Investor presentation march 2018
Investor presentation march 2018Investor presentation march 2018
Investor presentation march 2018
 
Deloitte Maverick Season III Round 1 Presentation
Deloitte Maverick Season III Round 1 Presentation Deloitte Maverick Season III Round 1 Presentation
Deloitte Maverick Season III Round 1 Presentation
 
Teekay Offshore Partners Q4-2019 Earnings Presentation
Teekay Offshore Partners Q4-2019 Earnings PresentationTeekay Offshore Partners Q4-2019 Earnings Presentation
Teekay Offshore Partners Q4-2019 Earnings Presentation
 
Conference Call 3Q13.
Conference Call 3Q13.Conference Call 3Q13.
Conference Call 3Q13.
 
Coming Late to the Party - Getting to Green on the Fly
Coming Late to the Party - Getting to Green on the FlyComing Late to the Party - Getting to Green on the Fly
Coming Late to the Party - Getting to Green on the Fly
 
Gx mfg 2013_globalad_industryoutlook
Gx mfg 2013_globalad_industryoutlookGx mfg 2013_globalad_industryoutlook
Gx mfg 2013_globalad_industryoutlook
 
2013 globlad industry outlook
2013 globlad industry outlook2013 globlad industry outlook
2013 globlad industry outlook
 
Miami University 2016 Cleveland Research Company Stock Pitch Competition Winner
Miami University 2016 Cleveland Research Company Stock Pitch Competition WinnerMiami University 2016 Cleveland Research Company Stock Pitch Competition Winner
Miami University 2016 Cleveland Research Company Stock Pitch Competition Winner
 
COMM430 Final Project
COMM430 Final Project COMM430 Final Project
COMM430 Final Project
 
Selling to the Government Best Prospects for Small Entreprene.docx
Selling to the Government   Best Prospects for Small Entreprene.docxSelling to the Government   Best Prospects for Small Entreprene.docx
Selling to the Government Best Prospects for Small Entreprene.docx
 
Aviation industry in india (2)
Aviation industry in india (2)Aviation industry in india (2)
Aviation industry in india (2)
 
648644
648644648644
648644
 

More from lmelaine

Jan 18, 2013 at 217pmNo unread replies.No replies.Post yo.docx
Jan 18, 2013 at 217pmNo unread replies.No replies.Post yo.docxJan 18, 2013 at 217pmNo unread replies.No replies.Post yo.docx
Jan 18, 2013 at 217pmNo unread replies.No replies.Post yo.docxlmelaine
 
Jan 10, 20141.Definition of law A set of rules and proced.docx
Jan 10, 20141.Definition of law A set of rules and proced.docxJan 10, 20141.Definition of law A set of rules and proced.docx
Jan 10, 20141.Definition of law A set of rules and proced.docxlmelaine
 
James RiverJewelryProjectQuesti.docx
James RiverJewelryProjectQuesti.docxJames RiverJewelryProjectQuesti.docx
James RiverJewelryProjectQuesti.docxlmelaine
 
Jacob claims the employer violated his rights. In your opinion, what.docx
Jacob claims the employer violated his rights. In your opinion, what.docxJacob claims the employer violated his rights. In your opinion, what.docx
Jacob claims the employer violated his rights. In your opinion, what.docxlmelaine
 
Ive been promised A+ papers in the past but so far I have not seen .docx
Ive been promised A+ papers in the past but so far I have not seen .docxIve been promised A+ papers in the past but so far I have not seen .docx
Ive been promised A+ papers in the past but so far I have not seen .docxlmelaine
 
It’s easy to dismiss the works from the Dada movement as silly. Cons.docx
It’s easy to dismiss the works from the Dada movement as silly. Cons.docxIt’s easy to dismiss the works from the Dada movement as silly. Cons.docx
It’s easy to dismiss the works from the Dada movement as silly. Cons.docxlmelaine
 
Its meaning is still debated. It could be a symbol of the city of Fl.docx
Its meaning is still debated. It could be a symbol of the city of Fl.docxIts meaning is still debated. It could be a symbol of the city of Fl.docx
Its meaning is still debated. It could be a symbol of the city of Fl.docxlmelaine
 
Jaffe and Jordan want to use financial planning models to prepar.docx
Jaffe and Jordan want to use financial planning models to prepar.docxJaffe and Jordan want to use financial planning models to prepar.docx
Jaffe and Jordan want to use financial planning models to prepar.docxlmelaine
 
Ive got this assinment due and was wondering if anyone has done any.docx
Ive got this assinment due and was wondering if anyone has done any.docxIve got this assinment due and was wondering if anyone has done any.docx
Ive got this assinment due and was wondering if anyone has done any.docxlmelaine
 
It is thought that a metabolic waste product produced by a certain g.docx
It is thought that a metabolic waste product produced by a certain g.docxIt is thought that a metabolic waste product produced by a certain g.docx
It is thought that a metabolic waste product produced by a certain g.docxlmelaine
 
it is not the eassay it is about anwering the question with 2,3 pa.docx
it is not the eassay it is about anwering the question with 2,3 pa.docxit is not the eassay it is about anwering the question with 2,3 pa.docx
it is not the eassay it is about anwering the question with 2,3 pa.docxlmelaine
 
It is now time to select sources and take some notes. You will nee.docx
It is now time to select sources and take some notes. You will nee.docxIt is now time to select sources and take some notes. You will nee.docx
It is now time to select sources and take some notes. You will nee.docxlmelaine
 
Its a linear equations question...Neilsen Media Research surveys .docx
Its a linear equations question...Neilsen Media Research surveys .docxIts a linear equations question...Neilsen Media Research surveys .docx
Its a linear equations question...Neilsen Media Research surveys .docxlmelaine
 
itively impact job satisfactionWeek 3 - Learning Team Paper - Due .docx
itively impact job satisfactionWeek 3 - Learning Team Paper - Due .docxitively impact job satisfactionWeek 3 - Learning Team Paper - Due .docx
itively impact job satisfactionWeek 3 - Learning Team Paper - Due .docxlmelaine
 
IT205 Management of Information SystemsHello, I am looking for he.docx
IT205 Management of Information SystemsHello, I am looking for he.docxIT205 Management of Information SystemsHello, I am looking for he.docx
IT205 Management of Information SystemsHello, I am looking for he.docxlmelaine
 
It is not an online course so i cannot share any login details. No d.docx
It is not an online course so i cannot share any login details. No d.docxIt is not an online course so i cannot share any login details. No d.docx
It is not an online course so i cannot share any login details. No d.docxlmelaine
 
IT Strategic Plan, Part 1Using the case provided, analyze the busi.docx
IT Strategic Plan, Part 1Using the case provided, analyze the busi.docxIT Strategic Plan, Part 1Using the case provided, analyze the busi.docx
IT Strategic Plan, Part 1Using the case provided, analyze the busi.docxlmelaine
 
It should be in API format.Research paper should be on Ethernet .docx
It should be in API format.Research paper should be on Ethernet .docxIt should be in API format.Research paper should be on Ethernet .docx
It should be in API format.Research paper should be on Ethernet .docxlmelaine
 
IT Strategic Plan, Part 2Using the case provided, build on Part .docx
IT Strategic Plan, Part 2Using the case provided, build on Part .docxIT Strategic Plan, Part 2Using the case provided, build on Part .docx
IT Strategic Plan, Part 2Using the case provided, build on Part .docxlmelaine
 
It seems most everything we buy these days has the label made in Ch.docx
It seems most everything we buy these days has the label made in Ch.docxIt seems most everything we buy these days has the label made in Ch.docx
It seems most everything we buy these days has the label made in Ch.docxlmelaine
 

More from lmelaine (20)

Jan 18, 2013 at 217pmNo unread replies.No replies.Post yo.docx
Jan 18, 2013 at 217pmNo unread replies.No replies.Post yo.docxJan 18, 2013 at 217pmNo unread replies.No replies.Post yo.docx
Jan 18, 2013 at 217pmNo unread replies.No replies.Post yo.docx
 
Jan 10, 20141.Definition of law A set of rules and proced.docx
Jan 10, 20141.Definition of law A set of rules and proced.docxJan 10, 20141.Definition of law A set of rules and proced.docx
Jan 10, 20141.Definition of law A set of rules and proced.docx
 
James RiverJewelryProjectQuesti.docx
James RiverJewelryProjectQuesti.docxJames RiverJewelryProjectQuesti.docx
James RiverJewelryProjectQuesti.docx
 
Jacob claims the employer violated his rights. In your opinion, what.docx
Jacob claims the employer violated his rights. In your opinion, what.docxJacob claims the employer violated his rights. In your opinion, what.docx
Jacob claims the employer violated his rights. In your opinion, what.docx
 
Ive been promised A+ papers in the past but so far I have not seen .docx
Ive been promised A+ papers in the past but so far I have not seen .docxIve been promised A+ papers in the past but so far I have not seen .docx
Ive been promised A+ papers in the past but so far I have not seen .docx
 
It’s easy to dismiss the works from the Dada movement as silly. Cons.docx
It’s easy to dismiss the works from the Dada movement as silly. Cons.docxIt’s easy to dismiss the works from the Dada movement as silly. Cons.docx
It’s easy to dismiss the works from the Dada movement as silly. Cons.docx
 
Its meaning is still debated. It could be a symbol of the city of Fl.docx
Its meaning is still debated. It could be a symbol of the city of Fl.docxIts meaning is still debated. It could be a symbol of the city of Fl.docx
Its meaning is still debated. It could be a symbol of the city of Fl.docx
 
Jaffe and Jordan want to use financial planning models to prepar.docx
Jaffe and Jordan want to use financial planning models to prepar.docxJaffe and Jordan want to use financial planning models to prepar.docx
Jaffe and Jordan want to use financial planning models to prepar.docx
 
Ive got this assinment due and was wondering if anyone has done any.docx
Ive got this assinment due and was wondering if anyone has done any.docxIve got this assinment due and was wondering if anyone has done any.docx
Ive got this assinment due and was wondering if anyone has done any.docx
 
It is thought that a metabolic waste product produced by a certain g.docx
It is thought that a metabolic waste product produced by a certain g.docxIt is thought that a metabolic waste product produced by a certain g.docx
It is thought that a metabolic waste product produced by a certain g.docx
 
it is not the eassay it is about anwering the question with 2,3 pa.docx
it is not the eassay it is about anwering the question with 2,3 pa.docxit is not the eassay it is about anwering the question with 2,3 pa.docx
it is not the eassay it is about anwering the question with 2,3 pa.docx
 
It is now time to select sources and take some notes. You will nee.docx
It is now time to select sources and take some notes. You will nee.docxIt is now time to select sources and take some notes. You will nee.docx
It is now time to select sources and take some notes. You will nee.docx
 
Its a linear equations question...Neilsen Media Research surveys .docx
Its a linear equations question...Neilsen Media Research surveys .docxIts a linear equations question...Neilsen Media Research surveys .docx
Its a linear equations question...Neilsen Media Research surveys .docx
 
itively impact job satisfactionWeek 3 - Learning Team Paper - Due .docx
itively impact job satisfactionWeek 3 - Learning Team Paper - Due .docxitively impact job satisfactionWeek 3 - Learning Team Paper - Due .docx
itively impact job satisfactionWeek 3 - Learning Team Paper - Due .docx
 
IT205 Management of Information SystemsHello, I am looking for he.docx
IT205 Management of Information SystemsHello, I am looking for he.docxIT205 Management of Information SystemsHello, I am looking for he.docx
IT205 Management of Information SystemsHello, I am looking for he.docx
 
It is not an online course so i cannot share any login details. No d.docx
It is not an online course so i cannot share any login details. No d.docxIt is not an online course so i cannot share any login details. No d.docx
It is not an online course so i cannot share any login details. No d.docx
 
IT Strategic Plan, Part 1Using the case provided, analyze the busi.docx
IT Strategic Plan, Part 1Using the case provided, analyze the busi.docxIT Strategic Plan, Part 1Using the case provided, analyze the busi.docx
IT Strategic Plan, Part 1Using the case provided, analyze the busi.docx
 
It should be in API format.Research paper should be on Ethernet .docx
It should be in API format.Research paper should be on Ethernet .docxIt should be in API format.Research paper should be on Ethernet .docx
It should be in API format.Research paper should be on Ethernet .docx
 
IT Strategic Plan, Part 2Using the case provided, build on Part .docx
IT Strategic Plan, Part 2Using the case provided, build on Part .docxIT Strategic Plan, Part 2Using the case provided, build on Part .docx
IT Strategic Plan, Part 2Using the case provided, build on Part .docx
 
It seems most everything we buy these days has the label made in Ch.docx
It seems most everything we buy these days has the label made in Ch.docxIt seems most everything we buy these days has the label made in Ch.docx
It seems most everything we buy these days has the label made in Ch.docx
 

Recently uploaded

microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 

Recently uploaded (20)

microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 

F-35 JOINT STRIKE FIGHTER Assessment Needed to A.docx

  • 1. F-35 JOINT STRIKE FIGHTER Assessment Needed to Address Affordability Challenges Report to Congressional Committees April 2015 GAO-15-364 United States Government Accountability Office United States Government Accountability Office Highlights of GAO-15-364, a report to congressional committees
  • 2. April 2015 F-35 JOINT STRIKE FIGHTER Assessment Needed to Address Affordability Challenges Why GAO Did This Study With estimated acquisition costs of nearly $400 billion, the F-35 Lightning II—also known as the Joint Strike Fighter—is DOD's most costly and ambitious acquisition program. The U.S. portion of the program will require annual acquisition funding of $12.4 billion on average through 2038 to complete development and procure a total of 2,457 aircraft. GAO’s prior work has found that the program has experienced significant cost, schedule, and performance problems. In 2009, Congress mandated that GAO review the F-35 acquisition program annually for 6 years. This report, GAO's sixth, assesses the program's (1) development and testing progress, (2) cost and affordability, and (3) manufacturing and supply chain performance. GAO reviewed and analyzed the latest available manufacturing, cost, testing, and performance data through December 2014; program test plans;
  • 3. and internal DOD analyses; and interviewed DOD, program, engine and aircraft contractor officials. What GAO Recommends GAO recommends that DOD assess the affordability of F-35’s current procurement plan that reflects various assumptions about technical progress and future funding. What GAO Found The F-35 Joint Strike Fighter program had to make unexpected changes to its development and test plans over the last year, largely in response to a structural failure on a durability test aircraft, an engine failure, and software challenges. At the same time, engine reliability is poor and has a long way to go to meet program goals. With nearly 2 years and 40 percent of developmental testing to go, more technical problems are likely. Addressing new problems and improving engine reliability may require additional design changes and retrofits. Meanwhile, the Department of Defense (DOD) has plans to increase annual aircraft procurement from 38 to 90 over the next 5 years. As GAO has previously reported, increasing production while concurrently developing and testing creates risk and could result in additional cost growth and schedule delays in the future. Cost and affordability challenges remain. DOD plans to
  • 4. significantly increase annual F-35 funding from around $8 billion to nearly $12 billion over the next 5 years (see figure) reaching $14 billion in 2022 and remaining between $14 and $15 billion for nearly a decade. Over the last year, DOD reduced near-term aircraft procurement by 4 aircraft, largely due to budget constraints. While these deferrals may lower annual near-term funding needs, they will likely increase the cost of aircraft procured in that time frame and may increase funding liability in the future. It is unlikely the program will be able to sustain such a high level of annual funding and if required funding levels are not reached, the program’s procurement plan may not be affordable. DOD policy requires affordability analyses to inform long-term investment decisions. The consistent changes in F- 35 procurement plans indicate that DOD’s prior analyses did not adequately account for future technical and funding uncertainty. F-35 Joint Strike Fighter Budgeted Costs by Service, 2015-2019 Manufacturing progress continued despite mixed supplier performance. The aircraft contractor delivered 36 aircraft as planned in 2014, despite a fleet grounding, added inspections, and software delays. In contrast, the labor hours needed to manufacture an aircraft and the number of major design changes have
  • 5. continued to decline over time. Because supplier performance has been mixed, late aircraft and engine part deliveries could pose a risk to the program's plans to increase production. The contractors are taking steps to address these issues. View GAO-15-364. For more information, contact Michael J. Sullivan at (202) 512-4841 or [email protected] http://www.gao.gov/products/GAO-15-364� http://www.gao.gov/products/GAO-15-364� Page i GAO-15-364 F-35 Joint Strike Fighter Letter 1 Background 2 Recent Technical Challenges Will Likely Result in Cost Growth and Schedule Delays 8 Affordability Challenges Will Likely Continue to Affect Program Plans to Increase F-35 Procurement 14 While Manufacturing Progress Remains Steady, Planned Production Increases Could Be a Challenge 17 Conclusions 23 Recommendations 23 Agency Comments and Our Evaluation 23 Appendix I Prior GAO Reports on F-35 Joint Strike Fighter
  • 6. (JSF) and Department of Defense (DOD) Responses and Subsequent Actions 26 Appendix II Scope and Methodology 30 Appendix III DOD Comments 32 Appendix IV GAO Contact and Staff Acknowledgments 34 Related GAO Products 35 Table Table 1: Changes in Reported F-35 Joint Strike Fighter Program Cost, Quantity, and Deliveries, 2001-2014 5 Figures Figure 1: Changes in F-35 Joint Strike Fighter Near-Term Procurements 4 Figure 2: Subsequent Development of F-35 Joint Strike Fighter Software Blocks 7 Contents Page ii GAO-15-364 F-35 Joint Strike Fighter
  • 7. Figure 3: Measured Mean Flight Hours between Failure-(design controlled) for the F-35 Joint Strike Fighter Engine Only 12 Figure 4: Budgeted Development and Procurement Costs by Service, 2015-2038 15 Figure 5: Trend of F-35 Joint Strike Fighter Contractual Delivery Dates Compared to Actual Delivery Dates 18 Figure 6: Trend in Labor Hours to Build the F-35 Joint Strike Fighter Aircraft by Variant 19 Figure 7: Trend in Percent of Labor Hours Spent on Scrap, Rework, and Repair for the F-35 Joint Strike Fighter 20 Figure 8: Average Number of F-35 Joint Strike Fighter Part Shortage Occurrences at Prime Contractor Facility 21 This is a work of the U.S. government and is not subject to copyright protection in the United States. The published product may be reproduced and distributed in its entirety without further permission from GAO. However, because this work may contain copyrighted images or other material, permission from the copyright holder may be necessary if you wish to reproduce this material separately. Page 1 GAO-15-364 F-35 Joint Strike Fighter
  • 8. 441 G St. N.W. Washington, DC 20548 April 14, 2015 Congressional Committees With estimated acquisition costs of nearly $400 billion, the F- 35 Lightning II—also known as the Joint Strike Fighter—is the Department of Defense’s (DOD) most costly and ambitious acquisition program. Through this program, DOD is developing and fielding a family of next generation strike fighter aircraft, integrating low observable (stealth) technologies with advanced sensors and computer networking capabilities for the United States Air Force, Navy, and Marine Corps, as well as eight international partners.1 The F-35 family is comprised of the F- 35A conventional takeoff and landing variant, the F-35B short takeoff and vertical landing variant, and the F-35C carrier-suitable variant. According to current projections, the U.S. portion of the program will require acquisition funding of $12.4 billion a year, on average, through 2038 to complete development and procure a total of 2,457 aircraft. In addition, DOD and program office estimates indicate that the F-35 fleet could cost around $1 trillion to operate and support over its lifetime,
  • 9. which will pose significant affordability challenges. We have reported on F-35 issues for many years. Over time, we have reported significant cost, schedule, and performance problems and have found those problems, in part, can be traced to (1) decisions made at key junctures without adequate product knowledge and (2) a highly concurrent acquisition strategy with significant overlap among development, testing, and manufacturing activities. We have made numerous recommendations for improvement in our previous reports. DOD has taken action to address many of our recommendations to varying degrees.2 1The international partners are the United Kingdom, Italy, the Netherlands, Turkey, Canada, Australia, Denmark, and Norway. These nations contributed funds for system development and signed agreements to procure aircraft. In addition, Israel, Japan, and South Korea have signed on as foreign military sales customers. 2See app. I for a matrix of prior GAO reports, recommendations, and DOD actions. Letter
  • 10. Page 2 GAO-15-364 F-35 Joint Strike Fighter The National Defense Authorization Act for Fiscal Year 2010 requires GAO to review the F-35 acquisition program annually for 6 years.3 This is the sixth and final report under that mandate, and in this report we assess program (1) development and testing progress, (2) cost and affordability and (3) manufacturing and supply chain performance. To conduct our work, we reviewed and analyzed program briefings, management reports, test data and results, and internal DOD program analyses. We collected data on and discussed key aspects of F- 35 development and test progress with program management and contractor officials as well as DOD test officials and program test pilots. We collected and analyzed program acquisition cost estimates and reviewed total program funding requirements to project annual funding requirements through 2038. To assess the reliability of the cost data, we reviewed the supporting documentation and discussed the development of those estimates with DOD officials instrumental in producing them. We collected and analyzed production and supply chain performance data from DOD, Lockheed Martin, and Pratt & Whitney. We assessed the reliability of the data by reviewing supporting documentation
  • 11. and interviewing knowledgeable agency officials. We determined that all of the data we used were sufficiently reliable for the purposes of this report. We also discussed ongoing manufacturing process improvements with contracting and Defense Contract Management Agency officials. Appendix Il contains a more detailed description of our scope and methodology. We conducted this performance audit from July 2014 to April 2015 in accordance with generally accepted government auditing standards. Those standards required that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objectives. DOD began the F-35 acquisition program in October 2001 without adequate knowledge about the aircraft’s critical technologies or design. In addition, DOD’s acquisition strategy called for high levels of concurrency 3Pub. L. No. 111-84, § 244 (2009).
  • 12. Background Page 3 GAO-15-364 F-35 Joint Strike Fighter between development, testing, and production.4 In our prior work, we have identified the lack of knowledge and high levels of concurrency as major drivers in the significant cost and schedule growth as well as performance shortfalls that the program has experienced since 2001. The program has been restructured three times since it began: first in December 2003, again in March 2007, and most recently in March 2012. The most recent restructuring was initiated in early 2010 when the program’s unit cost estimates exceeded critical thresholds established by statute—a condition known as a Nunn-McCurdy breach.5 DOD subsequently certified to Congress in June 2010 that the program was essential to national security and needed to continue. DOD then began efforts to significantly restructure the program and establish a new acquisition program baseline. These restructuring efforts continued through 2011 and into 2012, during which time the department increased the program’s cost estimates, extended its testing and delivery
  • 13. schedules, and reduced near-term aircraft procurement quantities by deferring the procurement of 450 aircraft into the future—total procurement quantities did not change. Figure 1 shows how planned quantities in the near-term have steadily declined over time. 4Concurrency is broadly defined as the overlap between technology development and product development or between product development and production. 5Section 2433 of title 10 of the United States Code, commonly referred to as Nunn- McCurdy, requires DOD to notify Congress whenever a major defense acquisition program’s unit cost experiences cost growth that exceeds certain thresholds. This is commonly referred to as a Nunn-McCurdy breach. Significant breaches occur when the program acquisition unit cost or procurement unit cost increases by at least 15 percent over the current baseline estimate or at least 30 percent over the original estimate. For critical breaches, when these unit costs increase at least 25 percent over the current baseline estimate or at least 50 percent over the original, DOD is required to take additional steps, including conducting an in-depth review of the program. Programs with critical breaches must be terminated unless the Secretary of Defense certifies to certain facts related to the program and takes other actions, including restructuring the program.
  • 14. 10 U.S.C. § 2433a. Page 4 GAO-15-364 F-35 Joint Strike Fighter Figure 1: Changes in F-35 Joint Strike Fighter Near-Term Procurements The new F-35 acquisition program baseline was finalized in March 2012, and since that time costs have remained relatively stable. Table 1 shows the significant cost, quantity, and schedule changes from the initial program baseline and the relative stability since the new baseline was established. Page 5 GAO-15-364 F-35 Joint Strike Fighter
  • 15. Table 1: Changes in Reported F-35 Joint Strike Fighter Program Cost, Quantity, and Deliveries, 2001-2014 October 2001 Initial Baseline March 2012 Latest Baseline December 2014 Estimates Change from 2001 to 2012 Change from 2012 to 2014 Expected quantities (number of aircraft) Developmental quantities 14 14 14 0% 0% Procurement quantities 2,852 2,443 2,443 -14 0 Total quantities 2,866 2,457 2,457 -14 0 Cost estimates (then-year dollars in billions) a Development $34.4 $55.2 $54.9 60% -0.5% Procurement 196.6 335.7 331.6 71 -1.2 Military construction 2.0 4.8 4.6 140 -4.2 Total program acquisition 233.0 395.7 391.1 70 -1.2 Unit cost estimates (then-year dollars in millions) a Program acquisition $81 $161 $159 99% -1.2%
  • 16. Average procurement 69 137 136 99 -0.7 Estimated delivery and production dates Initial operational capability 2010-2012 Undetermined 2015- 2018 Undetermined 5-6 years Full-rate production 2012 2019 2019 7 years 0 years Source: GAO analysis of DOD data | GAO-15-364 a Annual projected cost estimates expressed in then-year dollars reflect inflation assumptions made by a program In March 2012, when the new acquisition program baseline was finalized, DOD had not yet identified new initial operating capability dates for the military services.6 The following year, DOD issued a memorandum stating that the Marine Corps and Air Force were planning to field initial operating capabilities in 2015 and 2016 respectively, and that the Navy planned to field its initial operating capability in 2018, which represented a delay of 5 to 6 years since the program’s initial baseline. DOD is currently conducting developmental flight testing to verify that the F-35 system’s design works as intended and can reliably provide the capabilities needed for the services to field their respective initial
  • 17. 6Initial operating capability is generally obtained when organizations or units have received a specified number of systems and have the ability to employ and maintain those systems. Page 6 GAO-15-364 F-35 Joint Strike Fighter operational capabilities. The program’s flight testing is separated into two key areas referred to as mission systems and flight sciences. Mission systems testing is done to verify that the software and systems that provide warfighting capabilities function properly and meet requirements, while flight science testing is done to verify the aircraft’s basic flying capabilities. For the F-35 program, DOD is developing and fielding mission systems capabilities in software blocks: (1) Block 1, (2) Block 2A, (3) Block 2B, (4) Block 3i, and (5) Block 3F. Each subsequent block builds on the capabilities of the preceding blocks. Blocks 1 and 2A are essentially complete. The program is now focused on completing Block 2B testing to support Marine Corps initial operating capability, but some testing of specific Block 3i and Block 3F capabilities is also being conducted. Blocks 2B and 3i will provide initial warfighting capabilities
  • 18. while Block 3F is expected to provide the full suite of warfighting capabilities. Figure 2 identifies the sequence of software blocks and capabilities expected to be delivered in each. Page 7 GAO-15-364 F-35 Joint Strike Fighter Figure 2: Subsequent Development of F-35 Joint Strike Fighter Software Blocks As developmental flight testing continues, DOD is concurrently purchasing and fielding aircraft. The F-35 airframe and engine are managed as one program, but they are manufactured in separate facilities by different contractors. The airframe is being manufactured by Lockheed Martin, the prime contractor, in Fort Worth, Texas, while the engine—which is designated the F135—is manufactured by Pratt & Whitney in Middletown, Connecticut. The engines are purchased by the government directly from Pratt & Whitney and delivered as government furnished equipment to Lockheed Martin for integration into the airframes during production. As a result, engine development and testing activities are managed by Pratt & Whitney and not Lockheed Martin.
  • 19. Page 8 GAO-15-364 F-35 Joint Strike Fighter The F-35 program continued to experience development and testing discoveries over the past year, largely due to a structural failure on the F- 35B durability test aircraft, an engine failure, and more mission system test growth than expected. Together, these factors led to adjustments in the program’s test schedule. Test resources and some aircraft capabilities were reprioritized, and test points were deferred or eliminated. While these actions mitigated some of the schedule risk, ultimately the completion of key developmental test activities had to be delayed. Decisions were also made to restructure an early operational test event that likely would have reduced operational risk for the Marine Corps. The event will now be conducted over time and will not be completed as originally scheduled. Instability in the development program is likely to continue with more complex and demanding development testing still to go. As the program continues to discover problems in development and testing, it also faces a significant challenge to improve the reliability of the engine. Program data show that the reliability of the engine is
  • 20. very poor (less than half of where it should be) and has limited the program’s progress toward its overall reliability targets. The engine contractor, Pratt & Whitney, has identified a number of design changes that it believes will help improve engine reliability, but some of those changes have not yet been implemented. With complex and challenging developmental testing remaining and engine reliability challenges ahead, DOD still plans to increase procurement rates by nearly threefold over the next 5 years. This same highly concurrent strategy has already proven to have negatively impacted the program. According to program reports, $1.7 billion could be incurred in costs associated with retrofits to already delivered aircraft. This cost will likely increase, as more aircraft are purchased and delivered before development ends. A significant structural failure on the F-35B durability test aircraft, an engine failure, and a higher than expected amount of test point growth largely to address software rework, over the past year, delayed key test activities and forced unexpected adjustments to the program’s development schedule and test plans. Each of these three factors is discussed in more detail below.
  • 21. • At around 9,000 hours of durability testing—about half of the 16,000 hours required—a major airframe segment, known as a bulkhead, on the F-35B durability test aircraft severed, and one other bulkhead was Recent Technical Challenges Will Likely Result in Cost Growth and Schedule Delays Test Failures and Software Challenges Forced Program Changes Page 9 GAO-15-364 F-35 Joint Strike Fighter fractured as a result.7 Durability testing on the F-35B was halted for more than a year as program officials conducted a root cause analysis and Lockheed Martin worked to repair the durability test aircraft. The root cause analysis determined that the bulkhead severed because its design did not take into account appropriate factors in the manufacturing processes, resulting in a bulkhead that had less durability life than expected. According to officials, the fracture in the other bulkhead was caused by the added weight it had to bear after the first bulkhead severed. Lockheed Martin is currently
  • 22. redesigning the bulkheads to strengthen the aluminum and plans to incorporate the updated designs into the ninth low-rate initial production lot. A total of 50 aircraft will have to be modified using additional structural reinforcement techniques. According to program and contractor officials, because the incident occurred halfway through durability testing, retrofits will not be required until the aircraft reach about half of their expected service life, or about 10 years. According to officials, the total costs of related modifications are yet to be determined at this time. • In June 2014, an F-35A engine caught fire during take-off. As a result, the entire F-35 fleet was grounded for nearly one month and then placed under flight restrictions for several additional months. A root cause analysis conducted by Pratt & Whitney determined that excessive heat caused by rubbing between engine fan components ultimately led to parts of the engine breaking free at a high rate of speed, resulting in a fire. The program could not execute any planned flight test points while the fleet was grounded. After flying resumed there were still hundreds of planned test points that could not be
  • 23. executed because the fleet was restricted from flying at the speeds and conducting the maneuvers necessary to execute those points. Despite these obstacles, the program was able to keep its test aircraft productive and accomplished some test points that had been planned to be done in the future. Follow-up inspections conducted by the contractor identified 22 engines with evidence of overheating. Officials have identified a short-term fix that they believe will allow the fleet to return to normal flight test operations. As of January 31, 2015, 18 of 22 engines had received the short-term fix and were cleared to return 7The F-35B is the only aircraft affected as its bulkhead is made of aluminum material. The other F-35 variants have titanium bulkheads that are not as vulnerable to these cracks. Page 10 GAO-15-364 F-35 Joint Strike Fighter to normal flight operations. Pratt & Whitney has identified several potential long-term fixes but no final determination has been made. • While the program’s test plan for 2014 reflected an allowance
  • 24. of 45 percent growth in mission system software test points for the year— largely to address software rework that might be needed— officials from the Office of the Secretary of Defense noted that the program experienced around 90 percent growth, or nearly twice the planned amount. As of January 2015, 56 percent of the Block 2B functionality had been verified by program officials, which was about 10 percent short of its goal. According to DOD and contractor officials, the higher than anticipated amount of rework was largely due to the fact that portions of the Block 2B software did not function as expected during flight testing. To address these deficiencies, changes were made to the software and this extended the Block 2B test schedule by approximately 3 months. As of January 2015, all of the updated software was in flight testing. DOD continued to address other key technical risks that we have highlighted in the past including the Helmet Mounted Display, Arresting Hook System, and the Autonomic Logistics Information System (ALIS).8 A new helmet design was developed and integrated that includes previously developed updates and addresses shortfalls in night vision capability.
  • 25. Test pilots we spoke with noted that while testing of the new helmet design has just begun, some improvements over the previous design are evident, but more testing is needed. A redesigned Arresting Hook System was also integrated on the aircraft. While sea trial testing of the redesigned system was slightly delayed, the testing took place in November 2014 and the system performed very well with a 100 percent arrestment rate. Lastly, program officials began testing a more capable version of ALIS in September 2014 and expect to begin testing a deployable version in February 2015. Although DOD plans to release the deployable version in time for Marine Corps initial operational capability, it faces tight timeframes. A portion of the system’s capabilities, Prognostics Health Management downlink, has been deferred to follow-on development. 8GAO-14-322 http://www.gao.gov/products/GAO-14-322� Page 11 GAO-15-364 F-35 Joint Strike Fighter In response to the challenges faced in 2014, program officials reprioritized test resources and aircraft capabilities, deferred or
  • 26. eliminated test points, and ultimately delayed completion of some developmental test activities. Personnel and facilities that had been dedicated to developing and testing Block 3i and Block 3F—software blocks required by the Air Force and the Navy to field initial operational capabilities in 2016 and 2018 respectively—were reassigned to focus on delivering Block 2B to support the Marine Corps’ initial operational capability in 2015. In addition, program officials eliminated over 1,500 test points from the overall Block 2B developmental test plan, and deferred some Block 2B capabilities. According to program officials, they chose to delay some test points that had been scheduled to be accomplished in 2014, and accomplish other test points that they had scheduled to be done in the future. In addition, program officials, in conjunction with officials from the Director, Operational Test and Evaluation, restructured a Block 2B early operational test event that had been planned for 2015. The restructured event will now be conducted over time as resources allow but will not be completed as originally scheduled. While these changes allowed the program to accomplish nearly the same number of test points it had planned for the year, officials stated that not all of the specific test
  • 27. activities scheduled were completed. In the end, the completion of Block 2B developmental testing is 3 months behind schedule, Block 3i testing is about 3 months behind schedule, and Block 3F could be as much as 6 months behind schedule. The program has a long way to go to achieve its engine reliability goals. Reliability is a function of how well a system design performs over a specified period of time without failure, degradation, or need of repair. During system acquisition, reliability growth should occur over time through a process of testing, analyzing, and fixing deficiencies through design changes or manufacturing process improvements. Once fielded, there are limited opportunities to improve a system’s reliability without additional cost increases and schedule delays. Currently, the F- 35 engine’s reliability is very poor and overall aircraft reliability growth has been limited. Improving engine reliability will likely require additional design changes and retrofits. Need to Improve Engine Reliability Presents Additional Challenges
  • 28. Page 12 GAO-15-364 F-35 Joint Strike Fighter The program uses various measures to track and improve reliability, including the mean flying hours between failures (design controlled).9 Data provided by Pratt & Whitney indicate that the mean flight hours between failure for the F-35A engine is about 21 percent of where the engine was expected to be at this point in the program. The F- 35B engine is about 52 percent of where the engine was expected to be at this point. This means that the engine is failing at a much greater rate and requiring more maintenance than expected. Pratt & Whitney has identified a number of design changes that officials believe will improve the engine’s reliability and is in the process of incorporating some of those changes into the engine design, production, and retrofitted to already built aircraft; however, other design changes that Pratt & Whitney officials believe are needed, such as changes to engine hoses and sensors, are not currently funded. Figure 3 shows the trend in the engine’s mean flight hours between failures (design controlled). Figure 3: Measured Mean Flight Hours between Failure-(design controlled) for the F-35 Joint Strike Fighter Engine Only
  • 29. 9This specific metric tracks failures that are directly attributed to design and are considered fixable with design changes. Page 13 GAO-15-364 F-35 Joint Strike Fighter Poor engine reliability has limited the F-35’s overall reliability progress. The overall reliability of the aircraft, which includes engine reliability data, has been improving over the past year. Contractor officials attribute the improvements in reliability to having an increasing number of aircraft in flight operations that have received design changes to address previously identified problems. For example, design changes in the way certain metal plates—known as nut plates—are bonded to the aircraft, and changes to fix problems with contamination of the On-board Oxygen Generating System have been incorporated into 62 aircraft that were delivered and began flying throughout 2013 and 2014. While overall reliability has increased, engine reliability over the last year has remained well below expected levels. Improving the F-35 engine reliability to
  • 30. achieve established goals will likely require more time and resources than originally planned. In addition, in September 2014, we reported problems with the F-35 software reliability and maintainability. Specifically, we reported that the program continues to experience both hardware and software reliability issues, but DOD had no processes or metrics that provide sufficient insight into the impact of software reliability and maintainability contributing to the overall aircraft reliability. We recommended that DOD develop a software reliability and maintainability assessment process with metrics, and DOD concurred with this recommendation.10 While DOD has taken steps over the past few years to reduce concurrency, the program’s strategy still contains a noteworthy overlap between the completion of flight testing and the increase in aircraft procurement rates. With about 2 years and 40 percent of the developmental test program remaining and significant engine reliability growth needed, DOD plans to continue increasing procurement rates. Over the next 5 years, procurement will increase from 38 aircraft per year to 90 aircraft per year, and by the time developmental testing is finished— currently expected to occur in 2017—DOD expects to have
  • 31. purchased a cumulative total of 340 aircraft. During this time, there are plans to conduct testing to prove that the F-35 can provide full warfighting capabilities—Block 3F—needed to perform in more demanding and 10GAO- F-35 Sustainment: Need for Affordable Strategy, Greater Attention to Risks, and Improved Cost Estimates, GAO-14-778 (Washington, D.C.: September 23, 2014). Unexpected Technical Issues and Ongoing Reliability Challenges Amplify Concurrency Risk http://www.gao.gov/products/GAO-%20F-35� http://www.gao.gov/products/GAO-14-778� Page 14 GAO-15-364 F-35 Joint Strike Fighter stressing environments. In addition, DOD plans to complete operational testing in early 2019 and at that time will have procured 518 aircraft or 21 percent of its total planned procurement quantities. At the same time, efforts will be ongoing to improve F-35 engine reliability. As of June 2014, DOD estimated that at that point about $1.7 billion in
  • 32. funding was needed to rework and retrofit aircraft with design changes needed as a result of test discoveries. This concurrency cost estimate does not include any costs related to the most recent failures. According to DOD officials, the estimate takes into account some unexpected costs and they believe that the estimate will not exceed $1.7 billion. However, with more complex and demanding testing ahead and engine reliability improvements needed, it is almost certain that the program will encounter more discoveries. Depending on the nature and significance of the discoveries, the program may need additional time and money, beyond the current $1.7 billion estimate, to incorporate design changes and retrofit aircraft at the same time that it increases procurement. As of December 2014, the program office estimated that the total acquisition cost of the F-35 will be $391.1 billion, or $7.4 billion less than DOD reported in December 2013. Our analysis indicates that the program will require an average of $12.4 billion per year, which represents around one-quarter of DOD’s annual funding for major defense acquisition programs over the next 5 years. From fiscal years 2015 to 2019, DOD plans to increase annual development and procurement funding
  • 33. for the F- 35 from around $8 billion to around $12 billion, an investment of more than $54 billion over that 5-year period, while competing with other large programs for limited acquisition resources. This funding reflects the U. S. military services’ plans to significantly increase annual aircraft procurement buys from 38 in 2015 to 90 in 2019. International partners will also increase procurement buys during this time, and the combined purchases will peak at 179 aircraft in 2021, with the United States purchasing 100 aircraft and the international partners purchasing an additional 79 aircraft. DOD projects that the program’s acquisition funding needs will increase to around $14 billion in 2022. Funding needs will remain between $14 and $15 billion for nearly a decade and peak at $15.1 billion in 2029 (see figure 4). Given resource limitations and the funding needs of other major acquisition programs such as the KC-46A tanker, the DDG-51 Class Destroyer, the Ohio Class submarine replacement, and a long-range strike bomber, in addition to the high estimated costs of sustaining the fleet over the next several years, we Affordability Challenges Will Likely Continue to Affect Program Plans to
  • 34. Increase F-35 Procurement Page 15 GAO-15-364 F-35 Joint Strike Fighter believe funding of this magnitude will pose significant affordability challenges. Figure 4: Budgeted Development and Procurement Costs by Service, 2015-2038 Note: Annual projected cost estimates expressed in then-year dollars reflect inflation assumptions made by a program. Since the 2012 re-baselining, DOD has made changes to its F-35 procurement plans on an annual basis. In 2013, DOD reduced the number of aircraft that it planned to purchase between 2015 and 2019 by 37 aircraft and extended the procurement timeline by one year. In 2014, DOD deferred the purchase of 4 more aircraft over that same timeframe. DOD officials attribute this decision to affordability concerns due to budget constraints, among other factors. Although this action may reduce near-term funding requirements as well as concurrency risks, it will likely
  • 35. increase the average unit cost of the aircraft purchased over that time and may increase funding liability in the future. DOD policy requires Page 16 GAO-15-364 F-35 Joint Strike Fighter affordability analyses to inform long-term investment decisions.11 The consistent changes in F-35 procurement plans, made during the annual DOD budget process, indicate that the analysis done to support the program’s 2012 baseline did not accurately account for future technical risks or funding realities. Changes in procurement plans are also impacted by adjustments to military service and DOD priorities. Program office data indicates that after accounting for quantity changes, the program is unlikely to achieve the affordability unit cost targets set by the Under Secretary of Defense for Acquisition, Technology, and Logistics in 2012.12 The aircraft deferrals will also reduce the number of F- 35s fielded over the next several years, which could force the military services to invest in extending the life of their current aircraft fighter fleets, including the Air Force A-10 Thunderbolt II and the Navy F/A- 18 Hornet. We believe maintaining the level of sustained funding required
  • 36. to build an F-35 fleet in addition to incurring costs to extend the life of current aircraft will be difficult in a period of austere defense budgets. Officials from the Office of Secretary of Defense have stated that the current sustainment strategy is not affordable. Both the program office and the Cost Assessment and Program Evaluation (CAPE) office, within the Office of the Secretary of Defense, estimate sustainment costs will be about $1 trillion over the life of the F-35 fleet. Since 2012, CAPE’s sustainment cost estimate has decreased by nearly $100 billion. CAPE attributes the bulk of this decrease to updated cost estimating ground rules and assumptions related to the cost of spare parts, labor rates, and fuel efficiency. The program office has also issued a separate sustainment cost estimate of approximately $859 billion, which is $57.8 billion less than it estimated last year. The CAPE and program estimates differ primarily in assumptions about reliability, depot maintenance, personnel, and fuel consumption. However, as we reported in September 2014, the current estimates are still higher than the current operation and support costs of the existing aircraft the F-35 is expected to replace, and
  • 37. 11Department of Defense Instruction 5000.02, Operation of the Defense Acquisition System Encl. 8, para. 2 (Jan. 7, 2015). 12These targets are based upon planning assumptions reflected in the FY 2013 President’s Budget and the 2011 projection for international partner procurement. If there are subsequent changes to either the United States or international partner procurement quantities, the program will isolate the effect that this has on the targets as a factor that is not within its control. Page 17 GAO-15-364 F-35 Joint Strike Fighter according to officials from the Office of Secretary of Defense, remain unaffordable. In addition, we reported that DOD’s sustainment cost estimates may not reflect the most likely costs that the F-35 program will incur.13 While the F-35 program office and contractors have initiatives underway to improve affordability, those initiatives have a specific focus on reducing procurement and sustainment costs but do not assess the affordability of the program’s overall procurement plan within budget constraints. These initiatives include the “War on Cost,” “Cost War Room,” and “Blueprint for
  • 38. Affordability” that are intended to identify ways to reduce procurement and sustainment costs of the aircraft and engine. The initiatives are still ongoing and the total cost savings related to these initiatives is yet to be determined. As Lockheed Martin continues to deliver more aircraft, the number of hours needed to build each aircraft has declined and efficiency rates have improved despite increases in the time spent on scrap, rework, and repairs. Supplier performance has been mixed as late deliveries have resulted in increases to part shortages. Supplier quality defects have also increased while scrap, rework, and repair attributable to suppliers have remained steady. Pratt & Whitney is experiencing problems with quality and late deliveries from its suppliers. The number of aircraft produced in the Lockheed Martin’s final assembly facility has remained relatively stable over the last 3 years. The contractor has delivered a total of 110 aircraft since 2011—9 in 2011, 30 in 2012, 35 in 2013, and 36 in 2014. None of the aircraft delivered currently possess initial warfighting capability and are being used primarily for training
  • 39. purposes. As a result, delivered aircraft will have to be retrofitted with 2B initial warfighting capabilities prior to becoming operational. Although aircraft continued to be delivered later than contracted delivery dates— averaging 3.6 months late in 2014—Lockheed Martin officials believe they are closing the gap and expect to begin delivering to contract dates in 2015. Figure 5 shows actual aircraft deliveries compared to contracted 13For a full discussion of GAO’s previous analysis of the F-35 estimated sustainment costs and our recommendations, please see GAO- 14-778. While Manufacturing Progress Remains Steady, Planned Production Increases Could Be a Challenge Manufacturing Efficiency Remains Steady Page 18 GAO-15-364 F-35 Joint Strike Fighter delivery dates over the last 2 years. In 2014, Lockheed Martin achieved its goal of delivering 36 aircraft despite multiple setbacks throughout the
  • 40. year, such as late software deliveries, a fleet grounding, and increased engine inspections. Figure 5: Trend of F-35 Joint Strike Fighter Contractual Delivery Dates Compared to Actual Delivery Dates Note: This figure includes deliveries to the United States and all foreign partners. As Lockheed Martin produces more aircraft and learns more about its manufacturing processes, it continues to reduce the number of labor hours needed to manufacture aircraft. The reduction in labor hours remained relatively steady over the last year; however, in the case of the F-35B, labor hours briefly trended upward. Officials stated that a gap in production of the F-35B variant between lots four and six and part shortages drove the increased labor hours. The number of labor hours to produce the last F-35B delivered in 2014 was lower than previous aircraft, and officials believe labor hours will continue to decrease as production quantities for the F-35B increase. Figure 6 identifies the trend in reduction of labor hours per aircraft since the beginning of low-rate initial production.
  • 41. Page 19 GAO-15-364 F-35 Joint Strike Fighter Figure 6: Trend in Labor Hours to Build the F-35 Joint Strike Fighter Aircraft by Variant Note: Labor hour data only represents aircraft built start to finish at Lockheed Martin’s facility. Data includes aircraft delivered to foreign partners. The number of major engineering design changes has also continued to decline over time, and is currently tracking to the program’s plan. The reduction in labor hours and engineering design changes over time has allowed Lockheed Martin to increase manufacturing efficiency rates as measured by the hours it takes to complete certain production tasks compared to the number of hours established by engineering standards. The efficiency rate increased from about 16 to about 20 percent over the last year, nearly achieving Lockheed Martin’s goal of about 22 percent. Labor hours and efficiency rates improved despite increases in time spent on scrap, rework, and repair over the last year. The time spent on scrap, rework, and repair increased from 13.8 percent in production lot four to
  • 42. 14.9 percent in production lot five, falling short of Lockheed Martin’s goal of 12.8 percent. At 14.9 percent, Lockheed Martin’s scrap, rework, and repair rates are nearly equal to percentages experienced in the third production lot. According to Lockheed Martin officials, a majority of the scrap, rework, and repair hours are associated with fixing mislocated brackets and mismatched seams. Figure 7 shows the trend in percent of labor hours spent on scrap, rework, and repair along with the goal for the Page 20 GAO-15-364 F-35 Joint Strike Fighter fifth production lot. If these trends continue, Lockheed Martin could have difficulty improving its manufacturing efficiency at its expected rates. Figure 7: Trend in Percent of Labor Hours Spent on Scrap, Rework, and Repair for the F-35 Joint Strike Fighter Lockheed Martin reports that less than 40 percent of its critical manufacturing processes are considered in statistical control which means that for those processes it can consistently produce parts within quality tolerances and standards. Statistical control is a measure
  • 43. of manufacturing maturity. The best practice standard is to have 100 percent of the critical manufacturing processes in control by the start of low-rate initial production, which began in 2011 for the F-35 program. According to Lockheed Martin officials, only 54 percent of its F-35 critical manufacturing processes will provide enough data to measure statistical control. As a result, they do not expect to achieve 100 percent. Page 21 GAO-15-364 F-35 Joint Strike Fighter Suppliers continue to deliver late parts to Lockheed Martin resulting in part shortages. Since 2013, the average number of part shortage occurrences at Lockheed Martin’s facility has increased. The severity of part shortages is measured in five categories, category 1 being the least severe, and category 4 and above being the most severe with those shortages requiring a major workaround or work stoppage.14 Figure 8 identifies changes in the average number of part shortage occurrences at Lockheed Martin’s facility over the last year. Figure 8: Average Number of F-35 Joint Strike Fighter Part Shortage Occurrences at
  • 44. Prime Contractor Facility According to Lockheed Martin officials, suppliers are delivering late parts for several reasons. Those reasons include the need for suppliers to fix faulty parts and the inability of some suppliers to handle large amounts of throughput. In addition, Lockheed Martin officials stated that some delays are a result of late request for proposals, late responses to those proposals, and delayed contract negotiations with the government that result in late contract awards. Officials do not expect to begin making authorizations with appropriate lead time until the end of low- rate initial production in 2019. Part shortages will likely remain problematic and could be amplified as production rates increase over the next 5 years. Supplier quality at Lockheed Martin has been mixed. Lockheed Martin uses a reactive approach to managing most of its supplier base because, 14The severity of part shortages is measured in categories by Lockheed Martin. Category 1: the part is late to on-dock requirement date. Category 2: the part is late to the material kit start date of the kit build. Category 3: the part is late to the date when production needs the kit on the manufacturing floor. Category 4: the part is late
  • 45. to the extent that it has become sequence critical, meaning other work may be limited while waiting for the part. A major workaround is required or production may not proceed to the next work station. Category 4 and above: the part is late to the extent that work on the production floor is stopped and there is no workaround. Late Deliveries from Suppliers Continue, and Could Challenge Planned Production Increases Page 22 GAO-15-364 F-35 Joint Strike Fighter according to officials, they do not have access to supplier specific manufacturing data. The company uses internal metrics to track supplier performance such as the number of quality defects—known as non- conformances—discovered at the Lockheed Martin facility and the amount of scrap, rework, and repair driven by poor supplier performance. Over the last year, the number of supplier related non- conformances has slightly increased and Lockheed Martin continues to experience supplier related non-conformances for things like hole-drilling and bracket placement, among others. Lockheed Martin officials identified
  • 46. 22 of their more than 1,500 suppliers that contributed to 75 percent of the non- conformances. In order to address these non-conformances, Lockheed Martin developed a management team aimed at improving quality management at those suppliers. Lockheed Martin reported a 58 percent improvement in non-conformances for those suppliers over the last year, which it attributes to the work of its team. For example, the key supplier of the aircraft weapons bay door experienced quality problems in 2013. Over the last year, Lockheed Martin sent more personnel to the supplier’s facility to work with the supplier’s management team to identify problems in their production processes and solutions to those problems. As a result, the supplier adjusted its tooling and modified its quality management techniques, and the number of defects and part shortages from that supplier decreased. In addition, the percent of time spent on scrap, rework, and repair for supplied parts has remained steady. Supplier deliveries requiring scrap, rework, and repair averaged 1.3 percent of the hours spent building an aircraft over the last 2 years. Pratt & Whitney is also experiencing challenges with part shortages and supplier quality. Nearly 45 percent of Pratt & Whitney’s key
  • 47. suppliers have delivered late parts over the past year. In order to mitigate some of the risk, Pratt & Whitney has pulled or borrowed some parts meant for spare engines to use in place of the late parts. According to Pratt & Whitney officials, they have taken steps to reduce the number of parts that are borrowed; however, the number of borrowed parts remains high, which could lead to further part shortages and late engine deliveries if production rates increase over the next several years as planned. In addition, in 2014, poor supplier quality negatively impacted engine performance. For example, improper lubrication of an oil valve adapter by the valve supplier resulted in an in-flight emergency in June 2014. As a result, the oil valves on 136 F-35 aircraft—28 of which were in production and 108 of which were delivered—had to be removed and replaced. According to Pratt & Whitney officials, the associated retrofit costs were borne by the valve supplier. The supplier also made changes to its procedures to prevent future incidents. Page 23 GAO-15-364 F-35 Joint Strike Fighter
  • 48. The F-35 remains DOD’s most costly and ambitious programs and one of its highest priority acquisition programs. The program began with an acquisition strategy that called for high levels of concurrency between developmental testing and aircraft procurement. Since then, however, the program has experienced significant technical problems that have resulted in schedule delays and additional unplanned, or latent, concurrency. With more than 100 production aircraft delivered as of December 2014, the program continues to encounter significant technical problems like the engine and bulkhead failures that require design changes. Programs in developmental testing are expected to encounter technical problems that require design changes. However, in a concurrent acquisition environment, the destabilizing effects of design changes are amplified as more systems are produced and delivered, thus requiring costly retrofits, and rework. With around 40 percent of developmental testing remaining, additional unanticipated changes are likely as much of that testing will be very challenging. At the same time, DOD plans to steeply increase its procurement funding requests over the next 5 years and projects that it will need between $14 and $15 billion annually for nearly a decade. It is unlikely that the program will be able to
  • 49. receive and sustain such a high and unprecedented level of funding over this extended period, especially with other significant fiscal demands weighing on the nation. This poses significant affordability challenges to DOD as other costly, high priority acquisition efforts, including the KC- 46A Tanker and the DDG 51 Class Destroyer, compete for limited resources at the same time. DOD continues to adjust its F-35 procurement plans on an annual basis. This reactionary approach indicates that DOD may not be accurately accounting for the future technical and funding uncertainty it faces, and thus may not fully understand the affordability implications of increasing F-35 procurement funding at the planned rates. As DOD plans to significantly increase F-35 procurement funding over the next 5 years, we recommend that the Secretary of Defense conduct an affordability analysis of the program’s current procurement plan that reflects various assumptions about future technical progress and funding availability. We provided a draft of this report to DOD for comment. In its written comments, which are reprinted in appendix III, DOD concurred with our
  • 50. recommendation. DOD also provided technical comments which we incorporated as appropriate. Conclusions Recommendations Agency Comments and Our Evaluation Page 24 GAO-15-364 F-35 Joint Strike Fighter We are sending copies of this report to appropriate congressional committees; the Secretary of Defense; the Secretaries of the Air Force, Army, and Navy; the Commandant of the Marine Corps; and the Director of the Office of Management and Budget. The report is available at no charge on the GAO website at http://www.gao.gov. If you or your staff have any questions about this report, please contact me at (202) 512-4841 or [email protected] Contact points for our Offices of Congressional Relations and Public Affairs may be found on the last page of this report. Staff members making key contributions to this report are listed in Appendix IV.
  • 51. Michael J. Sullivan Director Acquisition and Sourcing Management http://www.gao.gov/� mailto:[email protected]� Page 25 GAO-15-364 F-35 Joint Strike Fighter List of Committees The Honorable John McCain Chairman The Honorable Jack Reed Ranking Member Committee on Armed Services United States Senate The Honorable Thad Cochran Chairman The Honorable Richard J. Durbin Ranking Member Subcommittee on Defense Committee on Appropriations United States Senate The Honorable Mac Thornberry Chairman The Honorable Adam Smith Ranking Member
  • 52. Committee on Armed Services House of Representatives The Honorable Rodney Frelinghuysen Chairman The Honorable Pete Visclosky Ranking Member Subcommittee on Defense Committee on Appropriations House of Representatives Appendix I: Prior GAO Reports on F-35 Joint Strike Fighter (JSF) and Department of Defense (DOD) Responses and Subsequent Actions Page 26 GAO-15-364 F-35 Joint Strike Fighter GAO report Estimated Development Costs Development Length Aircraft unit cost Key program event
  • 53. Primary GAO Conclusion/Recommendation DOD response and actions 2001 GAO-02-39 $34.4 Billion 10 years $69 Million Start of system development and demonstration approved. Critical technologies needed for key aircraft performance elements are not mature. Program should delay start of system development until critical technologies are mature to acceptable levels. DOD did not delay start of system development and demonstration, stating technologies were at acceptable maturity levels and stated it would manage risks in development. 2005 GAO-05-271 $44.8 Billion 12 years $82 Million
  • 54. The program underwent a re-plan to address higher than expected design weight, which added $7 billion and 18 months to development schedule. We recommended that the DOD reduce risks and establish an executable business case that is knowledge-based with an evolutionary acquisition strategy. DOD partially concurred but did not adjust strategy, believing that its approach was balanced between cost, schedule, and technical risk. 2006 GAO-06-356 $45.7 Billion 12 years $86 Million Program set in motion a plan to enter production in 2007 shortly after first flight of the non- production representative aircraft. The program was entering production with less than 1 percent of testing complete. We
  • 55. recommended that DOD delay investing in production until flight testing shows that JSF performs as expected. DOD partially concurred but did not delay start of production because it believed the risk level was appropriate. 2007 GAO-07-360 $44.5 Billion 12 years $104 Million Congress reduced funding for first two low- rate production buys thereby slowing the ramp up of production. Progress was being made but concerns remained about undue overlap in testing and production. We recommended limits to annual production quantities to 24 a year until flying quantities were demonstrated. DOD non-concurred and felt that the program had an acceptable level of concurrency and an
  • 56. appropriate acquisition strategy. 2008 GAO-08-388 $44.2 Billion 12 years $104 Million DOD implemented a Mid- Course Risk Reduction Plan to replenish management reserves from about $400 million to about $1 billion by reducing test resources. We found the new plan increased risks and recommended that DOD should revise the plan to address concerns about testing, management reserves, and manufacturing. We determined that the cost estimate was not reliable and that a new cost estimate and schedule risk assessment was needed. DOD did not revise risk plan or restore testing resources, stating that it will monitor the new plan and adjust it if necessary. Consistent with one of our recommendations, a new
  • 57. cost estimate was prepared, but DOD did not conduct a risk and uncertainty analysis. GAO report Estimated Development Costs Development Length Aircraft unit cost Key program event Primary GAO Conclusion/Recommendation DOD response and actions Appendix I: Prior GAO Reports on F-35 Joint Strike Fighter (JSF) and Department of Defense (DOD) Responses and Subsequent Actions http://www.gao.gov/products/GAO-02-39� http://www.gao.gov/products/GAO-05-271� http://www.gao.gov/products/GAO-06-356� http://www.gao.gov/products/GAO-07-360� http://www.gao.gov/products/GAO-08-388� Appendix I: Prior GAO Reports on F-35 Joint Strike Fighter (JSF) and Department of Defense (DOD) Responses and Subsequent Actions
  • 58. Page 27 GAO-15-364 F-35 Joint Strike Fighter GAO report Estimated Development Costs Development Length Aircraft unit cost Key program event Primary GAO Conclusion/Recommendation DOD response and actions 2009 GAO-09-303 $44.4 Billion 13 years $104 Million The program increased the cost estimate and added a year to development but accelerated the production ramp up. Independent DOD cost estimate (JET I) projects even higher costs and further delays. Moving forward with an accelerated procurement plan and use of cost reimbursement contracts is very risky. We
  • 59. recommended the program report on the risks and mitigation strategy for this approach. DOD agreed to report its contracting strategy and plans to Congress and conduct a schedule risk analysis. The program reported completing the first schedule risk assessment with plans to update semi- annually. The Department announced a major program restructure, reducing procurement and moving to fixed-price contracts. 2010 GAO-10-382 $49.3 Billion 15 years $112 Million The program was restructured to reflect findings of recent independent cost team (JET II) and independent manufacturing review team. As a result, development funds increased, test aircraft were added, the schedule was extended, and the
  • 60. early production rate decreased. Costs and schedule delays inhibited the program’s ability to meet needs on time. We recommended the program complete a full comprehensive cost estimate and assess warfighter and initial operating capability requirements. We suggested that Congress require DOD to tie annual procurement requests to demonstrated progress. DOD continued restructuring, increasing test resources and lowering the production rate. Independent review teams evaluated aircraft and engine manufacturing processes. Cost increases later resulted in a Nunn-McCurdy breach. Military services are currently reviewing capability requirements as we recommended. 2011 GAO-11-325 $51.8 Billion 16 years $133 Million
  • 61. Restructuring continued with additional development cost increases; schedule growth; further reduction in near-term procurement quantities; and decreased the rate for future production. The Secretary of Defense placed the Short-takeoff Vertical Landing (STOVL) variant on a two-year probation; decoupled STOVL from the other variants; and reduced STOVL production plans for fiscal years 2011 to 2013. The restructuring actions were positive and if implemented properly should lead to more achievable and predictable outcomes. Concurrency of development, test, and production was substantial and provided risk to the program. We recommended the DOD maintain funding levels as budgeted; establish criteria for STOVL probation; and conduct an independent review of software development, integration, and test processes. DOD concurred with all three
  • 62. of the recommendations. DOD lifted STOVL probation citing improved performance. Subsequently, DOD further reduced procurement quantities, decreasing funding requirements through 2016. The initial independent software assessment began and ongoing reviews were planned to continue through 2012. http://www.gao.gov/products/GAO-09-303� http://www.gao.gov/products/GAO-10-382� http://www.gao.gov/products/GAO-11-325� Appendix I: Prior GAO Reports on F-35 Joint Strike Fighter (JSF) and Department of Defense (DOD) Responses and Subsequent Actions Page 28 GAO-15-364 F-35 Joint Strike Fighter GAO report Estimated Development Costs Development
  • 63. Length Aircraft unit cost Key program event Primary GAO Conclusion/Recommendation DOD response and actions 2012 GAO-12-437 $55.2 Billion 18 years $137 Million The program established a new acquisition program baseline and approved the continuation of system development, increasing costs for development and procurements and extending the period of planned procurements by 2 years. Extensive restructuring placed the program on a more achievable course. Most of the program’s instability continued to be concurrency of development, test, and production. We recommended the Cost Assessment Program Evaluation office conduct an analysis on the impact of lower annual funding levels; and the program office conduct an assessment of the supply chain
  • 64. and transportation network. DOD partially concurred with conducting an analysis on the impact of lower annual funding levels and concurred with assessing the supply chain and transportation network. 2013 GAO-13-309 $55.2 Billion 18 years $137 Million The program continued to move forward following a new acquisition program baseline in 2012. In doing so, the program incorporated positive and more realistic restructuring actions taken since 2010 including more time and funding for development and deferred procurement of more than 400 aircraft to future years. The program was moving in the right direction but must fully
  • 65. validate design and operational performance and at the same time make the system affordable. We did not make recommendations to DOD in this report. DOD agreed with GAO’s observations. 2014 GAO-14-322 $55.2 Billion 18 years $135 Million The services established initial operational capabilities dates in 2013. The Marine Corps and Air Force are planning to field initial operational capabilities in 2015 and 2016, respectively, and the Navy plans to field its initial capability in 2018. Delays in developmental flight testing of the F-35’s critical software may hinder delivery of the warfighting capabilities the military services. We recommended DOD conduct an assessment of the specific
  • 66. capabilities that can be delivered and those that will not likely be delivered to each of the services by their established initial operational capability dates DOD concurred with our recommendation and is in the process of conducting the assessment. http://www.gao.gov/products/GAO-12-437� http://www.gao.gov/products/GAO-13-309� http://www.gao.gov/products/GAO-14-322� Appendix I: Prior GAO Reports on F-35 Joint Strike Fighter (JSF) and Department of Defense (DOD) Responses and Subsequent Actions Page 29 GAO-15-364 F-35 Joint Strike Fighter GAO report Estimated Development Costs Development Length Aircraft unit cost Key program event
  • 67. Primary GAO Conclusion/Recommendation DOD response and actions 2014 GAO-14-778 Not reported The Department of Defense (DOD) currently has or is developing several plans and analyses that will make up its overall F-35 sustainment strategy, which is expected to be complete in fiscal year 2019. The annual F-35 operating and support costs are estimated to be considerably higher than the combined annual costs of several legacy aircraft. DOD had not fully addressed several issues that have an effect on affordability and operational readiness. Operating and support cost estimates may not be reliable. We recommended that DOD develop better informed affordability constraints; address three risks that could affect sustainment, affordability, and operational readiness; and take steps to improve the reliability of its cost estimates. DOD concurred with all but
  • 68. one recommendation and partially concurred with the recommendation to conduct uncertainty analysis on one of its cost estimates, stating it already conducts a form of uncertainty analysis. GAO continues to believe that the recommended analysis would provide a more comprehensive sense of the uncertainty in the estimates. Source: GAO http://www.gao.gov/products/GAO-14-778� Appendix II: Scope and Methodology Page 30 GAO-15-364 F-35 Joint Strike Fighter To assess the program’s ongoing development and testing we reviewed the status of software development and integration and contractor management improvement initiatives. We also interviewed officials from the program office, Lockheed Martin, Pratt & Whitney, and the Defense Contract Management Agency (DCMA) to discuss current development
  • 69. status and software releases. In addition, we compared management objectives to progress made on these objectives during the year. We obtained and analyzed data on flights and test points, both planned and accomplished during 2014. We compared test progress against the total program plans to complete. In addition, we interviewed officials from the F-35 program office, Lockheed Martin, Pratt & Whitney, and Director, Operational Test and Evaluation office to discuss development test plans and achievements. We also collected information from the program office, prime contractor, engine contractor, and Department of Defense test pilots regarding the program’s technical risks including the helmet mounted display, autonomic logistics information system, carrier arresting hook, structural durability, and engine. We analyzed reliability data and discussed these issues with program and contractor officials. To assess the program’s cost and affordability, we reviewed financial management reports and monthly status reports available as of December 2014. In addition, we reviewed total program funding requirements from the December 2014 Selected Acquisition Report. We used these data to project annual funding requirements through the expected end of the F-35 acquisition in 2038. We also compared the
  • 70. December 2014 Selected Acquisition Report data to prior Selected Acquisition Reports to identify changes in cost and quantity. We obtained life-cycle operating and support cost through the program’s Selected Acquisition Report and projections made by the Cost Analysis and Program Evaluation (CAPE) office. We discussed future plans of the Department of Defense (DOD) and contractors to try and reduce life-cycle sustainment costs with officials from the program office, Lockheed Martin, and Pratt & Whitney. To assess manufacturing and supply chain performance we obtained and analyzed data related to aircraft delivery rates and work performance data through the end of calendar year 2014. This data was compared to program objectives identified in these areas and used to identify trends. We reviewed data and briefings provided by the program office, Lockheed Martin, Pratt & Whitney, and DCMA in order to identify issues in manufacturing processes. We discussed reasons for delivery delays and plans for improvement with Lockheed Martin and Pratt & Whitney. We also toured Pratt and Whitney’s manufacturing facility in Middletown, Appendix II: Scope and Methodology
  • 71. Appendix II: Scope and Methodology Page 31 GAO-15-364 F-35 Joint Strike Fighter Connecticut and collected and analyzed data related to aircraft quality through December 2014. We collected and analyzed supply chain performance data and discussed plans taken to improve quality and deliveries with Lockheed Martin and Pratt & Whitney. We assessed the reliability of DOD and contractor data by reviewing existing information about the data, and interviewing agency officials knowledgeable about the data. We determined that the data were sufficiently reliable for the purposes of this report. We conducted this performance audit from July 2014 to April 2015 in accordance with generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. We believe that the evidence obtained
  • 72. provides a reasonable basis for our findings and conclusions based on our audit objectives. Appendix III: DOD Comments Page 32 GAO-15-364 F-35 Joint Strike Fighter Appendix III: DOD Comments Appendix III: DOD Comments Page 33 GAO-15-364 F-35 Joint Strike Fighter Appendix IV: GAO Contact and Staff Acknowledgments
  • 73. Page 34 GAO-15-364 F-35 Joint Strike Fighter Michael Sullivan (202) 512-4841 [email protected] In addition the contact name above, the following staff members made key contributions to this report: Travis Masters, Assistant Director; Peter Anderson; James Bennett; Marvin Bonner; Kristine Hassinger; Megan Porter; Marie Suding; and Abby Volk. Appendix IV: GAO Contact and Staff Acknowledgments GAO Contact Acknowledgments Related GAO Products Page 35 GAO-15-364 F-35 Joint Strike Fighter F-35 Sustainment: Need for Affordable Strategy, Greater Attention to Risks, and Improved Cost Estimates. GAO-14-778. Washington, D.C.: September 23, 2014. F-35 Joint Strike Fighter: Slower Than Expected Progress in
  • 74. Software Testing May Limit Initial Warfighting Capabilities. GAO-14- 468T Washington, D.C.: March 26 2014. F-35 Joint Strike Fighter: Problems Completing Software Testing May Hinder Delivery of Expected Warfighting Capabilities. GAO- 14-322. Washington, D.C.: March 24, 2014. F-35 Joint Strike Fighter: Restructuring Has Improved the Program, but Affordability Challenges and Other Risks Remain. GAO-13- 690T. Washington, D.C.: June 19, 2013. F-35 Joint Strike Fighter: Program Has Improved in Some Areas, but Affordability Challenges and Other Risks Remain. GAO-13- 500T. Washington, D.C.: April 17, 2013. F-35 Joint Strike Fighter: Current Outlook Is Improved, but Long-Term Affordability Is a Major Concern. GAO-13-309. Washington, D.C.: March 11, 2013. Fighter Aircraft: Better Cost Estimates Needed for Extending the Service Life of Selected F-16s and F/A-18s. GAO-13-51. Washington, D.C.: November 15, 2012 Joint Strike Fighter: DOD Actions Needed to Further Enhance
  • 75. Restructuring and Address Affordability Risks. GAO-12-437. Washington, D.C.: June 14, 2012. Defense Acquisitions: Assessments of Selected Weapon Programs. GAO-12-400SP. Washington, D.C.: March 29, 2012. Joint Strike Fighter: Restructuring Added Resources and Reduced Risk, but Concurrency Is Still a Major Concern. GAO-12-525T. Washington, D.C.: March 20, 2012. Joint Strike Fighter: Implications of Program Restructuring and Other Recent Developments on Key Aspects of DOD’s Prior Alternate Engine Analyses. GAO-11-903R. Washington, D.C.: September 14, 2011. Related GAO Products http://www.gao.gov/products/GAO-14-778� http://www.gao.gov/products/GAO-14-468T� http://www.gao.gov/products/GAO-14-322� http://www.gao.gov/products/GAO-13-690T� http://www.gao.gov/products/GAO-13-500T� http://www.gao.gov/products/GAO-13-309� http://www.gao.gov/products/GAO-13-51� http://www.gao.gov/products/GAO-12-437� http://www.gao.gov/products/GAO-12-400SP� http://www.gao.gov/products/GAO-12-525T� http://www.gao.gov/products/GAO-11-903R�
  • 76. Related GAO Products Page 36 GAO-15-364 F-35 Joint Strike Fighter Joint Strike Fighter: Restructuring Places Program on Firmer Footing, but Progress Is Still Lagging. GAO-11-677T. Washington, D.C.: May 19, 2011. Joint Strike Fighter: Restructuring Places Program on Firmer Footing, but Progress Still Lags. GAO-11-325. Washington, D.C.: April 7, 2011. Joint Strike Fighter: Restructuring Should Improve Outcomes, but Progress Is Still Lagging Overall. GAO-11-450T. Washington, D.C.: March 15, 2011. Tactical Aircraft: Air Force Fighter Force Structure Reports Generally Addressed Congressional Mandates, but Reflected Dated Plans and Guidance, and Limited Analyses. GAO-11-323R. Washington, D.C.: February 24, 2011. Defense Management: DOD Needs to Monitor and Assess Corrective Actions Resulting from Its Corrosion Study of the F-35 Joint
  • 77. Strike Fighter. GAO-11-171R. Washington D.C.: December 16, 2010. Joint Strike Fighter: Assessment of DOD’s Funding Projection for the F136 Alternate Engine. GAO-10-1020R. Washington, D.C.: September 15, 2010. Tactical Aircraft: DOD’s Ability to Meet Future Requirements is Uncertain, with Key Analyses Needed to Inform Upcoming Investment Decisions. GAO-10-789. Washington, D.C.: July 29, 2010. Defense Acquisitions: Assessments of Selected Weapon Programs. GAO-10-388SP. Washington, D.C.: March 30, 2010. Joint Strike Fighter: Significant Challenges and Decisions Ahead. GAO-10-478T. Washington, D.C.: March 24, 2010. Joint Strike Fighter: Additional Costs and Delays Risk Not Meeting Warfighter Requirements on Time. GAO-10-382. Washington, D.C.: March 19, 2010. Joint Strike Fighter: Significant Challenges Remain as DOD Restructures Program. GAO-10-520T. Washington, D.C.: March 11, 2010. http://www.gao.gov/products/GAO-11-677T� http://www.gao.gov/products/GAO-11-325� http://www.gao.gov/products/GAO-11-450T�
  • 78. http://www.gao.gov/products/GAO-11-323R� http://www.gao.gov/products/GAO-11-171R� http://www.gao.gov/products/GAO-10-1020R� http://www.gao.gov/products/GAO-10-789� http://www.gao.gov/products/GAO-10-388SP� http://www.gao.gov/products/GAO-10-478T� http://www.gao.gov/products/GAO-10-382� http://www.gao.gov/products/GAO-10-520T� Related GAO Products Page 37 GAO-15-364 F-35 Joint Strike Fighter Joint Strike Fighter: Strong Risk Management Essential as Program Enters Most Challenging Phase. GAO-09-711T. Washington, D.C.: May 20, 2009. Defense Acquisitions: Assessments of Selected Weapon Programs. GAO-09-326SP. Washington, D.C.: March 30, 2009. Joint Strike Fighter: Accelerating Procurement before Completing Development Increases the Government’s Financial Risk. GAO- 09-303. Washington D.C.: March 12, 2009. Defense Acquisitions: Better Weapon Program Outcomes Require
  • 79. Discipline, Accountability, and Fundamental Changes in the Acquisition Environment. GAO-08-782T. Washington, D.C.: June 3, 2008. Defense Acquisitions: Assessments of Selected Weapon Programs. GAO-08-467SP. Washington, D.C.: March 31, 2008. Joint Strike Fighter: Impact of Recent Decisions on Program Risks. GAO-08-569T. Washington, D.C.: March 11, 2008. Joint Strike Fighter: Recent Decisions by DOD Add to Program Risks. GAO-08-388. Washington, D.C.: March 11, 2008. Tactical Aircraft: DOD Needs a Joint and Integrated Investment Strategy. GAO-07-415. Washington, D.C.: April 2, 2007. Defense Acquisitions: Analysis of Costs for the Joint Strike Fighter Engine Program. GAO-07-656T. Washington, D.C.: March 22, 2007. Joint Strike Fighter: Progress Made and Challenges Remain. GAO-07-360. Washington, D.C.: March 15, 2007. Tactical Aircraft: DOD’s Cancellation of the Joint Strike Fighter Alternate Engine Program Was Not Based on a Comprehensive Analysis. GAO-06-717R. Washington, D.C.: May 22, 2006. Defense Acquisitions: Major Weapon Systems Continue to Experience Cost and Schedule Problems under DOD’s Revised Policy. GAO-06-368.
  • 80. Washington, D.C.: April 13, 2006. Defense Acquisitions: Actions Needed to Get Better Results on Weapons Systems Investments. GAO-06-585T. Washington, D.C.: April 5, 2006. http://www.gao.gov/products/GAO-09-711T� http://www.gao.gov/products/GAO-09-326SP� http://www.gao.gov/products/GAO-09-303� http://www.gao.gov/products/GAO-08-782T� http://www.gao.gov/products/GAO-08-467SP� http://www.gao.gov/products/GAO-08-569T� http://www.gao.gov/products/GAO-08-388� http://www.gao.gov/products/GAO-07-415� http://www.gao.gov/products/GAO-07-656T� http://www.gao.gov/products/GAO-07-360� http://www.gao.gov/products/GAO-06-717R� http://www.gao.gov/products/GAO-06-368� http://www.gao.gov/products/GAO-06-585T� Related GAO Products Page 38 GAO-15-364 F-35 Joint Strike Fighter Tactical Aircraft: Recapitalization Goals Are Not Supported by Knowledge-Based F-22A and JSF Business Cases. GAO-06- 487T. Washington, D.C.: March 16, 2006. Joint Strike Fighter: DOD Plans to Enter Production before
  • 81. Testing Demonstrates Acceptable Performance. GAO-06-356. Washington, D.C.: March 15, 2006. Joint Strike Fighter: Management of the Technology Transfer Process. GAO-06-364. Washington, D.C.: March 14, 2006. Tactical Aircraft: F/A-22 and JSF Acquisition Plans and Implications for Tactical Aircraft Modernization. GAO-05-519T. Washington, D.C: April 6, 2005. Tactical Aircraft: Opportunity to Reduce Risks in the Joint Strike Fighter Program with Different Acquisition Strategy. GAO-05-271. Washington, D.C.: March 15, 2005. (121234) http://www.gao.gov/products/GAO-06-487T� http://www.gao.gov/products/GAO-06-356� http://www.gao.gov/products/GAO-06-364� http://www.gao.gov/products/GAO-05-519T� http://www.gao.gov/products/GAO-05-271� The Government Accountability Office, the audit, evaluation, and
  • 82. investigative arm of Congress, exists to support Congress in meeting its constitutional responsibilities and to help improve the performance and accountability of the federal government for the American people. GAO examines the use of public funds; evaluates federal programs and policies; and provides analyses, recommendations, and other assistance to help Congress make informed oversight, policy, and funding decisions. GAO’s commitment to good government is reflected in its core values of accountability, integrity, and reliability. The fastest and easiest way to obtain copies of GAO documents at no cost is through GAO’s website (http://www.gao.gov). Each weekday afternoon, GAO posts on its website newly released reports, testimony, and correspondence. To have GAO e-mail you a list of newly posted products, go to http://www.gao.gov and select “E-mail Updates.” The price of each GAO publication reflects GAO’s actual cost of production and distribution and depends on the number of pages in the publication and whether the publication is printed in color or black and white. Pricing and ordering information is posted on GAO’s website, http://www.gao.gov/ordering.htm.
  • 83. Place orders by calling (202) 512-6000, toll free (866) 801- 7077, or TDD (202) 512-2537. Orders may be paid for using American Express, Discover Card, MasterCard, Visa, check, or money order. Call for additional information. Connect with GAO on Facebook, Flickr, Twitter, and YouTube. Subscribe to our RSS Feeds or E-mail Updates. Listen to our Podcasts . Visit GAO on the web at www.gao.gov. Contact: Website: http://www.gao.gov/fraudnet/fraudnet.htm E-mail: [email protected] Automated answering system: (800) 424-5454 or (202) 512- 7470 Katherine Siggerud, Managing Director, [email protected], (202) 512- 4400, U.S. Government Accountability Office, 441 G Street NW, Room 7125, Washington, DC 20548 Chuck Young, Managing Director, [email protected], (202) 512- 4800 U.S. Government Accountability Office, 441 G Street NW, Room 7149 Washington, DC 20548 GAO’s Mission Obtaining Copies of
  • 84. GAO Reports and Testimony Order by Phone Connect with GAO To Report Fraud, Waste, and Abuse in Federal Programs Congressional Relations Public Affairs Please Print on Recycled Paper. http://www.gao.gov/� http://www.gao.gov/� http://www.gao.gov/ordering.htm� http://facebook.com/usgao� http://flickr.com/usgao� http://twitter.com/usgao� http://youtube.com/usgao� http://www.gao.gov/feeds.html� http://www.gao.gov/subscribe/index.php� http://www.gao.gov/podcast/watchdog.html� http://www.gao.gov/� http://www.gao.gov/fraudnet/fraudnet.htm� mailto:[email protected]� mailto:[email protected]� mailto:[email protected]�F-35 Joint Strike FighterAssessment Needed to Address Affordability ChallengesContentsLetterBackgroundRecent Technical Challenges Will Likely Result in Cost Growth and Schedule
  • 85. DelaysTest Failures and Software Challenges Forced Program ChangesNeed to Improve Engine Reliability Presents Additional ChallengesUnexpected Technical Issues and Ongoing Reliability Challenges Amplify Concurrency RiskAffordability Challenges Will Likely Continue to Affect Program Plans to Increase F-35 ProcurementWhile Manufacturing Progress Remains Steady, Planned Production Increases Could Be a ChallengeManufacturing Efficiency Remains SteadyLate Deliveries from Suppliers Continue, and Could Challenge Planned Production IncreasesConclusionsRecommendationsAgency Comments and Our EvaluationAppendix I: Prior GAO Reports on F-35 Joint Strike Fighter (JSF) and Department of Defense (DOD) Responses and Subsequent ActionsAppendix II: Scope and MethodologyAppendix III: DOD CommentsAppendix IV: GAO Contact and Staff AcknowledgmentsGAO ContactAcknowledgmentsRelated GAO Productsd15364_HIGHLIGHTS.pdfF-35 JOINT STRIKE FIGHTERAssessment Needed to Address Affordability ChallengesWhy GAO Did This StudyWhat GAO RecommendsWhat GAO FoundCost and affordability challenges remain. DOD plans to significantly increase annual F-35 funding from around $8 billion to nearly $12 billion over the next 5 years (see figure) reaching $14 billion in 2022 and remaining between $14 and $15 billion fo... << /ASCII85EncodePages false /AllowTransparency false /AutoPositionEPSFiles true /AutoRotatePages /PageByPage /Binding /Left
  • 86. /CalGrayProfile (Dot Gain 20%) /CalRGBProfile (sRGB IEC61966-2.1) /CalCMYKProfile (U.S. Sheetfed Uncoated v2) /sRGBProfile (sRGB IEC61966-2.1) /CannotEmbedFontPolicy /Warning /CompatibilityLevel 1.7 /CompressObjects /All /CompressPages true /ConvertImagesToIndexed true /PassThroughJPEGImages true /CreateJobTicket false /DefaultRenderingIntent /Default /DetectBlends true /DetectCurves 0.1000 /ColorConversionStrategy /LeaveColorUnchanged /DoThumbnails false /EmbedAllFonts true /EmbedOpenType false
  • 87. /ParseICCProfilesInComments true /EmbedJobOptions true /DSCReportingLevel 0 /EmitDSCWarnings false /EndPage -1 /ImageMemory 1048576 /LockDistillerParams true /MaxSubsetPct 100 /Optimize true /OPM 1 /ParseDSCComments true /ParseDSCCommentsForDocInfo true /PreserveCopyPage true /PreserveDICMYKValues true /PreserveEPSInfo true /PreserveFlatness true /PreserveHalftoneInfo false /PreserveOPIComments false
  • 88. /PreserveOverprintSettings true /StartPage 1 /SubsetFonts true /TransferFunctionInfo /Preserve /UCRandBGInfo /Preserve /UsePrologue false /ColorSettingsFile () /AlwaysEmbed [ true ] /NeverEmbed [ true ] /AntiAliasColorImages false /CropColorImages true /ColorImageMinResolution 150 /ColorImageMinResolutionPolicy /OK /DownsampleColorImages true /ColorImageDownsampleType /Bicubic /ColorImageResolution 300
  • 89. /ColorImageDepth -1 /ColorImageMinDownsampleDepth 1 /ColorImageDownsampleThreshold 1.50000 /EncodeColorImages true /ColorImageFilter /DCTEncode /AutoFilterColorImages true /ColorImageAutoFilterStrategy /JPEG /ColorACSImageDict << /QFactor 0.15 /HSamples [1 1 1 1] /VSamples [1 1 1 1] >> /ColorImageDict << /QFactor 0.76 /HSamples [2 1 1 2] /VSamples [2 1 1 2] >> /JPEG2000ColorACSImageDict << /TileWidth 256 /TileHeight 256
  • 90. /Quality 15 >> /JPEG2000ColorImageDict << /TileWidth 256 /TileHeight 256 /Quality 15 >> /AntiAliasGrayImages false /CropGrayImages true /GrayImageMinResolution 150 /GrayImageMinResolutionPolicy /OK /DownsampleGrayImages true /GrayImageDownsampleType /Bicubic /GrayImageResolution 300 /GrayImageDepth -1 /GrayImageMinDownsampleDepth 2 /GrayImageDownsampleThreshold 1.50000 /EncodeGrayImages true
  • 91. /GrayImageFilter /DCTEncode /AutoFilterGrayImages true /GrayImageAutoFilterStrategy /JPEG /GrayACSImageDict << /QFactor 0.15 /HSamples [1 1 1 1] /VSamples [1 1 1 1] >> /GrayImageDict << /QFactor 0.76 /HSamples [2 1 1 2] /VSamples [2 1 1 2] >> /JPEG2000GrayACSImageDict << /TileWidth 256 /TileHeight 256 /Quality 15 >> /JPEG2000GrayImageDict << /TileWidth 256
  • 92. /TileHeight 256 /Quality 15 >> /AntiAliasMonoImages false /CropMonoImages true /MonoImageMinResolution 1200 /MonoImageMinResolutionPolicy /OK /DownsampleMonoImages true /MonoImageDownsampleType /Bicubic /MonoImageResolution 1200 /MonoImageDepth -1 /MonoImageDownsampleThreshold 1.50000 /EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode /MonoImageDict << /K -1 >> /AllowPSXObjects false
  • 93. /CheckCompliance [ /None ] /PDFX1aCheck false /PDFX3Check false /PDFXCompliantPDFOnly false /PDFXNoTrimBoxError true /PDFXTrimBoxToMediaBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXSetBleedBoxToMediaBox true /PDFXBleedBoxToTrimBoxOffset [ 0.00000 0.00000 0.00000
  • 94. 0.00000 ] /PDFXOutputIntentProfile (None) /PDFXOutputConditionIdentifier () /PDFXOutputCondition () /PDFXRegistryName () /PDFXTrapped /False /CreateJDFFile false /Description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
  • 95. /BGR <FEFF04180437043F043E043B04370432043004390442043500 2004420435043704380020043D0430044104420440043E043904 3A0438002C00200437043000200434043000200441044A043704 3404300432043004420435002000410064006F00620065002000 500044004600200434043E043A0443043C0435043D044204380 02C0020043F043E04340445043E0434044F04490438002004370 4300020043D04300434043504360434043D043E0020044004300 4370433043B0435043604340430043D0435002004380020043F0 4350447043004420430043D04350020043D04300020043104380 437043D0435044100200434043E043A0443043C0435043D0442 0438002E00200421044A04370434043004340435043D04380442 0435002000500044004600200434043E043A0443043C0435043 D044204380020043C043E0433043004420020043404300020044 104350020043E0442043204300440044F0442002004410020004 100630072006F00620061007400200438002000410064006F006 20065002000520065006100640065007200200036002E0030002 004380020043F043E002D043D043E0432043800200432043504 40044104380438002E> /CHS <FEFF4f7f75288fd94e9b8bbe5b9a521b5efa76840020004100640 06f006200650020005000440046002065876863900275284e8e55 464e1a65876863768467e5770b548c62535370300260a853ef4ee5 4f7f75280020004100630072006f0062006100740020548c002000 410064006f0062006500200052006500610064006500720020003 6002e003000204ee553ca66f49ad87248672c676562535f00521b5 efa768400200050004400460020658768633002> /CHT <FEFF4f7f752890194e9b8a2d7f6e5efa7acb76840020004100640 06f006200650020005000440046002065874ef69069752865bc66 6e901a554652d965874ef6768467e5770b548c52175370300260a 853ef4ee54f7f75280020004100630072006f00620061007400205 48c002000410064006f0062006500200052006500610064006500 7200200036002e003000204ee553ca66f49ad87248672c4f86958b
  • 96. 555f5df25efa7acb76840020005000440046002065874ef63002> /CZE <FEFF0054006f0074006f0020006e006100730074006100760065 006e00ed00200070006f0075017e0069006a007400650020006b0 020007600790074007600e101590065006e00ed00200064006f00 6b0075006d0065006e0074016f002000410064006f00620065002 0005000440046002000760068006f0064006e00fd006300680020 006b0065002000730070006f006c00650068006c0069007600e90 06d0075002000700072006f0068006c00ed017e0065006e00ed00 2000610020007400690073006b00750020006f006200630068006 f0064006e00ed0063006800200064006f006b0075006d0065006e 0074016f002e002000200056007900740076006f01590065006e0 0e900200064006f006b0075006d0065006e007400790020005000 4400460020006c007a00650020006f007400650076015900ed007 400200076002000610070006c0069006b0061006300ed00630068 0020004100630072006f006200610074002000610020004100630 072006f0062006100740020005200650061006400650072002000 36002e0030002000610020006e006f0076011b006a016100ed006 30068002e> /DAN <FEFF004200720075006700200069006e0064007300740069006 c006c0069006e006700650072006e0065002000740069006c0020 006100740020006f0070007200650074007400650020004100640 06f006200650020005000440046002d0064006f006b0075006d00 65006e007400650072002c0020006400650072002000650067006 e006500720020007300690067002000740069006c002000640065 00740061006c006a006500720065007400200073006b00e600720 06d007600690073006e0069006e00670020006f00670020007500 640073006b007200690076006e0069006e0067002000610066002 00066006f0072007200650074006e0069006e006700730064006f 006b0075006d0065006e007400650072002e00200044006500200 06f00700072006500740074006500640065002000500044004600 2d0064006f006b0075006d0065006e0074006500720020006b006 1006e002000e50062006e00650073002000690020004100630072
  • 97. 006f00620061007400200065006c006c006500720020004100630 072006f0062006100740020005200650061006400650072002000 36002e00300020006f00670020006e0079006500720065002e> /DEU <FEFF00560065007200770065006e00640065006e00200053006 90065002000640069006500730065002000450069006e00730074 0065006c006c0075006e00670065006e0020007a0075006d00200 0450072007300740065006c006c0065006e00200076006f006e00 2000410064006f006200650020005000440046002d0044006f006 b0075006d0065006e00740065006e002c00200075006d00200065 0069006e00650020007a0075007600650072006c00e4007300730 0690067006500200041006e007a00650069006700650020007500 6e00640020004100750073006700610062006500200076006f006 e00200047006500730063006800e40066007400730064006f006b 0075006d0065006e00740065006e0020007a00750020006500720 07a00690065006c0065006e002e00200044006900650020005000 440046002d0044006f006b0075006d0065006e007400650020006 b00f6006e006e0065006e0020006d006900740020004100630072 006f00620061007400200075006e0064002000520065006100640 065007200200036002e003000200075006e00640020006800f600 680065007200200067006500f600660066006e006500740020007 70065007200640065006e002e> /ESP <FEFF005500740069006c0069006300650020006500730074006 100200063006f006e0066006900670075007200610063006900f3 006e0020007000610072006100200063007200650061007200200 064006f00630075006d0065006e0074006f007300200064006500 2000410064006f006200650020005000440046002000610064006 50063007500610064006f00730020007000610072006100200076 0069007300750061006c0069007a00610063006900f3006e00200 06500200069006d0070007200650073006900f3006e0020006400 6500200063006f006e006600690061006e007a006100200064006 500200064006f00630075006d0065006e0074006f007300200063 006f006d00650072006300690061006c00650073002e002000530
  • 98. 065002000700075006500640065006e0020006100620072006900 7200200064006f00630075006d0065006e0074006f00730020005 000440046002000630072006500610064006f007300200063006f 006e0020004100630072006f006200610074002c0020004100640 06f00620065002000520065006100640065007200200036002e00 3000200079002000760065007200730069006f006e00650073002 00070006f00730074006500720069006f007200650073002e> /ETI <FEFF004b00610073007500740061006700650020006e0065006 900640020007300e400740074006500690064002c002000650074 0020006c0075007500610020005000440046002d0064006f006b0 075006d0065006e00740065002c0020006d006900730020007300 6f00620069007600610064002000e4007200690064006f006b007 5006d0065006e00740069006400650020007500730061006c0064 00750073007600e400e4007200730065006b00730020007600610 06100740061006d006900730065006b00730020006a0061002000 7000720069006e00740069006d006900730065006b0073002e002 00020004c006f006f0064007500640020005000440046002d0064 006f006b0075006d0065006e00740065002000730061006100620 02000610076006100640061002000760061006900640020004100 630072006f0062006100740020006a0061002000410064006f006 20065002000520065006100640065007200200036002e00300020 006a00610020007500750065006d0061007400650020007600650 07200730069006f006f006e00690064006500670061002e> /FRA <FEFF005500740069006c006900730065007a002000630065007 30020006f007000740069006f006e00730020006100660069006e 00200064006500200063007200e90065007200200064006500730 0200064006f00630075006d0065006e0074007300200041006400 6f006200650020005000440046002000700072006f00660065007 300730069006f006e006e0065006c007300200066006900610062 006c0065007300200070006f007500720020006c0061002000760 069007300750061006c00690073006100740069006f006e002000 6500740020006c00270069006d007000720065007300730069006
  • 99. f006e002e0020004c0065007300200064006f00630075006d0065 006e00740073002000500044004600200063007200e900e900730 02000700065007500760065006e0074002000ea00740072006500 20006f007500760065007200740073002000640061006e0073002 0004100630072006f006200610074002c002000610069006e0073 0069002000710075002700410064006f006200650020005200650 06100640065007200200036002e00300020006500740020007600 65007200730069006f006e007300200075006c007400e90072006 900650075007200650073002e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
  •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a0065006b006b0065006c0020006100200062006 500e1006c006c00ed007400e10073006f006b006b0061006c0020
  • 101. 00fc007a006c00650074006900200064006f006b0075006d00650 06e00740075006d006f006b0020006d00650067006200ed007a00 680061007400f30020006d00650067006a0065006c0065006e00e d007400e9007300e900720065002000e900730020006e0079006f 006d00740061007400e1007300e10072006100200061006c006b0 061006c006d00610073002000410064006f006200650020005000 440046002d0064006f006b0075006d0065006e00740075006d006 f006b006100740020006b00e90073007a00ed0074006800650074 002e002000200041007a002000ed006700790020006c00e900740 07200650068006f007a006f007400740020005000440046002d00 64006f006b0075006d0065006e00740075006d006f006b0020006 1007a0020004100630072006f006200610074002000e900730020 0061007a002000410064006f00620065002000520065006100640 065007200200036002c0030002d0073002000e900730020006b00 e9007301510062006200690020007600650072007a006900f3006 900760061006c0020006e00790069007400680061007400f3006b 0020006d00650067002e> /ITA (Utilizzare queste impostazioni per creare documenti Adobe PDF adatti per visualizzare e stampare documenti aziendali in modo affidabile. I documenti PDF creati possono essere aperti con Acrobat e Adobe Reader 6.0 e versioni successive.) /JPN <FEFF30d330b830cd30b9658766f8306e8868793a304a30883073 53705237306b90693057305f002000410064006f0062006500200 050004400460020658766f8306e4f5c6210306b4f7f75283057307 e305930023053306e8a2d5b9a30674f5c62103055308c305f00200 05000440046002030d530a130a430eb306f300100410063007200 6f0062006100740020304a30883073002000410064006f0062006 5002000520065006100640065007200200036002e003000204ee5 964d3067958b304f30533068304c3067304d307e3059300230533 06e8a2d5b9a3067306f30d530a930f330c8306e57cb30818fbc307f 3092884c3044307e30593002>