SlideShare a Scribd company logo
1 of 24
DEVELOPMENT OF THE NETWORK DIAGRAM AND CRITICAL PATH Adapted and edited from A Practical Introduction to Management Science  4 th  edition
BUILDING A HOUSE THE NETWORK DIAGRAM IS ABOUT CREATING RELATIONSHIPS BETWEEN ACTIVITIES
BUILDING A HOUSE RELATIONSHIPS ARE ALSO REFERRED TO AS DEPENDENCIES – THE MOST BASIC IS “FINISH TO START”
BUILDING A HOUSE THUS THE BASIC QUESTION IS WHICH ACTIVITIES MUST BE FINISHED BEFORE WHICH ACTIVITIES CAN START
BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP Activity A Must Be Finished Before B Can Start A B
BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP But Activity E, F and G Don’t Have to Wait for Each Other D E F G Frame HVAC Rough Electric H Sheet Rock
BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP Note That E, F and G Don’t Have to Start and Finish At The Same Time D E F G Frame HVAC Rough Electric H Sheet Rock
BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP They However Need to Be Finished Before H Can Start D E F G Frame HVAC Rough Electric H Sheet Rock
Task 1 Is to Create These Dependencies By Listing the Steps That Happen Before Each Activity
SUMMARY OF ACTIVITIES Time Immediate Required Predecessor Activity Description  (in days) Activities A Excavate B Lay foundation C Rough plumbing D Frame E Finish exterior F Install HVAC G Rough electric H Sheet rock I Install cabinets J Paint K Final plumbing L Final electric M Install flooring
SUMMARY OF ACTIVITIES Time Immediate Required Predecessor Activity Description  (in days) Activities A Excavate -- B Lay foundation A C Rough plumbing B D Frame B E Finish exterior D F Install HVAC D G Rough electric D H Sheet rock C, E, F, G I Install cabinets H J Paint H K Final plumbing I L Final electric J M Install flooring K, L
Task 2  TEST THE LOGIC BY CONSTRUCTING THE NETWORK DIAGRAM
An Activity-On-Node (AON) Network Install Cabinets A B C D E F G H I J K L M Excavate Lay Foundation Rough Plumbing Frame Finish Exterior HVAC Rough Electric Sheet Rock Paint Final Plumbing Final Electric Install Flooring
Basic Rules for Constructing the Network Diagram ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Task 3  DETERMINE DURATIONS FOR EACH ACTIVITY
SUMMARY OF ACTIVITIES Time Immediate Required Predecessor Activity Description  (in days) Activities A Excavate 3 -- B Lay foundation 4 A C Rough plumbing 3 B D Frame 10 B E Finish exterior 8 D F Install HVAC 4 D G Rough electric 6 D H Sheet rock 8 C, E, F, G I Install cabinets 5 H J Paint 5 H K Final plumbing 4 I L Final electric 2 J M Install flooring 4 K, L
SUMMARY OF ACTIVITIES ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Look at this a different way ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
The first mistake of project management ,[object Object],[object Object]
The first mistake of project management ,[object Object],[object Object],[object Object]
The first mistake of project management ,[object Object],[object Object],[object Object]
In CPM you build from the future to the present ,[object Object],[object Object],[object Object],[object Object]
What does this mean for you? ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
The network-diagram-and-critical-path-adapted

More Related Content

What's hot

Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)Nikka Lopez
 
Project Network project approaches and rules
Project Network  project approaches and rules Project Network  project approaches and rules
Project Network project approaches and rules tassawarshahzad2
 
05 critical path analysis
05 critical path analysis05 critical path analysis
05 critical path analysisSam Catlin
 
Critical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueCritical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueJomari Gingo Selibio
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method Mkaur01
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)Nikhil Raj
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
PM Session 5
PM Session 5PM Session 5
PM Session 5dmdk12
 
How Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerHow Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerPraveen Malik, PMP
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysistutor2u
 

What's hot (18)

Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Project networks
Project networksProject networks
Project networks
 
Project Network project approaches and rules
Project Network  project approaches and rules Project Network  project approaches and rules
Project Network project approaches and rules
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
05 critical path analysis
05 critical path analysis05 critical path analysis
05 critical path analysis
 
Critical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueCritical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review Technique
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
PM Session 5
PM Session 5PM Session 5
PM Session 5
 
How Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerHow Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project Manager
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 

Similar to The network-diagram-and-critical-path-adapted

Constructing a network diagram
Constructing a network diagramConstructing a network diagram
Constructing a network diagramnelramlawy
 
1 Week 14 Program Evaluation and Review Technique (PERT.docx
 1 Week 14   Program Evaluation and Review Technique (PERT.docx 1 Week 14   Program Evaluation and Review Technique (PERT.docx
1 Week 14 Program Evaluation and Review Technique (PERT.docxjoyjonna282
 
Week 3 Homework AIB ProblemsBefore starting this homewo.docx
Week 3 Homework AIB ProblemsBefore starting this homewo.docxWeek 3 Homework AIB ProblemsBefore starting this homewo.docx
Week 3 Homework AIB ProblemsBefore starting this homewo.docxmelbruce90096
 
Project Topic 1 Moore Housing ContractorsMoore Housing Contra.docx
Project Topic 1 Moore Housing ContractorsMoore Housing Contra.docxProject Topic 1 Moore Housing ContractorsMoore Housing Contra.docx
Project Topic 1 Moore Housing ContractorsMoore Housing Contra.docxwkyra78
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newKatherineJack1
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newSarajacobe
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newEmmaJack2018
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newlizabonilla
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newemmywatson2017
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newLillieDickey
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newsarahlazeto
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newsweetsour2017
 
Critical Path(Re-visited)
Critical Path(Re-visited)Critical Path(Re-visited)
Critical Path(Re-visited)Ryan Veitch
 

Similar to The network-diagram-and-critical-path-adapted (20)

Constructing a network diagram
Constructing a network diagramConstructing a network diagram
Constructing a network diagram
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
 
1 Week 14 Program Evaluation and Review Technique (PERT.docx
 1 Week 14   Program Evaluation and Review Technique (PERT.docx 1 Week 14   Program Evaluation and Review Technique (PERT.docx
1 Week 14 Program Evaluation and Review Technique (PERT.docx
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Week 3 Homework AIB ProblemsBefore starting this homewo.docx
Week 3 Homework AIB ProblemsBefore starting this homewo.docxWeek 3 Homework AIB ProblemsBefore starting this homewo.docx
Week 3 Homework AIB ProblemsBefore starting this homewo.docx
 
Project Topic 1 Moore Housing ContractorsMoore Housing Contra.docx
Project Topic 1 Moore Housing ContractorsMoore Housing Contra.docxProject Topic 1 Moore Housing ContractorsMoore Housing Contra.docx
Project Topic 1 Moore Housing ContractorsMoore Housing Contra.docx
 
Cpm pert asgm. prashant
Cpm pert asgm. prashantCpm pert asgm. prashant
Cpm pert asgm. prashant
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Lecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdfLecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdf
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Critical Path(Re-visited)
Critical Path(Re-visited)Critical Path(Re-visited)
Critical Path(Re-visited)
 
PERT AND CPM 2.pdf
PERT AND CPM  2.pdfPERT AND CPM  2.pdf
PERT AND CPM 2.pdf
 

More from ldchristopher

Unit 5 lesson 3 conceptual design
Unit 5 lesson 3 conceptual designUnit 5 lesson 3 conceptual design
Unit 5 lesson 3 conceptual designldchristopher
 
Unit 5 lesson 2 supporting life
Unit 5 lesson 2 supporting lifeUnit 5 lesson 2 supporting life
Unit 5 lesson 2 supporting lifeldchristopher
 
Building a space telescope
Building a space telescopeBuilding a space telescope
Building a space telescopeldchristopher
 
Building a space telescope
Building a space telescopeBuilding a space telescope
Building a space telescopeldchristopher
 
Building a space telescope
Building a space telescopeBuilding a space telescope
Building a space telescopeldchristopher
 
Unit3 lesson3 howdoeshst_work
Unit3 lesson3 howdoeshst_workUnit3 lesson3 howdoeshst_work
Unit3 lesson3 howdoeshst_workldchristopher
 
Unit4 lesson4 it_just_dissapeared
Unit4 lesson4 it_just_dissapearedUnit4 lesson4 it_just_dissapeared
Unit4 lesson4 it_just_dissapearedldchristopher
 
Unit4 lesson3 howdoessoho_work
Unit4 lesson3 howdoessoho_workUnit4 lesson3 howdoessoho_work
Unit4 lesson3 howdoessoho_workldchristopher
 
Designing a lunar commercial venture
Designing a lunar commercial ventureDesigning a lunar commercial venture
Designing a lunar commercial ventureldchristopher
 
Building a Communications Satellite
Building a Communications SatelliteBuilding a Communications Satellite
Building a Communications Satelliteldchristopher
 
Lesson 4 newton in space
Lesson 4 newton in spaceLesson 4 newton in space
Lesson 4 newton in spaceldchristopher
 
Theshortestdistancenarrated
TheshortestdistancenarratedTheshortestdistancenarrated
Theshortestdistancenarratedldchristopher
 
Theshortestdistancenarrated
TheshortestdistancenarratedTheshortestdistancenarrated
Theshortestdistancenarratedldchristopher
 
The shortest distance narrated
The shortest distance narratedThe shortest distance narrated
The shortest distance narratedldchristopher
 
Engineering design process power point
Engineering design process power pointEngineering design process power point
Engineering design process power pointldchristopher
 

More from ldchristopher (16)

Unit 5 lesson 3 conceptual design
Unit 5 lesson 3 conceptual designUnit 5 lesson 3 conceptual design
Unit 5 lesson 3 conceptual design
 
Unit 5 lesson 2 supporting life
Unit 5 lesson 2 supporting lifeUnit 5 lesson 2 supporting life
Unit 5 lesson 2 supporting life
 
Building a space telescope
Building a space telescopeBuilding a space telescope
Building a space telescope
 
Building a space telescope
Building a space telescopeBuilding a space telescope
Building a space telescope
 
Building a space telescope
Building a space telescopeBuilding a space telescope
Building a space telescope
 
Unit3 lesson3 howdoeshst_work
Unit3 lesson3 howdoeshst_workUnit3 lesson3 howdoeshst_work
Unit3 lesson3 howdoeshst_work
 
Unit4 lesson4 it_just_dissapeared
Unit4 lesson4 it_just_dissapearedUnit4 lesson4 it_just_dissapeared
Unit4 lesson4 it_just_dissapeared
 
Unit4 lesson3 howdoessoho_work
Unit4 lesson3 howdoessoho_workUnit4 lesson3 howdoessoho_work
Unit4 lesson3 howdoessoho_work
 
Designing a lunar commercial venture
Designing a lunar commercial ventureDesigning a lunar commercial venture
Designing a lunar commercial venture
 
Building a Communications Satellite
Building a Communications SatelliteBuilding a Communications Satellite
Building a Communications Satellite
 
Moving objects
Moving objectsMoving objects
Moving objects
 
Lesson 4 newton in space
Lesson 4 newton in spaceLesson 4 newton in space
Lesson 4 newton in space
 
Theshortestdistancenarrated
TheshortestdistancenarratedTheshortestdistancenarrated
Theshortestdistancenarrated
 
Theshortestdistancenarrated
TheshortestdistancenarratedTheshortestdistancenarrated
Theshortestdistancenarrated
 
The shortest distance narrated
The shortest distance narratedThe shortest distance narrated
The shortest distance narrated
 
Engineering design process power point
Engineering design process power pointEngineering design process power point
Engineering design process power point
 

The network-diagram-and-critical-path-adapted

  • 1. DEVELOPMENT OF THE NETWORK DIAGRAM AND CRITICAL PATH Adapted and edited from A Practical Introduction to Management Science 4 th edition
  • 2. BUILDING A HOUSE THE NETWORK DIAGRAM IS ABOUT CREATING RELATIONSHIPS BETWEEN ACTIVITIES
  • 3. BUILDING A HOUSE RELATIONSHIPS ARE ALSO REFERRED TO AS DEPENDENCIES – THE MOST BASIC IS “FINISH TO START”
  • 4. BUILDING A HOUSE THUS THE BASIC QUESTION IS WHICH ACTIVITIES MUST BE FINISHED BEFORE WHICH ACTIVITIES CAN START
  • 5. BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP Activity A Must Be Finished Before B Can Start A B
  • 6. BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP But Activity E, F and G Don’t Have to Wait for Each Other D E F G Frame HVAC Rough Electric H Sheet Rock
  • 7. BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP Note That E, F and G Don’t Have to Start and Finish At The Same Time D E F G Frame HVAC Rough Electric H Sheet Rock
  • 8. BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP They However Need to Be Finished Before H Can Start D E F G Frame HVAC Rough Electric H Sheet Rock
  • 9. Task 1 Is to Create These Dependencies By Listing the Steps That Happen Before Each Activity
  • 10. SUMMARY OF ACTIVITIES Time Immediate Required Predecessor Activity Description (in days) Activities A Excavate B Lay foundation C Rough plumbing D Frame E Finish exterior F Install HVAC G Rough electric H Sheet rock I Install cabinets J Paint K Final plumbing L Final electric M Install flooring
  • 11. SUMMARY OF ACTIVITIES Time Immediate Required Predecessor Activity Description (in days) Activities A Excavate -- B Lay foundation A C Rough plumbing B D Frame B E Finish exterior D F Install HVAC D G Rough electric D H Sheet rock C, E, F, G I Install cabinets H J Paint H K Final plumbing I L Final electric J M Install flooring K, L
  • 12. Task 2 TEST THE LOGIC BY CONSTRUCTING THE NETWORK DIAGRAM
  • 13. An Activity-On-Node (AON) Network Install Cabinets A B C D E F G H I J K L M Excavate Lay Foundation Rough Plumbing Frame Finish Exterior HVAC Rough Electric Sheet Rock Paint Final Plumbing Final Electric Install Flooring
  • 14.
  • 15. Task 3 DETERMINE DURATIONS FOR EACH ACTIVITY
  • 16. SUMMARY OF ACTIVITIES Time Immediate Required Predecessor Activity Description (in days) Activities A Excavate 3 -- B Lay foundation 4 A C Rough plumbing 3 B D Frame 10 B E Finish exterior 8 D F Install HVAC 4 D G Rough electric 6 D H Sheet rock 8 C, E, F, G I Install cabinets 5 H J Paint 5 H K Final plumbing 4 I L Final electric 2 J M Install flooring 4 K, L
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.